Haryana Government Gazette

EXTRAORDINARY

Published by Authority

© Govt. of Haryana

No. 196-2019/Ext.] CHANDIGARH, THURSDAY, NOVEMBER 21, 2019 (KARTIKA 30, 1941 SAKA)

HARYANA GOVERNMENT

INDUSTIES AND COMMERCE DEPARTMENT

Notification

The 21st November, 2019

No. 49/43/2015-4IB1.— In pursuance to the provision under Chapter 12 of Enterprises Promotion Policy-2015

notified vide No. 49/43/2015-4IB1 dated 14th August, 2015, the Governor of Haryana is pleased to notify the

“Energy Audit Scheme” for Micro, Small & Medium Enterprises. The scheme will consist of the following

provisions:

1.

Objective

The objective of the scheme is to identify areas where excess energy consumption or wastage of energy is

taking place. It involves measuring the actual energy consumption of various electrical gadgets used in the

premises, comparing it with an estimate of the minimum energy required to undertake the process and

establishing technically and economically feasible means to achieve the same & suggest best ways to optimize

the energy consumption leading to energy saving and cutting down electricity bills.

2.

Quantum of Assistance

75% reimbursement of cost of energy audit subject to a maximum of Rs. 2 lakh and 50% subsidy on cost of

capital equipments required for undertaking measures to conserve energy, subject to maximum of Rs. 20 lakh

shall be provided to an eligible Micro, Small & Medium Enterprise.

3.

Commencement and Applicability

The Scheme shall commence with effect from 15th August, 2015 and shall remain in operation for a period of

5 years. MSMEs which have undertaken energy audit and purchased equipments after 14th August, 2015 and

before 14th August, 2020 shall be eligible under this scheme.

4.

Eligibility Criteria

All MSMEs existing anywhere in the state, which have filed UAM/EM Part-II shall be eligible under the

scheme. Such enterprises shall be provided financial assistance only if the energy audit has been done by an

Energy Auditor certified by the Bureau of Energy Efficiency (BEE) or Energy Service Companies (ESCO)

listed on the website of BEE.

The detailed scope of energy audit is mentioned at Annexure-I. The eligible units must also comply with the

following conditions:

(i)

The item of manufacture should not fall in the restrictive list as notified by the State Government from

time to time.

(ii)

The assistance on cost of capital equipment will be provided only if, there has been at least 15%

reduction in average monthly energy consumption (electrical and thermal) compared with average of

previous 12 months before conducting of audit.

4324

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK 30, 1941 SAKA)

(iii)

Even after taking all steps as mentioned above for efficient use of energy, if actual electricity

consumption is increasing due to increase in production then such claim will be examined separately by

a committee to be constituted by the Director of Industries & Commerce.

(iv)

Investments in new plant, machinery and equipments focussed towards enhancing energy efficiency

shall only be eligible for subsidy under this scheme.

(v)

The applicant must obtain and submit an undertaking along with the purchase bill from machinery

supplier confirming that the rates quoted by the supplier are not higher than those quoted with other

private organizations.

(vi)

The energy audit report must contain three quotations from different authorized dealers/suppliers for the

recommended machine/capital equipment to be installed.

(vii)

In case of any discrepancy identified by the competent authority the audit report may again be validated

by HAREDA.

(viii) The unit should have obtained NOC/CLU from competent authority, if applicable.

(ix)

The unit should be in commercial production.

(x)

The unit should be in regular production at the time of disbursement. The assistance shall not be

released to a closed unit.

5.

Procedure

a.

Application on prescribed Form (Annexure-II) for the reimbursement of expenses incurred in

conducting energy audit & purchase of capital equipments along with listed documents would be

submitted to the Director of Industries & Commerce, on the web portal of the department within Six

months from the date of completion of energy audit/purchase of capital equipments.

b.

The application would be processed and examined. The deficiencies, if any, would be communicated to

the applicant in writing within a period of 10 working days and the applicant would be given a time

period of eight weeks to rectify the deficiencies so pointed out.

c.

