GOVERNMENT OF KERALA

NOTIFICATION

In exercise of the powers conferred by 2nd proviso to subsection 7 of section 19 of the Right to

Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

(Central Act 30 of 2013), the Government of Kerala hereby extend the time limit in publishing the

declaration as per sub-section 1 of section 19 to the Notification issued under sub-section (1) of

section 11 as per Proceedings No.G3-10116/21 dated 14th January 2024 and published in the Extra

Ordinary Gazette No.152 dated 16th January 2024, namely:-

REVENUE (B) DEPARTMENT

G.O.(P)No.20/2026/RD

Dated, Thiruvananthapuram, 13th January, 2026.

©

േകരള സർകാർ

Government of Kerala

2026

േകരള ഗസറ്

KERALA GAZETTE

അസാധാരണം

EXTRAORDINARY

ആധികാരികമായി ്പസിദെപടുതുനത

PUBLISHED BY AUTHORITY

Regn.No. KERBIL/2012/45073

dated 05-09-2012 with RNI

Reg No.KL/TV(N)/634/2021-2023

വാല്ം 15

Vol. XV

തിരുവനനപുരം,

െവളി

Thiruvananthapuram,

Friday

2026 ജനുവരി 16

16th January 2026

1201 മകരം 2

2nd Makaram 1201

1947 െപൗഷം 26

26th Pousha 1947

നമർ

No.

185

S. R. O. No. 55/2026

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

Extension

Proceedings No. G3-10116/21 dated 14th January 2024 and published in the Extra Ordinary

Gazette No.152 dated 16th January 2024 has been issued in accordance with the provisions of

subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013 for the acquisition of land in Champakulam village of

Kuttanad taluk in Alappuzha District for the construction of Govenda Bridge and Approach Road.

AND WHEREAS, the District Collector, Alappuzha has reported that as per Section 19(7) of

LARR Act, 2013 mentions that the 19(1) Declaration has to be published within 12 months from the

date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as

per Proceedings No.G3-10116/21 dated 14th January 2024 and published in the Extra Ordinary

Gazette No.152 dated 16th January 2024 and extended as per G.O.(P)No.38/2025/RD dated 28th

January 2025 and published in the Extra Ordinary Gazette No.376 dated 04th February 2025 and

G.O.(P) No.262/2025/RD dated 17th July 2025 and published in the Extra Ordinary Gazette No.2657

dated 18th July 2025 expires on 15/01/2026 and therefore requested to extend the time limit for

publishing the 19(1) Declaration.

NOW THEREFORE, sanction is accorded to extend the time limit in publishing the Declaration

for a further period of six months from the date of expiry of the 11(1) notification ie. 15/01/2026 by

invoking the provisions contained in 2nd proviso to Section 19(7) of the LARR Act, 2013 for the

acquisition of land in Champakulam village of Kuttanad taluk in Alappuzha District for the construction

of Govenda Bridge and Approach Road.

By order of the Governor,

GEETHA A

ADDITIONAL SECRETARY TO GOVERNMENT

Explanatory Note

(This does not form part of the notification, but is intended to indicate its general purport.)

Proceedings No.G3-10116/21 dated 14th January 2024 and published in the Extra Ordinary

Gazette No.152 dated 16th January 2024, has been issued in accordance with the provisions of

subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013 for the acquisition of land in Champakulam village of

Kuttanad taluk in Alappuzha District for the construction of Govenda Bridge and Approach Road. As

per Section 19(7) of LARR Act, 2013, the 19(1) Declaration has to be published within 12 months from

the date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued

as per Proceedings No.G3-10116/21 dated 14th January 2024 and published in the Extra Ordinary

Gazette No.152 dated 16th January 2024 and extended as per G.O.(P)No.38/2025/RD dated 28th

January 2025 and published in the Extra Ordinary Gazette No.376 dated 04th February 2025 and

G.O.(P) No.262/2025/RD dated 17th July 2025 and published in the Extra Ordinary Gazette No.2657

dated 18th July 2025 expires on 15/01/2026 and hereby extend the time limit for publishing the 19(1)

Declaration.

The notification is intended to achieve the above object.

2

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

____________________________________________________________________________________________________________________________

PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES

AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2026