The 20th May, 2026
(Issued under Section 11(1) Read With Section 40(1) of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013)
(Invoking Urgency Clause)
No. LMD-13011(11)7/2026/304.—WHEREAS, it appears to the Governor, that a total of 51.683 Hectares
(516823.979 Sqm) of land is required at Tame Chung Chung, Bidak and Gelemo under Limeking Circle and
Taksing under Taksing Circle of Upper Subansiri District, Arunachal Pradesh for establishing elements of
Brigade Headquarters and Infantry Battalions of Indian Army.
A total of NIL/families are likely to be displaced due to the land acquisition. The reason necessitating
such as is given below.
The Deputy Commissioner, Daporijo, Upper Subansiri District, is appointed as Administrator for the
purpose of Rehabilitation and Resettlement/compensation of the affected families. Therefore, it is notified that
for the above said project in Tame Chung Chung, Bidak and Gelemo under Limeking Circle and Taksing under
Taksing Circle of Upper Subansiri District, a piece of land measuring 51.683 Hectares (516823.979 Sqm) of
standard measurement, whose detailed description is as follows, is under acquisition :-
SCHEDULE OF LAND
(Specification of Land)
SI.
District
Circle
Location
Requiring
Purpose
Area to be
Boundary
No.
of the Land
Authority
acquired
(in Ha)
1.
Taksing
Taksing
13.355 Ha
North : Private Land
South : Private Land
East
: Private Land
West
: Private Land
2.
Limeking
Tame
27.519 Ha
North : ITBP
Chung
South : Private Land
Chung
East
: Subansiri River
West
: Village Road/
Area
3.
Bidak
3.003 Ha
North : Private Land
South : Private Land
East
: River
West
: Road.
4.
Gelemo
7.806 Ha
North : Private Land
South : Private Land
East
: Road
West
: Private Land
Area
Total 51.683 Hectares
This notification is made under the provisions of Section 40(1) of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
A plan of the land may be inspected in the office of the Deputy Commissioner/Collector and DLRSO on
any working day during the working hours.
Establishing elements of Brigade Headquarters
and Infantry Battalions of Indian Army.
Indian Army
Upper Subansiri
2 The Arunachal Pradesh Extraordinary Gazette, 27th May, 2026
The Governor is pleased to authorize Deputy Commissioner, Daporijo, Upper Subansiri District/ Indian
Army (requiring Agency)., and their staff to enter upon and survey land, take levels of any land, dig or bore into
the sub-soil and do all other acts required for the proper execution of their work as provided and specified in
Section 12 of the said Act.
Under Section 11(4) of the Act., no person shall make any transaction or cause any transaction of land i.e.
sale/purchase, etc. or create any encumbrances on such land from the date of publication of such notification
without prior approval of the Collector.
The provisions of sub-section (1), (2) and sub-section (3) of Section 40 of the Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 are applicable to the
acquisition of the aforesaid land.
The provisions of Chapters- II and III and Sections 15 to 18 of the Act shall not apply to the acquisition
and declaration may be made under Section 19 in respect of the above land at any time after the date of
publication of the preliminary notification under sub-section (1) of Section 11;
The Collector (Deputy Commissioner), Upper Subansiri District, Arunachal Pradesh, though no award
has been, may, on expiration of thirty days from the publication of the notice mentioned in Section 21, take
possession of any land needed for a public/Defence purpose and such land shall thereupon vest absolutely in
the Government, free from all encumbrances; and
No additional compensation will be required to be paid for acquisition of the above land.
Since the land is urgently required for the project falling within the purview of Section 40(4), it has been
decided not to carry out the social impact assessment study.
A. K. Singh, IAS
Commissioner (Land Management),
Government of Arunachal Pradesh,
Itanagar.
—————