THE

JHARKHAND GAZETTE

EXTRAORDINARY

PUBLISHED BY AUTHORITY

26 AASHWIN, 1944 (S)

RANCHI, TUESDAY 18th OCTOBER, 2022

DEPARTMENT OF INDUSTRIES

--------

NOTIFICATION

17th October, 2022

Jharkhand Industrial Park and Logistic Policy 2022

Memo No. 06/U.Ni./Vividh/Logistics Park-3/2021........1132........

1. Preamble

The Government of Jharkhand introduced Jharkhand Industrial Park Policy in September 2015 for

a period of five years with a view to create industrial infrastructure for rapid industrialization in the

State. The state had provisioned to incentivize the private players to come forward and develop well-

equipped, state-of-the-art industrial parks which is quintessential to the development of industries.

The Government of Jharkhand believes that the government owned Industrial Area Development

Authorities coupled with engagement of private players in the area of development of industrial parks

can bring about a sea-change in tackling one of the most grievous issues of industrial development

i.e. availability of land. Jharkhand, in its endeavor to give policy push to encourage private players to

come forward and contribute with a vision for holistic development of the state as well as their own

interests, has come forward with a policy which not only caters to the development of industrial parks

but also delves into the area of incentivizing development of logistic parks and logistics units.

No. 516

2

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

The present policy has been drafted in the backdrop of Covid-19 pandemic, when MSMEs are

suffering from tremendous capital crunch, thus the new policy envisages and emphasizes on

development of industrial infrastructure and provide a plethora of incentives that could boost the

growth of industries including MSMEs units. This policy also realizes the importance of holistic

development of logistic sector and connectivity to industrial parks and major clusters. The present

policy has adopted all the amendments of the past policy, recommendations of High-Powered

Committee constituted under Single Window Clearance Act 2015, valuable inputs received from the

industry players during the Stakeholders meet. A special focus has been laid on to attract MSME and

non-MSME players in the logistics sectors through this policy.

Under this background, the policy aims at setting up of private, joint venture and PPP mode industrial

parks, Logistic Parks and Logistic Units with all necessary industrial infrastructure.

2. Objectives

•

To develop a robust infrastructure for industries in the State for their sustainable development.

•

To promote private investment in setting up industrial parks, logistic park and logistic units in

the State.

•

To upgrade and improve the existing warehousing and logistics infrastructure to boost

economic activities and generate mass employment opportunities.

•

To enhance the warehousing capacity to promote the interests of both primary and secondary

sectors.

3. Policy Duration and Coverage

The Policy will be known as Jharkhand Industrial Park and Logistic Policy 2022 and will come into

force from issuance of this resolution and remain in force for five years from the date of notification of

the Gazette. This policy will have provisions for incentives for following:

 Private Industrial Parks, Joint Venture and PPP mode Industrial Park

 Multi Modal Logistic Park

 Logistic Park

4. Private Industrial Parks

Jharkhand resolves to ensure that land for purpose of setting up industries does not remain a

constraint and will work towards creating enablers for establishing more sector specific, mix-use and

logistic parks.

4.1. Private Industrial Park- Eligible Institutions

Any Private entity or Joint Venture (of private entities or between Public and private entities) will

be eligible for setting up private industrial park including sector specific industrial park.

Eligible Activities for assistance in industrial parks including sector specific industrial parks.

Infrastructure facilities as may be required in an industrial park such as:

a)

Approach road and bridge to the industrial estate.

b)

Up-gradation of existing roads/widening of roads to the industrial park.

c)

Internal roads with the industrial estate.

d)

Drainage facilities.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 3

e)

Streetlights in Industrial Park.

f)

Water distribution network and related facilities.

g)

Electricity/Energy/Gas distribution network and related facilities.

h)

Communication Network and related facilities.

i)

Effluent treatment plant and related infrastructure.

j)

Warehousing and related facilities.

k)

Facilities Center, Primary Health Centre, Product Development Centre,

Training Centre, Testing Centre, R&D Centre and or any common facilities

center.

l)

Disaster Management Plan Fire-fighting equipment etc.

m)

Any other infrastructure facilities required in the industrial park specific to

industry as approved by Implementation Committee, case to case basis on

the basis of special requirement of the industrial park.

4.2. Procedure for Setting-up Private Industrial Park

4.2.1. To establish Private Industrial Park, the proposal shall be submitted to the Single

Window Clearance Committee. The Committee after thorough evaluation of proposal,

will give its recommendation after due examination of proposal within 60 days from the

date of receipt of application in complete details.

4.2.2. After the recommendation of the Committee, the Minister of Industries, Government of

Jharkhand can approve/reject the project proposal.

4.2.3. After approval, the Eligible Private Institution may form a Special Purpose Vehicle

(SPV) for the establishment, operation and maintenance of the proposed Industrial

Park. This Special Purpose Vehicle shall have to be registered under The Company

Act.

4.2.4. The Master Plan of private Industrial Park may be approved by Master Plan

Committee. After the approval of Master Plan, the Private Institution shall transfer the

ownership of land to SPV or acquire land for SPV. The Deputy Commissioner shall

give permission for transfer of land for establishment of industrial park wherever

necessary within two months from date of receipt of application under section 49 of the

Chotanagpur Tenancy Act, 1908.

4.2.5. The Private institution can procure land directly from Raiyat. In other cases, JIADA land

will be made available as per existing lease provision of JIADA for private industrial

park, Joint Venture (JV) Industrial Park or PPP mode Industrial park. In case of

allotment of government land for establishing industrial park, government land shall be

first transferred to JIADA and then as per existing provision the said land shall be

provided for establishing private industrial park, Joint Venture Industrial park or PPP

mode industrial park.