In case the deficiencies are not removed within the prescribed period, the claim will be filed by the

Competent Authority, under intimation to the applicant through an e-mail. The enterprise shall not be

required to submit any additional document other than specified under Annexure-I without approval of

competent authority.

d.

A claim application so filed may be reopened with the orders of Principal Secretary Industries &

Commerce provided request for the same is received within a period of 30 days from the date of

rejection of the claim by the designated Competent Authority.

6.

Time Limit

An enterprise shall forfeit its entitlement for the reimbursement of the expenses incurred in conducting the

energy audit, if it does not submit its claim, complete in all respects within Six months from the date of

completion of energy audit/purchase of capital equipments.

7.

Competent Authority for sanction:

The Director Industries & Commerce shall be competent authority for sanction of assistance for medium

enterprises and Additional Director Industries shall be competent for sanction in respect of Micro & Small

Enterprises within 30 days from the date of completion of the claim.

8.

Interpretation/ Relaxation

Secretary Industries & Commerce, Haryana shall be competent to make interpretation/relaxation of any

provision of this scheme.

9.

Appeal

An appeal against an order passed by the Competent Authority shall lie with the Principal Secretary, Industries

& Commerce, Haryana within a period of 30 days from the date of communication of order appealed against.

The order passed by the Principal Secretary in appeal shall be final.

10.

Penal Action

At any time if it is found that assistance form government has been availed on the basis of any false

information, the applicant shall besides refunding assistance with compound rate of interest @ 12% per annum

and facing legal action, will be debarred from grant of any incentives/assistance from the State Government.

DEVENDER SINGH,

Additional Chief Secretary to Government Haryana,

Industries and Commerce Department.

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK. 30, 1941 SAKA)

4325

Annexure-I

Scope of Detailed Energy Audit

Study Overview

Our Area Of Detail Energy Audit Covers Following Areas:

1.

Study of Electricity Bills, Contract Demand & Power Factor & Loading Pattern.

2.

Power Distribution Study

3.

Electrical Systems Study

4.

Power Quality Analysis

5.

Diesel Gen Set Audit or any other Generator Audit.

6.

Motor Management

7.

Air Conditioning Study

8.

Thermal Study: Boilers/Furnaces/Incinerators.

9.

Compressor Study

10.

Pump systems

11.

Study Of Lighting System

12.

Thermo graph study.

13.

Techno Economic Study of Power & Fuel with distribution drawings

14.

Projects for Implementing the Energy Saving Measures

Study of lighting system:

Performance test of system installed

Calculating recommended luminance level for various tasks

Calculation of installed lighting load efficacy and installed load efficacy ratio

ILER Assessment

Finding areas for improvement

Light control: Recommendation & design for grouping of lighting system, installation of occupancy

sensors, installation of PLC based time based lighting control sensors, installation for exclusive

transformer for lighting

Selection of luminaries for efficiency and colors rendering index

Electrical energy audit:

Power factor improvement,

Max. Demand analysis, solution for avoiding penalties,

Most economical voltage level study,

Capacitor performance,

Calculation of specific power consumption (units/kg),

Adaptation of new Energy conservation technology etc.

Calculation of electricity cost on various machines

Bifurcations of power consumption spend on productive machines and utilities and their comparison

with the standards

Power Quality Audit (Harmonic Analysis):

Detailed harmonic analysis, quantifying losses occurring due to high level of harmonics prevailing in the

system, ways and means to mitigate the same to improve power factor in presence of harmonic polluted

environment.

D.G. Audit:

Calculation of specific fuel consumption (units/liters) on existing and different load condition, load

optimization on D.G. and suggest the scope of fuel saving, D.G. efficiency trials, load bearing capacity of D.G.

set, checking of general maintenance and suggest measures to achieve better fuel efficiency, power factor

suggestions, techno-economic study of new D.G., solution for problems etc.

