Sentence arbitral du Travail

.. 434

Award of the Labour Court

.. 434

de Tribunal.



.. 454

Notifications du Gouvernement .. 454

Government Notifications

.. 454



.. 459

Avis d’Adjudications

.. 459

Tender Notices

.. 459



.. 459

Annonces

.. 459

Announcements

.. 459



.. 468

Corrigendum

.. 468

Corrigendum

.. 468

[ 433 ]

Registered with the Registrar

of Newspapers for India under

No. 10410

Registered No. PY/44/2018-20

WPP No. TN/PMG(CCR)/WPP-88/2018-20

Dated : 3-4-2018

Price : ` 25-00







2018 }

|

3 {

No.

14

Poudouchéry

Mardi

3

Avril

2018 (13 Chaitra 1940)

No.

Puducherry

Tuesday

3rd

April

2018

434

LA GAZETTE DE L’ETAT

[3 April 2018

GOVERNMENT OF PUDUCHERRY

LABOUR DEPARTMENT

(G.O. Rt. No. 12/Lab./AIL/T/2018,

Puducherry, dated 5th February 2018)

NOTIFICATION

Whereas, an Award in I.D (T) No. 03/2011, dated

18-12-2017 of the Industrial Tribunal, Puducherry in

respect of the Industrial Dispute between the

management of M/s. Pond’s Exports Limited, Footwear

Factory, Puducherry and the Pondicherry Hindustan

Lever Thozhilalar Sangam, Puducherry, over transfer

of 66 workmen (as mentioned in the Annexure) has

been received;

Now, therefore, in exercise of the powers conferred

by sub-section (1) of section 17 of the Industrial

Disputes Act, 1947 (Central Act XIV of 1947), read

with the notification issued in Labour Department’s

G.O. Ms. No. 20/91/Lab./L, dated 23-5-1991, it is

hereby directed by the Secretary to Government

(Labour), that the said Award shall be published in the

Official Gazette, Puducherry.

(By order)

S. MOUTTOULINGAM,

Under Secretary to Government (Labour).

————

BEFORE THE INDUSTRIAL TRIBUNAL-CUM-

LABOUR COURT AT PUDUCHERRY

Present : Thiru G. THANENDRAN, B.COM., M.L.,

Presiding Officer.

Monday, the 18th day of December 2017

I.D. (T) No. 03/2011

Pondicherry Hindustan Lever Thozhilalar Sangam,

Reg. No. 970/RTU/95,

Rep. by its President S. Pannirdasse,

Registered Office at No. 207,

LIG Housing Board,

Kurumbapet,

Muthiraiyarpalayam,

Puducherry-605 009.

. . Petitioner

Versus

M/s.. Pond’s Exports Limited,

Footwear Factory,

(Subsidiary of M/s. Hindustan Unilever Limited,

Rep. by its Factory Manager,

Post Box No. 18, Vazhuthavur Road,

Puducherry-605 009.

. . Respondent

This industrial dispute coming on 24-11-2017 before

me for final hearing in the presence of Thiruvalargal

P.R. Thiruneelakandan and A. Mithun Chakkaravarthy,

Counsel for the petitioner, Thiruvalargal L. Sathish,

N. Krishnamurthy, T. Pravin and V. Veeraragavan,

Advocates for the respondent, upon hearing both sides,

upon perusing the case records, after having stood over

for consideration till this day, this Court passed the

following:

AWARD

1. This Industrial Dispute has been referred by the

Government as per the G.O. Rt. No. 83/AIL/Lab./J/2011,

dated, 08-04-2011 for adjudicating the following:-

(i) Whether the dispute raised by Pondicherry

Hindustan Lever Thozhilalar Sangam, over transfer

of 66 workmen (as mentioned in the Annexure) by

the management of M/s. Pond’s Exports Limited,

(Footwear Factory), Puducherry is justified? If not,

to give appropriate directions?

(ii) To what relief the 66 workmen represented

by Pondicherry Hindustan Lever Thozhilalar Sangam

are entitled to?

(iii) Whether the dispute raised by Pondicherry

Hindustan Lever Thozhilalar Sangam, over closure

of the unit by the management is legal and justified?

If justified, to give appropriate directions?

(iv) To compute the relief, if any, awarded in

terms of money if, it can be so computed?

2. It is the case of the petitioner union that it is the

registered trade union and the members of the union

are the workers of the respondent establishment which

manufacturing show and other allied products and also

exporting the same and the respondent factory was

started business in the year 1989 and these workers

were appointed in the year 1989 and their services have

been confirmed as permanent workers and the

respondent establishment has paid wages and other

allowances and incentives to the workers as per the

settlement entered between the union and the

respondent from time to time once in every 4 year and

the petitioners were paid wages only at ` 2,000 per

month and after several settlement the salary of the

workers have been considerably increased after 22 years

and as per the last settlement, dated 24-10-2002, the

permanent employees derived about ` 10,000 to

` 15,000 as a salary per month and the said settlement

came to an end in the year 2006 and after the expiry

of the said settlement the union has submitted the new

charter of demand in the year 2007 and in the

435

3 April 2018]

LA GAZETTE DE L’ETAT

meanwhile the respondent recruited the contract

workers for very meagre wage of ` 2,000 to ` 3,000

and engaged them in direct manufacturing activity

along with the permanent workers and on 18-04-2008

the fresh charter of demand was submitted by the

petitioner union to revise the wages and allowances

and the respondent management did not want to

continue to engage the permanent workers and to

reduce the permanent workers the respondent

management has announced Voluntary Retirement

Scheme and out of 163 permanent workers, 97 workers

were accepted Voluntary Retirement Scheme and the

petitioner union has not accepted the same and

demanded for continuous employment and the

respondent management has stopped the production

with effect from effect from 21-10-2008 and the

respondent management also has threatened the

workers that they are going to close the factory and

they are going to transfer the workmen to other state

if, they failed to opt Voluntary Retirement Scheme on

or before 30-10-2008 and the workers have preferred

a complaint regarding apprehension of closure of

factory and transfer of workers before the Labour

Officer (Conciliation) and while dispute is pending

without the permission of the Labour Officer

(Conciliation), the respondent management has closed

down the factory on 30-10-2008 and transferred 66

workers to other places and that therefore, the union

has raised the dispute regarding the illegal closure and

illegal transfer of workers and prayed to hold the

transfer of 66 reference mentioned workmen by the

respondent is unjustified and illegal as it is mala fied

and colourable exercise and the transfer order are

violation of section 0-A. 33, 25-E of the Industrial

Disputes Act and to hold that the closure of the factory

is illegal as it is violation, of section 25-O of the

Industrial Disputes Act and to direct the respondent to

reinstate the reference mentioned petitioner union

members with back wages, continuity of service and

all other attendant benefits and to Award compensation

benefits to the petitioner union members for the

period of illegal closure.

3. On the other hand, it is the contended by the

respondent that though it is a subsidiary of M/s. Hindustan

Unilever Limited, a multinational company, it is a separate

entity, engaged in the business of manufacturing foot-wears

and 163 permanent workmen are working in this

factory and it is entirely dependent on export orders

received from overseas customers and due to business

fluctuations, outsourcing was also done based on need

and certain preparatory operations were also done by

third party units situated in and around Pondicherry

which was always part of respondent’s manufacturing

operations for a long period and the salary was based

on ‘Industry-cum-Region’-wise increase and the age

of the factory and they paid the best salary package

to its workers, the average salary for the unskilled and

skilled workers were around ` 8,500 to ` 9,600

respectively and the wage and other allowances and

incentives were determined and paid by them as per the

Long-term settlement from time to time and that they

had three unions including the petitioner union and

the petitioner union is the minority union with only

6 workers as its members and that the majority trade

unions (PELWWA) entered into a settlement with them

on 24-10-2002 for which the petitioner union has not

accepted the terms of the said settlement and raised

industrial dispute in I.D. 02/2002 for wage revision

which was dismissed on merits on 19-12-2006 and the

said Award was confirmed by the Hon’ble High Court

in W.P. No. 25952/2008 and the two majority trade

union placed its charter of demands for wage revision

and other benefits on 27-11-2006, but, the petitioner’s

union submitted its charter of demands only in the

year 2008 and even before the expiry of long-term

settlement on 30-09-2006 the respondent engaged in

various dialogues and negotiation with the majority

union and majority of workers and the respondent was

always willing to offer a reasonable increase in wages

and other benefits but, the demands of the union far-

reached the sensibilities and therefore, no settlement

could be concluded and in order to pressurize

respondent to accept unreasonable demands of wage

revision, the workers resorted to various illegal actions

including go-slow over several months as against the

average production and thus, hurt the business

drastically and since February, 2007, the respondent

repeatedly communicated to all the workmen through

various notices and letters about the danger of such

go-slow agitation by the workmen, especially in an

export unit which is sensitive to both price as well as

timely deliveries which directly impact the viability of

the factory and the continuous loss for more than one

and half years due to the illegal activities of the

workers and since, the unit had became completely

unviable respondent had no options but, to suspend its

production activities with effect from 21-10-2008 and

however, the respondent in its wisdom by considered

the collective benefits of its workers and was inclined

to be more generous and gratuitous towards its

workers who had served the company for good number

of years, instead of closing down the factory, the

respondent offered a handsome and generous voluntary

retirement schemel package to all its workers which

436

LA GAZETTE DE L’ETAT

[3 April 2018

was far better than the legal compensation payable to

workers in the event of closure of the unit and 97

workers out of 163 workers accepted voluntary

retirement scheme received monetary benefits under

the said scheme and submitted their resignation and

only 66 workmen were not interest in the voluntary

retirement scheme and requested for continuous

employment preferably in the same unit or any other

units in Puducherry and the respondent could not

accommodate 66 workers in Puducherry and hence it

decided to transfer 66 workmen to other factories in

the nearby states for which the petitioner raised

objection in various forms of agitations including

illegal strike, gheraoing, picketing, obstructing

movement

of

men

and

materials,

compelling

respondent to approach Civil Court in O.S. No. 1476/

2008 seeking injunction against the striking workers

and the petitioner also gave complaints to various

authorities, filed Writ Petitions challenging the

transfers and conciliation proceedings.

