अन्तिम समेकन स्कीम
Øekad 10054-59/4W.— न्िस्िार मसूदपुर राजिाह के न्नमााण के न्िए बुजी न० 63350 से 84000 न्नकासी
स्ििः बुजी न० 235768- दाए, हाांसी ब्ाांच गाांि िोहारी राघो, िहसीि नारनौंद और गाांि ठरिा, िहसीि हाांसी,
न्जिा न्हसार (Constructing Extension of Masudpur Disty. from RD 63350 to 84000 off taking at
RD 235768- R Hansi Branch in Village Lohari Ragho, Tehsil Narnaund and Village Tharwa,
Tehsil Hansi, District Hisar) पररयोजना के सम्बतध में हररयाणा पररयोजना भून्न समेकन (न्िशेष उपितध)
अन्धन्नयम, 2017 की धारा ि हररयाणा पररयोजना भून्म समेकन (न्िशेष उपबतध) न्नयम, 2018 के न्नयम 3
(iii) के अतिगाि पररयोजना भून्म की प्रारूप समेकन स्कीम अन्धसुन्चि की जा चुकी है न्जसके पैरा नां० 10 ि
धारा 8 (2) ि न्नयम 3 (iii) के िहि कोई आक्षेप इस कायाािय में प्राप्त नहीं हुआ। अिः अन्धन्नयम की धारा िथा
न्नयम 3(v) के अतिगाि स्कीम प्रारूप को अन्तिम समेकन स्कीम का रूप िदया जािा है न्जसका न्ििरण न्न्
प्रकार से है:-
पैरा न०-1
हररयाणा राज्य के पन्िम क्षेत्र न्जिा न्हसार िहसीि नारनौंद ि हाांसी में हररयाणा सरकार के ससांचाई
एिां जि सांसाधन न्िभाग द्वारा न्िस्िार मसूदपुर राजयाह के न्नमााण के न्िए बुजी ग० 63350 से 84000
न्नकासी स्ििः बुजी न० 235768-दाांए, हाांसी ब्ाांच गाांि िोहारी राघो, िहसीि नारनौंद और गाांि ठरिा,
िहसीि हाांसी, न्जिा न्हसार पररयोजना हेिू अन्धसूचना िदनाांक 18.06.2021 द्वारा गाांि िोहारी राघो, हदबस्ि
न० 82, का कुि रकबा 17.24 एकड़ ि गाांि ठरिा, हदबस्ि न० 84, िहसीि हाांसी का कुि रकबा 1.94 एकड़
उक्त माइनर न्नमााण हेिू कुि 19.18 एकड़ पररयोजना भून्म अन्धसून्चि िकया हुआ है। उक्त 19.18 एकड़ में से
भू-स्िान्मयों द्वारा अपनी इच्छा से कुि भून्म का 70 प्रन्िशि से अन्धक क्षेत्र की सेि डीड ससांचाई न्िभाग के नाम
4076
HARYANA GOVT. GAZ. (EXTRA.), DEC. 23, 2024 (PAUS. 2, 1946 SAKA)
करिाई जा चुकी हैं। ित्पिाि् उपरोक्त पररयोजना हेिू आिश्यक शेष न्नजी भून्म 7 कनाि 15 मरिे के कारण
पररयोजना की व्यिहायािा हेिु पररयोजना भून्म को हररयाणा पररयोजना भून्म समेकन (न्िशेष उपबतध)
अन्धन्नयम, 2017 की धारा 5 में समेकन हेिु अन्धसून्चि करिाया जा चुका है।
पैरा न०- 2
पररयोजना भून्म के रूप में घोन्षि पररयोजना भून्म की 70 प्रन्िशि से अन्धक भून्म हररयाणा न्सचाांई ि
जि सांसाधन न्िभाग द्वारा खरीदी की जा चुकी है। उक्त अन्धन्नयम की धारा 3 के अनुसार पररयोजना की