4.2.6. The plots in the Private Industrial Park will be allotted to industrial units by SPV on long

term lease basis. The lessee industrial Unit cannot transfer the allotted plot by way of

sub-lease or any other mode of transfer to any person or entity other than inheritance

without the permission of SPV. The industrial unit can mortgage the allotted plot with

4

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

commercial banks for securing loan of that concerned industrial unit and the

commercial bank will be free to auction sale of plot in case of recovery of loan with due

knowledge of SPV. The lessee industrial unit cannot change the nature of use of land

other than the purpose provided by SPV.

4.2.7. The finance for the project shall be planned for at least 10 years and need to be

upgraded every five years. The timeline is subject to the type of the Project. An up-

gradation fund shall have to be created by the applicant.

4.2.8. If required, The High-Powered Committee will stipulate other conditions for the

implementation of the project which shall be final and binding to the applicant.

4.3. Approval of Master Plan

4.3.1. The Master Plan for the proposed Private Industrial Park has to be approved by Master

Plan Committee before Industries Minister’s approval.

a)

Minimum 60 percent of developed land will be allotted for industrial units as

developed industrial plots.

b)

Minimum of 40 percent of developed land in the private industrial park will

be earmarked for setting up of MSMEs by investors other than the developer

of the private industrial park.

c)

Upto 33 percent of land shall be allotted for common use infrastructure or

Green area/Open Space.

4.3.2. No change or deviation in the Master Plan will be allowed once approved except with

the permission of Master Plan Committee.

4.3.3. Responsibility of allotment of developed plot for industrial unit will be of SPV.

4.3.4. The land rate for allotment of developed plot and its other terms conditions for

allotment will be decided by SPV subject to provision of this procedure and existing

policies and laws.

4.4. Comprehensive Project Investment Subsidy (CPIS) for Private Industrial Parks,

Joint Venture or PPP Mode Industrial Park

4.4.1. 50 % of the project cost, upto maximum limit which is given below and whichever of

lower shall be included by the State Government:

Size of the Industrial

Area

Minimum number of

Industrial Units

Maximum eligible Incentive

amount

10 Acres & above

5 units

Rs.7.00 Crores

15 Acres& above

6 Units

Rs. 9.55 Crores

20 Acres& above

7 Unit

Rs. 12.10 Crores

25 Acres& above

8 Unit

Rs. 14.65 Crores

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 5

30 Acres& above

9 Unit

Rs. 17.20 Crores

35 Acres& above

10 Unit

Rs. 19.75 Crores

40 Acres& above

11 Unit

Rs. 22.30 Crores

45 Acres& above

12 Unit

Rs. 24.85Crores

50 Acres& above

13 Unit

Rs. 27.40 Crores

55 Acres& above

14 Unit

Rs. 29.95Crores

60 Acres& above

15 Unit

Rs. 32.50Crores

65 Acres& above

16 Unit

Rs. 35.05 Crores

70 Acres& above

17 Unit

Rs. 37.60 Crores

75 Acres& above

18 Unit

Rs. 40.00 Crores

4.4.2. While calculating project cost, following items shall not be included in the project cost.

They are-

1. Cost of the land

2. Earth filling work for land levelling

3. Compound wall

4. Fuel Consumables Spares and Store

5. Computer and Allied Office Furniture

6. Transport Vehicles

7. Erection installation and Commissioning charges

8. Second Hand/Old Machines/Refurbished Machinery

9. All Types of service charges, Carriage and Freight Charges.

10. Expenditure on setting up of Machinery

11. Close Circuit TV Camera and related equipment

12. Consultancy Fee

13. Stationary Item

4.4.3. The incentives for development of infrastructure of private industrial park will be based

on project cost. The project cost will be assessed on the basis of per acre project cost

of JIADA for development of industrial area.

4.4.4. The developer of industrial park availing incentives under this policy would not be

eligible to avail incentives under any other schemes of the state government unless

specified otherwise while granting approval of the project, However, the industrial units

set up in the private industrial park shall be entitled to the benefits and incentives as

6

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

provided under prevalent state Industrial Policy and any schemes of the Central and

state Government for time being in force.

4.5. Procedure for Submission of Applications for Financial Assistance

Applicants/firms seeking financial assistance are required to submit their applications in the

manner prescribed under this procedure.

The application which is complete in all respect for availing grant shall be processed within 60 days

from the date of receipt.

4.5.1. Documents Required

The following documents will be required to be submitted. The list is only indicative

and not exhaustive.

i.

Application in the prescribed format with all the fields clearly filled.

ii.

Detailed Project Report, self-attested.

iii.

Sanction letter of term loan from bank / financial institution.

iv.

Appraisal report from Bank / Financial Institution along with sanctioned DPR

from the Bank.

v.

Certificate of incorporation of SPV, Memorandum and Articles of

Association

vi.

Annual Report of the Promoter Company / Companies.

vii.

Bio-data / background of the office bearers / promoters of the organization

and Annual Reports of the Promoter Company / Companies.

viii.

Blue Print of the Master Plan.

ix.

Notarized English / Hindi version of land document.

x.

Item wise and cost wise details of Civil Works envisaged duly certified by

Chartered Engineer (Civil).

xi.

Item wise and cost wise details of Plant & Machinery envisaged duly

certified by Chartered Engineer (Mechanical).

xii.

Quotations from the suppliers of Plant & machinery and equipment’s etc.

required for the project.

xiii.

Estimate of Civil Construction with the complete breakdown of costs for

each of the technical or non- technical civil works.

xiv.

NOC Certificate from Pollution Department.

xv.

Implementation schedule indicating (a) date of acquiring land (b) date of

start of construction of infrastructure (c) date of completion of infrastructure

(d) date for placing order for plant & machinery (e) date of installation/

erection (f) date of commercial Operation of Industrial Park.

xvi.

An affidavit duly executed on non-judicial stamp paper of Rs.100/- or more

duly notarized by Notary Public affirming:

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 7

•

Organization's sister concern (s)/ related company / group company as well

as the applicant company itself availed any financial assistance for establishing

industrial park in the past from Government or not. If yes, the details thereof.