4. In the course of enquiry on the side of the

petitioner PW1 was examined and Ex.P1 to Ex.P91

were marked and on the side of the respondent RW1

was examined and Ex.R1 to Ex.R73 were marked.

5. The point for consideration is:

(i) Whether the dispute raised by the petitioner

union over transfer of 66 workmen (as mentioned

in the Annexure) by the respondent management is

justified or not and what is the relief entitled to the

said 66 workmen.

(ii) Whether the dispute raised by the petitioner

union over closure of the unit by the management

is legal and justified or not.

6. Both sides are heard. The submission of both the

parties, the evidence let in by either sides and the

exhibits marked on both sides are carefully considered.

On both sides, written arguments were filed and the

same were carefully considered. The learned Counsel

for the petitioner relied upon the judgment reported

in 1974(79) Cal.W.N.410 : 1975 LIC 1153, AIR 1960

SC 777, 1970(1) SCC 225, (2005) 3 SCO 202, AIR

2005 SC 1555(1), 2012(3) LLN 358 (Mad.), (2002)

2 SCC 244, (2000) II LLJ 1005 Mad., 1986 I LLJ 506

and also relied upon several judgments. The learned

Counsel for the respondent also relied upon the

Judgement reported in W.P.(C).2116/2010 of Delhi

High Court, dated 11-09-2012, CDJ 2015 MHC 790,

CDJ 1979 MHC 021, CDJ 1984 SC 083, CDJ 2004

MHC 2066, W.P.6663/2002 of Jharkhand High Court,

dated 26-06-2009, CDJ 1991 MPHC 166, CDJ 2003

Kar HC 209, CDJ 2003 MHC 315, CDJ 2001 SC 260,

CDJ 2015 MHC 4789.

7. On point No. l;

The main contention of the petitioner union is

that the respondent management has illegally closed

the factory by announcing the voluntary retirement

scheme against the employees who have filed the

charter of demands on 18-04-2008 before the

Conciliation Officer for the revision of wages and

other allowances and while the union members have

not accepted the voluntary retirement scheme and

demanded continuous employment in the respondent

factory, the respondent management has illegally

closed the factory on 30-10-2008 and illegally

transferred the 66 workers of the petitioner union

on 01-11-2008 and therefore, the petitioner union

has raised the industrial dispute, over the transfer

against the respondent management.

8. On the other hand, it is contended by the

respondent management that the petitioner union is not

the majority union and it has only 6 members and the

workers were in go slow production and the production

was drastically dropped and no improvement in

production, the respondent management has suspended

the

production

at

the

respondent

factory

on

21-10-2008 and on the same day the respondent

management has announced voluntary retirement

scheme to the workers and that out of 163 permanent

workers 97 workers were opted for voluntary

retirement scheme and they have been settled and rest

of the 66 workers who have not opted voluntary

retirement scheme have been transferred on their own

request and that therefore, the respondent management

has not lockout or close down the factory and

therefore no violation of section 25(o) of the

Industrial Disputes Act and there is no illegal violation

committed by the respondent management.

9. From the pleadings of both the parties it can be

noticed that following facts are admitted by both the

parties that the petitioners are the permanent workers

of the respondent establishment and that there was a

dispute regarding the wage revision between the

petitioner union and the respondent management and

the petitioner union has raised the industrial dispute

regarding the wage revision and since no settlement

was arrived at between the petitioner and the

respondent management they raised the industrial

dispute

before

the

Conciliation

Officer

and

subsequently

the

respondent

management

has

suspended their production from 21-10-2008 and

announced

voluntary

retirement

scheme

and

thereafter, 97 workers out 163 permanent workers

were accepted voluntary retirement scheme and they

437

3 April 2018]

LA GAZETTE DE L’ETAT

have been settled and rest of the 66 workers have not

accepted the voluntary retirement scheme and they

have asked for continuous employment in the

respondent factory and the respondent management has

transferred the said 66 workers to their branches even

outside the State of U.T. of Puducherry and hence, the

petitioner union has raised the industrial dispute which

was referred by the Government to this Court for

adjudication.

10. In order to prove the case the petitioner union

has examined PWl and it is the evidence of PWl that

the petitioner union members are the permanent

workers of the respondent establishment and the union

has been registered under the Trade Union Act in the

year 1995 and they have raised an industrial dispute for

wage revision which was refused by the management

before the Conciliation Officer and that ` 2,000 to

` 3,000 were paid as monthly wages to the members

of the petitioner union though the respondent

management has paid huge salary to the executives of

the establishment and that the respondent management

has refused to revise the wages as per the demand of

the petitioner union and that therefore, on 04-04-2000

they submitted a charter of demands before the

respondent Industry and the same was refused by the

respondent establishment and thereafter, they raised an

industrial dispute before the Conciliation Officer on

30-04-2002 and on failure the case has been referred

to this Court for adjudication and the same was taken

on file in I.D(T).No. 02/2002 by the Industrial

Tribunal and the claim statement was filed by the union

on behalf of 194 workers and when the I.D was running

before the Tribunal, the respondent management has

created a labour union in the name of Ponds Exports

Limited Workers Welfare Association as puppet union

and they have entered into the wage settlement in which

the members of the union have also compelled to sign

the said settlement and the respondent establishment

also has compelled to sign within 31-10-2002 and all

other workers excepted the members of the petitioner

union signed the said settlement and the said I.D(T).

02/2002 was dismissed by the Tribunal stating that

most of the employees have accepted the settlement

for revision of wages and since, the said settlement was

in force for about 4 years the petitioner union has

raised the another demand on behalf of 81 workers for

revision of wages and other requirements, while so the

members of Ponds Exports Limited Workers Welfare

Association was divided by 20 workers and they have

created a new union in the name of Ponds Exports

Limited Workers Union and they have also raised the

charter

of

demands

before

the

respondent

establishment and while so, the petitioner union also

has raised the demand on 31-03-2008 with 81 members

and submitted a requisition to the management, while so,

the puppet union Ponds Exports Limited Workers

Welfare Association made an attempt to enter into an

agreement and the petitioner union has sent a letter

along with 81 members list as that they are the majority

union and however, the respondent establishment has not

considered the charter of demands raised by the

petitioner union and that therefore, on 18-04-2008, the

industrial dispute was raised by the petitioner unionand

that therefore, on 21-05-2008 both the parties are

directed to appear before the Conciliation Officer and

notice was given to both parties wherein, the

conciliation

was

failed

and

the

respondent

establishment has not supplied the raw materials to

raise the production and has arranged a third party unit

Aroma Leathers and Malik Leathers to produce the

leather shoes and further the respondent establishment

is manufacturing the shoes also at Vazhudavur Industry

and it gives more order to Aroma Leathers and Malik

Leathers to produce the shoes and though, the

respondent management has suspended the production

at respondent Industry in the month of October, 2008,

they are doing the same manufacturing business

through Aroma Leathers and Malik Leathers and earning

more than the profit and that therefore, a complaint

has been sent by the petitioner union on 21-05-2010

to the Inspector of Factories and that since the

petitioner union and other union workers have asked

the revision of wages the respondent management has

closed down the factory and announced the voluntary

retirement scheme on 21-10-2008 and workers have

been compelled to opt voluntary retirement scheme on

or before 25-10-2008 and 97 workers out of 163

workers opted voluntary retirement scheme and these

petitioners 66 workers have not opted voluntary

retirement scheme and as they have not opted voluntary

retirement scheme they have been transferred to

various places of the respondent establishment and

that therefore, the transfer of 66 workers are mala fide

and act of the transfer of 66 workers is unjustified and

that therefore, they have raised the industrial dispute

before the Conciliation Officer against the transfer of

66 workers.

11. In support of their case the petitioner union has

exhibited Ex.Pl to Ex.P91. Ex.Pl is the copy of the

petitioner union registration certificate. Ex.P2 is the

copy of the petitioner union members list. Ex.P3 is the

copy of the documents relates to salary structure of

the Executive of the respondent management. Ex.P4 is

438

LA GAZETTE DE L’ETAT

[3 April 2018

the copy of the petitioner union charter of demand

submitted to the respondent management. Ex.P5 is the

copy of the counter demand raised by the respondent

management. Ex.P6 is the copy of the Minutes of

meeting before the Conciliation Officer. Ex..P7 is the

copy of the conciliation failure report. Ex.P8 is the

copy of the Government reference. Ex.P9 is the copy

of the claim statement. Ex.P10 is the copy of the

letter of the individual worker accepting the 18(1)

settlement. Ex.P11 is the copy of the order passed by

the Hon’ble Court in W.P. No. 25952 of 2008. Ex.P12

is the copy of the charter of demand submitted by the

petitioner union on behalf of its 81 members. Ex.PI3

is the copy of the petitioner union’s letter to the

respondent management claiming majority status.

Ex.Pl4 is the copy of the conciliation notice on the

petitioner union dispute dated 18-04-2008. Ex.P15 is

the copy of the Licence issued by the Inspector of

Factory to the respondent under the Factories Act.

Ex.P16 is the copy of the delivery challan stands in the

name of respondent which shows. the respondent

engaging manufacturing activity in the name of Aroma

and Malic Leathers. Ex.P17 is the copy of the profit

and loss account of respondent and form 23AC

submitted before the company Law Board. Ex.P18 is the

copy of the petitioner union objection to the Inspector

of Factories. Ex.P19 is the copy of the trade union

complaint to the PW authority. Ex.P20 is the copy of

the trade union complaint to the PWA authority.

Ex.P21

is the copy of the High

Court order in

WP.No.24521 of 2008. Ex.P22 is the copy of the VRS

application issued by the respondent. Ex.P23 is the

copy of the letter issued by the respondent on receipt

of the VRS application. Ex.P24 is the copy of the

details of the resigned employees in Aroma and Malic.