व्यिहायािा हेिु शेष न्नजी भून्म के भू-खण्डों के दृन्िगि समस्ि पररयोजना भून्म का समेकन िकया जाना है न्जस
पर हररयाणा पररयोजना भून्म समेकन (न्िशेष उपितध) अन्धन्नयम, 2017 िथा हररयाणा पररयोजना भून्म
समेकन (न्िशेष उपबतध) न्नयम, 2018 िागू िकए गए हैं।
पैरा न०- 3
पररयोजने भून्म के समेकन को काया को करने हेिु पररगाणा पररयोजना भून्म समेकन (न्िशेष उपबतध
अन्धन्नयम, 2017 की पारा 4(1) के अतिगाि उपमण्डि अन्धकारी (ना०) को नारनौद िहसीि के क्षेत्र में न्स्थि
पररयोजना भून्म के समेकन हेिु सक्षम प्रान्धकारी को रूम में घोन्षि कर शन्क्तयाां प्रदान की गई हैं और उनको
इस काया के सहयोग के न्िए आिश्यकिा अनुसार हल्का पठिारी, हल्का न्गरदािर ि अतय कमाचारी उपिब्ध है।
सक्षम प्रान्धकारी द्वारा हररयाणा पररयोजना भून्म समेकन (न्िशेष उपबतध) न्नयम, 2018 के न्नयम 3 के
अतिगाि शन्क्तयों, कायों िथा किाव्यों का न्निाहन िकया गया है।
पैरा न०-4
इस पररयोजना की भून्म समेकन हेिु प्रारन्म्भक ररकाडा िैयार िकया जायेगा न्जसमें गाांि के इतडेसस
नम्बरान खसरा, सजरा िजिीजी, पररयोजना चकबतदी, खिौनी, फील्ड बुक, ििीमा राजरा, रजुिेशन समेकन,
पास बुक िैयार की जायेगी और पररयोजना भून्म के न्िए इस अन्तिम समेकन स्कीम के अनुरूप कायािाही अमि
में िाई जायेगी।
पैरा न०-5
पररयोजना के समेकन की प्रिकया के दौरान का एक मसाििी कमेटी का गठन िकया गया है जो िक
न्न्िि है।
1.
उपमण्डि अन्धकारी (ना०), नारनौंद-सह-सक्षम प्रान्धकारी, नारनौंद।
2.
श्री सतदीप कुमार माथुर, कायाकारी अन्भयतिा, जि सेिाएां मण्डि हाांसी।
3.
श्री महेतर ससांह पुत्र श्री कुडा राम्, भून्म-धारक।
4.
श्रीमिी चतरकातिा, पूिा सरपांच, िोहारी राघो।
5.
श्री सिपाि, नम्बरदार, िोहारी राघो।
6.
श्री मुनीष कुमार, सरबरा नम्बरादार िोहारी राघो।
7.
श्री रमेश कुमार, नम्बरदार, िोहारी राघो।
8.
श्री पिन चातदना पुत्र श्री रामिुभाया िकसान ि गाांि में भून्म-धारक।
9.
श्री राजकुमार पुत्र श्री दयानतद, न्निासी डाटा।
10.
श्री प्रन्िम चाििा पुत्र श्री जसिांि राय, िकसान ि गाांि में भून्म-धारक।
11.
श्री अन्नि कुमार पुत्र श्री जयदयाि, िकसान ि गाांि में भून्म-धारक।
12.
श्री मेहर ससांह शुद्ध श्री जीिन ससांह, िकसान ि गाांि में भून्म-धारक।
13.
श्री राांझा राम पुत्र श्री नादर राम्, ग्रामीण।
14.
श्री राजकुमार पुत्र श्री नानक, ग्रामीण।
HARYANA GOVT. GAZ. (EXTRA.), DEC. 23, 2024 (PAUS. 2, 1946 SAKA)
4077
15.
श्री सिीश कुमार पुत्र श्री रागनाथ, भून्म-धारक।
16.
श्री रामफि पुत्र श्री िेिू राम, िकसान ि गाांि भून्म-धारक।
17.