•

Organization has not obtained/applied for or will not obtain any

grant/subsidy from any Ministry/Department of State Govt. /Govt. of Jharkhand

organization/agencies for the same purpose/activity /same components.

4.6. Release of Incentives

The incentive amount will be released in three installments after the Beneficiary has spent

his share as per the following schedule:

Release of 1stInstalment: The first installment of 40 % of the total incentive under the

scheme will be released after ensuring that 40 % of the promoters’ contribution and 40 % of

the term loan has been utilized on the project. The applicant will have to submit the

following documents along with the request for the 1st Installment.

a)

Duly notarized Surety Bond - To be executed by the beneficiary company on

Non-Judicial stamp paper of not less than Rs. 100/-.

b)

Duly notarized Affidavit - To be executed by the beneficiary company on

Non-Judicial stamp paper of not less than Rs. 100/-.

c)

Bank Certificate certifying that they have released 40% of term loan and have no

objection on release of 1st installment of grant being provided by State.

d)

Chartered Accountant Certificate - Actual expenditure incurred on the project

showing the means of finances and 40% utilization of Promoters contribution & 40% of

Term loan.

e)

Itemized Summary Statement of expenses incurred on Plant and Machinery

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, Taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers.

f)

Itemized Summary Statement of expenses incurred on Technical Civil Works

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers.

g)

Certificate of the Chartered Engineer (Civil) for Technical Civil Works

indicating item wise progress, cost, quantity, manufacturer / supplier and comment

on quality annexed with color photographs (with date stamps) of the project site.

h)

Certificate of the Chartered Engineer (Mechanical) for Plant & Machinery

indicating item wise progress, cost, quantity, manufacturer / supplier and comment

on quality annexed with color photographs (with date stamps) of the project site.

i)

Compliance of conditions imposed in the approval letter of the grant-in-aid,

if any.

8

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

j)

Site Inspection Report by the Directorate of Industries to ascertain the

physical progress of the project.

k)

Environmental Clearance from MoEF as per existing guidelines.

Based on the above documents, the Director, Department of Industries would arrive at the

eligible amount of grant and release 40 % of the eligible amount as 1st installment subject

to the availability of all other requisite documents as per policy guidelines.

Release of 2nd Installment: The second installment of 40 % of the total incentive under the

scheme will be released after ensuring that 80% of the promoters’ contribution and 80% of

the term loan has been utilized on the project. The applicant will have to submit the

following documents along with the request for the 1st Installment.

a)

Utilization Certificate - as per GFR 19A duly certified by the C.A. and

countersigned by the Bank and promoter of the beneficiary company

b)

Bank Certificate - certifying that they have released 80% of term loan and

1stinstalment of grant released by the State. They have no objection in releasing

2nd installment of grant being released by State.

c)

Chartered Accountant Certificate - Actual expenditure incurred on the

project showing the means of finances and 80% utilization of Promoters

contribution, 80% of Term loan and 1st installment of released grant.

d)

Itemized Summary Statement of expenses incurred on Plant and Machinery

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers (for the components not submitted earlier).

e)

Itemized Summary Statement of expenses incurred on Technical Civil Works

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers (for the components not submitted earlier).

f)

Certificate of the Chartered Engineer (Civil) for Technical Civil Works

indicating item wise progress, cost, quantity, manufacturer/supplier and comment

on quality with color photographs (with date stamps) of the project site.

g)

Certificate of the Chartered Engineer (Mech.) for Plant & Machinery

indicating item wise progress, cost, quantity, manufacturer/supplier and comment

on quality with color photographs (with date stamps) of the project site.

h)

Compliance of conditions imposed at the time of release of 1st Installment of

grant.

i)

Site inspection to ascertain the physical progress of the project.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 9

Release of 3rd Installment: The Third and final installment of the remaining incentive would

be released only after physical verification by the Directorate of Industries and submission

of documents specified below by the firm, utilization of first and second installment of the

grant, 100% of Term Loan as well as 100% of Promoter's contribution.

a)

Utilization Certificate - as per GFR 19A duly certified by the C.A. and

countersigned by the Bank and promoter of the beneficiary company.

b)

Bank Certificate - certifying that they have released 100% of term loan and

2nd installment of grant released by the State. They have no objection in releasing

3rd installment of grant being released by State.

c)

Chartered Accountant Certificate - Actual expenditure incurred on the

project showing the means of finances and 100% utilization of Promoters

contribution, 100% of Term loan and 1st and2ndInstallment of released grant.

d)

Itemized Summary Statement of expenses incurred on Plant and Machinery

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers (for the components not submitted earlier).

e)

Itemized Summary Statement of expenses incurred on Technical Civil Works

components with breakup of machine name, supplier, date of order, date of

payment, date of arrival at factory, Gross Cost, taxes thereon, Freight, Other

Charges and Net Cost on the letterhead of CA (with a declaration that all the

vouchers have been properly checked and verified) & enclosure of all the bills and

vouchers (for the components not submitted earlier).

f)

Certificate of the Chartered Engineer (Civil) for Technical Civil Works

indicating item wise progress, cost, quantity, manufacturer/supplier and comment

on quality with color photographs (with date stamps) of the project site.

g)

Certificate of the Chartered Engineer (Mech.) for Plant & Machinery

indicating item wise progress, cost, quantity, manufacturer/supplier and comment

on quality with color photographs (with date stamps) of the project site.

h)

Compliance of conditions imposed at the time of release of 2ndInstalment of

grant.

i)

Site Inspection Report by the Directorate of Industries to ascertain the

completion of the project and setting up of the required number of industrial units in

the Park.

j)

Third Part Quality Assurance (TQPA) Certificate.

k)

The issue of Consent-to-operate from the state Pollution Control Board.

l)

Before release of 3rd & final installment of grant-in-aid, eligible grant-in-aid

for the project will be re-calculated based on the proposed/appraised /actual cost,

whichever is less, for the already approved items and released accordingly.

