PART I EXTRAORDINARY
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Water Resources Department - Godavari Delta System - Administrative sanction
for (1) Completion of balance works of D.L. Bridge on Kakinada Canal at
Km.25.350 in near Komaripalem Village limits under G.E. Delta for an amount
of Rs.149.30Lakhs (2) Completion of balance works of D.L. Bridge on
Kakinada Canal at Km.28.482 in near Konkuduru Village limits under G.E. Delta
for an amount of Rs.181.00 Lakhs - Orders - Issued.
-------------------------------------------------------------------------------------------------------------
WATER RESOURCES (Projects-II) DEPARTMENT
G.O.Rt.No.34.
Dated: 28.01.2023.
Read:
From the CE, GDS Letter No.CE/GDS/DWM/OT2/AEE1/JTO/37Govt.,
dated: 29.03.2022, 23.07.2022 & 28.10.2022.
--00--
ORDER:
The Chief Engineer, Godavari Delta System, Dowlaiswaram in the letter
read above., while stating the details and circumstances, has requested the
Government, to accord Administrative approval for the following (2) No.of
estimates for “Completion of balance works of Road bridges on Kakinada canal
near Konkuduru and Komaripalem village limits” for an amount of Rs.330.30
Lakhs:-
Registered No. HSE-49/2016
No.101
AMARAVATI, MONDAY, JANUARY 30, 2023
G.3431
NOTIFICATIONS BY GOVERNMENT
--x--
SI.No Name of the works
Amount
(Rs in Lakhs)
1
Completion of balance works of D.L. Bridge on Kakinada
Canal at
Km.25.350
in
near
Komaripalem
Village limits under G.E. Delta.
149.30
2
Completion of balance works of D.L. Bridge on Kakinada
Canal at
Km.28.482
in
near
Konkuduru
Village limits under G.E. Delta.
181.00
Total
330.30
2) After careful examination of the proposal, the Government hereby accord
administrative sanction for an amount of Rs.330.30 Lakhs (Rupees three
hundred thirty lakhs and thirty thousand only) for the following (2) works,
duly
relaxation
of
the
FRBM
norms,
under
Head
of
Account
“4700 Capital Outlay on Major Irrigation -01 Major Irrigation - Commercial -
M.H.114 Godavari Delta System - G.H.11 State Development Schemes – S.H
(27) Canals and Distributaries -530 Major works- 531 Major works”...
SI.No Name of the works
Amount
(Rs in Lakhs)
1
Completion of balance works of D.L. Bridge on Kakinada
Canal at
Km.25.350
in
near
Komaripalem
Village limits under G.E. Delta.
149.30
2
Completion of balance works of D.L. Bridge on Kakinada
Canal at
Km.28.482
in
near
Konkuduru
Village limits under G.E. Delta.
181.00
Total
330.30
3) The Chief Engineer, Godavari Delta System, Dowlaiswaram shall ensure
the following before according technical sanction:-
i The correctness of quantities, leads, rates and data proposed in the
estimates.
ii The estimates are prepared based on approved drawings.
iii In the estimates supporting calculations are not furnished for the proposed
steel quantity. The quantity may be obtained based on bar-bending schedule.
4) The Chief Engineer, Godavari Delta System, Dowlaiswaram shall take
further necessary action in the matter accordingly.
5) This order issues with the concurrence of Finance (FMU-W.R.II) Department,
vide their U.O.Note.No.FIN01-FMU0MRAS (WR2)/149/2022-FMU-WR-II, Computer
No. 1905689, dated: 23.01.2023.
6)
This
order
is
available
online
and
can
be
accessed
at
http://apegazette.cgg.gov.in.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
SHASHI BHUSHAN KUMAR
PRINCIPAL SECRETARY TO GOVERNMENT
To:
The Chief Engineer, Godavari Delta System, Dowlaiswaram.
Copy to:
The P.S to Hon’ble Minister for Water Resources.
The P.S to Principal Secretary to Government (WRD).
The Finance (FMU-WR.II) Dept.,
The Accountant General, A.P., Vijayawada.
The Director of Works and Accounts, Ibrahimpatnam, Vijayawada.
Sf/Sc. (1550112)
// FORWARDED::BY ORDER //
SECTION OFFICER