श्री कृष्ण कुमार, नम्बरदार
पैरा नo-6
न्िस्िार मसूदपुर राजयाह के न्नमााण के न्िए बुजी न० 63350 से 84000 न्नकासी स्ििः बुजी
न०235768 –दाए, हाांसी ब्ाच गाांि िोहारी राघो, िहसीि नारनौंद और गाांि ठरिा, िहसीि हाांसी, न्जिा
न्हसार पररयोजना की कुि पररयोजना भून्म 19.18 एकड़ है न्जसमें गाांि िोहारी राघो, हदबस्ि न० 82,
िहसीि नारनौंद, न्जिा न्हसार िक 17.24 एकड़ ि गाांि ठरिा, हदबस्ि न० 84, िहसीि हाांसी, न्जिा न्हसार
िक 1.94 एकड़ शान्मि है न्जसमें शजरा अनुसार गाांि िोहारी राघो के मुरब्बा नम्बर 81, 90, 115, 122,
148, 156, 183, 193, 218, 219, 232, 253, 267, 268, 286, 287, 288, 294, 295, 296, 318 से
सम्बन्तधि िकिा गम्बरान न्जनका कुि रकबा 17.24 एकड उक्त पररयोजना हेिु ररजिा रहेगा।
पैरा न०-7
पररयोजना के समेकन हेिु हररयाणा पररयोजना भून्म समेकन (न्िशेष उपबतध) अन्धन्नयम, 2017 की
धारा 6 के प्रािधानों के अनुरूप न्नजी भून्म के रह गए भू-खण्डो के स्िान्मयों को नोरटस जारी िकए गए।
ित्पिाि् केिि दो व्यन्क्तयों का उक्त नोरटस/अन्धसूचना के सम्बतध में प्रन्ििेदन प्राप्त हुआ ि उन द्वारा सरकार
द्वारा जारी िकए जाने िािे िकसी (कम्पनसेशन) पर अपना दािा िकया गया। अतय िकसी भू-स्िामी द्वारा धारा 7
में उपिब्ध दो न्िकल्पों में से िकसी एक का प्रयोग नहीं िकया गयाां है। अिः धारा 7 ि 8(1) में प्रदत्त शन्क्तयों का
प्रयोग करिे हुए धारा 7(i) के न्िकल्प का न्िन्निय करिे हुए शेष भून्म जो उक्त पररयोजना से सम्बन्तधि है का
प्रन्िकर (कम्पनसेशन) किेसटर दर जमा बीस प्रन्िशि के आधार पर पररयोजना भून्म के समेकन हेिु यह अन्तिम
समेकन स्कीम अन्धसून्चि की जािी है।
पैरा न0-8
न्िस्िार मसूदपुर राजयाह के न्नमााण के न्िए बुजी न0 63350 से 84000 न्नकासी स्ििः बुजी न०
235768-दाांए, हाांसी ब्ाांच गाांि िोहारी राघो, िहसीि नारनौंद और गाांि ठरिा, िहसीि हाांसी, न्जिा न्हसार
पररयोजना की कुि पररयोजना भून्म 19.18 एकड़ है न्जसमें गाांि िोहारी राघो हदबस्ि न० 82 िहसीि
नारनौंद, न्जिा न्हसार की पररयोजना भून्म के समेकन पिाि् 17.24 एकड़ के सभी भूस्िान्मयों का मािकाना
हक खत्म हो गया है िथा न्नधााररि प्रििया अनुसार पररयोजना भून्म के क्षेत्र का उक्त सरकारी न्िभाग के पक्ष में
इतिकाि िकया जाएगा।
पैरा न0. 4
न्िस्िार मसूदपुर राजबाह के न्नमााण के न्िए बुजी न० 63350 से 84000 न्नकासीं स्ििः बुजीं न०
235768-दाांए, हाांसी ब्ाांच गाांि िोहारी राघो िहसीि नारनौंद और गाांि ठरिा, िहसीि हाांसी, न्जिा न्हसार
पररयोजना की पररयोजना भून्म के समेकन के दौरान िकसी भूस्िामी की भून्म में चाह, कोठरी/कमरा, मकानाि,
बाग, ट्यूिैि आिद न्नर्माि िकया हुआ पाया जाएगा िो इस प्रकार के ढाांचे की कीमि का आकिन कायाकारी
अन्भयतिा, पी०डब्ियु०डी० (बी० एण्ड आर०) द्वारा करिाया जाएगा ि पाये जाने िािे ढाांचे की आकिन पर
न्नधााररि की गई कीमि के अनुसार प्रन्िकर (कम्पनसेशन) सम्बन्तधि भू-स्िामी को अदा की जािेगी|
पैरा न0-10
सक्षम प्रान्धकारी एिां उपमण्डि अन्धकारी (ना०), नारनौंद द्वारा 2017 के अन्धन्नयम की धारा 9 ि
न्नयम 3(v) के अनुसार यह अन्तिम समेकन स्कीम िैयार िक गई है न्जसकी अन्धसूचना के प्रकाशन पिाि् स्कीम
से कोई प्रभान्िि व्यन्क्त उपायुक्त, न्हसार के समक्ष अपीि कर सकिा है।
4078
HARYANA GOVT. GAZ. (EXTRA.), DEC. 23, 2024 (PAUS. 2, 1946 SAKA)
पैरा न०-11
कोई अपीि के प्राप्त ना होने की न्स्थन्ि में ि प्राप्त होने पर प्राप्त न्नणाय अनुसार सक्षम प्रान्धकारी द्वारा
2017 के अन्धन्नयम की धारा 10 और न्नयम 3(vi) के अनुरूप इस अन्तिम समेकन स्कीम अथिा सांशोन्धि
अन्तिम समेकन स्कीम, उपायुक्त, न्हसार के िकसी प्राप्त अपीि पर न्नणाय अनुसार जैसी न्स्थिी हो, अनुरूप न्नजी
भून्म के रह गए भूखतडो का कब्जा न्िया जाएगा ि प्रन्िकर (कम्पनसेशन) सांन्ििररि िकया जाएगा ि ित्पिाि्
धारा 11 ि न्नयम 7 के अनुरूप अन्तिम समेकन स्कीम के अनुसार ससांचाई जि सांसाधन न्िभाग के पक्ष में राजस्ि
अन्भिेख को अद्यिन िकया जाएगा |
¼gLrkå½---]
mie.My vf/kdkjh ¼uk0½] ukjukSan ,oa
vf/kfu;e ds vUrxZr l{ke izkf/kdkjhA
HARYANA GOVERNMENT
IRRIGATION DEPARTMENT
Notification
The 23rd December, 2024
Final Consolidation Scheme
No. 10054-59/4W.— A Draft Consolidation Scheme for project "Constructing Extension of Masudpur
Distributory from RD 63350 to 84000 off taking at RD 23578-R Hansi Branch in Village Lohari Ragho, Tehsil