10

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

4.7. Timeline

The commissioning of private Industrial Park project shall becompleted as per timelinegiven below

from the date of approval by Minister of Industries. The SWCC may grant extra time in case of

exception or the work delayed due to natural calamities and disaster.

Sl.No.

Size of industrial Park

(in acres)

Time to complete

1.

Up to 25

3 years

2.

Up to 50

4 years

3.

Up to 75

5 years

4.

75 & above

6 years

5. Joint Venture or PPP Mode Industrial Park

5.1. Eligible Institutions

Any Public Institutions will be eligible for setting up private industrial park including sector specific

industrial parks.

Eligible public institutions can propose to set up general purpose industrial purpose or sector

specific industrial park with the approval of board or sanction of Government as the case may be.

5.2. Procedure for setting-up Joint Venture or PPP mode Industrial Park

5.2.1. To establish Joint Venture or PPP mode Industrial Park by Public Institutions, the

proposal shall be submitted to the Single Window Clearance Committee. The High-

Powered Committee shall, after due examination of proposal, give its recommendation

to cabinet for final approval.

5.2.2. After approval of Cabinet, the eligible public Institution shall form a Special Purpose

Vehicle for the establishment, operation and maintenance of the proposed Industrial

Park. This Special Purpose Vehicle shall have to be registered under the Companies

Act.

5.2.3. In case of Joint Venture and PPP model, the concerned public institution shall follow

transparent process for selection of private or public sector industrial partners.

5.2.4. The SPV will be fully responsible for making available the land for the Joint Venture or

PPP mode Industrial Park. State Government may allot Government land or help in

acquiring/purchasing raiyati land for the Joint Venture or PPP mode Industrial Park.

The State Government may also allot land from its land banks for development of

Joint Venture or PPP mode industrial parks.

5.2.5. The SPV will follow the land allotment procedure of concerned industrial area

development authority regulation in case of IADA projects and in case of Non-IADA

public institutions projects, at the time of in-principal approval, the concerned public

institution may adopt the regulation of command area IADA or will get its own

procedure approved by Cabinet with the recommendation of High-Powered

Committee.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 11

5.3. Viability Gap Fund

Public institution will be eligible for Viability Gap Funding up to the amount as mentioned in

clause 4.4.1 and 4.4.2.

Viability Gap Funding for public institution will be released in two equal installments.

The procedure and documents, as applicable, required for release of installments will be same

as point 4.5, 4.6 mentioned above. However, the milestone for the release of installments will

be decided by High Powered committee at the time of making recommendations for the

project.

5.3.1. The joint venture industrial park shall be implemented with an industrial partner.

5.3.2. Industrial partner can be an anchor entrepreneur or a group of entrepreneurs.

5.3.3. Industry partner shall hold the majority stake in the Industrial Park SPV.

5.3.4. For PPP mode, this Policy recommends a Build Operate Transfer (BOT) model with

Viability Gap funding from state Government.

5.3.5. In case of PPP mode industrial park, the ownership of land shall remain with

Government or with State Government Industrial Area Development Authority.

5.3.6. The commissioning of public institution Industrial Park project shall be completed within

timeline as per table mentioned in clause 4.7 from the date of approval by Minister of

Industries:

6. Operations and Maintenance

6.1. The SPV will select Chief Operating Officer (CEO) as mentioned in the Article of Association.

The Chief Executive Officer (CEO) may work for maximum of three parks and remunerated

for his services. The Chief Executive Officer shall be experienced qualified and professional

having managerial capacity with an engineering/management degree. Each project proposal

will show cost/pay of CEO and its team as a part of the cost of the project.

6.2. The CEO shall be responsible for implementation, operation and maintenance of the project

as well as for strong monitoring and reporting to the Government.

6.3. SPV will arrange for Development Reserve Fund (DRF) by the contribution of 5 percent of

amount received by allotment of developed plot for industrial units and 10 percent of Annual

Net Profit of SPV be used for undertaking major infrastructure development up-gradation

works in the private, joint venture or PPP mode industrial park in the future. Amount of DRF

will be kept in fixed deposit. At any time, 33 percent of amount of DRF may be spent on

infrastructure development. For management of DRF, a committee of the representative of

SPV as well as the representative of industrial units in the industrial park will be constituted

and this provision should be part of Article of Association of the SPV.

6.4. SPV may charge maintenance fee from the Industrial Units. The fund collected through this

fee shall be part of DRF.

7. Monitoring Mechanism

7.1. The Directorate of Industries may engage a Project Monitoring Consultants (PMCs) if

necessary, for technical and financial evaluation of DPR submitted by SPV. PMCs from time

to time will assist the Directorate of Industries in project monitoring, evaluation, allotment of

fund and its utilization.

7.2. Directorate of Industries will exercise supervision and control over Joint Venture and PPP

mode Industrial Park in the State under the direction of Single Window Clearance

Committee.

12

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

7.3. Till the commencement of commercial operations, Directorate of Industries through State

Government Industrial Area Development Authority will exercise supervision and control over

private industrial park under their respective command area. Private Industrial parks outside

the command area of State Government Industrial Area Development Authority will be

supervised and controlled by respective DICs.

7.4. The Policy is valid for five year from the date of notification.

7.5. The industrial units established under these industrial parks will be eligible for financial

incentives and concessions provided under prevalent Jharkhand Industrial Policy and any

other schemes of Central and State Governments time being in force.

7.6. SWCC has right to prescribe/ modify/ add new forms, checklist and procedure and have

authority to issue additional guidelines in this regard.

7.7. Notwithstanding anything contained in the foregoing paragraphs of the Jharkhand Industrial

Park& Logistic Policy, the State Government by issuance of notification in the official gazette

may amend or withdraw any of the provisions and or the schemes mentioned herein above.

7.8. Any disputes/interpretation or contention under the procedure will be referred to the Single

Window Clearance Committee and decision of which shall be final and binding on the

applicants.

