THE
JHARKHAND GAZETTE
EXTRAORDINARY
PUBLISHED BY AUTHORITY
11 FALGUN 1945 (S)
RANCHI, FRIDAY 1st MARCH, 2024
Urban Development & Housing Department
--------
NOTIFICATION
28th February, 2024
No.-7/न०िव०/अिध/स०सो०/102/2013-820--In exercise of the powers conferred under clause-89 of the
Jharkhand Building Bye-laws, 2016, as amended, the Government of Jharkhand do hereby notify the Jharkhand
Building (Xth Amendment) Bye-laws, 2024.
Sl.
Chapter
Clause
Sub-
clause
Provision
AmendedProvision
1
IV
39
39.7
In case the plot is affected by a road
widening or in the way to construct a
new road/ parks/any public utility and if
the owner of the plot voluntarily
surrenders the affected portion of his
land to the Authority without any claim
of compensation or through a TDR
(Transferable
Development
Right)
scheme
implemented
by
the
Government the owner shall be entitled
to build on the remaining plot, an area
calculated on the basis of the FAR as
In case the plot is affected by a road
widening or in the way to construct a
new road/ parks/any public utility and
if the owner of the plot voluntarily
surrenders the affected portion of his
land to the Authority without any
claim of compensation or through a
TDR
(Transferable
Development
Right) scheme implemented by the
Government the owner shall be
entitled to build on the remaining
plot, an area calculated on the basis of
No. 125
Jharkhand Gazette (Extraordinary), Friday, 1st March, 2024
2
applied to the total area prior to such
surrender. Provided that the surrender
of the land shall be affected by a deed
of transfer to be executed by the owner
in favour of the Authority for widening
of road. The plot owner can use this
T.D.R for any other new building
project within the jurisdiction of the
Competent Authority.
Provided further that, in case of
individual house up to maximum height
of G+2 (where TDR is not availed), the
owner may execute an affidavit from
competent legal authority/public notary
in place of deed of transfer in the favour
of the authority concerned.
the FAR as applied to the total area
prior to such surrender. Provided that
the surrender of the land shall be
affected by a deed of transfer to be
executed by the owner in favour of
the Authority for widening of road.
The plot owner can use this T.D.R for
any other new building project within
the jurisdiction of the Competent
Authority.
Provided further that, in case
of individual house up to maximum
height of G+2 (where TDR is not
availed), the owner may execute an
affidavit
from
competent
legal
authority/public notary in place of
deed of transfer in the favour of the
authority concerned.
Provided in cases, where
affected portion of land through a
deed of transfer cannot be executed
by the owner in favour of the
Authoritydue to any provision of
law being in force, the applicant
shall submit an undertaking to the
effect that such portion of land
could be used for public utilities
(road widening or in the way to
construct a new road/park etc.)
without any hindrancein future. In
case, the applicant creates any
hindrance
in
use
of
affected/marked portions of land
for public utilities (road widening
or in the way to construct a new
road/park etc.)in future, approval
of concerned building plan shall be
deemed to be cancelled without any
further notice.
2
IV
56
56.2
Construction
of
energy
efficient
building shall be referred to Energy
Conservation Building Code, 2007.
Construction of commercial buildings
(as
per
Jharkhand
Energy
Conservation Building Code, 2022
and Jharkhand ECBC Rules, 2022)
having a connected load of 100 Kilo
Watt (kw) or contract demand of 120
Kilo-Volt-Ampere (kVA)and above
shall be referred to Jharkhand Energy
Conservation Building Code, 2022
and Jharkhand ECBC Rules, 2022 for
their compliance.
Jharkhand Gazette (Extraordinary), Friday, 1st March, 2024
3
3
VIII
76
Incentive for solar heating & lighting
and waste water recycling
76.1 Incentive
FAR
shall
be
admissible for Green Building
and
Sustainability
provisions
(installing
Solar
Heating,
Lighting
and
Waste
Water
Recycling, City & Site Level
Greenery,
Roof
Top
Solar
Energy
installation.)
by
the
Authority after assessing the
installation as per following
provisions:
76.1.1 GRIHA Three star/IGBC
Silver
or
equivalent
rating-3% incentive FAR
on basic FAR.
