[51]
GOVERNMENT OF PUDUCHERRY
LABOUR DEPARTMENT
(G.O. Ms. No. 03/Lab./2019, Puducherry, dated 21st January 2019)
NOTIFICATION
In order to achieve better services in this Union Territory and
policies of Government of India, viz., “Make in India” and “Ease of Doing
Business”, the Government of Union territory of Puducherry is in the
process of rationalising and simplifying the various Acts and Rules
etc., of the Office of the Chief Inspector of Boilers, Puducherry so as to
create more conducive environment for industries without compromising
safety and security of workers engaged in the enterprises. Currently,
La Gazette de L' État de Poudouchéry
The Gazette of Puducherry
PART - II
EXTRAORDINAIRE
EXTRAORDINARY
Publiée par
Published by
Autorité
Authority
` 6-00
Prix : ` 6-00
Price :
` 6-00
Registered with the Registrar
of Newspapers for India under
No. 10410
Registered No.
PY/44/2018-20
WPP No. TN/PMG(CCR)/
WPP-88/2018-20
Dated : 29-1-2019
Price : ` 6-00
2019 } | 29 {
No.
6 Poudouchéry Mardi
29
Janvier
2019
No.
Puducherry
Tuesday
29th
January
2019
(9 Magha 1940)
52
LA GAZETTE DE L'ETAT
[PART–II
the Inspecting Officers physically inspects the boiler/economiser and
certify the boiler/economiser in accordance with the provisions of the
Boilers Act, 1923 and the Indian Boiler Regulations, 1950.
The Government of Puducherry is fully aware of the material, design
or construction of boilers and is committed for rapid industrialization in
the Union territory of Puducherry. Therefore, it has become necessary
to exempt the boilers/economisers from some provisions of the Boilers
Act, 1923 (No. 5 of 1923) without compromising safety and security of
human life and properties.
Now, therefore, in exercise of the powers conferred by sub-section (3)
of section 34 of the Boilers Act, 1923 (No. 5 of 1923), the Lieutenant-Governor
is hereby pleased to exclude the boilers/economisers, and for exempting
such boilers/economisers, is proposing the introduction of the
Puducherry Self Certification Scheme-cum-Consolidated Annual Return
Scheme for Boilers and Economisers, 2018, namely:–
Puducherry Self Certification-cum-Consolidated Annual Return
Scheme for Boilers and Economisers, 2018
1. Title and commencement.—(1) This Scheme may be called the
Puducherry Self Certification Scheme-cum-Consolidated Annual Return
Scheme for Boilers and Economisers, 2018.
(2) It shall come into force from the date of its Notification in
the Official Gazette.
2. Objective.—The objective of this Scheme is to reduce visits of
the Inspecting Officers/competent persons for inspection of those
boilers, which opt for this Scheme without compromising on the safety.
3. Application and Scope of the Scheme.—This Scheme of “Self
Certification-cum-Consolidated Annual Return” is open to all the boilers/
economisers and will apply only to those owners, who opt to join the
Scheme by making written application for the same as specified in
Annexure-I, and II with a self-declaration as given in Annexure-III.
4. Resolution.—Keeping the above context in view, the Chief
Inspector of Factories and Boilers, Labour Department, Government of
Puducherry has decided to simplify and introduce a new system for
53
PART–II]
LA GAZETTE DE L'ETAT
enforcement of the Boilers Act, 1923 with simplification in inspection
norms and certification of boilers. The Government thus decided to
introduce a Self-certification-cum-Consolidated Annual Return Scheme
for various boilers/economisers and which are in use in the Union
Territory. This step is intended to minimize the visits of the officers to
the industries, while at the same time ensuring more effective compliance
with the Boilers Act, 1923, by the owners. As per section 34 of the
Boilers Act, 1923, the State Government has power to exempt certain
provisions of the Act if, it is satisfied that having regard to the material
design or construction of boilers and the need for the rapid
industrialization of the State. In exercise of these powers, the Government
has decided to exclude the boilers/economisers from the operation of
the provisions of sub-section (c) of section 6, sub-section (3), (4), (5)
and (6) of section-8, section-10, sub-section-1(a) and 1(b) of section-19,
20, 21 of this Act subject to the conditions and restrictions specified as
under:
(a) The boiler or economiser covered under Self Certification
Scheme shall be inspected every year in case of boilers and every two
years in case of economisers by engaging a Boiler Operation Engineer
(BOE) who will be in the regular employment of the owner as per Boiler
Operation Engineers Rules, 2011.
