GOVERNMENT OF KERALA
NOTIFICATION
In exercise of the powers conferred by 2nd proviso to subsection 7 of section 19 of the Right to
Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
(Central Act 30 of 2013), the Government of Kerala hereby extend the time limit in publishing the
declaration as per sub-section 1 of section 19 to the Notification issuedunder sub-section (1) of section
11 as per Proceedings No. C1-5068/2021 dated 10th May 2022 and published in the Extra Ordinary
Gazette No. 1571 dated 13th May 2022, namely:-
REVENUE (B) DEPARTMENT
G.O.(P)No.323/2024/RD
Dated, 23/12/2024
Thiruvananthapuram,
©
േകരള സർകാർ
Government of Kerala
2025
േകരള ഗസറ്
KERALA GAZETTE
അസാധാരണം
EXTRAORDINARY
ആധികാരികമായി ്പസിദെപടുതുനത
PUBLISHED BY AUTHORITY
Regn.No. KERBIL/2012/45073
dated 05-09-2012 with RNI
Reg No.KL/TV(N)/634/2021-2023
വാല്ം 14
Vol. XIV
തിരുവനനപുരം,
ബുധന
Thiruvananthapuram,
Wednesday
2025 ജനുവരി 08
08th January 2025
1200 ധനു 24
24th Dhanu 1200
1946 െപൗഷം 18
18th Pousha 1946
നമർ
No.
53
S. R. O. No. 28/2025
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
Extension
Proceedings No. C1-5068/2021 dated 10th May 2022 and published in the Extra Ordinary
Gazette No. 1571 dated 13th May 2022 has been issued in accordance with the provisions of sub-
section (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of 1.99 Hectares of land in
Velloorkunnam and Marady villages of Ernakulam district for the construction of Muvattupuzha Bypass
(From 130 junction to M.C.Road to Kadathy Junction in NH 85).
AND WHEREAS, the District Collector, Ernakulam has reported that as per Section 19(7) of
LARR Act, 2013 mentions that the 19(1) Declaration has to be published within 12 months from the
date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as
per Proceedings No. C1-5068/2021 dated 10th May 2022 and published in the Extra Ordinary Gazette
No. 1571 dated 13th May 2022 and extended as per G.O.(P)No.123/2023/RD dated 17th May 2023 and
published in the Extra Ordinary Gazette No. 1684 dated 18th May 2023 expired on 13/05/2024 and
therefore requested to extend the time limit for publishing the 19(1) Declaration.
NOW THEREFORE, sanction is accorded to extend the time limit in publishing the Declaration
for a further period of 12 months from the date of expiry of the 11(1) notification ie, 13/05/2024 by
invoking the provisions contained in 2nd proviso to Section 19(7) of the LARR Act, 2013 with regard to
the acquisition of 1.99 Hectares of land in Velloorkunnam and Marady villages of Ernakulam district for
the construction of Muvattupuzha Bypass (From 130 junction to M.C.Road to Kadathy Junction in NH
85).
By order of the Governor,
ABDUL NASAR B
ADDITIONAL SECRETARY TO GOVERNMENT
Explanatory Note
(This does not form part of the notification, but is intended to indicate its general purport)
Proceedings No. C1-5068/2021 dated 10th May 2022 and published in the Extra Ordinary
Gazette No. 1571 dated 13th May 2022, has been issued in accordance with the provisions of
subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of 1.99 Hectares of land in
Velloorkunnam and Marady villages of Ernakulam district for the construction of Muvattupuzha Bypass
(From 130 junction to M.C.Road to Kadathy Junction in NH 85). As per Section 19(7) of LARR Act,
2013, the 19(1) Declaration has to be published within 12 months from the date of issuance of 11(1)
Notification (preliminary notification) and that the 11(1) Notification issued as per Proceedings No. C1-
5068/2021 dated 10th May 2022 and published in the Extra Ordinary Gazette No. 1571 dated 13th May
2022 and extended as per G.O.(P)No.123/2023/RD dated 17th May 2023 and published in the Extra
Ordinary Gazette No. 1684 dated 18th May 2023 expired on 13/05/2024 and hereby extend the time
limit for publishing the 19(1) Declaration.
The notification is intended to achieve the above object.
2
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
____________________________________________________________________________________________________________________________
PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES
AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2025