Narnaund and Village Tharwa, Tehsil Hansi, District Hisar" under section 8 of Haryana Consolidation of Project
Land (special provision) Act, 2017 and Rule 3(3) of Haryana Consolidation of Project, Land (special provision)
Rules, 2018 has been notified under which no objection has been received in this office under Para No. 10 of the draft
scheme and section 8(2) of the act and rule 3(iii) there under. Therefore, under section 9 and rule 3(v) of the Act, the
draft scheme is now published as final consolidation scheme, the details of which are as follows:-
Para No. 1
In the western part of State of Haryana in Tehsil Narnaund & Hansi of District Hisar, a project of Constructing
Extension of Masudpur Disty, off taking at RD 235768-R Hansi Branch a total area 19.18 acre has been notified as
project land vide notification dated 18.06.2021 by the Haryana Irrigation & Water Resources Department with land in
village Lohari Ragho Hadbast No. 82 having area 17.24 acre and in village Tharwa that of 1.94 acre area. The land
owners have voluntarily executed sale deeds of above 70% area of the project land in favour of Haryana Irrigation &
Water Resources Department. For necessary land of the remaining left out pockets of private land measuring 7 Kanal
15 Marla for the viability of the project, the project has been notified for consolidation under section 5 of the Haryana
Consolidation of Project Land (special provision) Act, 2017.
Para No. 2
More than 70% of the project land has been purchased by the Irrigation & Water Resources Department, Govt.
of Haryana. According to section 3 of the above act, all the project land has to be consolidated in light of the
remaining private land plots to ensure the viability of the project on which The Haryana Consolidation of Project
Land (Special provision) Act, 2017 and The Haryana Consolidation of Project Land (Special provision) Rules, 2018
have been applied.
Para No. 3
For carrying out the work of consolidation of project land, under section 4(1) of the Haryana Consolidation of
Project Land (Special provision) Act, 2017 the Sub Divisional officer (Civil) Narnaund has been declared as
competent authority for Consolidation of the project land located in the area of Tehsil Narnaund and to support him in
this work Halqa Patwari, Halqa Girdawar and the other staff are available as per the requirement. The powers,
functions and duties are to be discharged by the competent authority as provided under rule 3 of The Haryana
Consolidation of Project land (special provision) Rules, 2018.
Para No. 4
Preliminary records will be prepared for the land consolidation of this project, in which index of Khasra
numbers, Sajra tajviji, Project Chakbandi, Khatauni, Field book, Tatima Sijra, resolution consolidation, pass book
will be prepared and action shall be implemented according to the prepared final consolidation scheme for the project
land.
HARYANA GOVT. GAZ. (EXTRA.), DEC. 23, 2024 (PAUS. 2, 1946 SAKA)
4079
Para No. 5
A Masavarti Committee has been constituted during the process of consolidation of the project. The formation
of Masavarti Committee of the following members has been approved/recommended in the presence of several land
owners present in the meeting for Masavarti Committee in village Lohari Ragho on 02.10.2021.
1.
Sub Divisional Officer(Civil) Narnaund-cum-Competent Authority, Narnaund.
2.
Sh. Sandeep Kumar Mathur, Executive Engineer, Hansi water Services Division Hansi.
3.
Sh. Mahendra Singh s/o Shri Kuda ram landholder.
4.
Smt. Chander Kanta, former Sarpanch Lohari Ragho.
5.
Sh. Satpal, Numberdar Lohari Ragho.
6.
Sh. Munish Kumar, Sarbra Numberdar, Lohari Ragho.
7.
Sh. Ramesh Kumar, Numberdar, Lohari Ragho.
8.