(b) The inspection shall be carried out as per the guidelines
provided by Indian Boiler Regulations, 1950, the Puducherry Boilers
Rules, 1988 or any other rules/notifications framed by Central Boiler
Board and/or Government of Puducherry or by Government of India from
time to time.
(c) The owner shall submit consolidated return for the boiler/
economiser as per Annexure-IV and V of this notification in two copies,
within seven days from the date of inspection as prescribed in Indian
Boiler Regulations, 1950 and as amended from time to time.
(d) On receipt of the consolidated return of the boiler/
economiser in Annexure-IV and V, Inspector of Boilers shall record the
necessary details in Memorandum of Inspection Book and Memorandum
of Registration Book and the boiler/economiser shall stand exempted
from the aforementioned clauses of the Act, for the period of 12 months
in case of boiler and 24 months in case of economisers.
54
LA GAZETTE DE L'ETAT
[PART–II
(e) The boiler/economiser shall be stopped immediately if, any
accident/leakage occurs through pressure parts of boiler or boiler
components attached to it and intimation of the same shall be made
immediately to the Chief Inspector of Boilers, Puducherry. In such case, the
Self-Certification of Annexure-V shall stand suspended. However, after
necessary compliance of repairs, etc., to pressure parts of boiler or boiler
components in the prescribed manner, the same shall be restored.
(f) However, it may be noted that safety under the Boilers Act, 1923
is of utmost importance and is at apex and it shall be the responsibility
of the owner to follow the provisions of Act, Rules and Regulations
framed under the Act for safe operation of boiler. The owner will also
be responsible for any negligence and the violations of the provisions
of the Boilers Act, 1923, if found, during investigation of the accident.
(g) The Self-Certification Scheme is optional for the owners.
However, the owner will be free to avail the services of Chief Inspector
of Boilers/Third Party Inspecting Authorities nominated by Central
Boilers Board if, he so desires as per the existing practice and norms in
this regard.
5. Procedure for Registration under the Self Certification
Scheme.—(a) The owner desiring to join the Scheme shall submit an
application in the prescribed pro forma as given in Annexure-I, II
and III along with required amount of security deposit and processing
fee as specified in this clause, for each boiler or economiser. The Self
Certification Scheme Committee set up in this regard shall scrutinize
the application within thirty days of its submission and allot a
registration number to the respective owner and this number shall
be quoted in all correspondence under the Scheme.
(b) This Scheme shall be open to the owners of all the
registered boilers or economisers in the State, and the owner can
opt for the Scheme by applying to the Self Certification Scheme
Committee.
(c) The Self Certification Scheme Committee shall consist of
the following Members:
(i) Chairman : Chief Inspector of Factories and Boilers,
Puducherry.
(ii) Secretary : Deputy Chief Inspector of Boilers, Puducherry.
(iii) Members
: Inspectors of Boilers, Puducherry.
55
PART–II]
LA GAZETTE DE L'ETAT
The Committee will operate in the office of the Chief Inspector of
Factories and Boilers, Puducherry and will meet as when required.
6. Security deposit.—The amount of security deposit along with
the application for self-certification shall be ` 1,00,000 (One lakh).
7. Processing fee.—One time processing fee for processing the
application ` 10,000 (Ten thousand).
8. Payment of security deposits and processing fees.—The
security deposit and processing fees under this Scheme shall be paid
to Head of Account “Fees for Inspection of Boilers-others-0230-00-103-
00-00-00” through e-payment through separate challans.
