RESOLUTION
The 10th September, 2019
Subject :
Re-distribution of Work and responsibilities among Public Health
Engineering Organization (PHEO), Orissa Water Supply &
Sewerage Board (OWS & SB) and WATCO.
Orissa Water Supply & Sewerage Board (OWS & SB) was entrusted with the
responsibility of Construction as well as Operation & Maintenance (O&M) of all Sewerage
and Septage Systems (except Government Quarters & Institutions) whereas PHEO was
entrusted with the responsibility to look after construction, operation and maintenance of
all drinking water supply systems/water works as well as sewerage systems of
Government Quarters and Institutions vide this Department Resolution No.27572/HUD.,
dated the 25th November, 2017. However, keeping in view the inadequate and
inexperienced human resources in OWS & SB, constraints are being faced in respect of
construction, operation and maintenance of the sewerage and septage systems in various
Urban Local Bodies of the State. Hence, Operation and Maintenance of sewerage and
septage projects in Puri have subsequently been transferred to PHEO vide this
Department Resolution No. 13643/HUD., dated the 2nd August, 2019 in modification of the
earlier Resolution.
However after full fledged functioning of WATCO with effect from 1st June, 2019
and for smooth distribution of responsibilities among all Government entities i.e. OWS &
SB, PHEO and WATCO and in partial modification to this Department Resolution
No.27572/HUD., dated the 25th November, 2017 read with subsequent Resolution
No. 13643/HUD., dated the 2nd August, 2019, Government after careful consideration
have been pleased to further decide the following:―
(i) Construction and O & M of all Sewerage and Septage projects/systems in the
WATCO area i.e. Bhubaneswar, Jatni and Khurda ULBs shall be looked after
by WATCO henceforth. In addition, the on-going Sewerage Projects/
Systems in Sewerage Districts I, II, III and IV along with the proposed septage
projects at Bhubaneswar shall be transferred to WATCO by OWSSB to
continue further activities.
2
(ii) The construction, O&M of all Sewerage and Septage Projects/Systems in all
other ULBs shall be looked after by PHEO on transfer of the same by OWSSB
except that the on-going work of Sewerage Systems at Sambalpur & Rourkela
towns are to be completed and commissioned by OWSSB and thereafter to be
transferred the same to PHEO for O&M.
(iii) The construction of Sewerage Systems in District-VI, Bhubaneswar shall be
continued under Chief Engineer, OISIP. The same after completion and
commissioning shall be handed over to WATCO for O&M. However, the
Sewerage System & Drainage System, Cuttack shall continue under Chief
Engineer, OISIP, Cuttack and shall be transferred to PHEO and Cuttack
Municipal Corporation respectively for O & M after completion and
commissioning.
(iv) The OWS & SB shall have the core function of providing technical support on
Sewerage and Septage systems, technical support in the Quality Assurance
and Quality Control along with Regulatory functions of clear water and waste
water management, capacity building in the above matters etc.
2. Order:
(i)
The Resolution shall come into force from the date of issue.
(ii)
Ordered that the Resolution be published in the Odisha Gazette and copies
thereof be forwarded to all Departments and all Heads of the Departments
and the Principal Accountant General, Odisha, Bhubaneswar with 50 copies
to this Department.