Ex.P25 is the copy of the petitioner union complaint

to the Commissioner of Labour, Conciliation Officer

regarding production in third party unit. Ex.P26 is the

copy of the petitioner union complaint to the

Commissioner

of

Labour,

Conciliation

Officer

regarding production in third party unit. Ex.P27 is the

copy of the petitioner union complaint to the

Commissioner of Labour regarding lock out. Ex.P28

is the copy of the petitioner union complaint regarding

removal of machinery. Ex.P29 is the copy of the

petitioner union complaint regarding closure of

production planning control and lock out. Ex.P30 is

the copy of the petitioner union objection to the

respondent. Ex.P31 is the copy of the petitioner union

complaint to the Superintendent of Police. Ex.P32 is the

copy of the petitioner union complaint to the Inspector

of Police. Ex.P33 is the copy of the news published

in the Dinakaran regarding removal of machinery to

the respondent factory. Ex.P34 is the copy of the

petitioner union complaint to the Government

regarding removal of machinery and its courier

receipt. Ex.P35 is the copy of the objection letter to

the Commissioner of Labour regarding shifting of

factory. Ex.P36 is the copy of the objection letter to

the Commissioner of Labour regarding shifting of

factory. Ex.P37 is the copy of the objection letter of

the HUL Employees Union. Ex.P38 is the copy of the

objection letter of the HUL TEA Union. Ex.P39 is the

copy of the petitioner union complaint to the

Conciliation Officer,

etc., regarding transfer of

workmen. Ex.P40 is the copy of the petitioner union

complaint to the Conciliation Officer, etc., regarding

transfer of workmen. Ex.P41 is the copy of the

petitioner union complaint regarding closure of

factory. Ex.P42 is the copy of the petitioner union letter

to the Commissioner of Labour, Secretary to the Labour

Department. Ex.P43 to Ex.P48 are the copy of the

Conciliation Officer notice. Ex.P49 is the copy of the

Conciliation Officer notice and dispute, dated

18-04-2008 raised by the petitioner union for charter

of demands for wage revision. Ex.P50 is the copy of

the conciliation failure report. Ex.P51 is the copy of

the conciliation failure report over the dispute of

closure of factory. Ex.P52 is the copy of the

Government reference. Ex.P53 is the copy of the High

Court order in Writ Petition No. 26180 of 2008,

23319/2009, 399/2010. Ex.P54 is the copy of the

Government reference as per the High Court. Ex.P55

is the copy of the report of the Inspector of Factories.

Ex.P56 is the copy of the Conciliation Officer notice.

Ex.P57 is the copy of the list of machinery removed

from the factory. Ex.P57A is the

copy of the

memorandum of Ground filed in CRP.PD. No. 294 of

2011. Ex.P58 is the copy of the commissioner’s show

cause notice to the respondent. Ex.P59 is the copy of

the news published in the daily news paper. Ex.P60 is

the copy of the ESI treatment refusal letter. Ex.P61 is

the copy of the news published in the Dinathanthi

regarding profit of the respondent company. Ex.P62 is

the copy of the petitioner letter to the Director, Labour

Department, New Delhi. Ex.P63 is the copy of the

petitioner letter to the Secretary to the Government,

Labour Department, New Delhi. Ex.P64 is the copy of

the acknowledgment card to letter, dated 21-05-2010.

Ex.P65 is the copy of the petitioner union letter to the

Secretary to the Government, Labour Department,

Puducherry. Ex.P66 is the copy of the petitioner union

complaint to the Inspector of Factories. Ex.P67 is the

copy of the Award of the Labour Court in I.D. 8 of

439

3 April 2018]

LA GAZETTE DE L’ETAT

2008 and I.D.No. 4 of 2001. Ex.P68 is the copy of the

transfer letter. Ex.P69 is the copy of the details of the

transfer workmen submitted to the Conciliation Officer.

Ex.P70 is the copy of the petitioner union letter to the

respondents. Ex.P71 is the copy of the petitioner

union letter to the respondents. Ex.P72 is the copy of

the petitioner union letter to the respondents. Ex.P73

is the copy of the petitioner union letter to the

Inspector of Factories. Ex.P74 is the copy of the Form

20B. Ex.P75 is the copy of the Form 20B. Ex.P76 is the

copy of the Form 20B. Ex.P77 is the copy of the

declaration Form submitted by respondent before

Central Excise Department. Ex.P78 is the copy of the

export Invoice of 3rd respondent. Ex.P79 is the copy

of the export invoice-cum-delivery challan. Ex.P80 is

the copy of the export invoice-cum-delivery challan.

Ex.P81 is the copy of the export invoice-cum-delivery

challan. Ex.P82 is the copy of the Form 23 AC. Ex.P83

is the copy of the Form 23 AC. Ex.P84 is the copy of

the Form 23 AC. Ex.P85 is the copy of the Form 23 AC.

Ex.P86 is the copy of the packing list in Poothurai

Factory. Ex.P87 is the copy of the invoice-cum-

challan. Ex.P88 is the copy of the invoice. Ex.P89 is

the copy of the respondent declaration submitted

before Central Excise Department. Ex.P90 is the

consignee copy of respondent factory. Ex.P91 is the

copy of the Tax information of the respondent factory.

12. On the other hand, to prove their contention the

respondent management has examined RW1 and it is

the evidence of RW1 that the petitioner union has got

only 6 members and it is not a majority union and apart

from the petitioner union two majority unions were

functioning at the respondent establishment and the

reference mentioned 66 workers are not the members

of the petitioner union and that they have not illegally

closed the factory and that they have announced the

voluntary retirement scheme only for the reason that

the production was suspended by the respondent

establishment since they have met loss due to workers

extracted various illegal actions including go-slow

over several months as against average production and

further, it is the evidence of respondent management

witness RWl that repeated communication to all the

workmen through various notices and letters to the

unions about the danger of such go-slow production of

the workmen especially in an export unit which is

sensitive to both price as well as timely deliveries

which directly impact the viability of the factory and

even then there was no improvement in productivity,

the undertaking had to cease production on 21-10-2008

and the respondent Industry was incurring loss in

its

business

because

of

their

agitation

and

uncompromising attitude coupled with other variable

factors and profit margin of the respondent started

declining considerably and therefore, the respondent

was entirely dependent on the work force to increase

not only the quantity of productions but, also the

quality of production and the respondent Industry met

with heavy loss more than 1 ½ years and the unit had

became completely unviable and there were no new

orders for production it had no options but, to suspend

the production activities with effect from 21-10-2008

and therefore, instead of closing down the factory the

respondent offered a handsome and generous voluntary

retirement scheme package to all its workers which

was far better than the legal compensation payable to

workers in the event of closure of the unit and

announced the voluntary retirement scheme and 97

workers out of 163 workers accepted the voluntary

retirement scheme out of their own will and received

monetary benefits under the voluntary retirement

scheme by submitting their resignation and only 66

workmen have not interested in the said scheme and

they are willing to be placed in any other factory of

the respondent and that therefore, they have been

transferred to other factory of the respondent and that

the transfer order were not accepted by 66 workers and

they have raised agitations in various forms including

illegal strike, gheraoing, picketing, obstructing

movement of men and materials compelling the

respondent to approach the Civil Court since, the

conciliation was failed before the Conciliation Officer.

13. In support of their contention the respondent

management has exhibited Ex.Rl to Ex.R73. Ex.Rl is

the

copy of the long-term settlement 2002-2006

Memorandum of Understanding. Ex.R2 is the Copy of

the letter from PHLTS union. Ex.R3 is the copy of the

various

notices/letter

and

warnings

given

by

respondent on the go slow adopted by petitioner and

communication by the unions on such go slow. Ex.R4

is the copy of the letter to workers by co-ordinated

union’s association regarding VRS. Ex.R5 is the copy

of the notice on VRS announcement by management.

Ex.R6 is the copy of the notices on VRS

announcement by management, VRS additional amount

by management and other benefits of VRS by

management. Ex.R7 is the copy of the notice to the

VRS opted employees and Union letter to Conciliation

Officer. Ex.R8 to Ex.R13 are the confirmation order

of the employees Ex.Rl4 is the copy of the certified

standing orders of respondent company. Ex.Rl5 is the

copy of the notice displayed on notice-board of the

respondent giving the details of transfer to 66

workers. Ex.R16 is the Registered letter addressed to

440

LA GAZETTE DE L’ETAT

[3 April 2018

the president of the petitioner union namely,

Pannirdasse to his residence which was returned to

respondent with endorsement of “Not claimed”.

Ex.R17 is the returned postal cover addressed to

president of the petitioner union namely Pannirdasse

to his residence which was returned to respondent with

endorsement of “Refused”. Ex.R18 is the copy of the

affidavit filed by the respondent in I.A.7/2009 in

I.A.253/2008 in OS. 1476/2008 on the file of Principal

District Munsif at Puducherry for appointment of

Advocate Commissioner for shifting goods, materials

and products from the respondent's factory premises

along with counter statement filed by the petitioner.

Ex.R19 is the copy of the Order in I.A78/2009

in O.S.

1476/2008. Ex.R20 is

the Advocate

Commissioner report in LA.78/2009 in O.S.No. 1476/

2008. Ex.R21 is the copy of the union letter to

Factory Manager. Ex.R22 is the copy of the union

letter to Labour Commissioner. Ex.R23 is the copy of

the letter to Station House Officer. Ex.R24 is the copy

of the letter to Thasildar. Ex.R25 is the copy of the

report in non-cognizable offence. Ex.R26 is the copy

of the transfer orders sent to all the 66 workers

involved in present dispute. Ex.R27 is the copy of the

union letter to Government Authorities on VRS.

Ex.R28 is the copy of the union letter to Conciliation

Officer on VRS. Ex.R29 is the copy of the advisory

notice on overstay, Ex.R30 is the copy of the letter

from Conciliation Officer on service condition.

