ENERGY DEPARTMENT

CORRIGENDUM

The 8th April 2025

No. 4588—ENG-TD&ER-I-DAPP-0001/2025-En.—The list of distibution assets transferred

to DISCOMs for FY 2024-25 in lieu of equity offer of the DISCOMs to GRIDCO has been notified

vide Energy Department Notification No. 4204, dated the 28th March 2025.

However,certain inadvertent typographical errors have been found in Annexure-C and

Annexure-D of the above notification which are hereby modified as mentioned below :—

1. Part-A (Distribution Transformer) of Annexure-C shall be replaced as follows :

SI. No.

DTR Capacity

No. of DTR

1

500KVA

21

2

250KVA

63

3

100KVA

389

4

25KVA

320

2. Part-B of (Primary Substation and its associated lines) of Annexure-C at SI. No. 12,

under asset location “PSS Ajodhya” the length of 33KV line and 11KV line shall be replaced as

9.28km and 6.63km respectively.

3. Part-A (Distribution Transformer) of Annexure-D shall be replaced as follows :

SI. No.

DTR Capacity

No. of DTR

1

500KVA

64

2

250KVA

57

3

100KVA

341

4

25KVA

30

5

16KVA

76

4. Part-B of (Primary Substation and its associated lines) of Annexure-D at SI. No. 11,

under asset and location “PSS Sidheswar” shall be replaced as “PSS Kalampur”.

The Notification No. 4204, dated the 28th March 2025 is modified to the above extent. All

other terms mentioned in the above notification shall remain unaltered. The revised Annexure-C

and Annexure-D are attached herewith for reference.

By order of the Governor

LIPSA DAS

Additional Secretary to Government

The Odisha

G a z e t t e

EXTRAORDINARY

PUBLISHED BY AUTHORITY

No. 916 CUTTACK, WEDNESDAY, APRIL 16, 2025/CHAITRA 26, 1947

Printed and Published by the Director, Directorate of Printing, Stationery & Publication, Odisha, Cuttack-10

Ex. Gaz. 126—173+50