Jharkhand State Electricity Regulatory Commission, Ranchi

--------

Notification

4th October, 2019

JSERC(Planning, Coordination, Developmentand Approval of an economic and

efficient Intra-State Transmission System)Regulations, 2019

Notification No. 72

CHAPTER I:

GENERAL

A1: PREAMBLE

1.1

The Electricity Act, 2003, along with specifying all the norms also specifies the promotion of

competition, protecting interest of consumers and supply of electricity to all areas.

1.2

Under section 61 (c) of the Act, the Commission is empowered to specify the terms and conditions for

the determination of tariff and in doing so shall also be guided by factors which would encourage

competition, efficiency, economical use of the resources, good performance and optimum investments.

1.3

The JSERC (State Grid Code) Regulations, 2008 and its amendments, provides the planning code,

planning criterion and other aspects for planning and development of Jharkhand State Grid System.In

the State Grid Code, an investment approval process has been provided for the projects to be executed

by the existing Transmission Licensee.However, in future, the projects may be awarded on tariff based

competitive bidding process under Section 63 of the Electricity Act, 2003. Therefore, the existing State

Transmission Licensee might not execute the projects. The developer may be selected through tariff

based competitive bidding process.

No. 797

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

2

1.4

The investments made in Intra-State Transmission System may ultimately be recovered through tariff

and as per the sharing mechanism determined by the State Commission. Further, there are multiple

Distribution Licensees and Generating Companies in the State. Therefore, there is a need to have a

transparent, economical, co-ordinated and consultative process for planning for the development of

intra state transmission system in an optimal matter.

1.5

In exercise of the powers conferred under clause 181 of the Actand all other powers enabling it in this

behalf, the Jharkhand State Electricity Regulatory Commission (JSERC) herebymakes the following

regulations to enable a more transparent, economical, co-ordinated and consultative processduring the

planning of Intra-State TransmissionSystem in the state of Jharkhand.

A2: Short title and commencement

2.1

These Regulations shall be called the Jharkhand State Electricity Regulatory Commission (Planning,

Coordination, Development and Approval of an economical and efficient Intra-State Transmission

System) Regulations, 2019;

2.2

These Regulations shall come into force from the date of its publication in the Official Gazette of the

Government of Jharkhand;

2.3

These Regulations shall extend to the entire state of Jharkhand;

A3: Definitions and interpretation

3.1

In these Regulations, unless the context otherwise requires-

a)

“Act” means the Electricity Act, 2003;

b)

“Commission” means the Jharkhand State Electricity Regulatory Commission referred to in

Section 82 of the Act;

c)

“Grid Coordination Committee or Committee” means the Committee constituted by the

Commission as per the Section 5 of State Grid Code.

d)

“Licence” means a licence granted by the Commission under Section 14 of the Act to a person

to undertake intra-state transmission of electricity, and includes a deemed licence;

e)

“Licensee” means a person who has been granted a licence, and includes a deemed licensee;

f)

“Petition” means and includes all petitions, applications, complaints, appeals, replies,

rejoinders, supplemental pleadings, other papers and documents filed in relation thereto, and

the word “Petitioner” shall be construed accordingly;

g)

“Project” means an element or elements of the intra-state transmission system;

h)

“Renewable Purchase Obligation (RPO)”shall be as defined in JSERC (Renewable Energy

Purchase Obligation and its compliance) Regulations, 2016 and its amendments;

i)

“Secretary” means the Secretary of the Jharkhand State Electricity Regulatory Commission;

j)

“State Grid Code” means the JSERC (State Grid Code) Regulations, 2008 and its

amendments as specified by the Commission under clause (h) of sub-section (1) of Section 86

of the Act;

k)

“Transmission Charges” means the transmission charges approved or adopted, as the case

may be, by the Commission for the project;

l)

“Transmission Licensee” means the licensee authorised to establish or operate transmission

lines in the State of Jharkhand;

3.2

Words or expressions used and not defined in these Regulations but defined in the Act or the State

Grid Code shall have the meanings respectively assigned to them in the Act or the State Grid Code

respectively;

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

3

CHAPTER-II:

A4: OBJECTIVE and SCOPE of the regulations:

4.1

These regulations shall apply to State Transmission Utility (STU), State Load Despatch Centre

(SLDC), Transmission Licensees, Distribution Licensees, GeneratingCompanies including Captive

Generatingstations and Open Access consumers, that are connected or areplanning to connect to the

Intra-State Transmission System,Grid Co-ordination Committee (GCC) and any other relevant entity

recognized by the Commission and involved in the planning and development of the Intra-State

Transmission System.

