GOVERNMENT OF KERALA
NOTIFICATION
In exercise of the powers conferred by 1st proviso to section 14 of the Right to Fair
Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013
(Central Act 30 of 2013), the Government of Kerala hereby extend the time limit in publishing the
Notification as per sub-section (1) of Section 11 of LARR Act, 2013, from the date of appraisal of the
Social Impact Assessment report by the Expert Group namely :-
REVENUE (B) DEPARTMENT
G.O.(P)No.475/2025/RD
Dated,Thiruvananthapuram, 17th December, 2025.
©
േകരള സർകാർ
Government of Kerala
2025
േകരള ഗസറ്
KERALA GAZETTE
അസാധാരണം
EXTRAORDINARY
ആധികാരികമായി ്പസിദെപടുതുനത
PUBLISHED BY AUTHORITY
Regn.No. KERBIL/2012/45073
dated 05-09-2012 with RNI
Reg No.KL/TV(N)/634/2021-2023
വാല്ം 14
Vol. XIV
തിരുവനനപുരം,
വ്ാഴം
Thiruvananthapuram,
Thursday
2025 ഡിസംബർ 18
18th December 2025
1201 ധനു 3
3rd Dhanu 1201
1947 അ്ഗഹായനം 27
27th Agrahayana 1947
നമർ
No.
4251
S. R. O. No. 1376/2025
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
Extension
Proceedings No.K6-48847/2022 dated 21st March 2024 and published in the Extra Ordinary
Gazette No.1126 dated 25th March 2024 has been issued in accordance with the provisions as per sub
section (1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition,
Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of
82.9 Ares of land in Vizhinjam Village of Thiruvananthapuram District for rail connectivity between
Vizhinjam International Seaport to Balaramapuram Railway station.
AND WHEREAS, the District Collector, Thiruvananthapuram has informed that as per section
14 of LARR Act, 2013 where a preliminary notification under sub-section (1) of section 11 is not issued
within twelve months from the date of appraisal of the Social Impact Assessment report submitted by
the Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh
Social Impact Assessment shall be required to be undertaken prior to acquisition proceedings under
section 11. The date of appraisal of the Social Impact Assessment report by the Expert Group under
section 7 was submitted on 17-12-2024 and the Notification under sub-section (1) of section 11 needs
to be issued on or before 16-12-2025.
AND WHEREAS, the District Collector, Thiruvananthapuram has requested to extend the time
limit in publishing the Notification as per sub-section (1) of Section 11 of LARR Act, 2013 from the date
of appraisal of the Social Impact Assessment report by the Expert Group.
NOW THEREFORE, sanction is accorded to extend the time limit for a further period of six
months from 17-12-2025 in publishing the Notification under subsection (1) of section 11 by invoking
the provisions contained in 1st proviso to section 14 of LARR Act, 2013 with regard to the acquisition
of 82.9 Ares of land in Vizhinjam Village of Thiruvananthapuram District for rail connectivity between
Vizhinjam International Seaport to Balaramapuram Railway station.
By order of the Governor,
GEETHA A
ADDITIONAL SECRETARY TO GOVERNMENT
Explanatory Note
(This does not form part of the notification, but is intended to indicate its general purport.)
Proceedings No.K6-48847/2022 dated 21st March 2024 and published in the Extra Ordinary
Gazette No.1126 dated 25th March 2024 has been issued in accordance with the provisions of section
(1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition, Rehabilitation
and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of 82.9 Ares of land
in Vizhinjam Village of Thiruvananthapuram District for rail connectivity between Vizhinjam
International Seaport to Balaramapuram Railway station. As per section 14 of LARR Act, 2013 where
a preliminary notification under subsection (1) of section 11 is not issued within twelve months from
the date of appraisal of the Social Impact Assessment report submitted by the Expert Group under
section 7, then, such report shall be deemed to have lapsed and a fresh Social Impact Assessment
shall be required to be undertaken prior to acquisition proceedings under section 11. The date of
appraisal of the Social Impact Assessment report by the Expert Group under section 7 expired on
16-12-2025 and therefore extend the time limit for publishing the Notification under sub-section (1) of
section 11.
The notification is intended to achieve the above object.
2
This is a digitally signed Gazette.
Authenticity may be verified through https://compose.kerala.gov.in/
____________________________________________________________________________________________________________________________
PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES
AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2025