ORDERS BY THE GOVERNOR

ASSAM ELECTRICITY REGULATORY COMMISSION

NOTIFICATION

The 12th January, 2022

Û?œˆ¬≈Mê√ Ú•§1 - 768 ˚97

Registered No.-768/97

FIXATION OF THRESHOLD LIMIT FOR ANY INTRASTATE TRANSMISSION

PROJECTS AS PER CLAUSE 5.3 OF THE TARIFF POLICY DATED 28TH JANUARY 2016.

No. AERC.687/2018/79.- In exercise of powers conferred under Sections 181

read with sections 61, 66 & 86 of the Electricity Act, 2003 and in pursuance to Clause

5.3 of the TARIFF POLICY, 2016, the Assam Electricity Regulatory Commission (AERC)

hereby determines the threshold limit of Rs 100 Cr, irrespective of the voltage level for

all new development and augmentation schemes of Intra State transmission projects.

Above this threshold limit, all new and augmentation of intra State transmission

projects shall be developed through Tariff Based Competitive Bidding (TBCB) in

accordance with the guidelines issued by the State Transmission Utility (STU).

State Transmission Utility shall frame the said guidelines within three months

from the issue of this notification and notify the same after approval of the Commission.

Guwahati : Printed and Published by the Director, Directorate of Printing & Stationery, Assam, Guwahati-21.

Extraordinary Gazette No. 43 -300 + 10 - 18 - 01 - 2022. (visit at– dpns.assam.gov.in)

M. K. DEKA (RETD.),

Secretary,

Assam Electricity Regulatory Commission.