21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6715
Gaz. No. 41/2014/DTP (CLR).
L. A. Notifications and Declarations
MALAPPURAM DISTRICT
NOTIFICATION
UNDER SECTION 6 (1) OF THE KERALA SURVEY AND
BOUNDARIES ACT, 1961
Ref. G3-3185/1998.
3rd September 2014.
Whereas, the Government have directed the survey
of land comprised in survey number noted below it is
hereby notified under sub-section (1) of section 6 of the
Kerala Survey and Boundaries Act, 1961, that the survey
operation will be started in the Village soon and
the survey number of the Village noted below will be
demarcated and surveyed and that every persons claiming
to be interested in the registered land situated within or
adjoining the under mentioned land is hereby invited to
attend immediately either in person or by agent on the
surveyor employed in the locality and also from time to
time when called upon for the purpose of pointing out
the boundaries and supplying information in connection
therewith.
Under sub-section (2) of section 6 of the above said
Act, this notification shall be held to be a valid notice to
every person having any interest in the under mentioned
land.
Under sub-section (3) of the section 6 of the above
said Act, all the registered holders are hereby required:—
(a)
to clear within fifteen days by cutting down or
removing any trees, jungle, fences, standing
crops or other material obstructions, the
boundaries or other lines the clearance of which
may be necessary for the purpose of survey; and
(b)
to provide labour at such time and for such
periods as may from time to time be required by
furnishing flag holders and the chainman; and
(c)
to provide suitable survey marks and
otherwise to give such assistance in the survey
as may be demanded under the said Act or
the rules made there under.
If any person fails to comply with these requisitions
under clauses (a) to (c) mentioned above, the work will be
got done by employing hired labour and the cost hereof
will be recovered from the defaulters as provided in the
Act and Rules made thereunder.
DETAILS OF LAND
District—Malappuram.
Taluk—Tirurangadi.
Village—Vengara.
Re-Survey No.—53.
Taluk Office,
(Sd.)
Tirurangadi.
Additional Tahsildar.
KOZHIKODE DISTRICT
NOTIFICATION
UNDER SECTION 13 OF THE KERALA SURVEY AND
BOUNDARIES ACT, 1961
Ref. E-742/1992.
23rd September 2014.
1.
It is hereby notified under section 13 of the
Kerala Survey and Boundaries Act 1961 (Act 37
of 1961) that the Survey of the undermentioned
areas are now completed.
2.
Unless the survey hereby notified is modified by a
decree of a Civil Court under the provisions of
section 14 of the said Act, the records of the
survey shall be conclusive proof that the
boundaries determined and recorded therein have
been correctly determined and recorded.
PARTICULARS OF THE AREA
District—Kozhikode.
Taluk—Kozhikode.
Village—Feroke.
Desom—Nallur.
RS No.
Sub Div.
Extent in
No.
Hectares
287/7A
287/7A
0.1469
287/9
0.0110
0.1579
288/1A
288/1A
1.1766
288/5
0.0510
1.2276
288/3A
288/3A
0.0917
288/6
0.0026
0.0943
289/5B
289/5B
0.4056
289/9
0.0275
0.4331
289/7A
289/7A
0.0291
289/10
0.0093
0.0384
Office of the
(Sd.)
Special Tahsildar (LA) General,
Special Tahsildar,
Kozhikode.
(LA) General.
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6716
WAYANAD DISTRICT
NOTICES
UNDER SECTION 9(2) OF THE KERALA SURVEY AND BOUNDARIES ACT, 1961
The subjoined statement is an extract from the Village survey field registers giving particulars of the lands
registered and surveyed in the name of concerned. Appeal, if any, against the survey should be presented within three
months from the date of Publication of this notice to the officer-in-charge of the survey, whose Headquarters are at
Vellamunda.
Field maps may be obtained on an application and on payment of the fees prescribed from time to time.
(1)
Ref. No. D2-511/2014.
16th September 2014.
Name of the Acquisition—Land for the formation of Venniyode Branch Canal of Banasura Sagar Irrigation Project.
SCHEDULE
District—Wayanad.
Taluk—Vythiri.
Village—Kuppadithara.
Block No.—7.
L.A. Block No.—3.
As per Revenue Accounts
As now surveyed
Sl.
Re-survey/
Sub-division
Area in
Survey
Sub-division
Area in
Remarks
No.
Survey Field No.
No.
Hectares
Field No.
No.