4.2

These regulations shall be in addition to the State Grid Code and other applicable JSERC Regulations,

and shall lay down the broad principles, procedures and processes to befollowed for planning, co-

ordination, development and approval of an efficient, co-ordinated, reliable and economical Intra-State

transmission System in the State of Jharkhand.

4.3

These regulations shall lay down broad principles and processes to bring about transparency and

ensure wider participation of stakeholders in the planning process through consultations.

4.4

These regulations shall also lay down the norms to be followed by the State Transmission Utility in

getting approval of the planned intra-state transmission schemes from the GCC and Commission

before initiation of execution of such schemes as per Section 62 or Section 63 of the Act.

A5: Roles and responsibilities

5.1

The STU shall plan the Intra-State Transmission Systems and while doing so, shall undertake system

studies for development of the transmission system. It shall also ensure proper coordination and ensure

inputs from various agencies such as SLDC, Transmission licensees, Distribution licensees,

Generating Companies including Captive Generating stations, Open Access Consumers and other

entities in the State. If required, the STU can seek inputs from RLDCs, NLDC, CEA, RPCs etc. also.

The inputs from various stakeholders shall form the input to the system studies, which shall be carried

out on a scientific basis by catering to the load growth and to improve the network strengthening and

reliability of the network in the State. The inputs shall be provided in the format prescribed by the

GCC.

5.2

The SLDC shall provide periodic operational statistics and feedback to the STU along with supporting

analysis and details, which have a bearing on the planning process of Intra-State Transmission System.

5.3

The GeneratingCompaniesincluding Captive Generating stations and Open Access Consumers,

connected or intending to connect to Intra-State Transmission System, shall provide the technical data

as per format prescribed by the GCC.

5.4

GeneratingCompanies including Captive Generating stations connected to or intending to connect to

Intra-State Transmission System shall furnish status of their projects to the STU from time to time as

specified in detailed procedure, which is to be prescribed by the GCC.

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

4

5.5

All the Distribution licensees in the State shall undertake periodic load growth studies within their

license area and provide inputs to the STU for carrying out system studies. The Distribution licensees

shall also provide details to the STU in respect of

(a)

Ongoing downstream projects which are under implementation along with the expected date of

commissioning,and

(b)

New downstream networks which are being planned by them

5.6

All the Transmission Licensee (s) in the State shall also provide details of the following:

(a)

Ongoing transmission projects which are under implementation along with the expected date of

commissioning, and

(b)

New transmission projectswhich are being planned by them, including their parent.

5.7

The STU shall consider all the inputs and undertake system/ load flow studies across the state.

5.8

The STU shall submit the results of the system/ load flow studies and scenarios of planned

projectsalong with base case (with cost/ benefit analysis) to the GCC with all the inputs/ assumptions.

The members of the GCC shall discuss, review, comment and give consent to the final plan. In case

any modifications are required, it shall suggest the modifications to STU.

5.9

Since the Intra-State Transmission projectsshall be integrated with the Inter-State Transmission

System, the STU shall share the final signed off-version with Central Electricity Authority (CEA)/

Regional Power Committee (RPC) for information and to seek feedback/ comments. RPC, on receipt

of proposal from STU, shall consider and convey its feedback to STU within 3 months of receipt of

such proposal.

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

5

CHAPTER-III:

A6: Strenghtening/ upgradation of the transmission system

6.1

The STU while planning the Intra-State Transmission System in the form of expansion or upgradation

shall also consider (but not limited to) the following, in addition to the guidelines given in the JSERC

(State Grid code) Regulations 2008 and its subsequent amendments:

a. New and emerging technologies;

b. Cost-benefit analysis outcome;

c. Likely shutting down of old/ inefficient GeneratingStations;

d. Renewable capacity addition;

e. Renewable Purchase Obligation;

f. System adequacy from the perspective of black start/ start-up supply;

g. Requirement of reactive power;

h. Optimal utilization of resources to ensure an efficient and economical system;

i. Upstream/ downstream infrastructure with respect to the augmentation or upgradationor

uprating of the existing system;

j. Consideration to inter-state schemes planned by CTU and perspective plan prepared by CEA;

and

k. Policy initiatives of Government of India and Government of Jharkhand.