7.9. The Annexure and appendix to this Policy will be treated as part of the Policy.

7.10. In case of any discrepancy between the English and Hindi Version of this policy, the English

Version of the policy will be considered as final.

8. Multi Modal Logistic Park

Taking a cue from the Government of India’s definition of logistics units considered as logistics

infrastructure, this policy shall incentivize Multi Modal Logistics Park, Logistics Parks and Logistics

Units.

8.1. Multi Modal Logistics Park- Eligibility condition

Multi Modal Logistics Park (MMLP) is defined as a multi-modal freight- handling facility with a

minimum area of 50 acres with a minimum investment of INR 50 Crore and comprising

mechanized warehouses, specialized storage solutions such as cold storage, facilities for

mechanized material handling and inter-modal transfers container terminals, bulk / break-bulk

cargo terminals.

•

Integrated/ Multi Modal Logistics Park (MMLP) shall have the following provision:

•

MMLP’s should be accessible, at minimum, by a 2- lane paved road, with a minimum

approach road of 60 ft.

•

MMLP’s should have access to a rail siding. The development of the rail siding should be

completed within three years of initiating the MMLP development.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 13

Below is the minimum list of the activities or facilities that can constitute a Multi Modal

Logistics Park:

Logistic services like cargo aggregation/segregation, distribution/ consumer distribution, multi-

modal transfer of material and container, open and closed storage, apt condition for storage in

cargo transit period, material handling equipment, container freight station, sorting, grading,

packaging/repackaging, tagging/ labelling, custom bonded warehouse.

Supporting infrastructure including internal roads, mobility facilities, water pipelines, sewage and

drainage lines, effluent treatment and disposal facilities, setting up power, lines, feeder, parking,

solar panels and others as per the requirements of the park.

Common facilities include Computer/IT center, Subcontract exchange, Container freight station,

Skill development center, Production inspection center, Weigh Bridge.

8.2. Incentives for Multimodal Logistic Park

Sl. No

Incentives

Provision

1.

Comprehensive

Project

Investment Subsidy

50 % of the project cost or the maximum amount

as indicated in CPIS for Industrial Parks,

whichever is lower(Section 4.4.1)

2.

Interest Subsidy

Reimbursement to the extent of 5% per annum for

5 years on loan taken for procurement of material

handling equipment, loading, and unloading plant

& machinery and other plant and machineries in

common facilities Centre, subject to maximum INR

2 crores per annum per unit, with an overall ceiling

limit of INR 10 crores.

Additional 5% per annum subsidy in form of

reimbursement on loan taken for setting up

automated supply chain technology in material

handling, cargo transportation and de-congesting

cargo traffic at Multimodal Transport Hubs or

Logistics Parks or CFS/ICDs, subject to maximum

ceiling of INR 1 crore per park.

3.

Stamp Duty / Registration

Fees

100%

reimbursement

of

stamp

duty

and

Registration fees paid on purchase of land

14

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

4.

Skill Development Subsidy

Logistics Park Developer providing skill training in

warehouse management & logistics management

will be reimbursed up to Rs. 13,000 per employee

upto 100 employees, for domiciled in Jharkhand.

Employment period should be minimum 2 year.

5

Employment Cost Subsidy

50% of employer’s contribution to the developer of

the Park providing direct employment to 150 or

more skilled and unskilled workers on account of

contribution toward ESI and EPF scheme for a

period of 5 years for new units for those

employees who are domicile of Jharkhand.

Maximum limit for reimbursement will be Rs. 1000

- per month for SC/ST and women employee and

Rs. 500/- per month for general employee.

A. Eligibility & Procedure for setting up private MMLP / logistic park and JVs/PPP mode will

be applicable as per above clause 4.0 and Clause 5.0.

B. Application for financial assistance, the timeline and release of grants for MMLP /logistic

park will be applicable as per clause 4.6, clause 4.7& clause 4.5 respectively.

C. Operational, Maintenance and Monitoring of Private MMLP /logistic park will be as per

clause 6.0 and clause 7.0

9. Logistic Park

A logistics park that includes Container Freight Station (CFS) and/or Inland Container Depot (ICD)

and/or warehouses and/or cold chains and related infrastructure, developed on at least 10 acres of

land with a minimum investment of INR 25 Crore shall be eligible for incentives under this policy.

9.1. Logistics Park- Eligibility condition

Logistic services like cargo aggregation/segregation, distribution/ consumer distribution, multimodal

transfer of material and container, open and closed storage, apt condition for storage in cargo

transit period, material handling equipment, Container freight station, sorting, grading,

packaging/repackaging, tagging/labelling, custom bonded warehouses.

Supporting infrastructure including internal roads, mobility facilities, water pipelines, sewage and

drainage lines, effluent treatment and disposal facilities, setting up power, lines, feeder, parking,

solar panels, Weigh Bridge and others as per the requirements of the park.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 15

9.2. Incentives for Logistic Park

Sl.

No.

Incentives

Provision

1.

Comprehensive

Project

Investment Subsidy

50 % of the project cost or the maximum amount as

indicated in CPIS for Industrial Parks, whichever is

lower (Section 4.4.1)

2.

Interest Subsidy

Reimbursement to the extent of 5% per annum for 5

years on loan taken for procurement of material

handling equipment, loading, and unloading plant &

machinery and other plant and machineries in

common facilities Centre, subject to maximum INR 2

crores per annum per unit, with an overall ceiling

limit of INR 10 crores.

Additional 5% per annum subsidy in form of

reimbursement on loan taken for setting up

automated supply chain technology in material

handling, cargo transportation and de-congesting

cargo traffic at Multimodal Transport Hubs or

Logistics Parks or CFS/ICDs, subject to maximum

ceiling of INR 1 crore per park.

3.

Stamp

Duty

/

Registration

Fees

100%

reimbursement

of

stamp

duty

and

Registration fees paid on purchase of land

4.

Skill Development Subsidy

Logistics Park Developer providing skill training in

warehouse management & logistics management

will be reimbursed up to Rs. 13,000 per employee

upto 100 employees, for domiciled in Jharkhand.

