THE
JHARKHAND GAZETTE
EXTRAORDINARY
PUBLISHED BY AUTHORITY
13 VAISHAKH, 1945 (S)
RANCHI, WEDNESDAY 3rd MAY, 2023
JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION,
--------
NOTIFICATION
24th April, 2023
Jharkhand State Electricity Regulatory Commission (Modalities of Tariff
Determination), Regulations, 2023
Notification No.90-- In the exercise of powers conferred by sub-section (1) of Section 181
and clause (zp) of sub-section (2) of Section 181, read with Sections 61, 62, 63, and 86, of
the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in that behalf, the
Jharkhand State Electricity Regulatory Commission, hereby makes the following
Regulations.
1. Short Title and Commencement
1.1. These Regulations may be called the Jharkhand State Electricity Regulatory
Commission (Modalities of Tariff Determination), Regulations, 2023.
1.2. These Regulations shall extend to the State of Jharkhand.
1.3. These Regulations shall come into force from the date of their publication in the
Jharkhand State Government Gazette.
No. 247
2
Jharkhand Gazette (Extraordinary), Wednesday 3rd May, 2023
2. Definitions and Interpretation
2.1. In this Regulation unless the context otherwise requires:
a) ‘Act’ means the Electricity Act, 2003 (36 of 2003) and subsequent amendments
thereof;
b) ‘Commission’ means the Jharkhand State Electricity Regulatory Commission
(JSERC);
c) ‘Developer’ means an entity proposing to develop a transmission system in the
State of Jharkhand;
d) ‘Existing Project’ means a project which has achieved commercial operation;
e) ‘Financial Year’ means a period commencing on April 01 of a calendar year and
ending on March 31 of the subsequent calendar year;
f) ‘Intra-State Transmission System’ or ‘inSTS’ in respect of the State shall have
the same meaning as defined in the Act
g) ‘Ongoing Project’ means a project which has been under implementation but has
not achieved commercial operation;
h) ‘Regulated Tariff Mechanism’ or ‘RTM’ means the determination of tariff by the
Commissionunder Section 62 of the Act in accordance with the Regulations
specified by the Commission under Section 61 of the Act;
i) ‘State Transmission Utility’ or ‘STU’ means the Board or the Government
Company specified as such by the State Government under sub-section (1) of
Section 39 of the Act;
j) ‘STU Transmission Plan’ means an updated five-year rolling Intra-State
Transmission System Plan for the State as prepared and issued every year by STU;
k) ‘Tariff Based Competitive Bidding’ or ‘TBCB’ means the determination of tariff
through a transparent process of bidding in accordance with the guidelines issued
by the Central Government under Section 63 of the Act;
l) ‘Threshold Limit’ means the limit set by the Commission beyond which the tariff
of a transmission project will be determined through a transparent process of
tariff-based competitive bidding.
m) ‘User’ means the generating companies, distribution licensees, buyers, Bulk
consumers (SEZ), sellers and open access consumers, captive generating stations,
as the case may be, who use the intrastate transmission network or the associated
facilities and services of State Load Despatch Centre;
n) ‘Year’ means a financial year;
2.2. Words and expressions used in these Regulations and not defined herein but defined
in the Act shall have the meanings respectively assigned to them in the Act.
2.3. Reference to any Act, Rules, and Regulations shall include the amendment(s),
consolidation(s), or re-enactment(s) thereof.
2.4. All proceedings under these Regulations shall be governed by the JSERC (Conduct of
Business) Regulations, 2016, as amended or re-enacted from time to time.
Jharkhand Gazette (Extraordinary), Wednesday 3rd May, 2023 3
CHAPTER I:
GENERATION
3. Tariff determination under Section 62 of the Act
3.1. All existing power-generating projects for which tariff is currently being determined in
accordance with the Regulated Tariff Mechanism (RTM) under Section 62 of the Act
shall be continued to be covered under the RTM framework and their tariffs will be
determined under Section 62 for the remainder of the PPA period or life of the plant,
whichever is later, with their respective extensions, if any, as approved by the
Commission.
3.2. Expansion of existing state-owned and controlled power-generating projects will be
allowed under Section 62 and their tariffs shall be determined based on norms
specified in the JSERC (Terms and Conditions for Determination of Generation Tariff)
Regulations, 2020, as amended from time to time.
Provided that in case of expansion of generating capacity by private developers, the
tariffs for the incremental generating capacity would be determined in accordance
with the RTM framework under section 62. However, such expansion under the RTM
framework would be restricted up to the quantum of power for which a PPA has been
signed and approved by the Commission, with the distribution licensee(s) in the state.
3.3. Tariff of all Waste-to-Energy plants for which a PPA has been signed and approved by
the Commission, shall be determined in accordance with the RTM framework under
Section 62.
3.4. Tariff for repowering of an existing generating station, and for a new plant to be set up
in place of the existing plant, for the quantum of power for which a PPA has been
signed and approved by the Commission would be determined in accordance with the
RTM framework under section 62.