6.2

When the augmentation of transmission system is undertaken for renewable energy sources,

transmission system shall be planned by considering estimated renewable capacity additions in the

state, Renewable Purchase Obligation (RPO) of the state and utilizing the available margins in the

system being planned for conventional power.

A7: Process of transmission planning

7.1

The STU shall carry out transmission planning as under:

a. The STU shall carry out transmission planning for five (5) yearsand shall update the same each

year.The STU shall plan the entire exercise well in advance and submit to the Commission as

per the stipulated timelines given in the JSERC (State Grid Code) Regulations, 2008 and its

amendments;

b. Consider applications for long term access, projections of electricity demand and generation,

policy imperatives including renewable energy addition, national electricity plan and

operational feedback from SLDC in terms of reliability and congestions;

c. Consider inputs from SLDC, Generating Stations including Captive Generating stations, Open

Access Consumers, Distribution Licensee (s)and Transmission Licensee (s). The inputs have to

be submitted to STU within 30 days. Provided, that the inputs shall mean consultations signed/

forwarded from the Managing Director/ Chief Executive Officer/ Chairman or equivalent of

the concerned organisations;

d. Conduct system studies for various probabilisticscenarios which includes generation and load

scenarios during peak, off-peak and other than peak/ off-peak hours for different seasons

considering low, moderate and high renewable capacity addition, varying import/export

requirements and scheduling of various generating stations under economic dispatch for which

variable cost of existing and upcoming generating stations shall be factored in;

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

6

e. Prepare base case for each probabilistic scenario (options) by considering details of generation

from Generating Stations including Captive Generating stations and demand from the

Distribution and Transmission licensees and Open Access Consumers in the State, existing,

under-construction and upcoming Inter-State and Intra-State Transmission System up to

desired voltage level for the above exercise. While preparing the scenarios, the STU shall

determine the schemes with proper phasing based on an end to end basis considering all

upstream and downstream projects;

f. Consider options of upgrading the existing transmission system in place of building new

transmission lines such as increasing line loading through use of compensation, re-

conductoring, etc., for optimally utilizing the existing assets, should also be considered;

g. The STU shall also review the Intra-State Transmission System in the event of change in

commissioning schedule of upstream and downstream system, shift of target region, phase out

of generating units, operational feedback of SLDC and exit from long term consumers;

h. Carry out a midcourse correction for transmission system, based on progress of implementation

of generating stations and upstream/ downstream systems, to the extent possible in respect of

(i) reconfiguration of planned transmission system, (ii) phasing of transmission elements and

(iii) delay/ deferment of some of the transmission elements;

i. The STU shall complete the initial planning exercise in a period of 3 months from the initiation

of the process. Before finalizing the transmission scheme, STU shall publish the details of all

probabilistic scenarios and suggested transmission schemes inits website and seek

stakeholder’s comments by giving a period of 30 days. STU shall finalise the draft

transmission scheme(s)only after considering the responses received from stakeholders. The

STU shall also keep all planning scenarios in archive for stakeholder comments also;

j. The STU shall review the stakeholder comments before finalising the schemes. Acceptance or

rejection of any comment should be supported by proper justification. The STU shall finalise

the schemes within 21 days of receiving stakeholder comments;

k. The finalised schemes along with results of system studies, scenarios, investments, cost-benefit

analysis, assumptions, methodologies, planning criteria, stakeholder comments etc. shall be

placed before the GCC;

l. The members of the GCC shall review the proposal of the STU in totality and give comments/

/suggestions with 30 days of receipt of the schemes from STU. The STU shall have 14 days to

incorporate the comments/ suggestions and re-submit the same before GCC for sign off. The

members of the GCC has to undertake prudence check and give its consent to the

proposalwithin 30 days in the form of a joint sign-off to the planned scheme (s).

m. In case, GCC does not reach to a consensus upon the receipt of the modified proposal (in case

of any modifications prescribed by the GCC in the sub- section (l.) above), then the GCC shall

approach the Commission with the points of contention and represent a detailed case for

review. In case STU is of the view that the scheme is in interest of grid security/ stability or

decongesting the network or overcoming a contingency, it shall record this in writing and

submit the same before the Commission.

n. The Commission shall review the proposed schemes and issue necessary regulatory direction.

The STU shall make the necessary changes to the scheme as directed by Commission and the

same shall be considered as the final signed-off version.

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

7

o. Post finalisation by GCC, the STU shall submit the final signed-off version before the CEA/

RPC for their views.They on receipt of proposal from STU, shall consider and convey their

viewsto STU,preferablywithin 3 months of receipt of such proposals.