Employment period should be minimum 2 year.

5

Employment Cost Subsidy

50% of employer’s contribution to the developer of

the Park providing direct employment to 150 or more

skilled and unskilled workers on account of

contribution toward ESI and EPF scheme for a

period of 5 years for new units for those employees

who are domicile of Jharkhand. Maximum limit for

reimbursement will be Rs. 1000 - per month for

SC/ST and women employee and Rs. 500/- per

month for general employee.

16

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

A. Eligibility & Procedure for setting up private MMLP / logistic park and JVs/PPP mode will be

applicable as per above clause 4.0 and Clause 5.0.

B. Application for financial assistance, the timeline and release of grants for MMLP /logistic

park will be applicable as per clause 4.6, clause 4.7& clause 4.5respectively.

C. Operational, Maintenance and Monitoring of Private MMLP /logistic park will be as per

clause 6.0 and clause 7.0

10. Logistics Units

Logistics Unit as mentioned in this Policy shall mean either Warehouse, Inland Container Depot

(ICD), Container Freight Services (CFS), or Cold Chain Facility if not specifically mentioned.

10.1. Logistics Unit - Eligibility condition

10.1.1 Container Freight Station (CFS) and Inland Container Depot (ICD)

It shall have a minimum area of 5 acres and minimum investment of 10 crores for CFS and 17

acres and minimum investment of 20 crores for ICD. Detail information regarding the

guidelines, infrastructure requirements, regulatory compliance regarding setting up of ICD and

CFS can be referred from the Circular No. 50/2020 or its updated version by the CBIC,

Department of Revenue, Ministry of Finance, Government of India. Following information

regarding regulatory compliance and infrastructure requirement for setting up of ICD and CFS

has been taken from the Circular No. 50/2020 by the CBIC.

a) For the land requirement for the construction of ICD or CFS the applicant must have the

legal rights if the land is owned. If the land is not owned and the land is leased, the lease

agreement should be for minimum 30 years.

b) Rail Linkage: In case of rail linked ICDs, rail infrastructure provided inside a container

depot should allow receipt and dispatch of full-length unit container trains running between

a single origin and a single destination, without requiring to be broken up or re marshaled

outside the ICDs.

c) ICD/CFS. Container Yard (CY) should be designed around rail access and not the reverse.

Loading and unloading of trains would ideally take place in centrally located sidings

comprising at least three tracks -loading, unloading and locomotive release. For a reach-

stacker served facility, container stacks at the CY shall be located on either side of the

tracks (to allow for separation of import and export containers and for loading and

unloading on both sides at a time). Rail loading/unloading tracks shall be centrally located,

permitting the operation of handling equipment on either side. The layout described above

is only indicative of best practice. Additionally, all operational and other requirements as

per extant rules of Indian Railways need to be complied with.

d) Access Road/ Connection with State Highways or National Highways: An approach road of

indicative 15 meters width with proper drainage on each side will be provided for the gate

complex. If the entry & exit gates of the ICD are planned in vicinity of each other, then

additional space to enable smooth flow of traffic will be factored into the design. Road

connections to ICD/CFS will be via slip roads off local or national highway system. Road

connections should be suitable for container and break-bulk trucks conveying containers or

break-bulk cargo between cargo sources and the ICD/CFS port.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 17

e) Direct Port Delivery (DPD) & Direct Port Entry (DPE) Area: Separate area for DPD&DPE

containers as per land requirements of this policy should be provided in ICD. The

nominated DPD&DPE area should have separate entry/exit gates with clear demarcation

from customs notified area. Further, DPD&DPE traffic should not impact the regular ICD

operations.

f) Truck Circulation Area: Internal roads shall be constructed with indicative width of 15

meters, to allow handling equipment and trucks to pass safely.

g) Storage of containers with Hazardous goods in yard: Storage space for minimum 50 TEUs

should be marked, this yard location should have unhindered transportation access, round

the clock monitoring, fire hydrant facility, fixed firefighting equipment 86 sensors to cater

for gas leakage and fire detection capabilities. All regulatory approvals from State Pollution

Control Board should be in place before handling, storage & Transportation of Hazardous

goods within ICD premises.

h) Marked Container repair yards & tank container cleaning stations: The allied services of

container repair stations, tank container cleaning stations should be clearly marked in the

yard plan.

Other essential infrastructure requirements for ICD and CFS

a) Weighbridges: Static weighbridges above 60 MT capacity should be installed in all

facilities. These should always be remain calibrated & certified by respective states Weight

& Measurement department.

b) Yard Paving: Yard paving must utilize Pavement Quality Concrete grade of M40 or dry

lean concrete with M30/M50 blocks or higher specification.

c) Container location: All ICDs & CFSs shall have a container location tracking system and

accurate information availability to all stakeholders through electronic or smart phone

application interface. All events of physical movement of container shall be recorded and

accessible to customs officer via such electronic interface.

d) For handling scrap cargo, provision of a compact track loader of reputed make in good

working condition and equipped with a telescopic spreader for operations in both 20 ft and

40 ft boxes should be ensured.

e) Handling equipment: An applicant should propose most modern handling equipment for

loading, unloading of containers from rail flats, chassis, their stacking, movement, cargo

handling, stuffing/ de-stuffing, etc. Equipment must have a minimum residual life of 8 years

duly certified by the Original Equipment Manufacturer or a recognized inspection agency.

f) High Masts: Adequate numbers of 30 meters high mast lighting tower with LED flood light

should be installed. The LED should have minimum lumen level of 20 lux in the ground up

to 50 meters from center of high mast. Beam angle of luminaries/ lamps positioning must

be suitable to cover illumination in ground as well as stored containers in the yard up to 16

meters high.

g) CCTV Coverage: The CCTV network should at minimum cover the ICD entry/ exit gates,

warehouse gates, warehouse storage area, admin building entry points, commercial

transaction area, container storage yard area and e-sealing work zones. CCTV equipment

18

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

must have night vision recording capabilities. The system should have minimum capability

to record & hold data for three months and 24×7 hours access and remote monitoring

facility shall be provided to Customs in addition to access within admin building of the ICD.

h) Access control: Entry to the customs notified area shall be controlled by KYC based/ RFID

enabled tags for all authorized personnel including customs, custodians, manual workmen,

vehicle drivers etc. Entry/ exit data should always be electronically available to customs

authorities.

