GOVERNMENT OF KERALA

NOTIFICATION

In exercise of the powers conferred by 1st proviso to section 14 of the Right to Fair

Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013

(Central Act 30 of 2013), the Government of Keralam hereby extend the time limit in publishing the

Notification as per sub-section (1) of Section 11 of LARR Act, 2013, from the date of appraisal of the

Social Impact Assessment report by the Expert Group namely:-

Revenue (B) Department

G.O.(P) No.271/2026/RD

Dated,Thiruvananthapuram, 31st August, 2026.

©

േകരള സർകാർ

Government of Kerala

2026

േകരള ഗസറ്

KERALA GAZETTE

അസാധാരണം

EXTRAORDINARY

ആധികാരികമായി ്പസിദെപടുതുനത

PUBLISHED BY AUTHORITY

Regn.No. KERBIL/2012/45073

dated 05-09-2012 with RNI

Reg No.KL/TV(N)/634/2021-2023

വാല്ം 15

Vol. XV

തിരുവനനപുരം,

ബുധന

Thiruvananthapuram,

Wednesday

2026 െസപറംബർ 02

02nd September 2026

1202 ചിങം 17

17th Chingam 1202

1948 ഭാ്ദം 11

11th Bhadra 1948

നമർ

No.

2388

S. R. O. No. 732/2026

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

Extension

Proceedings No.DCWYD/1620/21-B1 dated 9th August 2021 and published in the Extraordinary

Gazette No.2786 dated 25th September 2021 has been issued in accordance with the provisions as per

section (1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition,

Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of

land in Vythiri Taluk of Wayanad District for Banasura Sagar Irrigation Project.

AND WHEREAS, the District Collector, Wayanad has informed that as per section 14 of LARR

Act, 2013 where a preliminary notification under sub-section (1) of section 11 is not issued within

twelve months from the date of appraisal of the Social Impact Assessment report submitted by the

Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh Social

Impact Assessment shall be required to be undertaken prior to acquisition proceedings under section 11.

The date of appraisal of the Social Impact Assessment report by the Expert Group under section 7

extended as per G.O.(P)No.431/2025/RD dated 25th October 2025 and published in the Extraordinary

Gazette No.3781 dated 27th October 2025 expired on 17-05-2026.

AND WHEREAS, the District Collector, Wayanad has requested to extend the time limit in

publishing the Notification as per sub-section (1) of Section 11 of LARR Act, 2013 from the date of

appraisal of the Social Impact Assessment report by the Expert Group.

NOW THEREFORE, sanction is accorded to extend the time limit for a further period of six

months from the date of expiry ie. 17-05-2026 in publishing the Notification under sub-section (1) of

section 11 by invoking the provisions contained in 1st proviso to section 14 of LARR Act, 2013 with

regard to the acquisition of land in Vythiri Taluk of Wayanad District for Banasura Sagar Irrigation

Project.

By order of the Governor,

GEETHA A.

Additional Secretary to Government.

Explanatory Note

(This does not form part of the notification, but is intended to indicate its general purport.)

Proceedings No.DCWYD/1620/21-B1 dated 9th August 2021 and published in the Extraordinary

Gazette No.2786 dated 25th September 2021 has been issued in accordance with the provisions of

section (1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition,

Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of

land in Vythiri Taluk of Wayanad District for Banasura Sagar Irrigation Project. As per section 14 of

LARR Act, 2013 where a preliminary notification under subsection (1) of section 11 is not issued

within twelve months from the date of appraisal of the Social Impact Assessment report submitted by

the Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh Social

Impact Assessment shall be required to be undertaken prior to acquisition proceedings under section 11.

The date of appraisal of the Social Impact Assessment report by the Expert Group under section 7

extended as per G.O.(P)No.431/2025/RD dated 25th October 2025 and published in the Extraordinary

Gazette No.3781 dated 27th October 2025 expired on 17-05-2026 and therefore extend the time limit for

publishing the Notification under sub-section (1) of section 11.

The notification is intended to achieve the above object.

2

This is a digitally signed Gazette.

Authenticity may be verified through https://compose.kerala.gov.in/

____________________________________________________________________________________________________________________________

PUBLISHED BY THE SUPERINTENDENT OF GOVERNMENT PRESSES

AT THE GOVERNMENT CENTRAL PRESS, THIRUVANANTHAPURAM, 2026