Notification

The 30th January, 2026

No. 2/13/2025-1E.— In continuation of the Energy Department, Government of Haryana Notification

No. 2/13/ 2025-IE dated 02.12.2025, whereby a committee comprising the following members was constituted to

examine and resolve issues relating to the PPA/SPPA of M/s Adani Power Limited (APL).

(a)

Hon'ble Mr. Justice Krishna Murari, former Judge. Supreme Court of India

Chairman

(b)

Sh. S.D. Dubey, former Chairman, Central Electricity Authority (CEA)

Member

(c)

Sh. T.C. Gupta. IAS (Retd.). Chief Commissioner. Haryana Right to Service Commission

Member

The Governor of Haryana hereby notifies the following Terms of Reference of the High-Power Committee:-

(i)

The committee should examine and analyze all the relevant documents related to the APL Mundra TPP

Units 7 to 9.

(ii)

Analyze and ascertain any hardship faced by Adani Power Limited (APL) – If yes, mode and manner

for mitigating the hardship faced by APL duly considering all the actual costs incurred by APL for

delivery of power at Haryana periphery as compared to the quoted energy charge rate under the PPA.

(iii)

Call HPPC and APL for submission of details/ clarification as required by the committee.

(iv)

To find amicable solution for all the pending claims and counter claims of both Haryana Discoms and APL.

(v)

Rights and obligations of APL and Haryana Discoms in relation to the Payment Security Mechanism

(PSM) under the PPAs.

(vi)

Examine the viability of PPA with existing tariff structure and suggest mitigation measures to ensure

long term viability.

(vii)

Any other relevant issue which the High-Power Committee would like to examine and advice.

(viii) Suggest sustainable solution(s) - for resolving the issues.

(ix)

The Committee may suggest any other measure for overall reduction in the cost of Generation of Power

in the interest of Consumers.

192

HARYANA GOVT. GAZ. (EXTRA.), JAN. 30, 2026 (MAGH. 10, 1947 SAKA)

(x)

The High-Power Committee shall, after due examination, finalize its recommendations, preferably

within a period of 180 days from the date of issue of this Notification.

(xi)

The Chief Engineer/HPPC, UHBVNL, Panchkula shall act as a Nodal Officer, on behalf of the

Government for presenting the relevant document before the aforesaid committee & preparing relevant

Minutes of Meeting (MoM), from time to time.

(xii)

Notwithstanding anything contained in this Notification, the State Government reserves its right to

recourse to any further action, as deemed fit, at any point of time.

SHYAMAL MISRA,