PART II EXTRAORDINARY
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION
PUBLICATION OF THE OPERATIVE PORTION OF THE ORDER IN O.P.No. 5 OF
2017 PASSED BY THE COMMISSION ON 13-07-2018.
O.P.No. 05 of 2017
Present
Justice Sri G. Bhavani Prasad, Chairman
Dr. P. Raghu, Member
Sri P. Rama Mohan, Member
Between :
Southern Power Distribution Company of Andhra Pradesh Limited
Eastern Power Distribution Company of Andhra Pradesh Limited
....Petitioner(s)
AND
-NIL-
....Respondent
The operative portion of the order
Lr.No. APERC / JD (PPP) / F.No. S-19 / D.No. /2018,
(a)
In exercise of the powers conferred on the Commission by Section 181
of the Electricity Act, 2003, Section 54 of the Andhra Pradesh
Electricity Reform Act, 1998 and clause 1 (2) of The Andhra Pradesh
Electricity Regulatory Commission (Terms and Conditions for Tariff
[1]
Registered No. HSE-49/2016
No.97
AMARAVATI, FRIDAY , JULY 13, 2018
G.385
NOTIFICATIONS BY HEADS OF DEPARTMENTS, Etc.
--x--
Determination for Wind Power Projects) Regulations, 2015, Regulation 1
of 2015, it is hereby declared that the Andhra Pradesh Electricity
Regulatory Commission (Terms and Conditions for Tariff Determination
for Wind Power Projects) Regulations, 2015, Regulation 1 of 2015 shall
be deemed to have remained in force upto 31-03-2017 and shall be
deemed to have ceased to be in force with effect from 01-04-2017;
(b)
The petitioners are at liberty to procure power through a transparent
process of bidding in accordance with the guidelines for tariff based
competitive bidding process for procurement of power from grid
connected wind power projects formulated and issued by the Ministry
of Power, Government of India Dated : 08-12-2017 under Section 63
of the Electricity Act, 2003;
(c)
The petitioners are also at liberty to procure power from wind power
projects in accordance with Sections 61, 62, 64 and 86 (1) (b) of the
Electricity Act, 2003 and Sections 21 and 26 of the Andhra Pradesh
Electricity Reform Act, 1998 and Rules, regulations, practice directions
and orders issued there under until an appropriate regulation in that
behalf is made by this Commission and any Power Purchase Agreement
or tariff there under for such procurement shall be guided by the
principles contained in the provisions of the Central Electricity
Regulatory Commission (Terms and Conditions for Tariff Determination
from Renewable Energy Sources) Regulations, 2017;
(d)
The order of the Commission Dated : 13-12-2017 in the matter of 41
Power Purchase Agreements between Southern Power Distribution
Company of Andhra Pradesh Limited and various wind power developers
and the order of the Commission in O.P.No.15 of 2017 Dated :
30-03-2017 shall be subject to this order as already stated in the
said two orders respectively;
(e)
This operative portion of this order shall be notified and published
in the official Gazette of the State of Andhra Pradesh;
AND
This Original Petition is ordered accordingly.
P. Rama Mohan
Dr. P. Raghu
Justice G. Bhavani Prasad
Member
Member
Chairman
(BY ORDER OF THE COMMISSION)
Hyderabad,
Dr. A. SRINIVAS,
13-07-2018.
Commission Secretary (i/c).
Published and Uploaded by the Commissioner of Printing, Government of Andhra Pradesh at
Government Regional Press, Vijayawada, www.apegazette.cgg.gov.in
2
ANDHRA PRADESH GAZETTE EXTRAORDINARY
[Part-II