Ex.R31 is the copy of the reply to Conciliation Officer

notice 06-11-2008. Ex.R32 is the copy of the letter

to Inspector of Factories on inspection. Ex.R33 is the

copy of the letter to Conciliation Officer on Over stay.

Ex.R34 is the copy of the report from Police Station

to Labour Commissioner. Ex.R35 is the copy of the

notice on over stay. Ex.R36 is the copy of the

complaint letter to Police Station by management.

Ex.R37 is the copy of the notices on over stay. Ex.R38

is the copy of the notices on over stay. Ex.R39 is the

copy of the letter to Station House Officer on

unauthorized protests. Ex.R40 is the copy of the

notice to all the transferred employees. Ex.R41 is the

copy of the notice to enquiry from Conciliation Officer.

Ex.R42 is the copy of the reply to Conciliation Officer

notice. Ex.R43 is the copy of the notice from

Commissioner of Labour. Ex.R44 is the copy of the

letter by management on Wage dispute to Labour

Commissioner. Ex.R45 is the copy of the notice from

Commissioner of Labour. Ex.R46 is the copy of the

reply letter to Notice from LC, dated 22-12-2008.

Ex.R47 is the copy of the letter from Management to

Conciliation Officer on 2248/08/LO/AIL dispute.

Ex.R48 is the copy of the letter from Union to Labour

Commissioner. Ex.R49 is the copy of the report on

failure of conciliation. Ex.R50 is the copy of the

Government order-Labour Department reference of

ID. Ex.R51 is the copy of the show cause notice from

Labour Department. Ex.R52 is the copy of the reply

from Management on show cause notice. Ex.R53 is the

copy of the letter from Arokiadass on request for VRS.

Ex.R54 is the copy of the letter from P. Janakiraman

on request for VRS. Ex.R55 is the copy of the points

discussed during the meeting on 17-02-2010. Ex.R56

is the copy of the agreement with Maulick Leather

Crafts. Ex,R57 to Ex,R66 are the copy of the Maulick

Leather Crafts renewal letters. Ex.R67 is the copy of

the certificate of registration under Contract Labour

(Regulation & Abolition) Act, 1970. Ex.R68 is the

copy of the Factory Licence copy. Ex.R69 is the

computer generated list of the employees at Poothurai

Unit, who have received VRS announced by Pond’s

Exports Limited and left services. Ex.R70 is the copy

of the cessation of manufacturing operation letter

given by Pond’s Exports Limited to Deputy Director

of Industrial Safety and Health, Villupuram District,

Tamil Nadu. Ex,R71 is the copy of cessation of

manufacturing operation letter given by Pond’s Exports

Limited to Joint Director of Indsutrial Safety and

Health, Villupuram District, Tamil Nadu. Ex.R72 is the

copy of letter addressed by Pond's Exports Limited,

surrendering factory licence of Poothurai unit to Joint

Director of Industrial Safety and Health, Villupuram

District, Tamil Nadu, Ex.R73 is the copy of letter

addressed by Pond's Exports Limited, surrendering

factory licence of Poothurai unit copy marked to

Deputy Director of Industrial Safety and Health,

Villupuram District, Tamil Nadu.

14. It is the first contention of the respondent

establishment that the petitioner has only 6 members

and they could not represent for the 66 workmen and

the 66 workmen have not signed the dispute raised by

the petitioner union on 29-08-2008 and it only signed

by the office bearers and the letter exhibited under

Ex.P39 though signed by 66 workmen which was given

to the Labour Officer which is not a letter for

authorization to file the claim statement or to raise the

industrial dispute on behalf of them and that the letter

under Ex.P39 is not at all sufficient enough to

authorize the petitioner to raise the present industrial

dispute and the said Ex.P39 would not complete

requirement of sec.36 of Industrial Disputes Act to

represent the other workmen who have not singed.

On this aspect records submitted by the petitioner are

441

3 April 2018]

LA GAZETTE DE L’ETAT

carefully perused. On perusal of records, it could be

seen that the petitioner union has exhibited the

certificate of registration of trade union and its

members list. The certificate of registration of trade

union is exhibited as Ex.Pl. Though the petitioners have

exhibited the members of the union list as Ex.P2 it

does not authorize by anybody else, just the petitioner

union has listed the members along with the token

number and even the said workmen have not signed in

the list or authorize by anybody to represent on behalf

of them. On perusal of Ex.P39 under which the

petitioner union has raised the industrial dispute

before the Conciliation Officer, it is learnt to this Court

that all the 66 members have signed the said document.

Furthermore, the Ex.P54 is the reference which is sent

to this Court attached with the annexure and the

Secretary of the Labour Department has signed the

same and that therefore, the contention raised by the

respondent management that the trade union has no

authority to represent 66 workers is not sustainable

and it is to be held that the union can represent the 66

workers.

15. The main contention of the petitioner union is

that the members of the union the 66 workers have

been

mala fidely transferred by the respondent

management from the respondent factory to other

States with an intention to compel them to accept the

Voluntary Retirement Scheme announced by the

respondent management. On the other hand, it is the

contention of the respondent management that the

petitioner members had extracted various illegal

activities and go slow over several months as against

average production and therefore, the company met

with a loss and the production chart of the year 2006

and 2007 would reveal the considerable reduction in

productivity level and in October, 2008 the last average

production of about 16 pairs for a day which was

agreed to in the 12(3) settlement in 2002 it came

down to 3.31 pairs per man while the expected average

production of 16 pairs per man and since the

respondent management has met with loss it suspend

the production and announced Voluntary Retirement

Scheme. The main allegation of the petitioner union

is that on 18-04-2008 they have made charter of

demands before the Labour Officer (Conciliation) for

revision of wages and other allowances. The respondent

management engaged contract workers in the direct

manufacturing unit along with the permanent workers

for a meager wage of ` 4,000 per month whereas, the

workers who rendered 15 to 20 years where paid

` 10,000 to ` 15,000 per month and that the respondent

management did not want to engage permanent workers

and while dispute is pending the respondent

management voluntarily has announced voluntary

retirement scheme and compelled the petitioner union

members to opt voluntary retirement scheme by

suspending

the

production

with

effect

from

21-10-2008 and threatened the workers that the

factory will be closed and the service will be

transferred to other State if, they failed to opt voluntary

retirement scheme in the month of October, 2008.

16. On this aspect, evidence and documents are

carefully perused. It is not disputed by either sides that

these petitioners are the permanent workers of the

respondent factory and they have raised the industrial

dispute for revision of wages before the Conciliation

Officer and that was pending before the Conciliation

Officer and the respondent management suspended

production from 21-10-2008 due to the loss occurred

to them and they transferred 66 workers to various

branches of the factory for which the petitioners have

raised the industrial dispute. It is not in dispute that

apart from the petitioner union two other union were

functioning at the respondent establishment and the

respondent establishment has suspended its production

and announced voluntary retirement scheme and

admittedly, the respondent has not closed down the

factory. It is the case of the respondent management

that they have transferred the workers on 05-11-2008

on their request to other state and there is no illegal

transfer since it was opted by the workers and the

standing order of the company provide for such

transfer and the terms and conditions of the

appointment order also provides to transfer of the

workmen.

17. The respondent management has exhibited the

notices issued to the petitioner workmen to improve

the production of the industry from 14-03-2007 to

17-09-2008 under Ex.R3 and these notices would go

to show that the respondent management has

communicated the repeated notices to improve the

production of the factory and the said notice have been

displayed at the factory premises since the petitioner

workmen have

indulged in go-slow agitation. The

respondent management has also asked the petitioner

workmen not to indulge in go-slow agitation and to

improve the production and it is also learnt from

records that the Company has met with the loss for

more than 1½ years due to the low production and that

therefore, the respondent has suspended its production

activities with effect from 21-10-2008 and announced

voluntary retirement scheme. The company has only

suspended production activities and announced

voluntary retirement scheme in which 97 out of 163

workers were accepted the voluntary retirement

scheme and their benefits have been settled under the

442

LA GAZETTE DE L’ETAT

[3 April 2018

said scheme on their resignation. Since, the respondent

management has suspended the production activities

and the factory was not functioning the 66 workmen

have been transferred to some other sister concerns

of the respondent establishment. But, it is the case of

the petitioner union, that the respondent management

has not obtained any prior permission from the

Government to close the factory under section 25(o)

of the Industrial Disputes Act and only to victimize

the members of the union workers who have demanded

for wage revision has announced suspension of

production and announced Voluntary Retirement

Scheme and transferred the workers who have not

opted Voluntary Retirement Scheme and in support of

his case, the learned Counsel for the petitioner has

relied upon the judgment reported in 2010 II LLJ 783

(Mad) wherein the Hon’ble High Court of Madras has

held that,

“15. Under section 25-J (2) of the Industrial

Disputes Act, only the terms rendered by the

employer in respect of the provisions of ChapterV-A

and V-B. If, they are more favourable, that alone is

protected. Otherwise, section 25-J(l) over rides

inconsistent provisions contained in any other law

for the time being in force. Therefore, the argument

that the present partnership firm which is running

the Mill has no role for the closure and that the

settlement between the individual workers and the

Management is binding on them does not stand to

reason.

16. Further, when Section 25-O makes its clear

that the workmen are entitled to get wages if, there

is no prior permission or when the permission is

refused, the Parliament itself has given a declaratory

relief to the workers and therefore, it is unnecessary

even for the workers to raise a dispute in such

contingencies. If, there is no prior permission

before effecting the closure, the workmen can even

apply directly to the State Government for

appropriate revenue recovery certificate under

section 32/76 with effect from March 5, 1976. The

Supreme Court vide its judgment in Fabril Gasosa

V. Labour Commissioner and others AIE 1997 SC

954 : (1997) 3 SCC 150 : 1997-1-LLJ-872 has held

that in such cases the workmen can apply directly

to the State Government for the Revenue Recovery

Certificate without any judicial adjudication on the

issue relating to closure. Therefore, the contention

made by the petitioner's Counsel that the Tribunal

ought to have gone into the merits of the closure

does not stand to reason...”

