PART I EXTRAORDINARY
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Water Resources Department - “Detailed Investigation, Designs and Construction of
Pump House, Associated Civil, Electro Mechanical Works, Electrical Sub Station
including installation and laying of MS Pressure Mains, Manifolds, Construction of
Delivery Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM
106.800 on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi
(M) of WG Dist under EPC Turnkey System” for Rs.68,85,00,000/- (Rupees Sixty
Eight Crores and Eight Five Lakhs only) - Administrative Approval – Accorded –
Orders-Issued.
WATER RESOURCES (PROJECTS.I) DEPARTMENT
G.O.Rt.No:119
Dated: 16/03/2023
Read:
From
the
Chief
Engineer,
Polavaram
Irrigation
Project,
Dowlaiswaram,
Lr.No.CE/PIP/DCE/OT1/AEE/RMC JLIS, Dated.26.02.2021, 29.06.2021, 24.09.2021,
04.02.2022 14.03.2022 and 25.05.2022.
ORDER:
In the reference read above the Chief Engineer, Polavaram Irrigation Project,
Dowlaiswaram has submitted proposal of Jagannadhapuram Lift Irrigation Scheme,
proposed on the Right Side of the Polavaram Irrigation Project Right Main Canal
near Jagannadhapuram (V) of Pedavegi (M) to irrigate an ayacut of 5268.66 Acs
(4786 Acs dry ayacut, duly deleting the same from Chinthalapudi LI Scheme and
supplementation of 482.66 Acs of wet crop) for utilization of 187.68 Mcft with peak
discharge of 54.25 cusecs at 16 Hrs of pumping per day.
2.
The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram, while
explaining the above, requested to issue necessary administrative sanction for the
Registered No. HSE-49/2016
No.392
AMARAVATI, TUESDAY, APRIL 18, 2023
G.35
NOTIFICATIONS BY GOVERNMENT
--x--
work of “Detailed Investigation, Designs and Construction of Pump House,
Associated Civil, Electro Mechanical Works, Electrical Sub Station including
installation and laying of MS Pressure Mains, Manifolds, Construction of Delivery
Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM 106.800
on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi (M) of WG
Dist under EPC Turnkey System” for Rs. 72,18,90,000/-.
3.
After careful examination, Government hereby accorded administrative
sanction for the work of “Detailed Investigation, Designs and Construction of Pump
House, Associated Civil, Electro Mechanical Works, Electrical Sub Station including
installation and laying of MS Pressure Mains, Manifolds, Construction of Delivery
Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM 106.800
on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi (M) of
West Godavari Dist under EPC Turnkey System” for Rs. 68,85,00,000/- (Rupees
Sixty Eight Crores and Eight Five Lakhs only ) in relaxation of FRBM Norms, subject
to the condition that the Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram
shall ensure i) correctness of quantities, leads, rates and data proposed in the
estimate ii) Designs & drawings shall got approved by the competent authority iii)
Supporting details for the proposed LS provisions shall obtained and iv) As LA is
involved, Land value certificate from the Revenue department shall obtained.
4.
The expenditure is chargeable to the head of account 4700 Capital Outlay on
Major Irrigation – 01 – Major Irrigation (Commercial) – MH 120 Polavaram Barrage –
GH 11 State Development Schemes – SH – 27 Canals and Distributaries – 530 –
Major Works – 531 OE. / 532 LA.
5.
The Chief Engineer, Polavaram Irrigation Project shall take necessary action
accordingly.
6.
This order issues with the concurrence of the Finance (FMU.WR.II)
Department vide their U.O. Note No. FIN01-FMU0MRAS (WR2)/35/2022-FMU-WR-
II, dated: 17.12.2022. (Computer No.1689188)
7.
This
order
is
available
on
online
and
can
be
accessed
at
http://apegazette.cgg.gov.in.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
SHASHI BHUSHAN KUMAR
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram.
Copy to:
The Director of Works & Accounts, Mangalagiri.
The Pay and Account Officer, Mangalagiri.
The Finance (FMU-WR.II) Department.
The P.S. to Secretary to CM.
The P.S. to Minister (WRD).
The P.S. to Secretary (WRD).
File No. ICD01-MJIR0IC05/19/2019-PROJECTS-I, Computer no. 811666.
SF/SC.
//FORWARDED::BY ORDER//
SECTION OFFICER