Automation & Modification:

Detail analysis of system, product up gradation by value engineering, study and need of drives, sensors & PLC

etc. analysis of feedback control in compressor D.G, humidification towers etc, development of on line

4326

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK 30, 1941 SAKA)

monitoring & control system, need base implementation of SCADA (supervisory control and data acquisition

system)

Motor Management:

Motor’s addressing and coding, general checks for installation safety and starting, check for the level of

heating etc, general procedure for overhaul of motors, critical checkpoints of motor after rewinding ,motor’s

performance evaluation incorporating percentage loading, formulation of maintenance schedule.

Compressor Study:

Evaluating Efficiency-EPI

Air Leakage losses

Evaluating actual CFM/KW generation

Designing system for energy saving on compressor as per requirement

Air Conditioning Study:

Evaluating tonnage & system efficiency

Determining CFM/KW for each supply fan

Determining Fan efficiency

Determining Pump efficiency

Evaluating insulation of ducts

Determining plant heat load requirement

Evaluating CFM required to match plant’s heat load

Determining actual CFM flow on shop floor inside plant

Ways & means for conservation of energy

Thermal audit:

Boiler efficiency evaluation & measures of improvement, efficient steam distribution & utilization, waste heat

recovery system, optimization of steam pressure for generation distribution and utilization, insulation/radiation

loss calculation, steam pipe line study, pressure optimization for fuel saving, flue gas analysis, use of alternate

energy resources, water quality analysis, adaptation of new technology, process optimization for fuel saving

etc. (saving can be achieved in the terms of 10-20%).

The following Meters shall be used during audit as per requirement.

S. No.

Type of Instrument

1

Three Phase Power Analyzer

2

CT (AC)- 1000/5 Amps.- 3 Nos.

1

Three Phase Power Analyzer

2

CT (AC)- 1000/5 Amps.- 3 Nos.

3

CT (DC)- 1000/5 Amps.- 3 Nos.

4

CT (AC)- 6000/5 Amps.- 3 Nos.

5

Portable flue Gas Analyzer

6

Hand Held Techo- Meter

7

Lux-Meter

8

Digital Clamp Meter

9

Digital Power Meter

10

Digital Infra Red Thermo Meter

11

Digital Temperature and Humidity meter

12

Pitot Tube anaemometer

13

Manometer

14

Digital Ultrasonic transit flow meter

15

Bomb Calori Meter

16

Digital Infra Red scanner

17

Thermal imager

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK. 30, 1941 SAKA)

4327

Annexure-II

Application Form for Detailed Energy Audit

S. No.

Description

1.

Name of the Applicant (Authorised person of the unit)

2.

Name & factory address of the unit with telephone no.

and e-mail

3.

Registered Office address

4.

Category of unit (Micro/ Small/ Medium)

5.

EM Part-II/Udyog Aadhar No. & Date

6.

Date of commencement of commercial production (As

per first sale bill)

7.

Item of manufacture

8.

Constitution of the Unit [Proprietary, Partnership, Pvt.

Ltd., Public Ltd., LLP (Limited Liability Partnership)]

9.

Sector/ type of Industry

10.

No. of Employees

11.

Name of the Energy Audit agency

12.

Total amount & details of expenditure incurred for

conducting Energy Audit

13.

Total Reimbursement claimed against Energy Audit

14.

Details of investment made

15.

Details of All Energy using processes and equipment

including Cooling Tower etc.

16.

Amount of Electricity Bills of last 12 Months

17.

Capacity of Transformers

18.

Contract Demand and Connected load

19.

Cost & Details of Power Factor control Equipment

installed

20.

Cost & Details of DG sets installed with capacity

1.

2.

3.

21.

Cost & Details Thermal Equipment installed (Like

Boiler, Furnace etc.)

22.

Cost & Details of compressed Air Equipment installed

23.

Cost & Details of Welding machines installed

24.

Cost & Details of Pneumatic Air Tools installed

25.