Hectares
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
1
189
1
0.0450
189
7
0.0430
Dry Irrigation
2
189
2
0.0050
189
8
0.0050
Dry Irrigation
3
188
1
0.0250
188
4
0.0240
Dry Irrigation
4
187
1
0.1600
187
4
0.1450
Wet Irrigation
5
187
2
0.1500
187
6
0.1480
Wet Irrigation
6
187
3
0.0550
187
8
0.0420
Wet Irrigation
7
203
1
0.1000
203
8
0.0720
Wet Irrigation
8
203
2
0.1000
203
9
0.0460
Dry Irrigation
9
203
5
0.0500
203
10
0.0200
Dry Irrigation
10
203
6
0.0800
203
11
0.0420
Dry Irrigation
11
203
7
0.0200
203
12
0.0100
Dry Irrigation
12
186
2
0.0300
186
7
0.0150
Wet Irrigation
13
186
6
0.0150
186
8
0.0070
Wet Irrigation
14
184
4
0.1050
184
9
0.0480
Wet Irrigation
15
184
5
0.1100
184
10
0.0460
Wet Irrigation
196
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6717
16
183
8
0.0050
183
11
0.0008
Wet Irrigation
17
204
2
0.2000
204
5
0.1530
Dry Irrigation
18
204
4
0.2000
204
7
0.1400
Dry Irrigation
19
205
1
0.1000
205
8
0.0960
Dry Irrigation
20
178
1
0.0700
..
..
..
..
21
178
2
0.0400
178
11
0.0010
Wet Irrigation
22
178
3
0.0200
..
..
..
..
23
178
4
0.0010
..
..
..
..
24
178
7
0.0200
178
16
0.0140
Dry Irrigation
25
178
9
0.2400
178
18
0.2480
Wet Irrigation
26
300
1
0.0800
300
15
0.0140
Dry Irrigation
27
300
3
0.0700
300
18
0.0640
Dry Irrigation
28
300
9
0.0400
300
20
0.0360
Dry Irrigation
29
300
14
0.0250
300
21
0.0760
Dry Irrigation
30
305
1
0.0050
305
8
0.0020
Wet Irrigation
31
305
3
0.0200
305
9
0.0165
Wet Irrigation
32
305
4
0.1000
305
10
0.1065
Wet Irrigation
33
305
5
0.0700
305
11
0.0660
Dry Irrigation
34
305
6
0.0500
305
12
0.0190
Dry Irrigation
35
..
..
..
305
13
0.0065
Dry Irrigation
36
306
3
0.1000
306
26
0.0980
Dry Irrigation
37
306
4
0.0200
306
28
0.0160
Dry Irrigation
38
306
5
0.0200
306
29
0.0125
Dry Irrigation
39
306
6
0.0350
306
30
0.0405
Dry Irrigation
40
306
8
0.0800
306
31
0.0730
Dry Irrigation
41
306
9
0.0080
306
33
0.0060
Dry Irrigation
42
306
10
0.0150
306
34
0.0100
Dry Irrigation
43
306
11
0.0200
306
35
0.0150
Dry Irrigation
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6718
(2)
Ref. No. D2-705/2014.
16th September 2014.
Name of the Acquisition—Land for the formation of Kuppadithara Distributory Canal (LAB-12A) of Banasura
Sagar Irrigation Project.
SCHEDULE
District—Wayanad.
Taluk—Vythiri.
Village—Kuppadithara.
Block No.—7.
L.A. Block No.—12A.
As per Revenue Accounts
As now surveyed
Sl.
Re-survey/
Sub-division
Area in
Survey
Sub-division
Area in
Remarks
No.
Survey Field No.
No.
Hectares
Field No.
No.
Hectares
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
1
395
2
0.0250
395
29
0.0245
Dry Irrigation
2
395
3
0.0010
395
31
0.0003
Dry Irrigation
3
395
5
0.0120
395
32
0.0120
Dry Irrigation
4
395
8
0.0520
395
34
0.0090
Dry Irrigation
5
..
..
..
395
35
0.0420
Dry Irrigation
6
395
9
0.0400
395
37
0.0400
Dry Irrigation
7
395
25
0.0110
395
39
0.0105
Dry Irrigation
8
395
27
0.0110
395
40
0.0105
Dry Irrigation
9
396
1
0.0120
396
14
0.0120
Wet Irrigation
10
396
2
0.0170
396
15
0.0160
Dry Irrigation
11
396
3
0.0075
396
16
0.0070
Dry Irrigation
12
396
4
0.0090
396
18
0.0085
Dry Irrigation
13
396
6
0.0110
396
19
0.0110
Dry Irrigation
14
396
10
0.0075
396
20
0.0075
Dry Irrigation
15
396
11
0.0120
396
22
0.0115
Dry Irrigation
16
396
12
0.0350
396
23
0.0140
Dry Irrigation
17
408
12
0.0350
408
19
0.0340
Dry Irrigation
18
408
13
0.0150
408
21
0.0140
Dry Irrigation
19
408
18
0.0420
408
23
0.0410
Dry Irrigation
20
409
2
0.0050
409
17
0.0050
Dry Irrigation
21
409
3
0.0075
409
18
0.0070
Dry Irrigation
22
424
2
0.0385
424
9
0.0380
Dry Irrigation
23
..