9. Validity of the Scheme.—Once the owner has opted for the
Scheme, it shall be valid for a period of five consecutive calendar years.
After five consecutive calendar years, owner may renew the registration
under the Self Certification Scheme for further five calendar years by
submitting a fresh application with the required security deposit and
processing fee as the case may be. The owner shall also be free to
withdraw from the Self-Certification Scheme at any time before
completion of five years by informing the Self-Certification Scheme
Committee in this regard. In such cases of premature withdrawal from
the Scheme, the security deposit paid at the time of registration shall
stand forfeited.
10. Filing of Self Certification-cum-Consolidated Annual
Return.— After getting enrolled for the Scheme, the concerned owner
shall file Self-Certification-cum-Consolidated annual return in the
pro forma prescribed in annexure-IV and V along with required supporting
documents/information. This return must be filed within 7 days from the
date of inspection of boilers/economisers done by their own Boiler
Operation Engineer. In no case, the validity period for boilers covered
under this Scheme shall exceed twelve months and for economiser shall
exceed twenty four months. On failure to submit the return within
prescribed limit or extension in time-limit if, any granted by the Chief
Inspector of Boilers, Puducherry the owner shall cease to be the covered
under the Self-Certification Scheme. In such case, the security deposit
shall be forfeited.
56
LA GAZETTE DE L'ETAT
[PART–II
11. Consequences of submitting false information in the return.—
Any submission of false, incorrect information, in the Self-Certification-
cum-Consolidated Annual return, shall make the owner liable for action
as per the prevalent legal frame work and cancellation of registration
under the Self Certification Scheme. However, before taking any such
action, the Self Certification Committee shall inform the owner of such
grounds/information/charges as the case may be and afford him an
opportunity of being heard or represent his case before the Committee.
12. Inspection
procedure
under
the
scheme-process
of
randomization.—(a) The Self Certification Scheme Committee shall
follow the procedure of randomization for selection of the Boiler/
Economisers for inspection, which shall not exceed more than 20% of
total numbers of boilers in that category, in any particular year. The
boilers/economisers so randomly selected every year shall be inspected
only once in the five years to verify implementation of the Boilers Act, 1923
under the Scheme. The boilers/economisers inspected once during the
period of the Scheme shall not be inspected again during the remaining
period of five years for the Scheme unless there are any specific
complaints of violations received by the Self Certification Scheme
Committee in this respect. If, any violations are detected during the
course of inspection, it shall be processed as per the provisions of the
Boilers Act, 1923 or rules or regulations made under.
(b) Visits for inspections for enquiry into complaints shall be
made by Inspector of Boilers or Deputy Chief Inspector of Boilers only
on specific authorization by the Chief Inspector of Boilers, Puducherry.
13. Exception.—The Scheme shall not cover any inspections/visits
made by the Inspectors of Chief Inspectorate of Boilers for the purpose
of conducting enquiry into accidents and dangerous occurrence. Also,
the Scheme shall only apply to boilers/economisers registered under the
Scheme in the Union territory of Puducherry.
(By order)
E. VALLAVAN,
Additional Secretary to Government (Labour).
57
PART–II]
LA GAZETTE DE L'ETAT
ANNEXURE - I
APPLICATION FORM
From
M/s.
To
The Chief Inspector of Boilers,
Office of the Chief Inspector of Factories and Boilers,
Labour Deparment,
Puducherry - 605 009.
Sir,
Sub. : Application for registration under the Self Certification
Scheme.
Ref. : Government of Puducherry, Labour Department, G.O. Ms.
No. ......................, dated ........................ regarding Puducherry
Self Certification Scheme-cum-Consolidated Annual Return
Scheme for Boilers and Economizers, 2018.
* * * *
I/We have gone through the abovesaid Scheme and have
understood the same. I/We wish to be covered under the said Scheme.
