203 GI/2026
(1)
रजिस्ट्री सं. डी.एल.- 33004/99
REGD. No. D. L.-33004/99
xxxGIDHxxx
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग III—खण् ड 4
PART III—Section 4
प्राजधकार से प्रकाजित
PUBLISHED BY AUTHORITY
dsUæh; fo|qr fofu;ked vk;ksx
अजधसूचना
ubZ fnYyh] 24 fnlEcj] 2025
Lka- bZdks&,e12@2025&dsfofovk.—Þforj.k vuqKfIr/kkfj;ksa }kjk ÅtkZ dh mikfIRk ds fy, cksyh
çfØ;k }kjk VSfjQ dk vo/kkj.k djus gsrq ekxZn'kZd fl)karß ls lacaf/kr fo|qr ea=ky; dh le;≤ ij
;Fkkla'kksf/kr rkjh[k 19-01-2005 dh vf/klwpuk ds [kaM 5-6 ¼vi½ ds vuqlj.k esa] dsUnzh; fo|qr fofu;ked
vk;ksx dks fo|qr ea=ky; ds i= fnukad 13-04-2022 vkSj **'kfDr ¼Hkkjr esa dks;yk] ikjn'khZ :Ik esa vkcafVr
djus okys vkSj gkuZsflax ds fy, ;kstuk½ uhfr** fnukad 06-03-2019 ds ch¼I½] ch¼III½ vkSj ch¼IV½ ds v/khu
dks;ys ds vkcaVu lfgr ekWMy cksyh nLrkostksa ds v/khu ;FkkçnÙk fMtkbu] fuekZ.k] foÙk] LokfeRo vkSj
çpkyu ¼Mhch,Qvksvks½ vk/kkj vkSj lzksr bZa/ku ij LFkkfir FkeZy ikoj LVs'kuksa ls fo|qr dh nh?kZdkfyd
mikfIr ds fy, ekxZfunsZ'k** ds la'kks/ku ij fnukad 11-07-2022 ds çLrko ds vuqlj.k esa] dsfofovk Hkqxrku ds
iz;kstu ds fy, fuEufyf[kr o`f) njksa dks vf/klwfpr djrk gSA
सं. 27]
नई दिल्ली, िुक्रवार, िनवरी 9, 2026/पौष 19, 1947
No. 27]
NEW DELHI, FRIDAY, JANUARY 9, 2026/PAUSHA 19, 1947
सी.जी.-डी.एल.-अ.-09012026-269250
CG-DL-E-09012026-269250
2
THE GAZETTE OF INDIA : EXTRAORDINARY
[PART III—SEC.4]
mijksä ekxZfunsZ'kksa ds varxZr gq, ÅtkZ Ø; djkj ds vuqlkj forj.k vuqKfIr/kkfj;ksa }kjk ÅtkZ dh mikfIRk
gsrq lank; ds ç;kstu ds fy, fnlEcj 2025 gsrq ykxw ekfld o`f) njsa%
Ø-la-
fooj.k
Hkqxrku gsrq ekfld o`f)
nj
1-
vk;kfrr dks;ys ds fy, o`f) nj
7.88%
2-
vk;kfrr dks;ys ds ifjogu ds fy, o`f) nj
(-)2.15%
3-
vk;kfrr dks;ys dh varnsZ'kh; mBkbZ&/kjkbZ ds fy, o`f) nj
(-)0.03%
gjizhr flag çqFkh, lfpo
[जवज्ञापन-III/4/असा./602/2025-26]
CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
New Delhi, the 24th December, 2025
No. Eco-M12/2025-CERC.—In pursuance of Clause 5.6 (vi) of the Ministry of Power (MOP) Notification on
“Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees” dated
19.01.2005 as amended from time to time, MOP communication to the Central Electricity Regulatory Commission
(CERC) dated 13.04.2022, and MOP Resolution dated 11.07.2022 on an amendment to the “Guidelines for long term
Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO)
basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal under B (I), B(III)
and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India) Policy” dated
6.03.2019, the CERC notifies the following escalation rates for the purpose of payment.
Monthly Escalation Rates applicable for December 2025 for the purpose of payment for Procurement of Power
by Distribution Licensees as per the Power Purchase Agreement entered into under the Guidelines mentioned
above:
Sr.
No.
Description
Monthly Escalation Rates
for Payment
1
Escalation rate for imported coal
7.88%
2
Escalation rate for transportation of imported coal
(-)2.15%
3
Escalation rate for inland handling of imported coal
(-)0.03%
HARPREET SINGH PRUTHI, Secy.
[ADVT.-III/4/Exty./602/2025-26]
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.
SARVESH KUMAR
SRIVASTAVA
Digitally signed by SARVESH
KUMAR SRIVASTAVA
Date: 2026.01.09 22:43:30
+05'30'