..
..
424
10
0.0021
Dry Irrigation
24
424
7
0.0010
424
11
0.0004
Dry Irrigation
25
424
8
0.0525
424
12
0.0520
Dry Irrigation
26
425
7
0.0590
425
12
0.0580
Dry Irrigation
27
425
9
0.0725
425
13
0.0720
Dry Irrigation
198
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6719
(3)
Ref. No. D2-702/2014.
19th September 2014.
Name of Acquisition—Land for the formation of Kurumbala Distributory Canal of Banasura Sagar Irrigation Project.
SCHEDULE
District—Wayanad.
Taluk—Vythiri.
Village—Kuppadithara.
Block No.—7.
L.A. Block No.—16.
As per Revenue Accounts
As now surveyed
Sl.
Re-survey/
Sub-division
Area in
Survey
Sub-division
Area in
Remarks
No.
Survey Field No.
No.
Hectares
Field No.
No.
Hectares
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
1
316
1
0.1110
316
5
0.1020
Wet Irrigation
2
316
2
0.0420
316
8
0.0415
Wet Irrigation
3
317
1
0.0120
317
9
0.0115
Wet Irrigation
4
317
2
0.0220
317
11
0.0160
Wet Irrigation
5
317
4
0.0450
317
12
0.0425
Wet Irrigation
6
317
7
0.0170
317
15
0.0165
Wet Irrigation
7
317
8
0.0250
317
17
0.0220
Wet Irrigation
8
326
5
0.0210
326
10
0.0185
Wet Irrigation
9
326
8
0.0160
326
12
0.0115
Wet Irrigation
10
327
1
0.0150
327
6
0.0140
Wet Irrigation
11
328
1
0.0750
328
12
0.0540
Wet Irrigation
328
14
0.0004
Wet Irrigation
12
328
2
0.0500
328
16
0.0415
Wet Irrigation
13
328
4
0.0020
328
17
0.0016
Wet Irrigation
14
328
10
0.0390
328
18
0.0390
Wet Irrigation
15
329
2
0.0170
329
20
0.0140
Dry Irrigation
16
329
3
0.0280
329
21
0.0180
Dry Irrigation
17
329
16
0.0120
329
22
0.0130
Dry Irrigation
18
330
10
0.0020
330
15
0.0005
Dry Irrigation
Gaz. No. 41/2014/DTP (CLR).
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6720
19
331
3
0.0160
331
11
0.0140
Wet Irrigation
20
331
5
0.0200
331
13
0.0200
Wet Irrigation
21
331
6
0.0320
331
14
0.0340
Wet Irrigation
22
331
8
0.0220
331
15
0.0190
Wet Irrigation
23
332
4
0.0200
332
7
0.0185
Wet Irrigation
24
332
6
0.0250
332
9
0.0235
Wet Irrigation
25
335
4
0.0460
335
7
0.0420
Wet Irrigation
26
335
5
0.0320
335
9
0.0290
Wet Irrigation
27
335
6
0.0380
335
11
0.0345
Wet Irrigation
28
337
1
0.0650
337
4
0.0580
Wet Irrigation
29
337
2
0.0380
337
6
0.0325
Wet Irrigation
30
338
1
0.0650
338
7
0.0590
Wet Irrigation
31
338
4
0.0210
338
9
0.0210
Wet Irrigation
32
338
6
0.0250
338
11
0.0235
Wet Irrigation
33
339
1
0.0550
339
7
0.0480
Wet Irrigation
34
339
3
0.0015
339
9
0.0010
Wet Irrigation
35
340
1
0.0650
340
7
0.0459
Wet Irrigation
36
340
2
0.0180
340
9
0.0130
Wet Irrigation
37
344
1
0.0480
344
10
0.0200
Wet Irrigation
38
345
1
0.0200
345
12
0.0115
Wet Irrigation
39
345
4
0.0320
345
13
0.0260
Wet Irrigation
40
345
5
0.0750
345
16
0.0760
Wet Irrigation
41
345
6
0.0180
345
17
0.0175
Wet Irrigation
42
345
7
0.0040
345
18
0.0030
Wet Irrigation
43
345
8
0.0040
345
19
0.0035
Wet Irrigation
44
345
9
0.0080
345
20
0.0060
Wet Irrigation
45
361
2
0.0040
361
4
0.0035
Wet Irrigation
46
361
3
0.0160
361
5
0.0150
Wet Irrigation
47
373
2
0.0360
373
3
0.0135
Dry Irrigation
373
4
0.0080
Dry Irrigation
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
200
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6721
(4)
Ref. No. D2-704/2014.