Sh. Pawan Chandana s/o Shri Ramlubhaya, farmer and land holder in the village.
9.
Sh. Rajkumar s/o Sh. Dayanand resident.
10.
Sh. Pratim Chawla, s/o Jaswant Rai, farmer and land holder in the village.
11.
Sh. Anil Kumar s/o Mr. Jaldayal, farmer and land holder in the village.
12.
Sh. Meher s/o Mr. Jeevan Singh, Farmer and land holder in the village.
13.
Sh. Ranjha Ram s/o Sh. Nanak, Villager.
14.
Sh. Rajkumar s/o Sh. Nanak, Villager.
15.
Sh. Satish Kumar s/o Sh. Ramnath, Land holder.
16.
Sh. Ramphal s/o Sh. Telu Ram, farmer and village land holder.
17.
Sh. Krishan Kumar, Nambardar.
Para No. 6
The total Project Land of the project Constructing Extension of Masudpur Disty. from RD 63350 to 84000 off
taking at RD 23578-R, Hansi Branch in village Lohari Ragho, Tehsil Narnaund and village Tharwa, Tehsil Hansl,
District Hisar is 19.18 acres in which 17.24 acres is from village Lohari Ragho, Hadbast No. 82, Tehsil Narnaund
District Hisar and 1.94 acre is from village Tharwa Hadbast No. 84 Tehsil Hansi District Hisar in which as per the
Aks-Shijra of village Lohari Ragho Kila numbers related to rectangle no. 81, 90, 115, 122, 148, 156, 183, 193, 218,
219, 232, 253, 267, 268, 286, 287, 288, 294, 295, 296, 318 having total area of 17.24 acres shall be reserved for the
said project.
Para No. 7
As per the provisions of section 6 of Haryana Consolidation of Project Land (Special Provisions) Act, 2017,
notices were issued to the owners of the remaining plots of private land for the consolidation of the project.
Thereafter, representations of only two persons were received in respect of the said notices/notification in which both
of them made claim, as per their shareholding, on any compensation to be issued by the Govt. Neither of the two
options available under the section 7 has been exercised by any other land owner. Therefore, in exercise of power
conferred by section 7 and 8(1), while deciding the option of section 7(1) for compensation this final consolidation
scheme is being notified for the consolidation of the project land with compensation of the remaining land related to
the project disbursed on the basis of the option of Collector Rate plus twenty percent.
Para No. 8.
Project Constructing extension of Masudpur Disty, from RD 63350 to 84000 off taking at RD 235768-R Hansi
Branch in village Lohari Ragho Tehsil Narnaund & village Tharwa Tehsil Hansi Distt. Hisar has a total project land is
19.18 acres in which the ownership rights of all the land owners of 17.24 acres land Village Lohari Ragho, Hadbast
No. 82, Tehsil Narnaund, Distt. Hisar, have extinguished, and mutation of the area of project land will be done in
favour of before mentioned department of the Govt. In accordance with the prescribed procedure.
Para No. 9
During the consolidation of project land of Constructing extension of Masudpur Disty. from RD 63350 to
84000 off taking at RD 235768-R Hansi Branch in village Lohari Ragho Tehsil Narnaund & village Tharwa Tehsil
Hansi Distt: Hisar if any chah, kotha/room, house, orchard, tubewell etc. Is found to have been constructed then the
value of such building/structure will be got assessed from the Executive Engineer, PWD (B&R) and compensation
will be paid to the concerned land owners as per the value determined after such assessment.
4080
HARYANA GOVT. GAZ. (EXTRA.), DEC. 23, 2024 (PAUS. 2, 1946 SAKA)
Para No. 10
This Final consolidation scheme has been prepared by the competent authority-cum-Sub Divisional Officer
(Civil), Narnaund in accordance with section 9. and Rule 3(v) of the 2017 Act. After the publication of the
notification of this final consolidation scheme appeal can be filed by any aggrieved person before the Deputy
Commissioner, Hisar.
Part No. 11
In case no appeal is received, or as per orders on the appeals received, then in accordance with section 10 of
the Act of 2017 and rule 3(vi) the possession of remaining plots of private land shall be taken by the competent
authority as per this final consolidation scheme or the modified final consolidation scheme, as the case may be in
accordance with orders in any received appeal by the Deputy Commissioner, Hisar, and compensation will be
disbursed and thereafter, in accordance with the provisions under section 11 and rule 7, the revenue records will be
updated in favour of Irrigation & Water Resources Department, as per the final consolidation scheme.
(Sd.)…,
Sub Divisional Officer (C),
Narnaund-cum-Competent Authority.
11493—C.S.—H.G.P., Pkl.