dsUæh; fo|qr fofu;ked vk;ksx

अजधसूचना

ubZ fnYyh] 24 fnlEcj] 2025

Lka- bZdks&,e12@2025&dsfofovk.—Þforj.k vuqKfIr/kkfj;ksa }kjk ÅtkZ dh mikfIRk ds fy, cksyh

çfØ;k }kjk VSfjQ dk vo/kkj.k djus gsrq ekxZn'kZd fl)karß ls lacaf/kr fo|qr ea=ky; dh le;≤ ij

;Fkkla'kksf/kr rkjh[k 19-01-2005 dh vf/klwpuk ds [kaM 5-6 ¼vi½ ds vuqlj.k esa] dsUnzh; fo|qr fofu;ked

vk;ksx dks fo|qr ea=ky; ds i= fnukad 13-04-2022 vkSj **'kfDr ¼Hkkjr esa dks;yk] ikjn'khZ :Ik esa vkcafVr

djus okys vkSj gkuZsflax ds fy, ;kstuk½ uhfr** fnukad 06-03-2019 ds ch¼I½] ch¼III½ vkSj ch¼IV½ ds v/khu

dks;ys ds vkcaVu lfgr ekWMy cksyh nLrkostksa ds v/khu ;FkkçnÙk fMtkbu] fuekZ.k] foÙk] LokfeRo vkSj

çpkyu ¼Mhch,Qvksvks½ vk/kkj vkSj lzksr bZa/ku ij LFkkfir FkeZy ikoj LVs'kuksa ls fo|qr dh nh?kZdkfyd

mikfIr ds fy, ekxZfunsZ'k** ds la'kks/ku ij fnukad 11-07-2022 ds çLrko ds vuqlj.k esa] dsfofovk Hkqxrku ds

iz;kstu ds fy, fuEufyf[kr o`f) njksa dks vf/klwfpr djrk gSA

सं. 27]

नई दिल्ली, िुक्रवार, िनवरी 9, 2026/पौष 19, 1947

No. 27]

NEW DELHI, FRIDAY, JANUARY 9, 2026/PAUSHA 19, 1947

सी.जी.-डी.एल.-अ.-09012026-269250

CG-DL-E-09012026-269250

2

THE GAZETTE OF INDIA : EXTRAORDINARY

[PART III—SEC.4]

mijksä ekxZfunsZ'kksa ds varxZr gq, ÅtkZ Ø; djkj ds vuqlkj forj.k vuqKfIr/kkfj;ksa }kjk ÅtkZ dh mikfIRk

gsrq lank; ds ç;kstu ds fy, fnlEcj 2025 gsrq ykxw ekfld o`f) njsa%

Ø-la-

fooj.k

Hkqxrku gsrq ekfld o`f)

nj

1-

vk;kfrr dks;ys ds fy, o`f) nj

7.88%

2-

vk;kfrr dks;ys ds ifjogu ds fy, o`f) nj

(-)2.15%

3-

vk;kfrr dks;ys dh varnsZ'kh; mBkbZ&/kjkbZ ds fy, o`f) nj

(-)0.03%

gjizhr flag çqFkh, lfpo

[जवज्ञापन-III/4/असा./602/2025-26]

CENTRAL ELECTRICITY REGULATORY COMMISSION

NOTIFICATION

New Delhi, the 24th December, 2025

No. Eco-M12/2025-CERC.—In pursuance of Clause 5.6 (vi) of the Ministry of Power (MOP) Notification on

“Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees” dated

19.01.2005 as amended from time to time, MOP communication to the Central Electricity Regulatory Commission

(CERC) dated 13.04.2022, and MOP Resolution dated 11.07.2022 on an amendment to the “Guidelines for long term

Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO)

basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal under B (I), B(III)

and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India) Policy” dated

6.03.2019, the CERC notifies the following escalation rates for the purpose of payment.

Monthly Escalation Rates applicable for December 2025 for the purpose of payment for Procurement of Power

by Distribution Licensees as per the Power Purchase Agreement entered into under the Guidelines mentioned

above:

Sr.

No.

Description

Monthly Escalation Rates

for Payment

1

Escalation rate for imported coal

7.88%

2

Escalation rate for transportation of imported coal

(-)2.15%

3

Escalation rate for inland handling of imported coal

(-)0.03%

HARPREET SINGH PRUTHI, Secy.

[ADVT.-III/4/Exty./602/2025-26]

Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064

and Published by the Controller of Publications, Delhi-110054.

SARVESH KUMAR

SRIVASTAVA

Digitally signed by SARVESH

KUMAR SRIVASTAVA

Date: 2026.01.09 22:43:30

+05'30'