From the above observation of the Hon’ble High

Court of Madras, it is clear that the workers are

entitled for wages if any, permission is not obtained for

closure. But, in this case, it is the contention of the

respondent management that they have not closed the

factory and they have suspended their production and

announced Voluntary Retirement Scheme and since

there is no retrenchment or termination, there is no

employer- employee relationship is broken down by the

respondent and they have only transferred the

employees to some other establishments of the

respondent management and that there is no closure

and hence, section 25-o would not attract and prior

permission is not required to the respondent

management since they have not closed the factory.

18. The another contention of the respondent

management is that the charter of demand of wage

revision sought of by the petitioner union is

unreasonable and hence, it is not accepted by the

respondent management and to pressurize the

management the workers of the Industry resorted

agitation by which the respondent management has met

with the loss. On this aspect, the evidence of PW1 is

carefully considered which runs as follows :

“Ex.R3





go-slow misconduct

pairs per day



shoesmeterial supply



meterial supply

Ex.P16





go-slow

go-slow

VRS announce



go-slow

VRS scheme announce







VRS scheme













Ex.R.4Ex.R.4









”

443

3 April 2018]

LA GAZETTE DE L’ETAT

From the above evidence of PWl, it is clear that

for a period of January-2007 to April-2008, the

production was only 3.5 pairs per day which was

disclosed in Ex.R3 and further, it reveal from Ex.RS

that notice has been

given to the workers on

14-03-2007 as a reminder stating that production is not

improved deteriorating day by day and further, it

reveals that in the month of February-2007 the

production level achieved in the factory was below the

expected level and though they were keeping sufficient

raw materials in the factory on 13-03-2007, the total

production is only 10,219 pairs which is against 930

pairs per day and the management has requested all the

employees to co-operate with the management for

effective function of the factory by producing

maximum number of pairs. Ex.R3 would further reveal

that various notices have been sent to the workers

which would go to show that production level of the

factory was reduced and the management has declared

that management has met with loss and that therefore,

it is not in dispute that the production level was

reduced in the factory since the union has started go-

slow strike from January-2007. In such circumstances,

the Ex.P17 marked by the petitioner would go to show

that respondent company has met a loss of ` 22,1703,00

for the period 01-01-2007 to 31-12-2007 and heavy

loss of ` 64,315.00 for the period 01-01-2008 to

31-03-2009. Therefore, it is established by the

respondent management that company has met with the

loss and since that there was go-slow strike of the

workers from the period of January-2007, the

respondent has declared Voluntary Retirement Scheme

to the workers of the respondent establishment on

25-10-2008 as the company has suspended the

production at their factory on 25-10-2008 and decided

to settle the workers under Voluntary Retirement

Scheme and since these petitioners have not accepted

the Voluntary Retirement Scheme the respondent

management was compelled to transfer these members

of the union to other establishments of the respondent

management.

19. It is the further case of the respondent

management that they could not accommodate the

66 workmen at Puducherry and hence, they have been

transferred to other factories in the nearby states and

that therefore, the petitioner union has raised the

industrial dispute before the Conciliation Officer

challenging the transfer of 66 workmen. It is not

denied by the petitioner workmen that the Company

has met with a loss and the production was reduced in

the year 2007 and 2008. Further, the petitioner union

has exhibited the profit and loss account of the

respondent firm as Ex.P17 which would go to show that

the respondent establishment has met a loss of

` 22,173,000 for the period from 01-10-2007 to

31-12-2007 and the respondent establishment has met

with loss of

` 64,315,000 in the period from

01-01-2008 to 31-03-2009 due to the low production

in the respondent establishment.

20. As rightly pointed out by the respondent Counsel

that the management has not terminated any employee

though they have met a loss at the respondent

establishment due to go-slow in production by the

workers and the respondent management has only

transferred these petitioners to other respondent

establishments and has not retrenched them from

service. Furthermore, it is the case of the respondent

management

that

these

petitioners

have

been

transferred only on the terms and conditions of the

appointment that they could be transferred to any other

place wherein, the respondent establishments are

situated. On this aspect, the learned Counsel for the

respondent pointed out that even as per the standing

order of the respondent establishment which is

exhibited as Ex.R14 the employees can be transferred

to any other establishments which are conducting by

the respondent management and the petitioner union

members after announcement of the Voluntary

Retirement Scheme have submitted an application to

the respondent establishment stating that they are not

willing to get Voluntary Retirement Scheme and that

they have to be transferred to other establishments of

the respondent establishment and they have given

consent to transfer them to any other establishments

of the respondent management. On this aspect, the

evidence of PW1 is carefully considered which runs

as follows :

“Ex.R8, R9. R10, R11, R12, R13

A. Paul Mary George,

K. Dhayanidhi, S. Arokiaraj, B. Vijayakumar and

S. Dhandapani













Ex.R8



Ex.R14





(Standing Order)











444

LA GAZETTE DE L’ETAT

[3 April 2018





(transfer

order)





W.P.No.

22319/2009



??Writ

PetitionWrit Petition

writ

Petition







?





?









?

















Ex.R15



”

From the above evidence, it is clear that

appointment

order

issued

by

the

respondent

management has terms and conditions in which the

respondent management has reserved a right to

transfer the workman to anywhere else wherever, the

respondent establishment conducting business and

wherein, the signature of the employees were obtained

by the management and further evidence would reveal

the fact that standing order of the factory would permit

the respondent establishment to transfer them to any

other factory which are conducting by the respondent

management and as the respondent management has

suspended the production of the factory without

terminating any employee or given any retrenchment

it has announced

only Voluntary Retirement

Scheme and rest of the 66 workers have transferred

to other factories of the respondent establishment.

Furthermore, it is learnt from the above evidence that

as per the rule 16 of the standing order, the workers of

the respondent management can be transferred to other

factories which are situated even outside the

Puducherry unit and further it is also clear from the

evidence that in the appointment order of the members

of the petitioner union, the respondent management

has reserved their right to transfer them to any other

factories and those appointment orders which are

exhibited as Ex.R8 to Ex.R13 would reveal the fact that

the respondent management can transfer the employees

to other factories of the respondent management and

that therefore, the transfer of 66 workers is not against

the standing order of the company or against the terms

and conditions of the appointment order of the

workers.

21. Further, the learned Counsel for the respondent

has relied upon the judgment reported in CDJ 2015

MHC 790, wherein, the Hon'ble Madras High Court

has observed that,

“Petitioner is a company engaged in the

manufacture of shoes - company suspended its

operation - Employees Union took up the mater

before

the

Joint

Commissioner

of

Labour-

settlement between the petitioner Management and

the Employees Union was entered - some workmen

were reengaged on restructured wages in the

petitioner company and the remaining more workers

accepted the compensation in lieu of agreeing

cessation of employment - Labour Court has

allowed all the computation petitions filed by the

workers and directed the petitioner company to pay

monetary value as prayed for by them -

Held that suspension of operations was declared

till the date of signing of the settlement - in order

to wriggle out the financial constrains and adverse

market conditions, the petitioner management was

not in a position to continue the business operation,

has genuinely resorted to suspension of operation

-petitioner management has declared suspension of

operation in order to negotiate with the respondent/

workers and as expected by it, the Union -

settlement is a valid one - it is settled law that the

workmen, having received the amounts in full, quit

all their claims, cannot question the same later and

once an agreement was entered - once the

agreement is acted upon, there was a performance

of the terms and once it is so performed, even in

part, would attract the principle of equitable

estoppels - Petitions are allowed.”

From the above observation, it is clear that

whenever the management is not in a position to

continue the business operation has genuinely resorted

to suspension of operation in order to negotiate with

445

3 April 2018]

LA GAZETTE DE L’ETAT

the workers. In this case also, the respondent

management has announced Voluntary Retirement

Scheme and has transferred the workers who have not

opted Voluntary Retirement Scheme and that therefore,

the act of the respondent management declaring

suspension of production is not against the provisions

of the Industrial Disputes, Act and that therefore, it

is just and necessary to hold that transfer order issued

by the respondent management to 66 workers is

bona fide while the respondent management has

suspended the production without terminating the

employees and announced Voluntary Retirement

Scheme and transferred the employees who have not

accepted Voluntary Retirement Scheme and therefore,

it is held that the transfer of 66 workers is not

mala fide and it is just and necessary to hold that the

industrial dispute raised by the petitioner union over

transfer of 66 workmen by the respondent management

is not justified. As this Tribunal has held that the

industrial dispute raised by the petitioner union over

transfer of 66 workers by the respondent management

is not justified, it is just and necessary to decide

whether the petitioners are entitled for any relief.

From the above discussions already made by this

Tribunal, it is clear that the 66 members of the

petitioner union have been totally transferred since the

respondent management has suspended their operation

of production and that there is a chance to restart the

production operation of the respondent establishment

and hence, it can be ordered by this Tribunal that if the

suspension of production of the respondent factory is

revoked and the factory is restarted these petitioners

have to be given employment at the respondent factory

and that they have to be accommodated at the

respondent establishment with the same seniority by

transferring them from the unit of the factory where

they have been now transferred.

22. On Point No.2 :

The next point is to be decided is that whether the

industrial dispute raised by the petitioner union, over

closure of the unit by the management is legal and

justified or not. It is contended by the petitioner

union that the act of the respondent management

suspending the production of the factory and

shifting the same to Vazhudhavur factory would

amount to closure and the closure of the factory by

the respondent management is illegal. On the other

hand, it is contended by the respondent management

that they have not closed down the factory and that

they have only suspended its production and

relationship of employer - employee have not been

broken out so far since the workers have been only

transferred to other units of the respondent

management.

