No. 1 ]
CHANDIGARH, FRIDAY, JANUARY 1, 2021 (PAUSA 11, 1942 SAKA)
PART I
Punjab Government Notifications and Orders
( 10)
GOVERNMENT OF PUNJAB
DEPARTMENT OF POWER
(Energy Branch)
NOTIFICATION
The 28th December, 2020
No. 10/63/2020-EV4/3390.- In exercise of the powers conferred by section 12 of the Punjab Electricity
(Duty) Act, 2005 (Punjab Act No. 9 of 2005), and all other powers enabling him in this behalf, the Governor of
Punjab is pleased to grant hundred percent(100%) exemption to M/s Pardeep Engg. Industries having its
manufacturing unit at 45, Industrial Area, Phagwara, District Kapurthala from the payment of electricity
duty (except Social Security Fund) for a period of seven years, in terms of the Detailed Scheme and Operational
Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest and subject to the
following conditions, namely:-
CONDITIONS
(i)
the exemption shall be granted to the said Firm for manufacturing of Auto & Auto components as
per the conditions contained in the Eligibility Certificate issued by the Convener-cum-General
Manager, District Level Committee, Kapurthala vide Endorsement No. DIC/KPT/2055 dated
the 3rd November, 2020;
(ii)
the exemption shall be granted for the period from the 25th February, 2019 to 24th February, 2026
or the date of exhaustion or utilization of quantum of eligible incentive i.e. Rs 36,96,000/- (rupees
thirty six lakhs ninety six thousand only) whichever is earlier, as per the Eligibility Certificate
dated 3rd November, 2020. However, the date of commercial production of the unit after expansion
is also certified as 25th February, 2019;
(iii)
in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption
to the extent of revised levied rate of electricity duty (except contributions out of electricity
duty e. g. Social Security Fund etc.) shall be applicable to the unit;
PART I]
PUNJAB GOVT. GAZ., JANUARY 1, 2021 (PAUSA 11, 1942 SAKA)
11
(iv)
the usage of the power by the Firm during the aforesaid period shall be regulated through a
transparent metering arrangement installed or approved by the Punjab State Power Corporation
Limited or the Chief Electrical Inspector to record the consumption of the unit under exemption;
(v)
the exemption shall not be applicable for the residential area of the said premises and to that effect,
an undertaking shall be submitted by the unit that no residential area exists in the premises. If
there is a residential area in the premises, in that event, a separate meter has to be installed or
a separate electricity connection shall be obtained in order to record the electricity consumption
of that residential area, which shall be excluded from the total electricity consumption of the unit;
(vi)
it shall be ensured that the Firm does not connect the load of any other unit with this unit for the
purpose of availing exemption from electricity duty;
(vii) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-
cum-General Manager, District Level Committee, Kapurthala vide no. DIC/KPT/2055 dated the
03rd November, 2020; and
(viii) in case any excess claimed exemption is detected at any point of time, it shall be liable for recovery
and penal action.
To ensure the compliance of the above conditions and proper utilization of incentive, the
Auditors of the Department of Chief Electrical Inspector may inspect the unit at any time. In case, any violation
of any of the provisions of the Punjab Electricity (Duty) Act, 2005 or the rules made thereunder and the above
conditions, is detected, the owner of the Unit shall be liable for action under Section 8 of the said Act and
exemption shall automatically be ceased for which the supplier and owner of the Unit shall be responsible.
Sd/-
ANURAG AGARWAL,
Chandigarh
Additional Chief Secretary to Government of Punjab,
The 14th December, 2020
Department of Power.
2190/12-2020/Pb. Govt. Press, S.A.S. Nagar