xxxGIDHxxx
xxxGIDExxx
असाधारण
EXTRAORDINARY
प्राधिकार से प्रकाशित
PUBLISHED BY AUTHORITY
Part II - Section 3
केन्द्र-शासित प्रदेश लद्दाख प्रशािन
ADMINISTRATION OF UNION TERRITORY OF LADAKH
GENERAL ADMINISTRATION DEPARTMENT
F. No.: M / 1004 / 2022 - GAD SEC
N O T I F I C A T I O N
Leh, 21st November, 2025
S.O. No. 137, — In exercise of the powers conferred by section 4 read with section 8 of the Jammu and Kashmir
Public Services Guarantee Act, 2011 (Act No. IX of 2011) (hereinafter referred to as the ‘said Act’), in its application
to the Union territory of Ladakh; the Administration of Union territory of Ladakh, hereby notifies the following
public services, timelines and the designated officers / appellate authorities for the purposes of the said Act, in
respect of the Departments specified in the table below, namely:—
लद्दाख, 24 नवंबर, 2025
LADAKH, MONDAY, NOVEMBER, 24, 2025
भारत सरकार
GOVERNMENT OF INDIA
एस.जी.-एल.डी.-अ.-25112025-1646
SG-LD-E-25112025-1646
LADAKH GAZETTE : EXTRAORDINARY 2
S.
No.
Name of the public
service
Timeline
Designated
Officer
First
Appellate
Authority
Second Appellate
Authority
Public Health Engineering (PHE) / Irrigation & Flood Control (I&FC) Department
1.
Sanction
for
Commercial
water
connection.
03
working
days
Chief
Engineer,
PHE / I&FC
Deputy
Commissioner
concerned
Administrative
Secretary, PHE /
I&FC Department
2.
Actual
Commercial
water
connection
supply.
07
working
days
Chief
Engineer,
PHE / I&FC
Deputy
Commissioner
concerned
Administrative
Secretary, PHE /
I&FC Department
Power Development Department (PDD)
1.
Timeline for Load Sanction / Additional Load
(a)
Aggregate
Loads
upto 25 kVA
03
days
of
receipt
of
Application
Assistant
Executive
Engineer
Executive
Engineer
Superintending
Engineer
(b)
Aggregate
Loads
above 25 kVA &
upto 50 kVA
03
days
of
receipt
of
Application
Executive
Engineer
Superintending
Engineer
Chief Engineer
(c)
Aggregate
Loads
above 50 kVA &
upto 100 kVA
03
days
of
receipt
of
Application
Superintending
Engineer
Chief Engineer
Administrative
Secretary, PDD
(d)
Aggregate
Loads
above 100 kVA &
upto 500kVA
03
days
of
receipt
of
Application
Chief Engineer
Administrative
Secretary, PDD
Designated
Committee as
notified by the PDD
(e)
Aggregate
Loads
above 500 kVA &
upto 1000 kVA
03
days
of
receipt
of
Application
Administrative
Secretary, PDD
Designated
Committee as
notified by the
PDD
(f)
Aggregate
Loads
above 1000 kVA
03
days
of
receipt
of
Application
Designated
Committee as
notified by the
PDD
2.
Timeline for Conversion of Services
(a) Low Tension (LT) Single Phase to LT Three Phase (or vice versa)
Urban Area
Within 10
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
LADAKH GAZETTE : EXTRAORDINARY 3
Rural Area
Within 20
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(b) LT to High Tension (HT) (or vice versa)
Urban Area
Within 10
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 20
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(c) HT to Extra High Tension (EHT) (or vice versa)
Urban Area
Within 10
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
Rural Area
Within 20
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
Remote Area
Within 30
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
3.
Timeline for release of Temporary Connection
(a)
Where supply can be provided from existing network
Urban Area
Within 03
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 05
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
LADAKH GAZETTE : EXTRAORDINARY 4
Remote Area
Within 07
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(b)
Where supply can be provided after extension / augmentation of network
(i)
Low Tension (LT)
Urban Area
Within 15
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 20
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(ii)
High Tension (HT)
Urban Area
Within 15
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 25
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(iii)
Extra High Tension (EHT)
Urban Area
Within 15
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
Rural Area
Within 25
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
Remote Area
Within 30
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
4.
Timeline for releasing new electricity connection (energization)
(a)
New connection / additional load where supply can be provided from existing network
LADAKH GAZETTE : EXTRAORDINARY 5
Urban Area
Within 03
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 05
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 07
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(b)
Connection requiring enhancement work or transformer capacity enhancement
(i)
Low Tension (LT)
Urban Area
Within 15
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 20
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(ii)
High Tension (HT)
Urban Area
Within 15
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Within 25
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Within 30
working days
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
(iii)
Extra High Tension (EHT)
Urban Area
Within 15
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
LADAKH GAZETTE : EXTRAORDINARY 6
Rural Area
Within 25
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
Remote Area
Within 30
working days
Executive
Engineer
(Electrical)
Superintending
Engineer
Chief Engineer
(c)
Connection requiring erection of new substation to extend supply.
Urban Area
Case to case
basis as per
Commission
approval
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Rural Area
Case to case
basis as per
Commission
approval
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Remote Area
Case to case
basis as per
Commission
approval
Assistant
Executive
Engineer
(Electrical)
Executive Engineer
(Electrical)
Superintending
Engineer
Note: The above timelines for conversion of connection, temporary connection, new electricity connection, etc.;
requiring the creation of new infrastructure, shall be subject to availability of funds / materials (like distribution
transformer, poles, conductors, insulators and allied line materials).
By order of the Lt. Governor (Administrator), Union territory of Ladakh.
(Jigmet Raftan) JKAS,
Deputy Secretary,
General Administration Department.
Copy to the:
1.
All Administrative Secretaries, UT Administration of Ladakh
2.
Director General of Police, Ladakh.
3.
Deputy Commissioner / CEO, LAHDCs, Leh and Kargil.
4.
All Heads of Department / Chief Engineers, UT of Ladakh.
5.
Director, NIC, UT of Ladakh for uploading on UT website
6.
OSD to Lt. Governor, UT of Ladakh for kind information of Hon’ble Lt. Governor,
Ladakh.
7.
OSD to the Chief Secretary, UT of Ladakh for kind information of the Chief Secretary,
Ladakh.
8.
E-Office file
LADAKH GAZETTE : EXTRAORDINARY 7
“No legal responsibility is accepted for the contents of publication of advertisements/publications in this part of The
Ladakh Gazette. Persons notifying the advertisements/public notices will remain solely responsible for the legal
consequences and also for any other misrepresentation etc.”
RIGZIN
SPALGON
Digitally signed by
RIGZIN SPALGON
Date: 2025.11.24
17:29:54 +05'30'
MICHAEL
MANNY
DSOUZA
Digitally signed by
MICHAEL MANNY
DSOUZA
Date: 2025.11.25
13:34:52 +05'30'