As such I/We request you to kindly issue me/us necessary registration
under the same. The necessary information and other documents, as
required under the Scheme are enclosed. I/We undertake to abide by all
terms and conditions of the Scheme. It is also certified that I/We
am/I are competent and duly authorized to make any statement or provide
any information to any Central/State Government agency, on behalf of
this Factory/Establishment name .....................................
Kindly issue the necessary approval at the earliest.
Yours faithfully,
[Name and address of the owner]
Encl.: 1. Annexure-II [List of documents]
2. Annexure-III (Undertaking)
58
LA GAZETTE DE L'ETAT
[PART–II
ANNEXURE - II
LIST OF DOCUMENTS TO BE ATTACHED WITH ANNEXURE-I
1. Status of the Factory/Establishment :
[ C o m p a n y / F i r m/ S h o p / O t h e r s .
please specify].
2. Nature of work of the Factories/ :
Establishment [What work/business,
it is carried out].
3. Registry Number of Boiler/Economiser :
under the Boilers Act, 1923.
4. List of raw materials used and end :
products, if, the factory is a
manufacturing or processing unit.
5. Details of security deposit and :
Processing fee paid online.
6. Name and address of the Establishment/
:
Factory with telephone/mobile/fax.
Nos. and e-mail address, if any.*
7. Name and residential address of the
:
Owner with telephone/mobile/fax.
Nos. and e-mail address, if any.
8. Name and residential address of the :
Boiler Operation Engineer in-charge
with Certificate No., date and issuing
authority/telephone/mobile/Fax Nos.
and e-mail address, if any.
9. Name and certificate details of Boiler :
Attendants’ presently working at the
Boiler/ Economiser.
*Note:- Any communication send to this address shall be final
unless the change is not communicated to Office of the
Chief Inspector of Factories and Boilers, Puducherry.
Signature of the Owner
(Name and signature of authorized
signatory along with the Company Stamp)
59
PART–II]
LA GAZETTE DE L'ETAT
ANNEXURE-III
UNDERTAKING
(To be filled by the Owner)
I/We Shri/Ms. .............................................. son/daughter/wife of
Shri/Ms. ..................................... of residing at ........................................ is/
are the Owner of Boiler/Economiser located at M/s. ..................................
(Complete name and address of establishment/factory where the boiler
is installed), hereby apply for Puducherry Self Certification-cum-
Consolidated Annual Return Scheme for Boilers and Economisers, 2018
for boiler/economiser having registration No. ..................... under the
Boilers Act, 1923 and state as under:-
1. That I/We have applied for grant of coverage of boiler/
economiser having Registration No. .................... situated at .......................
(Complete name and address of establishment/factory where the boiler
is installed) under the Puducherry Self Certification-cum-Consolidated
Annual Return Scheme for Boilers and Economisers, 2018 notified by
Labour Department, Government of Puducherry vide Notification
No. ....................., dated ................. .
2. That I/We have gone through the Scheme and have fully
understood the contents of the Scheme and undertake to abide by the
same.
3. That it is declared that I/We am/are complying and will
continue to comply with all provisions of the Boilers Act, 1923, Rules and
Regulations made thereunder.
4. In case of any violation of the said Act will make us liable for
the penalty or their legal provisions as per the existing legal frame work
in this regard.
Owner
Place :
(Name and signature of authorized signatory
Date
:
along with the company Stamp)
Self attested
Photo of
Owner
(Size:
50 x 60 mm)
60
LA GAZETTE DE L'ETAT
[PART–II
ANNEXURE-IV
FORM FOR FILING ANNUAL RETURN FOR SELF
CERTIFICATION SCHEME UNDER THE BOILERS ACT, 1923
I/We Mr/Mrs/Miss ............................................ hereby, certify that
I/We am/are the Owner of the Boiler/Economiser, whose identification and
general details are as follows–
I/We hereby certify that my/our Boiler/Economiser have fully and
correctly complied with all the provisions under the Scheme and the
status of compliance of following the Boilers Act, 1923 and annual return
of my/our Boiler/Economiser, during the year ...................................... is
as under:
1. Name of Establishment/Factory, its :
postal address and location.
