xxxGIDHxxx

xxxGIDExxx

असाधारण

EXTRAORDINARY

प्राधिकार से प्रकाशित

PUBLISHED BY AUTHORITY

Part II - Section 3

केन्द्र-शासित प्रदेश लद्दाख प्रशािन

ADMINISTRATION OF UNION TERRITORY OF LADAKH

GENERAL ADMINISTRATION DEPARTMENT

F. No.: M / 1004 / 2022 - GAD SEC

N O T I F I C A T I O N

Leh, 21st November, 2025

S.O. No. 137, — In exercise of the powers conferred by section 4 read with section 8 of the Jammu and Kashmir

Public Services Guarantee Act, 2011 (Act No. IX of 2011) (hereinafter referred to as the ‘said Act’), in its application

to the Union territory of Ladakh; the Administration of Union territory of Ladakh, hereby notifies the following

public services, timelines and the designated officers / appellate authorities for the purposes of the said Act, in

respect of the Departments specified in the table below, namely:—

लद्दाख, 24 नवंबर, 2025

LADAKH, MONDAY, NOVEMBER, 24, 2025

भारत सरकार

GOVERNMENT OF INDIA

एस.जी.-एल.डी.-अ.-25112025-1646

SG-LD-E-25112025-1646

LADAKH GAZETTE : EXTRAORDINARY 2

S.

No.

Name of the public

service

Timeline

Designated

Officer

First

Appellate

Authority

Second Appellate

Authority

Public Health Engineering (PHE) / Irrigation & Flood Control (I&FC) Department

1.

Sanction

for

Commercial

water

connection.

03

working

days

Chief

Engineer,

PHE / I&FC

Deputy

Commissioner

concerned

Administrative

Secretary, PHE /

I&FC Department

2.

Actual

Commercial

water

connection

supply.

07

working

days

Chief

Engineer,

PHE / I&FC

Deputy

Commissioner

concerned

Administrative

Secretary, PHE /

I&FC Department

Power Development Department (PDD)

1.

Timeline for Load Sanction / Additional Load

(a)

Aggregate

Loads

upto 25 kVA

03

days

of

receipt

of

Application

Assistant

Executive

Engineer

Executive

Engineer

Superintending

Engineer

(b)

Aggregate

Loads

above 25 kVA &

upto 50 kVA

03

days

of

receipt

of

Application

Executive

Engineer

Superintending

Engineer

Chief Engineer

(c)

Aggregate

Loads

above 50 kVA &

upto 100 kVA

03

days

of

receipt

of

Application

Superintending

Engineer

Chief Engineer

Administrative

Secretary, PDD

(d)

Aggregate

Loads

above 100 kVA &

upto 500kVA

03

days

of

receipt

of

Application

Chief Engineer

Administrative

Secretary, PDD

Designated

Committee as

notified by the PDD

(e)

Aggregate

Loads

above 500 kVA &

upto 1000 kVA

03

days

of

receipt

of

Application

Administrative

Secretary, PDD

Designated

Committee as

notified by the

PDD

(f)

Aggregate

Loads

above 1000 kVA

03

days

of

receipt

of

Application

Designated

Committee as

notified by the

PDD

2.

Timeline for Conversion of Services

(a) Low Tension (LT) Single Phase to LT Three Phase (or vice versa)

Urban Area

Within 10

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

LADAKH GAZETTE : EXTRAORDINARY 3

Rural Area

Within 20

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(b) LT to High Tension (HT) (or vice versa)

Urban Area

Within 10

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 20

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(c) HT to Extra High Tension (EHT) (or vice versa)

Urban Area

Within 10

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

Rural Area

Within 20

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

Remote Area

Within 30

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

3.

Timeline for release of Temporary Connection

(a)

Where supply can be provided from existing network

Urban Area

Within 03

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 05

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

LADAKH GAZETTE : EXTRAORDINARY 4

Remote Area

Within 07

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(b)

Where supply can be provided after extension / augmentation of network

(i)

Low Tension (LT)

Urban Area

Within 15

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 20

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(ii)

High Tension (HT)

Urban Area

Within 15

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 25

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(iii)

Extra High Tension (EHT)

Urban Area

Within 15

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

Rural Area

Within 25

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

Remote Area

Within 30

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

4.

Timeline for releasing new electricity connection (energization)

(a)

New connection / additional load where supply can be provided from existing network

LADAKH GAZETTE : EXTRAORDINARY 5

Urban Area

Within 03

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 05

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 07

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(b)

Connection requiring enhancement work or transformer capacity enhancement

(i)

Low Tension (LT)

Urban Area

Within 15

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 20

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(ii)

High Tension (HT)

Urban Area

Within 15

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Within 25

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Within 30

working days

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

(iii)

Extra High Tension (EHT)

Urban Area

Within 15

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

LADAKH GAZETTE : EXTRAORDINARY 6

Rural Area

Within 25

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

Remote Area

Within 30

working days

Executive

Engineer

(Electrical)

Superintending

Engineer

Chief Engineer

(c)

Connection requiring erection of new substation to extend supply.

Urban Area

Case to case

basis as per

Commission

approval

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Rural Area

Case to case

basis as per

Commission

approval

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Remote Area

Case to case

basis as per

Commission

approval

Assistant

Executive

Engineer

(Electrical)

Executive Engineer

(Electrical)

Superintending

Engineer

Note: The above timelines for conversion of connection, temporary connection, new electricity connection, etc.;

requiring the creation of new infrastructure, shall be subject to availability of funds / materials (like distribution

transformer, poles, conductors, insulators and allied line materials).

By order of the Lt. Governor (Administrator), Union territory of Ladakh.

(Jigmet Raftan) JKAS,

Deputy Secretary,

General Administration Department.

Copy to the:

1.

All Administrative Secretaries, UT Administration of Ladakh

2.

Director General of Police, Ladakh.

3.

Deputy Commissioner / CEO, LAHDCs, Leh and Kargil.

4.

All Heads of Department / Chief Engineers, UT of Ladakh.

5.

Director, NIC, UT of Ladakh for uploading on UT website

6.

OSD to Lt. Governor, UT of Ladakh for kind information of Hon’ble Lt. Governor,

Ladakh.

7.

OSD to the Chief Secretary, UT of Ladakh for kind information of the Chief Secretary,

Ladakh.

8.

E-Office file

LADAKH GAZETTE : EXTRAORDINARY 7

“No legal responsibility is accepted for the contents of publication of advertisements/publications in this part of The

Ladakh Gazette. Persons notifying the advertisements/public notices will remain solely responsible for the legal

consequences and also for any other misrepresentation etc.”

RIGZIN

SPALGON

Digitally signed by

RIGZIN SPALGON

Date: 2025.11.24

17:29:54 +05'30'

MICHAEL

MANNY

DSOUZA

Digitally signed by

MICHAEL MANNY

DSOUZA

Date: 2025.11.25

13:34:52 +05'30'