PART I EXTRAORDINARY

GOVERNMENT OF ANDHRA PRADESH

ABSTRACT

Water Resources Department - Godavari Delta System - Administrative sanction

for (1) Completion of balance works of D.L. Bridge on Kakinada Canal at

Km.25.350 in near Komaripalem Village limits under G.E. Delta for an amount

of Rs.149.30Lakhs (2) Completion of balance works of D.L. Bridge on

Kakinada Canal at Km.28.482 in near Konkuduru Village limits under G.E. Delta

for an amount of Rs.181.00 Lakhs - Orders - Issued.

-------------------------------------------------------------------------------------------------------------

WATER RESOURCES (Projects-II) DEPARTMENT

G.O.Rt.No.34.

Dated: 28.01.2023.

Read:

From the CE, GDS Letter No.CE/GDS/DWM/OT2/AEE1/JTO/37Govt.,

dated: 29.03.2022, 23.07.2022 & 28.10.2022.

--00--

ORDER:

The Chief Engineer, Godavari Delta System, Dowlaiswaram in the letter

read above., while stating the details and circumstances, has requested the

Government, to accord Administrative approval for the following (2) No.of

estimates for “Completion of balance works of Road bridges on Kakinada canal

near Konkuduru and Komaripalem village limits” for an amount of Rs.330.30

Lakhs:-

Registered No. HSE-49/2016

No.101

AMARAVATI, MONDAY, JANUARY 30, 2023

G.3431

NOTIFICATIONS BY GOVERNMENT

--x--

SI.No Name of the works

Amount

(Rs in Lakhs)

1

Completion of balance works of D.L. Bridge on Kakinada

Canal at

Km.25.350

in

near

Komaripalem

Village limits under G.E. Delta.

149.30

2

Completion of balance works of D.L. Bridge on Kakinada

Canal at

Km.28.482

in

near

Konkuduru

Village limits under G.E. Delta.

181.00

Total

330.30

2) After careful examination of the proposal, the Government hereby accord

administrative sanction for an amount of Rs.330.30 Lakhs (Rupees three

hundred thirty lakhs and thirty thousand only) for the following (2) works,

duly

relaxation

of

the

FRBM

norms,

under

Head

of

Account

“4700 Capital Outlay on Major Irrigation -01 Major Irrigation - Commercial -

M.H.114 Godavari Delta System - G.H.11 State Development Schemes – S.H

(27) Canals and Distributaries -530 Major works- 531 Major works”...

SI.No Name of the works

Amount

(Rs in Lakhs)

1

Completion of balance works of D.L. Bridge on Kakinada

Canal at

Km.25.350

in

near

Komaripalem

Village limits under G.E. Delta.

149.30

2

Completion of balance works of D.L. Bridge on Kakinada

Canal at

Km.28.482

in

near

Konkuduru

Village limits under G.E. Delta.

181.00

Total

330.30

3) The Chief Engineer, Godavari Delta System, Dowlaiswaram shall ensure

the following before according technical sanction:-

i The correctness of quantities, leads, rates and data proposed in the

estimates.

ii The estimates are prepared based on approved drawings.

iii In the estimates supporting calculations are not furnished for the proposed

steel quantity. The quantity may be obtained based on bar-bending schedule.

4) The Chief Engineer, Godavari Delta System, Dowlaiswaram shall take

further necessary action in the matter accordingly.

5) This order issues with the concurrence of Finance (FMU-W.R.II) Department,

vide their U.O.Note.No.FIN01-FMU0MRAS (WR2)/149/2022-FMU-WR-II, Computer

No. 1905689, dated: 23.01.2023.

6)

This

order

is

available

online

and

can

be

accessed

at

http://apegazette.cgg.gov.in.

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

SHASHI BHUSHAN KUMAR

PRINCIPAL SECRETARY TO GOVERNMENT

To:

The Chief Engineer, Godavari Delta System, Dowlaiswaram.

Copy to:

The P.S to Hon’ble Minister for Water Resources.

The P.S to Principal Secretary to Government (WRD).

The Finance (FMU-WR.II) Dept.,

The Accountant General, A.P., Vijayawada.

The Director of Works and Accounts, Ibrahimpatnam, Vijayawada.

Sf/Sc. (1550112)

// FORWARDED::BY ORDER //

SECTION OFFICER