REVENUE AND DISASTER MANAGEMENT DEPARTMENT
NOTIFICATION
S.R.O. No. 203/2025
Dated 27-01-2025
Whereas the Notification under section 4(1) of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013, was issued from Government in Revenue and
D.M. Department vide No. 18927 Dated. 25.05.2023 to carry out SIA
study for acquisition of private land of Ac.5.1750 in 01 village under
Kendrapara Tahasil of Kendrapara District for "Construction of District
Head Quarter Hospital with 100 bedded mother child hospital at
Kendrapara ( Phase-2, Front side)" and Declaration under section 8(2)
has been issued vide No. 7363 dated 13.03.2024 as per the
recommendations of the Collector, Kendrapara and appraisal of the
Social Impact Assessment report submitted by the Expert Group on
26.09.2023 and Notification under section 11(1) of the Act in respect of
the above schedule of land has not been issued till date;
And whereas, as per section 14 of the Act, where a preliminary
notification under section 11 is not issued within twelve months from the
date of appraisal of the Social Impact Assessment report submitted by
the Expert Group under section 7, then, such report shall be deemed to
have lapsed and the first proviso to section 14 provides that the
appropriate Government shall have the power to extend the period of
twelve months, if in its opinion circumstances exist justifying the same;
The Odisha
G a z e t t e
EXTRAORDINARY
PUBLISHED BY AUTHORITY
No. 815 CUTTACK, FRIDAY, APRIL 4, 2025/CHAITRA 14, 1947
And whereas, Collector, Kendrapara has requested with reasons to
extend the period of twelve months and the appropriate Government is
of the opinion that circumstances existed for the delay;
Now, therefore, in exercise of the powers conferred by first proviso to
section 14 of the Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013, the State
Government do hereby decided to extend the period of twelve
months from the date of appraisal of the Social Impact Assessment
report submitted by the Expert Group U/s-7 of the RFCTLAR&R Act,
2013 up to 26th September 2025 for issue of preliminary Notification
U/s-11(1) of the said Act.
[No. 2764--RDM-LAA-KPD-0006/2023-R&DM]
By order of the Governor
SURANJAN PRADHAN
Additional Secretary to Government