PART I EXTRAORDINARY

GOVERNMENT OF ANDHRA PRADESH

ABSTRACT

Water Resources Department - “Detailed Investigation, Designs and Construction of

Pump House, Associated Civil, Electro Mechanical Works, Electrical Sub Station

including installation and laying of MS Pressure Mains, Manifolds, Construction of

Delivery Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM

106.800 on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi

(M) of WG Dist under EPC Turnkey System” for Rs.68,85,00,000/- (Rupees Sixty

Eight Crores and Eight Five Lakhs only) - Administrative Approval – Accorded –

Orders-Issued.

WATER RESOURCES (PROJECTS.I) DEPARTMENT

G.O.Rt.No:119

Dated: 16/03/2023

Read:

From

the

Chief

Engineer,

Polavaram

Irrigation

Project,

Dowlaiswaram,

Lr.No.CE/PIP/DCE/OT1/AEE/RMC JLIS, Dated.26.02.2021, 29.06.2021, 24.09.2021,

04.02.2022 14.03.2022 and 25.05.2022.

ORDER:

In the reference read above the Chief Engineer, Polavaram Irrigation Project,

Dowlaiswaram has submitted proposal of Jagannadhapuram Lift Irrigation Scheme,

proposed on the Right Side of the Polavaram Irrigation Project Right Main Canal

near Jagannadhapuram (V) of Pedavegi (M) to irrigate an ayacut of 5268.66 Acs

(4786 Acs dry ayacut, duly deleting the same from Chinthalapudi LI Scheme and

supplementation of 482.66 Acs of wet crop) for utilization of 187.68 Mcft with peak

discharge of 54.25 cusecs at 16 Hrs of pumping per day.

2.

The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram, while

explaining the above, requested to issue necessary administrative sanction for the

Registered No. HSE-49/2016

No.392

AMARAVATI, TUESDAY, APRIL 18, 2023

G.35

NOTIFICATIONS BY GOVERNMENT

--x--

work of “Detailed Investigation, Designs and Construction of Pump House,

Associated Civil, Electro Mechanical Works, Electrical Sub Station including

installation and laying of MS Pressure Mains, Manifolds, Construction of Delivery

Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM 106.800

on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi (M) of WG

Dist under EPC Turnkey System” for Rs. 72,18,90,000/-.

3.

After careful examination, Government hereby accorded administrative

sanction for the work of “Detailed Investigation, Designs and Construction of Pump

House, Associated Civil, Electro Mechanical Works, Electrical Sub Station including

installation and laying of MS Pressure Mains, Manifolds, Construction of Delivery

Cistern and Canal / Piped System by gravity for Lift Irrigation Scheme at KM 106.800

on Right Side Bank of PIPRMC near Jagannadhapuram (V) in Peddavegi (M) of

West Godavari Dist under EPC Turnkey System” for Rs. 68,85,00,000/- (Rupees

Sixty Eight Crores and Eight Five Lakhs only ) in relaxation of FRBM Norms, subject

to the condition that the Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram

shall ensure i) correctness of quantities, leads, rates and data proposed in the

estimate ii) Designs & drawings shall got approved by the competent authority iii)

Supporting details for the proposed LS provisions shall obtained and iv) As LA is

involved, Land value certificate from the Revenue department shall obtained.

4.

The expenditure is chargeable to the head of account 4700 Capital Outlay on

Major Irrigation – 01 – Major Irrigation (Commercial) – MH 120 Polavaram Barrage –

GH 11 State Development Schemes – SH – 27 Canals and Distributaries – 530 –

Major Works – 531 OE. / 532 LA.

5.

The Chief Engineer, Polavaram Irrigation Project shall take necessary action

accordingly.

6.

This order issues with the concurrence of the Finance (FMU.WR.II)

Department vide their U.O. Note No. FIN01-FMU0MRAS (WR2)/35/2022-FMU-WR-

II, dated: 17.12.2022. (Computer No.1689188)

7.

This

order

is

available

on

online

and

can

be

accessed

at

http://apegazette.cgg.gov.in.

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

SHASHI BHUSHAN KUMAR

PRINCIPAL SECRETARY TO GOVERNMENT

To

The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram.

Copy to:

The Director of Works & Accounts, Mangalagiri.

The Pay and Account Officer, Mangalagiri.

The Finance (FMU-WR.II) Department.

The P.S. to Secretary to CM.

The P.S. to Minister (WRD).

The P.S. to Secretary (WRD).

File No. ICD01-MJIR0IC05/19/2019-PROJECTS-I, Computer no. 811666.

SF/SC.

//FORWARDED::BY ORDER//

SECTION OFFICER