KERALA STATE ELECTRICITY REGULATORY COMMISSION
THIRUVANANTHAPURAM
NOTIFICATION
No. 3401/Com.Ex./2023/KSERC.
Dated, 6th January, 2025.
KERALA ELECTRICITY SUPPLY CODE (REMOVAL OF DIFFICULTIES) ORDER, 2025
WHEREAS, the Kerala Electricity Supply Code, 2014 (hereinafter referred to as the Code)
came into force on the 1st April, 2014;
AND WHEREAS, Regulation 36(iii) of the Code provides that the expenditure for
extension or upgradation or both of the distribution system undertaken exclusively for giving
new service connection to any person or a collective body of persons or a developer or a builder
or for enhancing the load demand of a consumer or a collective body of consumers or a
developer or builder, shall be borne by the respective applicant or consumer or collective body
of consumers or developer or builder, as the case may be, for meeting the demand of the
©
േകരള സർകാർ
Government of Kerala
2025
േകരള ഗസറ്
KERALA GAZETTE
അസാധാരണം
EXTRAORDINARY
ആധികാരികമായി ്പസിദെപടുതുനത
PUBLISHED BY AUTHORITY
Regn.No. KERBIL/2012/45073
dated 05-09-2012 with RNI
Reg No.KL/TV(N)/634/2021-2023
വാല്ം 14
Vol. XIV
തിരുവനനപുരം,
െചാവ
Thiruvananthapuram,
Tuesday
2025 ജനുവരി 07
07th January 2025
1200 ധനു 23
23rd Dhanu 1200
1946 െപൗഷം 17
17th Pousha 1946
നമർ
No.
49
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
domestic or commercial or industrial complex or colony constructed by a developer or a builder
with a demand above one megawatt(MW);
AND WHEREAS, as per Kerala Electricity Supply (Fifth Amendment) Code, 2024, sub
regulation (1) of Regulation 49 provides that the expenditure for modification, upgradation and
uprating of the distribution system of the licensee executed, if any, exclusively for giving
connection shall be realised from the applicants for the cases specified in Regulation 36 of the
Code;
AND WHEREAS, as per Kerala Electricity Supply (Amendment) Code, 2020, sub
regulation (5) of Regulation 49 provides that the development authority or the promoter or the
builder or the developer or such other person, as the case may be, who constructs such colony
or complex or high rise building under the clauses (a), (b) and (c) of sub regulation (1) above,
shall, at his cost, construct the required internal distribution network, including the service line,
transformer, switchgear, metering cubicles etc., as per the detailed scheme approved by the
Electrical Inspector, for receiving power from the licensee and for distributing it and shall
handover the metering cubicle to the licensee before commencement of supply of electricity.
The internal distribution network including the transformer and switchgears and the
underground service line cable of transformers are to be maintained by the development
authority or the promoter or the builder or the developer or present occupier/building
association or any other person who is the present registered consumer of the colony or
residential complex or a commercial complex or an industrial complex or a high-rise building;
AND WHEREAS, as per Kerala Electricity Supply (Fifth Amendment) Code, 2024, sub
regulation (7) of Regulation 49 provides that in the case of colony or residential complex or
commercial complex or industrial complex except high rise building, with total load demand
of and below one megawatt (MW), the following conditions shall be applicable:—
(a) The licensee shall bear the expenditure for modification or upgradation or
uprating of the distribution system;
(b) The responsibility for construction of the required internal distribution network,
including the service line, switchgear etc. for receiving power from the licensee and distributing
it, shall be that of the authority or promoter or builder or developer or any other person who
constructs such complex;
2
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
(c) The security deposits and other charges if any payable by the consumer shall be
borne individually by each applicant at the time of applying for electricity connection.
Provided that, individual consumers have to remit the charges based on normal per
kVA/kW rates.