23. On this aspect, the learned Counsel for the

petitioner has argued that when the dispute raised by

the petitioner union, over the wage revision is pending

before the Conciliation Officer, the act of the

respondent management without prior permission of

the Conciliation suspended the production from

21-10-2008 amount to lock-out of the factory and

then the factory was closed with effect from

30-10-2008 and since the members of the petitioner

union are rendered unemployment it is to be inferred

that the factory was illegally closed on 30-10-2008

and that the respondent management has closed down

the factory to victimize the workers who have raised

the dispute before the Conciliation Officer for wage

revision and in support of his argument the learned

Counsel for the petitioner has relied upon the

judgment reported in 1958(1) SCC 312 wherein, the

Hon’ble Supreme Court of India has held that,

“...........Therefore, the true test is that when it is

claimed that the employer has resorted to closure

of industrial activity, the Industrial Court in order

to determine whether the employer is guilty of

unfair labour practice must ascertain on evidence

produced before it whether the closure was a device

or pretence to terminate services of workmen or

whether it is bona fide and for reasons beyond the

control of the employer. The duration of the

closure may be a significant fact to determine the

intention and bona fides of the employer at the time

of closure but, is not decisive of the matter. To

accept the view taken by the Industrial Court would

lead to a startling result in that if, an employer who

has resorted to closure, bona fide wants to reopen,

revive and re-start the industrial activity, he cannot

do so on the pain that the closure would be

adjudged a device or pretence. Therefore, the

correct approach ought to be that when it is claimed

that the employer is not guilty of imposing a

lock out but, has closed the industrial activity, the

Industrial Court before which the, action of the

employer is questioned must keeping in view all the

relevant circumstances at the time of closure

decide and determine whether the closure was a

bona fide one or was a device or a pretence to

determine the services of the workmen. Answer to

this question would permit the Industrial Court to

come to the conclusion one way or the other. ......”

and further the learned Counsel for the petitioner

has also relied upon the judgment reported in 2012(3)

LLN 358 (Mad) wherein, the Hon’ble High Court of

Madras has held that,

446

LA GAZETTE DE L’ETAT

[3 April 2018

“.........19. It is clearly pleaded that it is a factory

covered by Chapter V-B of the Industrial Disputes

Act and in as much as a prior approval under

section 25-N of the Industrial Disputes Act was not

obtained, it is a clear case of illegal retrenchment

and the workers are entitled to be continued in

service. Though the Labour Court was wrong in

stating that it cannot go into any incidental

question, namely, whether the workman has assigned

permanent status in terms of Act 46 of 1981, that

need not be gone into at this stage. Under section

3 of Act 46 of 1981, the workers are deemed to be

become permanent without there being any order of

any Court and it is a satisfactory declaration

conferred on the workers. The fact that the other

workers have not challenged the Award is not a

conciliation for denying the relief to the present

workman. ...”

and the learned Counsel for the petitioner has also

relied upon the judgment reported in 1986(1) LLN 490

wherein, the Hon’ble Supreme Court of India has held

that,

“A. Industrial Disputes Act, 1947, sections 25T,

25O and 25K - Unfair labour practice - Marketing

division of a company closed down without

complying with the provisions of section 25-O of

Industrial Disputes Act - Requirement of section

25-K of engaging of not less than 100 workmen in

the industrial establishment stood fulfilled in view

of the total number of workmen employed in the

marketing division and factory of the company-

Both

the units

having constituted a single

establishment-Termination

of

services

of

the

workmen in contravention of terms of existing

settlement between the employer and workmen

amounts

to

unfair

labour

practice

of

not

implementing the settlement - Reinstatement with

back wages ordered. ............”

24. On the other hand, the learned Counsel for the

respondent has argued that the respondent management

has not closed down the factory and they have

temporarily suspended the production and the

relationship of employer-employee has not been

broken out since the workers have only been

transferred to other units of the respondent management

and hence, it could not be termed as closure and that

the respondent management has not retrenched any

workman from their factory and it announced only

Voluntary Retirement Scheme and 97 workers out of

163 workers were settled and that the rest of the

workers who have not opted Voluntary Retirement

Scheme alone have been transferred to other units of

the respondent establishment. Further, in support of

his argument, the learned Counsel for the respondent

has relied upon the judgment reported in CDJ 2015

MHC 4789, wherein, the Hon’ble Madras High Court

has held that,

“The third respondent suspended the Factory

Operation without serving mandatory notice as per

law, hence, it goes against it. However, considering

the present situation, the third respondent had

settled the benefits under the voluntary retirement

scheme for 123 employees out of 185 total

workforces. Hence, it is near impossible to run the

factory with such a meager strength of workers.

The third respondent/management has offered

employment to the petitioner at the Virudhunagar

Factory, which is co-unit of the Pallavaram unit, on

the same status salary, etc., The third respondent has

also offered the usual voluntary retirement benefits

as per the terms and conditions on par with the

co-employees numbering 123.

The highly competent Counsel appearing for the

petitioner submits that the employees are willing to

join at the Pondicherry unit. However, the highly

competent Counsel appearing for third respondent

replied that 62 employees cannot be accommodated

at the Pondicherry Unit since there is surplus

employees who are working at the Pondicherry unit.

Therefore, this Court cannot compel the third

respondent to provide employment to the employees

in the petitioner union at the Pondicherry unit.

Likewise this Court cannot compel the third

respondent/management to restore the original

position of the factory in order for the running of

the same, since the third respondent has given two

options to the employees viz., either the employees

can join at the Virudhunagar unit or receive benefits

under the voluntary retirement scheme of the

management.

On considering the facts and circumstances of

the case and arguments advanced by the highly

competent Counsels on either side and on perusing

the typed-set of papers and the views of this Court

as mentioned above (i) to (v), this Court dismisses

the above writ petitions since the management has

come forward to protect the employees of the

petitioner union by way of providing the same jobs

at their co-unit at Virudhunagar or even prepared to

pay benefits under the voluntary retirement scheme

and to treat the employees with their co-employees

on par. Therefore, there is no prejudice to the

petitioner union whatsoever.......”

447

3 April 2018]

LA GAZETTE DE L’ETAT

and further, the learned Counsel for the respondent

has also relied upon the judgment reported in CDJ

2015 MHC 790, wherein, the Hon'ble Madras High

Court has held that,

“In the present case, the petitioner management

declared suspension of operation on 12-11-2004

and admittedly, the petitioner management has not

resorted to termination of its employees. However,

even presuming that there was a closure as contended

by the respondent workers, it is relevant to

determine whether such closure was device or a

pretence to terminate the service of the workmen

or whether it is bona fide and far beyond the control

of the employer, has to be decided on the evidence

produced before the Court. On a perusal of the

entire material and evidence as the award passed by

the Labour Court, this Court finds that the Labpur

Court has not given any cogent reasons that the

alleged closure resorted to by the petitioner

management is not bona fide and tainted with

mala fide intention to terminate the services of the

workmen and the workers have not alleged that the

so-called closure is not genuine one and merely

alleging that the closure is illegal without assigning

any reasons, it cannot be construed that it is illegal

closure when the employer has proved that the

suspension of operation was for bona fide reasons.

On overall consideration of the facts and evidence

available on record, this Court could analyze that in

order wriggle out the financial constrants and

adverse market conditions which were prevailing

during the material period due to which, the

petitioner management was not in a position to

continue the business operation, has genuinely

resorted to suspension of operation and a notice to

that effect was put on board on 12-11-2004.

Therefore, this Court is of the considered view that

the petitioner management has resorted to only

suspension of operation and not closure as

contended by the learned Counsel for the

respondent/workmen. The decision relied upon by

the learned Counsel for the respondents/workmen

in Sri Arunachaleswarar Mills (cited Supra), cannot

be made applicable to the facts of the present case

in view of the fact that in the present case, the

petitioner management has only resorted to

suspension of operation and not closure, whereas,

the abovesaid decision deals with the closure and

since the management therein had resorted to

closuire without prior permission, this Court held

that the same was not binding on the workmen and

the settlement relied on by the management could

not be upheld as it was contrary to the statutory

provisions. It js well settled law that the closure or

stoppage of the whole or part of the business is the

function of the management which is entirely in the

discretion of the employer carrying on the business.

The industrial adjudication cannot interfere with the

discretion exercised by the employer in such a

matter and it has no power to direct the employer

to continue the whole or part of the business which

the employer has decided to shut down. However,

it is no doubt true and settled that if, the employer

resorted to closure, it is mandatory on his part to

comply with all the requirements as envisaged under

the Act..”

From the above observations of the Hon’ble High

Court, it is clear that mere suspending the factory

production is not a closure and offering of

employment in some other factory of the respondent

establishment on the same status and salary would not

amount to closure. In this case, the respondent

management has only suspended its production and not

retrenched any employee and not terminated any

employee from the factory and further, the respondent

management has only transferred these workers to

some other factory of the respondent establishment.

From the above citations relied upon by the learned

Counsel for the petitioner, it is clear that if, the

employer has closed the factory without bona fide

intention then it can be termed as unfair labour

practice. But, in this case, it is established by the

respondent management that they have met with loss

in the year 2007 and 2008 since, the production level

was drastically reduced and the same was also admitted

by the petitioner side and the documents filed on the

side of the petitioner would go to show that there was

a huge loss to the respondent establishment in the

year 2007 and 2008 and further, it is observed by the

Hon'ble High Court in the above-mentioned judgment

relied Upon by the learned Counsel for the petitioner

that if the employer closed down the factory with

compliance of section 25(o) of the Industrial Disputes

Act and committed termination of service of the

workmen in contravention of terms of existing

settlement, then it can be termed that the respondent

management has committed unfair labour practice.

But, in this case no one had been terminated from

service by the respondent management and out of

163 workers, 97 workers have opted for Voluntary

Retirement Scheme and 66 workers who were willing

to get continuous employment only transferred to

some other industries of the respondent establishment

and that therefore, the citations relied upon by the

448

LA GAZETTE DE L’ETAT

[3 April 2018

petitioner would not support the case of the petitioner.