10.1.2 Warehousing facility

It shall have a minimum storage capacity of 25000 MT with minimum investment of INR 50

Crore and built on a minimum area of 5 Lakh square feet. The warehouse facility should have

following minimum features to avail the incentives under this policy:

•

Use of Warehouse Management system for the enterprise resource planning.

•

Alternate power back-up for at least 8 hours.

•

Loading & Unloading bay for the Commercial Vehicles arriving at the Warehouse facility.

•

Sufficient lighting system for each using energy efficient lighting system.

•

Storage grading and tracking system for each unit.

•

Storage and retrieval system using battery operated Material Handling Equipment (MHEs)

in case of multi storage facility.

•

CCTV system for each unit for continuous monitoring with storage back-up of at least 1

month.

10.1.3 Cold Chain

It shall have a minimum storage of 2000 MT with minimum investment of INR 30 Crore and

built on a minimum area of 40,000 square feet.

The cold chain facility should be multi chamber for the storage facility of Multi

Commodity with following minimum features:

•

Continuous temperature and humidity monitoring system and alarm system connected with

automatic and manual switching system with each inner storage unit.

•

Alternate Power back-up for at least 12 Hours.

•

All Electrical installations with Power Factor not less than 0.95.

•

Air curtain system at the loading/unloading bay.

•

Loading & Unloading bay for the Commercial Vehicles arriving at the cold chain facility.

•

Air Shower room is optional for products or operators if requirement is for air shower, for

cleaning of dusts during operation.

•

Sufficient lighting system using energy efficient lighting system.

•

Storage grading and tracking system for each unit.

•

Storage and retrieval system using battery operated Material Handling Equipment’s

(MHEs) in case of multi storage facility.

•

CCTV system for each unit for continuous monitoring with storage back-up of at least 1

month.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 19

10.2. Incentives for Logistic Units

Sl.

No.

Incentives

Provisions

1

Comprehensive

Project

Investment Subsidy (CPIS)

One time reimbursement of 25% of eligible Fixed

Capital Investment per project. The reimbursement

is capped at INR 5 Crore per project and INR 6

Crore

for

SC/ST/Women/Differently

abled

Entrepreneurs

SC/ST/Women/Differently abled entrepreneurs will

avail 5%additional benefits under CPIS. This benefit

is only applicable only to residents of Jharkhand

2

Interest Subsidy

Reimbursement to the extent of 5% per annum for 5

years on loan taken for development of logistics

facilities, subject to maximum INR 50 lacs per

annum per unit.

3.

Stamp

Duty

/

Registration

Fees

100% reimbursement of stamp duty/exemption of

stamp duty and Registration fees paid on purchase

of land

4.

Quality Certification

50% of cost of quality certification upto maximum 10

lakhs will be reimbursed to units defined in the policy

5

Technology Assistance

One time Reimbursement of 50% of amount spent

on purchase of technology from the NRDC or other

government research centers, maximum upto 50

Lakh

6

Patent Assistance

Reimbursement of 70% of amount spent on original

research with maximum limit of 25 Lakhs

NOTE 1–

A. All incentives for eligible projects defined under this policy in the form of reimbursement,

subsidies, exemptions etc., will be subject to maximum 100% of fixed capital investment made

by defined units in this policy, subject to annual ceiling of 15% of fixed capital investment.

11. Empowered Committee

In line with the guidelines for operationalization of PM Gati Shakti Master Plan, the Government of

Jharkhand emphasizes on Governance Framework by constituting Empowered Group of Secretaries

which will also act as State Logistics Coordination Committee.

Empowered Group of Secretaries (EGoS) / State Logistics Coordination Committee: The Committee

will comprise of the following Members:

20

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

1.

Chief Secretary, Govt. of Jharkhand

Chairman

2.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Planning and Development

Member

3.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Finance

Member

4.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Building Construction

Member

5.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Rural Development

Member

6.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Road Construction

Member

7.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Energy

Member

8.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Water Resource

Member

9.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Forest, Environment & Climate Change

Member

10.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Food, Public Distribution & Consumer Affairs

Member

11.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Transport

Member

12.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Revenue, Registration & Land Reforms

Member

13.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Agriculture, Animal Husbandry & Co-operative

Member

14.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Tourism, Arts, Culture, Sports & Youth Affairs

Member

15.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Urban Development and Housing

Member

16.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Information Technology and e-Governance

Member

17.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Mines and Geology

Member

18.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Drinking Water and Sanitation

Member

19.

Representative from Logistic Units, DPIIT, Government of India

Member

20.

Additional Chief Secretary/Principal Secretary/Secretary, Department

of Industries

Convenor

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 21

The Committee shall be empowered to take all necessary decisions for the smooth implementation of

policy such as:

•

Implement Jharkhand Industrial Park & Logistics Policy 2022.

•

Prepare and implement Integrated Logistics Master Plan for the State.

•

Monitor the progress of City Logistics Co-ordination Committee and other development

according to State Integrated Logistics Master plan.

•

To review various measures for favorable business environment in the State for Logistics,

Warehousing and Logistics Park.

•

To frame and/or amend any guidelines or schemes under this policy.

•

Mapping of existing logistics related public and private assets in the State.

•

Prepare strategies and action plans to reducing the logistics cost of the State.

•

Undertake necessary actions for integrating and enhancing the efficient utilization of available

assets.

•

Monitor the overall disbursement under various incentives of Jharkhand Industrial Park &

Logistic policy 2022.

