PART I EXTRAORDINARY
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Water Resources Department – Polavaram Irrigation Project Head Works-
Administrative Approval to the work of "Investigation, Preparation of Designs &
Drawings and Execution of works of Scour Treatment, Construction of Parallel
Diaphragm Wall including improvements to Degraded D-wall in ECRF Dam Gap-I
and Gap-II " for an amount of Rs. 2020.05 Crores (Two Thousand Twenty Crores
and Five Lakhs only) & Permission to call for Tenders - Orders-Issued.
----------------------------------------------------------------------------------------------------------------
WATER RESOURCES (PROJECTS.I) DEPARTMENT
G.O.Rt.No.138 Dated: 10.04.2023
Read
From the Chief Engineer, Polavaram Irrigation Project, Lr.No.ENC/PIP/DCE-
1/AEE-1/MEIL/Vol6 dt.16.03.2023.
ORDER:
In the reference read above, the Chief Engineer, Polavaram Irrigation Project
while explaining the circumstances requested the Government to accord necessary
Administrative approval for the work of "Investigation, Preparation of Designs &
Drawings and Execution of works of Scour Treatment, Construction of Parallel
Diaphragm Wall including improvements to Degraded D-wall in ECRF Dam Gap-I
and Gap-II " with current SOR 2022-23 for an amount of Rs.2022.48 Crores and
accord approval for calling tenders under reverse tendering system.
2.
After careful examination, Government hereby accorded Administrative
Approval for the work of "Investigation, Preparation of Designs & Drawings and
Execution of works of Scour Treatment, Construction of Parallel Diaphragm Wall
including improvements to Degraded D-wall in ECRF Dam Gap-I and Gap-II " with
current SOR 2022-23 for an amount of Rs.2020.05/- Crores (Two Thousand and
Twenty Crores and Five Lakhs only) (the detailed provisions is annexure to this G.O)
Registered No. HSE-49/2016
No.394
AMARAVATI, TUESDAY, APRIL 18, 2023
G.37
NOTIFICATIONS BY GOVERNMENT
--x--
and also accord permission to the CE for calling tenders under reverse tendering
system.
3.
The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram shall ensure
i.
Reimbursement from the Ministry of Jal Shakti, Government of India of
the entire additional cost of the proposed work of scour treatment, etc.,
without recourse to the State exchequer.
ii.
Inclusion of the aforementioned work in the comprehensive revised
estimate of the Polavaram project.
iii.
Re-examination of the provision made in the estimate towards
insurance and seigniorage charges.
iv.
The correctness of rates, quantities and leads proposed in the
estimate.
v.
The design/drawings shall get approved by the competent authority.
vi.
The sand rate shall adopt as per the revised sand policy of the Govt.
from time to time.
4.
The expenditure is chargeable to the head of account 4700-01-120-12-26-
530-531.
5.
The Chief Engineer, Polavaram Irrigation Project shall take necessary action
accordingly.
6. This order issue with the concurrence of Finance (FMU.WR.II) Department vide
their
U.O.No.FIN01-FMU0MRAS(WR2)/37/2023-FMU-WR-II,
Computer
No:
2025678, dated:24.03.2023.
7.
This
order
is
available
on online
and
can
be
accessed
at
http://apegazette.cgg.gov.in.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
SHASHI BHUSHAN KUMAR
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Polavaram Irrigation Project, Dowlaiswaram.
Copy to:-
The Member Secretary, Polavaram Project Authority, Hyderabad.
The Engineer-in-Chief, Irrigation, Vijayawada.
The Director of Works & Accounts, Mangalagiri, Guntur District.
The Pay & Accounts office, Mangalagiri, Guntur District.
The Finance (FMU-WR.II) Department.
The P.S. to Secretary to CM
The P.S. to Minister (WRD)
The P.S. to Principal Secretary (WRD)
File No. ICD01-MJIR0IC28/43/2023-PROJECTS-I .Computer no. 2023179
SF/SC
//FORWARDED::BY ORDER//
SECTION OFFICER
Annexure to the G.O.Rt.No.138, Water Resources (Project.I) Department, Dated:
10.04.2023.
Polavaram Irrigation Project Head Works - "Investigation, Preparation of Designs &
Drawings and Execution of works of Scour Treatment, Construction of Parallel
Diaphragm Wall including improvements to Degraded D-wall in ECRF Dam Gap-I and
Gap-II " classified abstract
(Rs. in Crores)
S.No
Description of work
Amount
PART-A
1
Sand Filling in ECRF Dam Gap-I Scour Area
46.66
2
Vibro Compaction works in Gap-I
97.87
3
Sand Filling ECRF Dam Gap-II Scour Area
156.85
4
Vibro Compaction works in Gap-II
392.21
5
Sand filling beyond 100m berm on D/s Toe of U/s Coffer
Dam to U/s Toe of ECRF Dam in Gap-II
56.96
6
Vibro compaction works in 100-m berm at Toe of both
Coffer Dam including Trail Areas
213.30
7
Construction of Parallel Diaphragm wall at Scored
Portion including joining to original D-Wall and
restoration of Degraded D-Wall in ECRF Dam Gap-II
331.31
8
Surface De-watering in ECRF Dam Gap-II Area
127.91
9
Well Point Pumping system in ECRF Dam Gap II Area
149.00
10 Provision for Misc., works viz., Excavation of sand bed,
Removal of Pipes, Boulders and Damaged D-Wall
panels and Conducting Post ECPT tests etc.
55.67
Sub Total
1627.74
PART-B
2
GST@18%
306.34
3
1.63
4
Insurance @0.385%
6.27
5
Seigniorage charges
72.53
6
Investigation,
designs
and
drawings,
sub
soil
exploration, collection of samples, tender publication
charges, Xerox, Misc.
5.54
Grand Total
2020.05
SHASHI BHUSHAN KUMAR
PRINCIPAL SECRETARY TO GOVERNMENT