AND WHEREAS, sub section (1) of Section 43 of the Electricity Act, 2003 provides that
the licensee, shall, on an application by the owner or occupier of any premises, give supply of
electricity to such premises, within one month after receipt of the application requiring such
supply:
Provided that where such supply requires extension of distribution mains, or
commissioning of new sub-stations, the distribution licensee shall supply the electricity to such
premises immediately after such extension or commissioning or within such period as may be
specified by the Appropriate Commission:
AND WHEREAS, several complaints have been received regarding the supply of electricity
to individual beneficiaries or collective bodies of beneficiaries in residential colonies/villa
projects. These issues have arisen due to the non-performance of mandatory obligations by the
promoters or developers of such projects. The problems include failure to complete the projects
within the timelines stipulated by the Real Estate Regulatory Authority, abandonment of
projects midway before handing them over to the beneficiaries and/or ongoing disputes
between the promoters and beneficiaries pending before the Kerala Real Estate Regulatory
Authority or the Appellate Tribunal;
AND WHEREAS, the licensees face difficulties in providing timely electricity supply to
individual beneficiaries or collective bodies of beneficiaries due to the failure of promoters or
developers of such residential colonies and villa projects to fulfil their obligations. This include
the non-remittance of the required expenditure for modifications, upgradations, and uprating
of the distribution system, as well as the construction of the necessary internal distribution
network, including service lines, transformers, switchgear, and other components, for reasons
outlined in the preceding paragraph;
AND WHEREAS, the Kerala Real Estate Regulatory Authority is empowered to protect the
interests of individuals affected by the non-performance of mandatory obligations, including
financial frauds, as well as the abandonment or failure of projects for any reason midway,
3
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
before they are handed over to individual beneficiaries/collective body of beneficiaries by the
promoters or developers of residential colonies/villa projects registered and approved by the
Kerala Real Estate Regulatory Authority;
AND WHEREAS, the Kerala Real Estate Regulatory Authority lacks jurisdiction to direct
the licensees under the Electricity Act, 2003 to take necessary action to provide the basic
amenities such as electricity connection due to non-performance of mandatory action on the
part of promoters/developers of the residential colonies/villa projects;
AND WHEREAS, the Commission has satisfied that the difficulties arisen in providing
electricity connection to the individual beneficiary/collective body of beneficiaries within
residential colonies/villa projects developed by promoters/developers wherein the
promoter/developer fails to discharge responsibilities envisaged under Regulations 36 and 49
of the Code, need to be addressed;
AND WHEREAS, the Commission has satisfied that the issues relating to recovery of
capital cost incurred by the licensee for providing electricity connection to the individual
beneficiary/collective body of beneficiaries within the residential colonies/villa projects due to
abandonment of projects in the mid-way before handing over it to the individual beneficiary or
due to pendency of disputes between the promoter/developer and the individual beneficiary
before the Kerala Real Estate Regulatory Authority/Appellate Tribunal or due to failure of
projects within the time line allotted by Kerala Real Estate Regulatory Authority for any other
reasons need to be addressed;
NOW, THEREFORE, the Commission in exercise of its powers conferred by Regulation
179 of the Code, hereby makes the following order in public interest and to remove the
difficulties related to implementation of Regulations 36 and 49 of the Code, namely:—
1. Short title and commencement.—(1) These Regulations shall be called the “Kerala
Electricity Supply Code (Removal of Difficulties) Order 2025.”
(2) It shall come into force from the date of this order.
2. Relaxation of Regulation 36 and 49.—(1) Notwithstanding anything contained in
Regulations 36 and 49 of the Code, individual beneficiaries within residential colonies or villa
projects, where projects have been abandoned midway before being handed over to the
4
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
beneficiaries, or where disputes between the promoter/developer and individual beneficiaries
are pending before the Kerala Real Estate Regulatory Authority or the Appellate Tribunal, or
where projects have failed to meet the timelines allotted by the Kerala Real Estate Regulatory
Authority shall be at liberty to approach the licensee for availing service connections by
submitting separate applications.
(2) The licensee shall verify the application form and if the application form is in
order estimate and inform the expenditure as follows:—
(a) If the total load of the residential colony/villa projects is more than one
megawatt, estimate the expenditure to be incurred for extension or upgradation or both of the
distribution system undertaken exclusively for giving new service connection and the expenses
for constructing internal distribution network including service line, transformer, switch gear,
metering cubicles etc. for receiving power from the licensee and intimate the proportionate
expenditure to be remitted by the applicant based on the connected load of his/her premises.
(b) If the total load of the residential colony/villa projects is of and below one
megawatt, estimate the expenditure to be incurred for constructing the required internal
distribution network including the service line, transformer, switchgear, metering cubicles etc.
for receiving power from the licensee and intimate the proportionate expenditure to be remitted
by the applicant based on the connected load of his/her premises.
(3) Upon receiving the intimation regarding the expenses, the individual
beneficiary/collective body of beneficiaries shall remit the proportionate share of the expenses,
calculated based on their connected load, to avail the service connection.
(4) The remaining expenditure for the extension or upgradation of the distribution
system and/or the construction of the internal distribution network, as applicable, shall be
recovered from other individual beneficiaries in proportion to their connected load as and when
they apply for electrical connection to their individual villas.
(5) The capital cost incurred by the licensee in this regard can be initially included
in the GFA/NFA in the ARR & ERC for the corresponding year and the said expenses may be
netted off from the GFA/NFA based on the consumer contribution on receipt of the recovery of
balance expenses from other individual beneficiaries.
5
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
(6) The internal distribution network including the transformer and switch gears and
the underground service line cable of transformers developed as above are to be maintained by
the distribution licensee and the expenses thereof can be claimed in the ARR & ERC of the
licensee based on the norms provided in the tariff regulations.
By order of the Commission,
C. R. SATHEESH CHANDRAN,
Secretary, Kerala State Electricity Regulatory Commission.
6
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
____________________________________________________________________________________________________________________________
PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES
AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2025