7.2

Consultation from Stakeholders

a. STU shall consult with all stakeholders such asSLDC, Transmission licensee (s), Distribution

licensee (s), Generating companies including Captive Generating stations, Open Access

Consumers, Grid Co-ordination Committee and other stakeholdersidentified relevant by the

Commission;

Provided that consultations with Generating companies including Captive Generating stations /

Transmission Licensee (s)/ Distribution licensee (s)/ Open Access Consumer (s) shall mean

consultations signed/ forwarded from the Managing Director/ Chief Executive Officer/

Chairman of concerned Generating company including Captive Generating stations/

Transmission Licensee (s) / Distribution licensee (s)/ Open Access Consumer (s) or its

specifically designated nominee.

b. The STU shall ensure transparency while carrying out transmission planning through sharing

of information, underlying assumptions, methodology, planning criteria and result of system

study regularly.

c. The STU shall publish the following on its website and update the same on a yearly basis:

i.

Detailed justification for the scheme along with details of the complete scheme;

ii.

Results of System studies;

iii.

Assumptions made in system studies and inputs received from stakeholders;

iv.

Comments/ suggestions of stakeholders along with its treatment;

v.

Likely capital costs and estimated monthly tariff;

vi.

Likely timeline of execution;

vii.

Status of upstream/ downstream system.

d. STU in discharge of its functions under Section 39 (2)(b) of the Act may make such procedure

and prescribe such forms as may be necessary for the purpose of planning and co-ordination

relating to Intra-State Transmission System, which is not inconsistent with these regulations or

any other regulations of the Commission

7.3

The STU shall finalise the Intra- State transmission plan for five (5)years and also for each annual

revision after incorporating all stakeholder comments, suggestions and recommendations from the

GCC/ CEA/ RPC (if any).STU has to mention reasons for accepting/ rejecting any suggestion from

stakeholder (s).

A8: Regulatory filings

8.1

Post finalisation of the schemes by GCC, the STU shall submit the schemes before the Commission

for Regulatory approval.

8.2

The STU at the time of seeking regulatory approval, shall submit the following to the Commission

a. Recommendations/ Consensus/ sign-offon the scheme(s) by GCC;

b. Results of the system studies carried out by STU;

c. Assumptions and Inputs considered in system studies;

d. Status of upstream/ downstream transmission system;

e. Status of consultation with the stakeholders along with Comments/ suggestions of stakeholders

and its treatment.

f. Likely capital costs and estimated monthly tariff;

g. Transmission project (s) identified on an end to end basis;

Jharkhand Gazette (Extraordinary), Thursday, 10th October, 2019

8

h. Likely timeline of execution with proper phasing of sub-project (s);

i. Views of RPC and CEA– minutes of the meeting etc. may be attached

j. Any other point as mentioned in State Grid Code.

8.3

Exception:- ifany Intra-State transmission project (s) are developed exclusively using the grant from

the State or Central Government, it would be under intimation to the Commission by S.T.U that all the

processes have been diligently completed.

A9: Manpower deployment in transmission planning

9.1

STU shall ensure proper and adequate manpower for conducting transmission planning exercise on a

yearly basis.

A10: Miscellaneous

10.1

The STU shall be the custodian of the base case files and system study files along with all relevant

details of final accepted network configuration.

10.2

STU shall furnish to the Commission status of on-going schemes and status of approval of proposed

schemes on quarterly basis.

A11: power to amend

11.1

The Commission may, at any time and on such terms as to costs or otherwise, as it may think fit,

amend any defect or error in any proceeding before it, and all necessary amendments shall be made for

the purpose of determining the real question or issue arising in the proceedings.

A12: Power to remove difficulties

12.1

If any difficulty arises in giving effect to these Regulations, the Commission may remove, by general

or special order, consistent with the provisions of the Act, which appears to it to be necessary or

expedient for the purpose of removing the difficulties.

A13: Repeal and Savings

13.1

Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent powers of the

Commission to make such orders for the ends of justice to meet or to prevent abuses of the process of

the Commission.

13.2

Nothing in these Regulations shall, expressly or impliedly, bar the Commission dealing with any

matter or exercising any power under the Act for which no Regulations have been framed, and the

Commission may deal with such matters, powers and functions in a manner it thinks fit.

By Order of the Commission,

Rajendra Prasad Nayak,

Secretary

Jharkhand State Electricity Regulatory Commission.

---------------