2. Name and address of the Owner along :
with e-mail ID, telephone and mobile
number.
3. Name of the certified Boiler Operation :
Engineer responsible for supervision
and control of the Boiler/Economiser.
4. Nature of business, industry or trade :
or occupation carried on by the
employer.
5. Boiler/Economiser Registration number :
8. Registration number allotted under :
the Self Certification Scheme.
Owner
Place :
(Name and signature of authorized
Date :
Signatory along with the company stamp)
Encl.: Annexure-V [Certificate]
————
61
PART–II]
LA GAZETTE DE L'ETAT
ANNEXURE-V
CERTIFICATE OF BOILER/ECONOMISER UNDER
SELF CERTIFICATION SCHEME AND ANNUAL RETURN
FOR THE YEAR ..................
1. Registration number allotted under :
the Self Certification Scheme.
2. Name and address of Owner
:
3. Registry number of Boiler/Economiser :
4. Type of Boiler/Economiser
:
5. Boiler/Economiser rating (m2)
:
6. Place and Year of Manufacture
:
7. Boiler Manufacturer
:
8. Approved Working Pressure
:
Kg/cm2
9. Quality of steam and its temperature :
10. Rate of steam generation
:
11. Brief description of boiler
:
12. Whether fired or waste heat boiler
:
13. Date of registration
:
14. Last date of annual inspection
:
15. Expiry date of current certificate/validity :
16. Details of past repair (Year-wise)
:
17. Quality of Boiler feed water and boiler :
water.
18. Whether requisite number of Feed :
pumps are in satisfactory working
condition at present?
19. Number of safety valve mounted
:
20. Whether safety valve are blowing :
satisfactorially at or below approved
working Pressure?
62
LA GAZETTE DE L'ETAT
[PART–II
21. Whether safety valve assemble is Free :
from jamming as verified by Operating
casing lever?
22. Whether high and low water level :
alarms is in good working condition.
23. Number of water level gauges mounted :
and its conditions.
24. Whether main steam stop valve, Feed :
check valves, blow down valves and
master pressure gauge is in working
condition?
25. Whether conditional requirements :
for
automatic
boiler
as
per
Regulation 281 are complied with?
(if no, give detail).
26. Latest date of calibration for master :
Pressure gauge, temperature indicator/
recorder for superheated, hot reheat,
Cold reheat and main steam.
27. Latest date when boiler protection :
devices were satisfactorily tested.
28. Details of boiler tripping for last three :
months with reason thereof.
29. Present irregularities in instrument :
and control if any, observed in
control room of boiler house.
30. Date when boiler water sample tested :
(enclosed copy of test Report
showing TDS).
31. State at what interval such test carried :
out.
32. When boiler was last opened for :
internal and/or external cleaning.
63
PART–II]
LA GAZETTE DE L'ETAT
33. State at what intervals such cleaning :
is carried out.
34. Whether working pressure of the :
boiler ever exceeded in the past
beyond certified limit? If any give
details.
35. Particulars of boiler operation Engineers/ :
attendants.
36. Open inspection on
:
37. Observation during open inspection :
38. Hydraulically tested on
:
Date .....……….……………..
to ……………….. Kg/cm2
39. List of Enclosures attached
:
I have inspected the above boiler/economiser as required under
notification No. ....................., dated ..................... of Government of
Puducherry and I, hereby certify that the boiler/economiser is fit for
further use at the approved working pressure i.e. ............... kg/cm2 for
twelve months/twenty-four months i.e. from ..................... to .....................
Signature of Owner :
Signature of BOE :
Name of Owner under Section 2(d)
Name of BOE
:
of the Boilers Act, 1923 .................
Office Seal :
Details of BOE Certificate No.,
date and issuing authority ..........
Address
:
Address
:
Place :
Date :
online publication at “https://styandptg.py.gov.in”
Published by The Director, Government Press
Printed at: Government Central Press, Puducherry.
Posted at: Puducherry HPO on every Tuesday