24th September 2014.
Name of Acquisition—Land for the formation of Kuppadithara Distributory Canal of Banasura Sagar Irrigation
Project.
SCHEDULE
District—Wayanad.
Taluk—Vythiri.
Village—Kuppadithara.
Block No.—7.
L.A. Block No.—11.
As per Revenue Accounts
As now surveyed
Sl.
Re-survey/
Sub-division
Area in
Survey
Sub-division
Area in
Remarks
No.
Survey Field No.
No.
Hectares
Field No.
No.
Hectares
1
490
2
0.0185
495
5
0.0185
Wet Irrigation
2
490
3
0.0500
490
7
0.0500
Wet Irrigation
3
494
5
0.1050
494
14
0.1040
Dry Irrigation
4
495
1
0.0700
495
10
0.0183
Dry Irrigation
0.0311
Dry Irrigation
0.0186
Dry Irrigation
5
495
2
0.0850
495
12
0.0830
Dry Irrigation
6
496
3
0.0400
496
10
0.0016
Dry Irrigation
0.0358
Dry Irrigation
7
496
5
0.0330
496
12
0.0127
Dry Irrigation
0.0180
Dry Irrigation
0.0023
Dry Irrigation
8
496
6
0.0250
496
14
0.0063
Dry Irrigation
0.0138
Dry Irrigation
496
14
0.0009
Dry Irrigation
9
496
7
0.0010
496
16
0.0010
Dry Irrigation
10
496
8
0.0650
496
17
0.0640
Dry Irrigation
11
500
1
0.0050
500
17
0.0040
Dry Irrigation
12
500
2
0.0030
500
18
0.0030
Dry Irrigation
13
500
5
0.0410
500
19
0.0405
Dry Irrigation
Office of the Special Tahsildar (LA),
(Sd.)
BSIP, Kattayad P. O.,
Special Tahsildar (LA),
Vellamunda.
BSIP, Vellamunda.
21st OCT. 2014]
COMMISSIONERATE OF LAND REVENUE
6722
KANNUR DISTRICT
NOTIFICATIONS
UNDER SECTION 13 OF THE KERALA SURVEY AND
BOUNDARIES ACT, 1961
1.
It is hereby notified under Section 13 of the
Kerala Survey and Boundaries Act, 1961 (Act 37
of 1961) that the Survey of the undermentioned
areas are now complete.
2.
Unless the survey hereby notified is modified by
a decree of a Civil Court under the provisions of
Section 14 of the said Act, the records of the
survey shall be conclusive proof that the
boundaries determined and recorded there in
have been correctly determined and recorded.
(1)
Ref. A-1842/2004.
19th September 2014.
PARTICULARS OF AREA
District—Kannur.
Taluk—Thalassery.
Village—Kottayam.
Amsom—Kottayam.
Desom—Eruvatty.
Field Numbers (Survey Numbers)—32, 34, 36, 37, 40,
42, 44, 49, 46, 47, 50, 51, 54, 55, 58, 101, 59,
60, 104.
Sub Division No.—32/8, 34/5, 34/6, 34/7, 34/8, 34/9,
36/8, 36/10, 36/11, 37/9, 37/7, 37/8, 37/10, 37/11, 37/
12, 40/7, 40/8, 40/9, 42/15, 42/16, 42/17, 44/12, 44/13,
44/14, 44/15, 44/16, 49/12, 49/13, 46/9,
46/10, 47/7, 47/8, 47/9, 47/10, 47/11, 50/5, 50/6, 50/7,
51/4, 54/3, 55/5, 55/6, 58/13, 58/14, 58/15, 58/16,58/
17, 101/12, 101/13, 59/11, 59/12, 59/13, 60/11, 60/12,
60/`13, 60/14, 60/15, 104/3.
(2)
Ref. A-1853/2004.
19th September 2014.
PARTICULARS OF AREA
District—Kannur.
Taluk—Thalassery.
Village—Kottayam.
Amsom—Kottayam.
Desom—Kottayam.
Field Numbers (Survey Numbers)—82, 85, 86, 87, 89.
Sub Division No.—82/11, 82/12, 82/13, 82/14, 85/4, 86/9,
86/10, 87/5, 87/6, 89/3.
Office of the
(Sd.)
Special Tahsildar, LA (KSTP),
Special Tahsildar,
Thalassery.
LA (KSTP), Thalassery.
202