On the other hand, the citations relied upon by the

respondent would scorely applicable to this case since

in this case also the production of the factory was

suspended and the remaining workers who have not

opted Voluntary Retirement Scheme have been transferred

to some other industries which are maintained by the

respondent management.

25. As already discussed above that the respondent

management has established that they have met with a

huge loss since there was go-slow strike of the

workers and production was drastically reduced from

13.00 pairs to 3.50 pairs, it is clear that suspension

of production ordered and Voluntary Retirement

Scheme announced by the respondent management is

bona fide and is not announced with any mala fide

intention and that therefore, the industrial dispute

raised by the petitioner union that there was an illegal

closure is not justified and hence, the industrial dispute

raised by the petitioner union is liable to be held as

unjustified.

26. In the result, the industrial disputes raised by

the petitioner union over transfer of 66 workers and

closure of the unit by the respondent management are

not justified. However, Award is passed directing the

respondent management to accommodate the members

of the petitioner union who are mentioned in the

reference at the respondent establishment whenever

the respondent establishment starts its production by

revoking the order of suspension of production by

giving first preference to the members of the

petitioner union who have joined in the respective

transferred post within one month from the date of

this Award. No cost.

Dictated to the Stenographer, transcribed by her,

corrected and pronounced by me in the open Court on

this the 18th day of December, 2017.

G. THANENDRAN,

Presiding Officer,

Industrial Tribunal-cum-

Labour Court, Puducherry.

————

List of petitioner’s witness:

PW.1

—03-07-2013 S. Pannirdasse

List of petitioner’s exhibits:

Ex.Pl

— 1995

Copy

of

the

petitioner

union registration certificate.

Ex.P2

—

—

Copy of the petitioner union

members list.

Ex.P3

—

—

Copy

of

the

documents

relates to salary structure of

the

Executive

of

the

respondent management.

Ex.P4 —04-04-2000 Copy

of

the

petitioner

union

charter of demand

submitted to the respondent

management.

Ex.P5

— 2000

Copy of the counter demand

raised by the respondent

management.

Ex.P6

— 2000

Copy of the Minutes of

meeting

before

the

Conciliation Officer.

Ex.P7—30-04-2002

Copy of the Conciliation

failure report.

Ex.P8—05-06-2002

Copy of the Government

reference.

Ex.P9—02-10-2002

Copy of the claim statement.

Ex.P10—24-10-2002 Copy of the letter of the

individual worker accepting

the 18(1) settlement.

Ex.P11 —09-03-2011 Copy of the order passed by

the Hon’ble Court in W.P.

No. 25952 of 2008.

Ex.P12—07-03-2008 Copy of the charter of

demand submitted by the

petitioner union on behalf

of its 81 members.

Ex.P13—31-03-2008 Copy

of

the

petitioner

union’s

letter

to

the

respondent

management

claiming majority status.

Ex.P14—21-05-2008 Copy of the conciliation

notice on the petitioner

union

dispute

dated

18-04-2008.

Ex.P15

—

—

Copy of the Licence issued

by

the

Inspector

of

Factories to the respondent

under the Factories Act.

Ex.P16

—

—

Copy of the delivery challan

stands in the name of

respondent which shows

the respondent engaging

manufacturing activity in

the name of Aroma and

Malic Leathers.

449

3 April 2018]

LA GAZETTE DE L’ETAT

Ex.P17

—

—

Copy of the profit and loss

account of respondent and

Form

23AC

submitted

before the company Law

Board.

Ex.P18—21-05-2010 Copy

of

the

petitioner

union

objection to

the

Inspector of Factories.

Ex.P19—27-08-2008 Copy of the trade union

complaint

to

the

PW

authority.

Ex.P20—24-09-2008 Copy of the trade union

complaint to the

PWA

authority.

Ex.P21—07-10-2008 Copy of the High Court

order in WP. No. 24521of

2008.

Ex.P22—25-10-2008 Copy

of

the

VRS

application issued by the

respondent.

Ex.P23 —

—

Copy of the letter issued by

the respondent on receipt

of the VRS application.

Ex.P24 —

—

Copy of the details of the

resigned

employed

in

Aroma and Malic.

Ex.P25—14-10-2008 Copy

of

the

petitioner

union

complaint

to

the

Commissioner

of Labour,

Conciliation

O fficer

regarding

production in

third party unit.

Ex.P26—23-10-2008 Copy

of

the

petitioner

union

complaint

to

the

Commissioner

of Labour,

Conciliation

Officer

regarding

production in

third party unit.

Ex.P27—23-10-2008 Copy of the petitioner

union

complaint

to

the

Commissioner

of

labour

regarding lock out.

Ex.P28—24-10-2008 Copy

of

the

petitioner

union complaint regarding

removal of machinery.

Ex.P29—29-10-2008 Copy

of

the

petitioner

union complaint regarding

closure

of

production

planning control and lock

out.

Ex.P30—31-10-2008 Copy

of

the

petitioner

union

objection

to

the

respondent.

Ex.P31—31-10-2008 Copy of the petitioner

union complaint to the

Superintendent of Police.

Ex.P32—31-10-2008 Copy

of

the

petitioner

union

complaint

the

Inspector of Police.

Ex.P33—01-10-2008 Copy of the news published

in the Dinakaran regarding

removal of machinery to

the respondent factory.

Ex.P34—01-11-2008 Copy

of

the

petitioner

union

complaint

to

the

Government

regarding

removal of machinery and its

courier receipt.

Ex.P35—20-11-2008 Copy of the objection letter

to

the

Commissioner

of

Labour regarding shifting of

factory.

Ex.P36—20-11-2008 Copy of the objection lette

to the Commissioner of

Labour regarding shifting

of factory.

Ex.P37—16-11-2008 Copy of the objection letter

of the HUL Employees

Union.

Ex.P38—02-12-2008 Copy of the objection letter

of the HUL TEA Union.

Ex.P39—06-11-2008 Copy

of

the

petitioner

union

complaint to the

Conciliation Officer, etc.,

regarding

transfer

of

workmen.

Ex.P40—06-11-2008 Copy

of

the

petitioner

union

complaint to the

Conciliation Officer, etc.,

regarding

transfer

of

workmen.

Ex.P41—06-02-2009 Copy

of

the

petitioner

union complaint regarding

closure of factory.

Ex.P42—13-02-2009 Copy

of

the

petitioner

union

letter

to

the

Commissioner of Labour,

Secretary to the Labour

Department.

450

LA GAZETTE DE L’ETAT

[3 April 2018

Ex.P43—21-05-2008 Copy of the Conciliation

Officer notice.

Ex.P44—06-11-2008 Copy of the Conciliation

Officer notice.

Ex.P45—21-11-2008 Copy of the Conciliation

Officer notice.

Ex.P46—16-12-2008 Copy of the Conciliation

Officer notice.

Ex.P47—30-12-2008 Copy of the Conciliation

Officer notice.

Ex.P48—13-01-2009 Copy of the Conciliation

Officer notice.

Ex.P49—21-05-2008 Copy of the Conciliation

Officer notice and dispute,

dated 18-04-2008 raised by

the petitioner union for

charter of demand for wage

revision.

Ex.P50—27-11-2008 Copy of the conciliation

failure report.

Ex.P51—20-02-2009 Copy of the conciliation

failure report over the

dispute

of

closure

of

factory.

Ex.P52—24-03-2009 Copy of the Government

reference.

Ex.P53—01-12-2010 Copy of the High Court

order in Writ

Petition

No. 26180 of 2008, 23319/

2009, 399/2010.

Ex.P54—08-04-2011 Copy of the Government

reference as per the High

Court.

Ex.P55 —

—

Copy of the report of the

Inspector of Factories.

Ex.P56—24-02-2009 Copy of the Conciliation

Officer notice.

Ex.P57 —

—

Copy of the list of

machinery removed from

the factory.

Ex.P57A —

—

Copy of the memorandum

of

Ground

filed

in

CRP.PD. No. 294 of 2011.

Ex.P58—09-04-2009 Copy of the Commissioner’s

show cause notice to the

respondent.

Ex.P59 —

—

Copy of the news published

in the daily news paper.

Ex.P60 —

—

Copy of the ESI treatment

refusal letter.

Ex.P61—29-01-2010 Copy of the news published

in the Dinathanthi regarding

profit of the respondent

company.

Ex.P62—21-05-2010 Copy

of

the

petitioner

letter

to

the

Director,

Lab our

Department,

New Delhi.

Ex.P63—21-05-2010 Copy

of

the

petitioner

letter to the Secretary to

the Government, Labour

Department, New Delhi.

Ex.P64 —

—

C o p y

o f

t h e

acknowledgment card to

letter, dated 21-05-2010.

Ex.P65—24-05-2010 Copy

of

the

petitioner

union

letter

to

the

S e c r e t a r y

t o

t h e

G o v e r n m e n t

L a b o u r

Department, Puducherry.

Ex.P66—21-05-2010 Copy

of

the

petitioner

union complaint to the

Inspector of Factories.

Ex.P67—28-02-2002 Copy of the Award of the

Labour Court in I.D. 8 of

2008 and I.D. No. 4 of

2001.

Ex.P68 —

—

Copy of the transfer letter.

Ex.P69 —

—

Copy of the details of the

transfer workmen submitted

to the Conciliation Officer.

Ex.P70—17-05-2010 Copy

of

the

petitioner

union

letter

to

the

respondents.

Ex.P71—17-05-2010 Copy

of

the

petitioner

union

letter

to

the

respondents.

Ex.P72—17-05-2010 Copy

of

the

petitioner

union

letter

to

the

respondents.

Ex.P73—14-08-2009 Copy

of

the

petitioner

union

letter

to

the

Inspector of Factories.

Ex.P74—31-03-2010 Copy of the Form 20B

451

3 April 2018]

LA GAZETTE DE L’ETAT

Ex.P75—31-03-2011 Copy of the Form 20B.

Ex.P76—31-03-2012 Copy of the Form 20B

Ex.P77—22-04-2013 Copy of the declaration

Form

submitted

by

respondent before Central

Excise Department.