Cost & Details of any other energy consuming

equipment installed

26.

Total cost of the equipments installed for energy saving

(in Rs.)

4328

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK 30, 1941 SAKA)

S. No.

Description

27.

Amount of subsidy claimed @50% of the total cost of

energy saving equipments

28.

Amount of assistance obtained from Government of

India, if any

29.

Self attested copies of documents to be attached with the

application:

1.

Acknowledgement of Entrepreneur Memorandum (EM) part-II.

2.

Certificate of Incorporation/ Partnership deed.

3.

Board resolution/ Power of attorney

4.

Change of Land Use (CLU)/ NOC from competent authority, if applicable.

5.

Copy of first sale bill.

6.

Copy of Energy audit certification.

7.

CA certificate of Expenditure (in original) giving the details ( as per prescribed format)

8.

Copy of the bills raised by certifying agency and proof of payment thereof.

9.

Audited balance sheet of the unit of last year.

Signature of the applicant

(with seal)

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK. 30, 1941 SAKA)

4329

Annexure-III

Undertaking/Declaration (to be submitted on non-judicial stamp paper of Rs. 50/- (Min) duly sworn before a Notary

Public (duly affixed with Notarial Stamp; and with Notary Seal & Notary Registration Number) or First Class

Magistrate):

I,_____________ do hereby solemnly state that I am proprietor/ partner/ director/_________________of

M/s_______________________ located____________ which is engaged in the manufacture of____________ and I

have been authorized to file the claim of Energy Audit & subsidy on purchase of capital equipment for energy

conservation with the Department of Industries and Commerce, Haryana.

2.

I do hereby affirm that the particulars given in the application are correct. In case any of the statement/

information furnished in the application/ documents later found to be wrong or incorrect or misleading, I do hereby

undertake to refund the entire amount of assistance of Rs.__________ (Rupee_____________________________)

granted to me at the compound rate of interest @12% per annum, besides facing legal action in case facts contained

in this application are proved to be wrong at the time of verification/ checking or otherwise at any stage.

Dated:

Signature of the Proprietor/Partner/

Managing Director/Director

(with seal)

4330

HARYANA GOVT. GAZ. (EXTRA.), NOV. 21, 2019 (KRTK 30, 1941 SAKA)

Annexure-IV

Certificate from Chartered Accountant in respect of Proof of Expenditure incurred for conducting energy audit and

about investment in plant & machinery (on a CA letter head)

To whom it may concern

The document & records of M/s .................... with their regd. office at .......... and factory located at ...............

and EM no............... dated .......... ) in respect of the expenditure incurred in conducting energy audit have been

verified, and it is certified that the said company have incurred a total expenditure of Rs. .......... (Rupees ..........)

towards, Application fee, assessment/ audit fee, annual fee/ licence fee, training, calibration and technical consultancy

etc. (excluding hotel & travel expenses & surveillance charges) in conducting energy audit from the certification

agency namely........... as per the following details of payments.

Details of payments (Name of certification agency/ org.) amount paid (in rupees)

(a)

Application fee paid to ................................................

(b)

Assessment/audit fee paid to .....................................

(c)

Annual fee/ licence fee paid to ...................................

(d)

Calibration charges paid to ..........................................

(e)

Technical consultancy charges paid to .........................

(f)

Training expenses paid to ............................................

Total ..........................................

AND

Verified from the books of accounts & records of above firm that the cost of capital equipments installed for

energy conservation is Rs..............

AND

Verified from the books of accounts of above firm that the total investment in plant and machinery (original

purchase value) of the unit as on date............. stands as Rs.................. (Rupees ................)

Name & signature of the Chartered Accountant

with stamps & CA membership number

Dated ......................

Payment at (a) to (f) above should be supported by copies of receipts of payments made to the certification

agency duly attested. The payment receipts must indicate the purpose for which the payments have been made to the

certification agency.

57496—C.S.—H.G.P., Chd.