•

Provide suitable directions for implementing Jharkhand Industrial Park and Logistic Policy and

State Logistics Master Plan.

•

Propose various infrastructure projects for improving the logistics network, measures for

enhancing Ease of Doing Business and requirement of grants under various schemes for

logistics to State Logistics Co-ordination Committee.

•

Coordinate with concern allied departments for the overall development of logistics sector in

the state.

•

Co-ordinate with multi-lateral agencies for projects requiring support.

11.1. District / City Logistics Coordination Committee:

The Committee will comprise of following members (Initially Ranchi, Bokaro, Dhanbad,

Jamshedpur, Hazaribagh, Deoghar, East Singhbhum, Ramgarh, Sahibganj)

1.

Deputy Commissioner, Govt. of Jharkhand

Chairperson

2.

Deputy Development Commissioner

Vice Chairperson

3.

Municipal Commissioner

Member

4.

District Transport Officer, Government of Jharkhand

Member

5.

District Forest Officer, Government of Jharkhand

Member

6.

District officer Animal and Fisheries Resource Department,

Government of Jharkhand

Member

7.

District Agriculture Officer, Government of Jharkhand

Member

8.

Project Director, NHAI

Member

9.

Executive Engineer RCD, Government of Jharkhand

Member

10.

District Planning Officer, Government of Jharkhand

Member

11.

Divisional

Manager of Jharkhand State Warehousing

Corporation

Member

12.

District Mining Officer, Government of Jharkhand

Member

13.

Superintendent Engineer/ Executive Engineer (Electrical),

Government of Jharkhand

Member

14.

GM, Department of Industries Centres, Government of

Jharkhand

Convenor

Other Nodal Officers can be added as and when required to the Committee

22

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022

11.2. The City Logistics Co-ordination Committee:

The City Logistics Co-ordination Committee: shall perform all tasks related to development

of logistics at city level, including overall but not limited to:

•

Represent the City on city's freight performance at state Logistics cell.

•

Preparing City Logistics Plan in line with State Logistics Master plan.

•

Providing inputs during preparation of Integrated State Logistics Master plan for efficiency

freight management in the city.

•

Engaging with stakeholders across the ecosystem for preparing implementable action

plans as part of City Logistics plan.

•

Monitoring and regularly evaluating the implementation of measures outlined in City

Logistics plan.

•

Reviewing and recommending proposals for improving logistics planning for the city from

different stakeholders.

•

Setting a vision and targets for the city's freight performance.

•

Ensuring alignment of city's freight efficiency objectives with existing or proposed

transport, vehicle, zoning, and land use planning for the city.

•

Identifying and supporting key actions and pilot projects that can be undertaken for

improved freight performance.

•

The city Logistics co-ordination committee may co-opt any private/ official/expert members

from Logistics, Freight Forwarder and warehouse providers’ associations, Freight

Transport Associations, Logistics Professional Association as required for the overall

development of logistics sector.

•

Provide adequate and efficient green, sustainable and environment friendly logistics

infrastructure for reducing carbon footprint.

12. Definitions

“High-Powered Committee” means High-Powered Committee formed as per Single Window

Clearance Act 2015.

“JIADA” means Jharkhand Industrial Area Development Authority established under Jharkhand

Industrial Areas Development Authority Act 2001.

“Industrial Park” means an industrial estate which is developed for establishment of industrial units

to manufacture any goods or service and having basic industrial infrastructures like developed plot,

internal roads, water distribution facilities, sewage collection and treatment, power distribution,

communication facilities, disaster management plans such as fire-fighting system and such other

facilities as may be required.

“Master Plan Committee” “means Master Plan Committee headed by Managing Director, Jharkhand

Industrial Area Development Authority (JIADA) as Chairman and Director of Industries, Chief Factory

Inspector and Chief Engineer of Jharkhand Industrial Infrastructure Development Corporation

(JIIDCO) as Members”.

“Private Institution” means any Industry Association, Chamber of Commerce or Federation

registered under Societies Act, Trust Act, partnership Act or Companies Act will be treated as a

private institution.

“Public Institution” means Jharkhand Industrial Area Development Authority established under

Jharkhand Industrial Areas Development Authority Act 2001, Public Sector undertakings of Jharkhand

Government, Urban Local Bodies, or Zila Parishad.

Jharkhand Gazette (Extraordinary), Tuesday, 18th October, 2022 23

“Sector Specific Industrial Park” means industrial parks envisaged for specific sector like

a) Apparel Fiber and Textile Park

b) IT Park / Software Technology Park

c) Gems and Jewellery Park

d) Bio-tech and Herbs Park

e) Chemical and Pharmaceutical Park

f) Food Park

g) Logistic Park

h) Automobile Vendor – Ancillary Industrial Park

i) Any other specific sectors e.g. Ceramic Park, Plastic Park, Solar Park, Knowledge Park, Film

City

“Single Window Clearance Committee” means Single Window Clearance Committee (SWCC)

constituted under Jharkhand Single Window Clearance Act 2015.

13. Doubt resolution

a) Doubts relating to interpretation of any term and / or dispute relating to the operation of any

provision under this Policy shall have to be referred to the Industries Department, Government

of Jharkhand for clarification / resolution and the decision of Department in this regard shall be

final and binding on all concerned.

b) In case of any doubt the "English Version" of the policy will be considered an authentic

version.

14. Power of the State Government

Notwithstanding anything contained in the foregoing paragraphs of this policy, the State Government

by the issuance of notification in the official gazette may amend or withdraw any of the provisions

and/or the schemes mentioned herein above.

By the Order of the Governor of

Jharkhand,

Vandana Dadel,

Principal Secretary

Department of Industry

Government of Jharkhand.

-------

झारखड राजक य मुणालय

झारखड राजक य मुणालय, राँची वारा काश

राँची वारा काशत एवं मुत

त एवं मुत,

झारखड गजट

झारखड गजट (असाधारण

असाधारण)

) 516 -- 50