[ 277 ]

GOVERNMENT OF PUDUCHERRY

CHIEF SECRETARIAT (HOUSING)

(G.O. Ms. No. 05/2020-Hg., Puducherry, dated 9th April 2020)

NOTIFICATION

(A) Risk Based Classification of building proposals (Classification of

buildings based on Risk Matrix): There is a need to make provisions for fast-

tracking building permission procedures for all non-automatic approvals. Therefore,

in the spirit of ‘Ease of Doing Business’, the buildings have been classified further

on the basis of risk parameters/risk based classification to clear the building permits

on the fast track system. The Town and Country Planning Organisation (TCPO),

Ministry of Urban Development, Government of India, has suggested that the

buildings may be classified into (i) Very Low Risk, (ii) Low Risk, (iii) Moderate Risk,

(iv) High Risk based on the plot area, height of building and road width and the

usage.

Registered with the Registrar

of Newspapers for India

under No. 10410

Registered No. PY/44/2018-20

WPP No. TN/PMG(CCR)/WPP-88/2018-20

Dated : 15-4-2020

Price : ` 3-00



La Gazette de L' État de Poudouchéry

The Gazette of Puducherry

PART - I



EXTRAORDINAIRE

EXTRAORDINARY



Publiée par

Published by



Autorité

Authority

` 3-00

Prix : ` 3-00

Price : ` 3-00







2020 }

|

15 {

No.

60

Poudouchéry

Mercredi

15

Avril

2020 (26 Chaitra 1942)

No.

Puducherry

Wednesday

15th

April

2020

278

LA GAZETTE DE L’ETAT

[ PART-I

278

2. The procedure suggested in the Model Building Bye-laws, 2016 by Town

and Country Planning Organization (TCPO), Government of India, was examined in

relation to the existing provisions under Puducherry Building Bye-laws and Zoning

Regulations, 2012 (with amendments) and up on having deliberations and in

consultations with the Expert Committee constituted for the purpose vide G.O. Ms.

No. 20/2007-Hg., dated 11-07-2007 of the Chief Secretariat (Housing), Government

of Puducherry, the following risk based classifications of Building Plan Proposals

is devised based on the category, height of the building and mode of approval

granted through Online Building Permission System (OBPS) by the Planning

Authority.

(B) Timeline required for getting ‘No Objection Certificate’ (NOC)/Clearance

from the line Departments/Agencies/Authority concerned before granting approval

by the Planning Authority :

3. For streamlining the procedure for clearance to be obtained from the

various Departments, reducing the time-limit for granting building permission by

the Planning Authority is one of the method suggested in the Model Building

Bye-laws, 2016 issued by the Town and Country Planning Organisation (TCPO),

Ministry of Urban Development, Government of India. No Objection Certificate

(NOC)/Clearance will be given at various stages viz., Pre-construction/Construction/

Post construction by the various Departments/Agencies/Authorities with regard

to Fire, Structural Stability, National Highways and Irrigation (Public Works

Department), Lift Erection, Railways, Archaeological, Heritage, Ground water and

Electricity, etc. In order to streamline the approval process and to reduce the

timeline, the No Objection Certificate (NOC) shall be granted within 21 days (3

weeks) by all the line Departments concerned.

4. In exercise of the powers conferred by section 47 of the Puducherry

Town and Country Planning Act, 1969 (No. 13 of 1970), the Lieutenant-Govemor,

Puducherry, in consultation with the Town and Country Planning Department,

hereby makes the following amendment to the Puducherry Building Bye-laws and

Zoning Regulations, 2012 issued in the Notification vide G.O. Ms. No. 5/ 2012- Hg,

dated 5th March 2012 of the Chief Secretariat (Housing), Government of Puducherry

and published in the Part-I of the Extraordinary Official Gazette No. 21, dated 8th

March, 2012, namely:-

(1) These Bye-laws and Regulations may be called the Puducherry

Building Bye-laws and Zoning Regulations (Amendment), 2019.

(2) The provisions of these Bye-laws and zoning regulations shall apply

to the planning area declared vide:-

(i) G.O. Ms. No. 79/84/F 6, dated 17th August, 1984, notified in the

Gazette No. 35, dated 28th August 1984;

(ii) G.O. Ms. No. 93/85/F 6, dated 8th July, 1985, notified in the Gazette

No. 31, dated 30th July 1985 ; and

PART-I ]

LA GAZETTE DE L’ETAT

279

(iii) G.O. Ms. No. 68/89/F 6, dated 26th July, 1989, notified in the Gazette

No. 83, dated 31st July 1989 of the Housing Secretariat,

Government of Puducherry and such other areas in the Union

territory of Puducherry notified from time to time.

(3) They shall come into force on and from the date of their publication

in the Official Gazette.

5. In the Puducherry Building Bye-laws and Zoning Regulations, 2012,

after the Annexure XXIV, the following shall be inserted, namely:—

“ANNEXURE-XXV

(A) Risk Based Classification of building proposals (Classification of

buildings based on Risk Matrix):

(i) Residential, Commercial/Public and Semi-public buildings

Sl.

Risk

Building

Height of

Mode of approval

No.

category

category

the building

and time

(1)

(2)

(3)

(4)

(5)

1.

Very low risk

Ordinary building Less than 10.5 mts.

Online (10 working

and Low risk

(Up to two floors)

days)

2.

Medium risk

Special building

Less than 17.0 mts.

Online (30 working

days)

3.

High risk

Multi-Storied

More than 17.0 mts. Online and after

Building

obtaining in-

principle approval

of the Planning

Authority. (45 working

days)

(ii) Industrial Buildings

Sl.

Risk

building

Height of

Mode of approvl

No.

category

category

the building

and time

(1)

(2)

(3)

(4)

(5)

1.

Low

Ordinary building Less than 10.5 mts.

Online (10 working

days)

2.

Medium risk

Special building

Less than 17.0 mts.

Online (30 working

days)

3.

High risk

Multi-Storied

More than 17.0 mts. Online and after

Building

obtaining in-

principle approval

of the Planning

Authority. (45 working

days)

280

LA GAZETTE DE L’ETAT

[ PART-I

280

online publication at “https://styandptg.py.gov.in”

Published by The Director, Government Press

Printed at: Government Central Press, Puducherry.

Posted at: Puducherry HPO on every Tuesday

(B) Timeline required for getting ‘No Objection Certificate (NOC)’/

Clearance from the line Departments/Agencies/Authority concerned before granting

the approval by the Planning Authority:

No Objection Certificate (NOC)/Clearance on the proposal for issue of

approval by the Planning Authority shall be issued within 21 days by all the line

Departments concerned. Once the Online Building Permission System (OBPS) is

introduced, the timeline stipulated above may be reduced further in consultation

with the line Departments/Agencies integrated with the Online Building Permission

System except the Department of Science, Technology and Environment (proposal

requiring clearance from the environmental angle and Coastal Regulation Zone). If,

the required Clearance/No Objection Certificate (NOC) are not received within the

time-limit, then shall be presumed as “Deemed to have been granted”.

(By order of the Lieutenant-Governor)

GEORGE K. MARAM,

Additional Secretary to Government (Housing).

————