76.1.2 GRIHA Four star/IGBC
Gold
or
equivalent
rating-5% incentive FAR
on basic FAR.
76.1.3 GRIHA Five star/IGBC
Platinum or equivalent
rating-7% incentive FAR
on basic FAR.
Provided that, achieving
minimum GRIHA Three
star/IGBC
Silver
or
equivalent
rating
for
construction
projects
shall be mandatory for all
buildings belonging to
Government,
Semi-
Government, local bodies
and
public
sector
undertakings.
76.2 Incentive FAR will be awarded
after
certification
from
the
empanelled agency. This FAR
shall be exclusive of the limits
specified
in
the
Master
Plan/Building Bye-laws.
76.3 In case that the developer fails to
achieve committed rating as per
certification at the time of final
occupancy, a penalty shall be
imposed at the rate two (2) times
of the land cost as per Circle Rate
for the incentive FAR for the
rating not achieved.
Incentive for solar heating &
lighting and waste water recycling
76.1 Incentive
FAR
shall
be
admissible for Green Building
and Sustainability provisions
(installing
Solar
Heating,
Lighting and Waste Water
Recycling, City & Site Level
Greenery, Roof Top Solar
Energy installation.) by the
Authority after assessing the
installation as per following
provisions:
76.1.1 GRIHA
Three
star/IGBC
Silver/ASSOCHAM
GEM 3 or equivalent
rating-3%
incentive
FAR on basic FAR.
76.1.2 GRIHA
Four
star/IGBC
Gold/ASSOCHAM
GEM 4 or equivalent
rating-5%
incentive
FAR on basic FAR.
76.1.3 GRIHA Five star/IGBC
Platinum/ASSOCHAM
GEM 5 or equivalent
rating-7%
incentive
FAR on basic FAR.
Provided
that,
achieving
minimum
GRIHA
Three
star/IGBC
Silver,
ASSOCHAM GEM 3
or equivalent rating for
construction
projects
shall be mandatory for
all buildings belonging
to Government, Semi-
Government,
local
bodies
and
public
sector undertakings.
76.2 Incentive FAR will be awarded
after certification from the
empanelled agency. This FAR
shall be exclusive of the limits
specified
in
the
Master
Plan/Building Bye-laws.
76.3 In case that the developer fails
Jharkhand Gazette (Extraordinary), Friday, 1st March, 2024
4
76.4
Competent
Qualified
and
experience agencies shall be
empanelled at the State level by
UD&HD who shall duly carryout
the certification activities in all
the areas under Urban Local
Bodies/Regional
Development
Authorities/Urban Public Sector
Undertakings.
76.5 The system of Green Rating for
buildings shall be adopted as per
the guidelines issued under Green
Rating for Integrated Habitat
Assessment (GRIHA) developed
by The Energy and Resource
Institute
(TERI)/Indian
Green
Building Council (IGBC) formed
by the Confederation of Indian
Industry (CII).
to achieve committed rating as
per certification at the time of
final occupancy, a penalty shall
be imposed at the rate two (2)
times of the land cost as per
Circle Rate for the incentive
FAR
for
the
rating
not
achieved.
76.4 Competent
Qualified
and
experience agencies shall be
empanelled at the State level by
UD&HD
who
shall
duly
carryout
the
certification
activities in all the areas under
Urban Local Bodies/Regional
Development
Authorities/Urban
Public
Sector Undertakings.
76.5
The system of Green Rating
for buildings shall be adopted
as per the guidelines issued
under
Green
Rating
for
Integrated Habitat Assessment
(GRIHA) developed by The
Energy and Resource Institute
(TERI)
or
Indian
Green
Building
Council
(IGBC)
formed by the Confederation
of Indian Industry (CII) or
ASSOCHAM GEM developed
by Associated Chamber of
Commerce and Industry of
India (ASSOCHAM).
76.6
The Urban Development &
Housing Department shall be
competent
to
include
or
exclude any process developed
by reputed agencies in future.
By the order of the Governor of Jharkhand,
Arava Rajkamal,
Secretary to Government.
Urban Development & Housing Department.
----------
Printed & Published by the Superintendent of Jharkhand Government Press, Doranda, Ranchi.
Jharkhand Gazette (Extraordinary) 125 -- 50.