GOVERNMENT OF KERALA

NOTIFICATION

In exercise of the powers conferred by 2nd proviso to subsection 7 of section 19 of the Right to

Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

(Central Act 30 of 2013), the Government of Kerala hereby extend the time limit in publishing the

declaration as per sub-section 1 of section 19 to the Notification issued under sub-section (1) of

section 11 as per Proceedings No.DCTSR/1312/2023-E5 dated 3rd October 2024 and published in the

Extra Ordinary Gazette No.3098 dated 3rd October 2024, namely:-

REVENUE (B) DEPARTMENT

G.O.(P)No.15/2026/RD

Dated, Thiruvananthapuram, 11th January, 2026.

©

േകരള സർകാർ

Government of Kerala

2026

േകരള ഗസറ്

KERALA GAZETTE

അസാധാരണം

EXTRAORDINARY

ആധികാരികമായി ്പസിദെപടുതുനത

PUBLISHED BY AUTHORITY

Regn.No. KERBIL/2012/45073

dated 05-09-2012 with RNI

Reg No.KL/TV(N)/634/2021-2023

വാല്ം 15

Vol. XV

തിരുവനനപുരം,

െചാവ

Thiruvananthapuram,

Tuesday

2026 ജനുവരി 13

13th January 2026

1201 ധനു 29

29th Dhanu 1201

1947 െപൗഷം 23

23rd Pousha 1947

നമർ

No.

138

S. R. O. No. 43/2026

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

Extension

Proceedings No.DCTSR/1312/2023-E5 dated 3rd October 2024 and published in the Extra

Ordinary Gazette No.3098 dated 3rd October 2024 has been issued in accordance with the provisions

of subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of 0.0355

Hectares of land in Nellayi and Chengalur villages of Thrissur district for the construction of Regulator

cum bridge and its approach road across Kurumali river.

AND WHEREAS, the District Collector, Thrissur has reported that as per Section 19(7) of

LARR Act, 2013 mentions that the 19(1) Declaration has to be published within 12 months from the

date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as

per Proceedings No.DCTSR/1312/2023-E5 dated 3rd October 2024 and published in the Extra

Ordinary Gazette No.3098 dated 3rd October 2024 expired on 02-10-2025 and therefore requested to

extend the time limit for publishing the 19(1) Declaration.

NOW THEREFORE, sanction is accorded to extend the time limit in publishing the Declaration

for a further period of six months from the date of expiry of the 11(1) notification ie, 02-10-2025 by

invoking the provisions contained in 2nd proviso to Section 19(7) of the LARR Act, 2013 with regard to

the acquisition of 0.0355 Hectares of land in Nellayi and Chengalur villages of Thrissur district for the

construction of Regulator cum bridge and its approach road across Kurumali river.

By order of the Governor,

GEETHA A

ADDITIONAL SECRETARY TO GOVERNMENT

Explanatory Note

(This does not form part of the notification, but is intended to indicate its general purport.)

Proceedings No.DCTSR/1312/2023-E5 dated 3rd October 2024 and published in the Extra

Ordinary Gazette No.3098 dated 3rd October 2024 has been issued in accordance with the provisions

of subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of 0.0355

Hectares of land in Nellayi and Chengalur villages of Thrissur district for the construction of Regulator

cum bridge and its approach road across Kurumali river. As per Section 19(7) of LARR Act, 2013, the

19(1) Declaration has to be published within 12 months from the date of issuance of 11(1) Notification

(preliminary notification) and that the 11(1) Notification issued as per Proceedings

No.DCTSR/1312/2023-E5 dated 3rd October 2024 and published in the Extra Ordinary Gazette

No.3098 dated 3rd October 2024 expired on 02-10-2025 and therefore extend the time limit for

publishing the 19(1) Declaration.

The notification is intended to achieve the above object.

2

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

____________________________________________________________________________________________________________________________

PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES

AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2026