Ex.P78—22-04-2013 Copy of the export Invoice

of 3rd respondent.

Ex.P79—22-04-2013 Copy of the export invoice-

cum-Delivery challan.

Ex.P80—22-04-2013 Copy of the export invoice-

cum-Delivery challan.

Ex.P81—22-04-2013 Copy of the export invoice-

cum-Delivery challan.

Ex.P82—01-04-2010 Copy of the Form 23 AC.

Ex.P83—31-03-2011 Copy of the Form 23 AC.

Ex.P84—01-04-2011 Copy of the Form 23 AC.

Ex.P85—31-03-2012 Copy of the Form 23 AC.

Ex.P86—27-07-2012 Copy of the packing list

in Poothurai Factory.

Ex.P87—27-07-2012 Copy of the iinvoice- cum-

Delivery challan.

Ex.P88—10-07-2012 Copy of the invoice.

Ex.P89—10-07-2012 Copy of the respondent

Declaration

submitted

before

Central

Excise

Department.

Ex.P90—27-07-2012 Consignee

copy

of

respondent factory.

Ex.P91—28-07-2012 Copy

of

the

Tax

information

of

the

respondent factory.

List of

respondent’s witness:

RW1—18-02-2015

Youvarajan

List of respondent’s exhibits:

Ex.Rl

—24-10-2002 Copy of the long-term

&

settlement 2002-2006

07-02-2003 Memorandum of understanding.

Ex.R2 —11-10-2008 Copy of the letter from

PHLTS union.

Ex.R3 —14-03-2007 Copy of the various notices/

to

letter and warnings given by

17-09-2008 respondent on the go slow

adopted by petitioner and

communication

by

the

unions on such go slow.

Ex.R4—22-10-2008

Copy

of

the

letter

to

workers

by

coordinated

union’s

association

regarding VRS.

Ex.R5—21-10-2008

Copy of the notice on

VRS

announcement

by

management.

Ex.R6 —22-10-2008 Copy of the-

23-10-2008 1. notice on VRS announcement

23-10-2008 by management.

2. notice on VRS additional

amount by management.

3. notice on other benefits

of VRS by management.

Ex.R7 —25-10-2008 Copy of the notice to the

29-10-2009VRS opted employees and

Union letter to Conciliation

Officer.

Ex.R8 —01-06-1997 Confirmation order of an

employee (Pannirdasse).

Ex.R9 —14-04-2007 Confirmation order of an

employee

(Paul

Marie

George).

Ex.R10—31-12-1998 Confirmation order of an

employee (Dhayanidhi).

Ex.R11—31-12-1998 Confirmation order of an

employee (Aroquiaradjou).

Ex.R12—31-12-2001 Confirmation order of an

employee (V. Vijayashankar).

Ex.R13—31-07-1996 Confirmation order of an

employee (Dhandapani).

Ex.R14 —

—

Copy

of

the

certified

standing orders of respondent

company.

Ex.R15—05-11-2008 Copy

of

the

notice

displayed on notice-board

of the respondent giving the

details of transfer to 66

workers.

Ex.R16—06-11-2008 Registered letter addressed

to the President of the

petitioner union namely,

Pannirdasse to his residence

which

was

returned to

respondent with endorsement

of “Not claimed”.

452

LA GAZETTE DE L’ETAT

[3 April 2018

Ex.R17—06-11-2008 Returned

postal

cover

addressed to president of

the petitioner union namely,

Pannirdasse to his residence

which

was

returned to

respondent with endorsement

of “Refused”.

Ex.R18—09-01-2009 Copy of the affidavit filed

by

the respondent in I.A.

7/2009 in I.A. 253/2008 in

OS. 1476/2008 on the file

of Principal District Munsif

at Puducherry for appointment

of Advocate Commissioner

for shifting goods, materials

and

products

from

the

respondent’s factory premises

along with counter statement

filed by the petitioner.

Ex.R19—12-01-2009 Copy of the Order in I.A78/

2009 in O.S.1476/2008.

Ex.R20—02-02-2009 Advocate

commissioner

report in I.A.78/2009 in

O.S. No. 1476/2008.

Ex.R21—31-10-2008 Copy of the union letter to

Factory Manager.

Ex.R22—01-11-2008 Copy of the union letter to

Labour Commissioner.

Ex.R23—05-11-2008 Copy of the letter to Station

House Officer, Mettupalayam

Police Station.

Ex.R24—05-11-2008 Copy of the letter to Tahsildar.

Ex.R25—06-11-2008 Copy of the report in

Non-cognizable offence.

Ex.R26—05-11-2008 Copy of the transfer orders

sent to all the 66 workers

involved in present dispute.

Ex.R27—06-11-2008 Copy of the union letter to

Government Authorities on

VRS.

Ex.R28—06-11-2008 Copy of the union letter

to Conciliation Officer on

VRS.

Ex.R29—06-11-2008 Copy of the advisory notice

on overstay.

Ex.R30—06-11-2008 Copy of the letter from

Conciliation

Officer

on

service condition.

Ex.R31—24-11-2008 Copy

of

the

reply

to

Conciliation Officer notice

06-11-2008.

Ex.R32—07-11-2008 Copy

of

the

letter

to

Inspector of Factories on

inspection.

Ex.R33—07-11-2008 Copy

of

the

letter

to

Conciliation

Officer

on

over stay.

Ex.R34—07-11-2008 Copy of the report from

Police Station to Labour

Commissioner.

Ex.R35—07-11-2008 Copy of the notice on over

stay.

Ex.R36—07-11-2008 Copy of the complaint

letter to Police Station by

management.

Ex.R37—07-11-2008 Copy of the notices on over

stay.

Ex.R38—08-11-2008 Copy of the notices on over

stay.

Ex.R39—08-11-2008 Copy of the letter to station

House

Officer

on

unauthorized protests.

Ex.R40—15-11-2008 Copy of the notice to all the

transferred employees.

Ex.R41—21-11-2008 Copy of the notice to

enquiry from Conciliation

Officer.

Ex.R42—24-11-2008 Copy

of

the

reply

to

Conciliation Officer notice.

Ex.R43—22-12-2008 Copy of the notice from

Commissioner of Labour.

Ex.R44—02-01-2009 Copy

of the letter by

management on wage dispute

to Labour Commissioner.

Ex.R45—22-12-2008 Copy of the notice from

Commissioner of Labour.

Ex.R46—05-01-2009 Copy of the reply letter to

Notice from LC, dated

22-12-2008.

Ex.R47—22-01-2009 Copy of the letter from

Management to Conciliation

Officer on 2248/08/LO©/

AIL dispute.

Ex.R48—13-02-2009 Copy of the letter from

U n i o n

t o

L a b o u r

Commissioner.

453

3 April 2018]

LA GAZETTE DE L’ETAT

Ex.R49—20-02-2009 Copy of

the report on

failure of conciliation.

Ex.R50—24-03-2009 Copy of the Government

order - Labour Department

reference of ID.

Ex.R51—09-04-2009 Copy of the show cause

notice

from

Labour

Department.

Ex.R52—27-04-2009 Copy of the reply from

Management on show cause

notice.

Ex.R53—04-02-2009 Copy of the letter from

Arokiadass on request for

VRS.

Ex.R54—30-04-2009 Copy of the letter from

P. Janakiraman on request

for VRS.

Ex.R55—17-02-2010 Copy of the points discussed

during

the

meeting

on

17-02-2010.

Ex.R56—01-09-1999 Copy of the agreement with

Maulick Leather Crafts.

Ex.R57—01-08-2004 Copy

of

the

Maulick

Leather

Crafts

renewal

letter.

Ex.R58—01-08-2008 Copy

of

the

Maulick

Leather

Crafts

renewal

letter.

Ex.R59—31-08-2010 Copy

of

the

Maulick

Leather

Crafts

renewal

letter.

Ex.R60—18-08-2011 Copy

of

the

Maulick

Leather

Crafts

renewal

letter.

Ex.R61—01-10-2003 Copy of the agreement with

Auroma Leather Crafts.

Ex.R62—04-09-2004 Copy of the Auroma Leather

Crafts renewal letter.

Ex.R63—31-12-2007 Copy of the Auroma Leather

Crafts renewal letter.

Ex.R64—26-12-2009 Copy of the Auroma Leather

Crafts renewal letter.

Ex.R65—31-12-2010 Copy of the Auroma Leather

Crafts renewal letter.

Ex.R66—31-12-2011 Copy of the Auroma Leather

Crafts renewal letter.

Ex.R67—16-01-1997 Copy of the certificate of

Registration under Contract

Labour (Regulation and

Abolition) Act, 1970.

Ex.R68 —

—

Copy

of

the

Factory

Licence copy.

Ex.R69 —

—

Computer generated list of

the employees at Poothurai

unit, who have received

VRS announced by Pond’s

Exports Limited and left

services.

Ex.R70—09-02-2017 Copy of the cessation of

manufacturing

operation

letter

given

by

Pond’s

Exports Limited to Deputy

Director

of

Industrial

Safety

and

Health,

Villupuram

District,

Tamil Nadu.

Ex.R71—09-02-2017 Copy

of

cessation

of

manufacturing

operation

letter

given

by

Pond’s

Exports Limited to Joint

Director of Indsutrial Safety

and

Health,

Villupuram

District, Tamil Nadu.

Ex.R72—17-02-2017 Copy of letter addressed by

Pond’s Exports Limited,

surrendering factory licence

of Poothurai unit to Joint

Director of Industrial Safety

and

Health,

Villupuram

District, Tamil Nadu.

Ex.R73—17-02-2017 Copy of letter addressed by

Pond’s Exports Limited,

surrendering

facto ry

licence of Poothurai unit

copy marked to Deputy

Director of Industrial Safety

and Health Villupuram

District, Tamil Nadu.

G. THANENDRAN,

Presiding Officer,

Industrial Tribunal-cum-

Labour Court, Puducherry.