3.5. Tariff for all new generating stations plant, for the quantum of power for which a PPA
has been signed and approved by the Commission would be determined in
accordance with the RTM framework under section 62.
4. Tariff determination under Section 63 of the Act
4.1. Tariff for all power procurement not covered in Regulation 3 shall be discovered
through a transparent process of tariff-based competitive bidding with prior approval
of the Commission for the requirement of such capacity to be bid in pursuance to
Section 86 (1) of the Act. Further, any deviation from the TBCB guidelines shall
require prior approval of the Commission.
CHAPTER II:
TRANSMISSION
5. STU Transmission Plan
5.1. The STU shall prepare an updated five-year Transmission System Plan for the State,
identifying specific transmission projects which are required to be taken up along
with other transmission licenseesincluding but not limited to (a) Brief Scope of Work;
(b) Estimated Cost (c) Estimated COD/ implementation timelines, for approval of the
Commission by the 28th of February on a rolling basis every year (or as stipulated in
the State Grid Code) in accordance with the State Grid Code read with Indian
4
Jharkhand Gazette (Extraordinary), Wednesday 3rd May, 2023
Electricity Grid Code and other Guidelines/ Regulations of Central Electricity
Authority.
5.2. All intra-State transmission projects shall be consistent with the STU Transmission
Plan.
5.3. No intra-State transmission project shall be considered for implementation unless the
project is a part of the STU Transmission Plan and has been duly approved by the
Commission.
6. Tariff Determination for InSTS Projects under Section 63 of the Act
6.1. All new greenfield intra-State transmission projects costingbeyond the threshold limit
of Rs. 175 Cr.shall be implemented through Tariff Based Competitive Bidding (TBCB)
in accordance with the guidelines issued by the Central Government under Section
63 of the Act and any deviation from the guidelines should have prior approval of the
Commission. The tariff of such intra-State transmission projects shall be discovered
under Section 63 of the Act.
7. Tariff Determination for InSTS Projects under Section 62 of the Act
7.1. Tariff for all other intra-State transmission projects not covered under Regulation 6.1,
shall be determined in accordance with the RTM framework under Section 62 of the
Act.
7.2. Implementation of augmentation/ strengthening works, excluding O&M works as
approved in the Tariff Order, at the intra-State transmission substation and/or line,
being part of the STU Transmission Plan, shall be carried out by the respective
developer in accordance with the provisions under Section 62 of the Act read with
JSERC (Terms and Conditions for Determination of Transmission Tariff) Regulations,
2020, as amended from time to time, for which the STU shall obtain prior approval of
the Commission on a case-to-case basis.
CHAPTER III:
DISTRIBUTION
8. Determination of Retail Tariff
8.1. Retail Tarifffor the consumers of the state shall be determined in accordance with
Section 62 of the Electricity Act, 2003 along with JSERC (Terms and Conditions for
Determination of Distribution Tariff) Regulations, 2020, as amended from time to
time.
CHAPTER IV:
MISCELLANEOUS
9. Ongoing Projects
9.1. Nothing in these Regulations shall affect the mode of tariff determination for an
existing project and an ongoing project and tariff for such projects shall be continued
to be determined either under Section 62, or under Section 63 as per their existing
arrangements.
Jharkhand Gazette (Extraordinary), Wednesday 3rd May, 2023 5
10. Inherent powers of the Commission
10.1. Nothing in these Regulations shall be deemed to limit or otherwise affect the power
of the Commission to make such orders as may be necessary to meet the ends of
justice.
10.2. Nothing in these Regulations shall bar the Commission from adopting in conformity
with provisions of the Act, a procedure which is at variance with any of the
provisions of these Regulations, if the Commission, in view of the special
circumstances of a matter or a class of matters, deems it just or expedient for
deciding such matter or class of matters.
10.3. Nothing in these Regulations shall, expressly or implied, bar the Commission from
dealing with any matter or exercising any power under the Act for which no
Regulations have been framed, and the Commission may deal with such matters,
powers, and functions in a manner, as it considers just and appropriate.
11.
Power to Relax
11.1. The Commission may by general or specific order, for reasons to be recorded in
writing, and after giving an opportunity of hearing to the parties likely to be affected,
may relax any of the provisions of these Regulations on its own motion or on an
application made before it by the affected party.
12.
Power to Remove Difficulties
12.1. If any difficulty arises in giving effect to the provisions of these Regulations, the
Commission may, by general or specific order, give directions, not inconsistent with
the provisions of the Act, as may appear to be necessary or expedient for the purpose
of removing difficulties.
13.
Power to amend
13.1. The Commission may from time to time add, vary, alter, modify or amend any
provisions of these Regulations after following the necessary procedures.
14.
Interpretation
14.1. The decision of the Commission regarding the interpretation of these Regulations
shall be final and binding.
By Order of the Commission,
Rajendra Prasad Nayak,
Secretary
----------
Printed & Published by the Superintendent of Jharkhand Government Press, Doranda, Ranchi.
Jharkhand Gazette (Extraordinary) 247 -- 50.