GOVERNMENT OF PUNJAB

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION

NOTIFICATION

The 6th December, 2023

No. PSERC/Secy/Regu./182.- In exercise of the powers conferred under Section 181 of the Electricity

Act, 2003 (Central Act 36 of 2003) and all powers enabling the Commission in this behalf and after previous

publication, the Punjab State Electricity Regulatory Commission hereby makes the following Regulations to

amend the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 including

the first to sixth amendments thereof (hereinafter referred as "the Principal Regulations") namely:-

1.

Short Title and Commencement:

(1)

These regulations shall be called the Punjab State Electricity Regulatory Commission (Conduct of

Business) (7th Amendment) Regulations, 2023.

(2)

These Regulations shall come into force from the date of their publication in the official gazette of the

State.

2.

Amendment in Regulation 53 of the Principal Regulations - Subsidy from the State Government: -

Regulation 53 (5) of the Principal Regulations shall be substituted as under:

"The Distribution Licensee shall be required to furnish a quarterly report for the accounting of subsidy

payable within thirty days from the end of therespective quarter to the Commission. The Commission shall

examine the report and issue it with corrections, if any, stating that the demand forsubsidy raised by the Distribution

Licensee in the relevant quarter based on accounts of energy consumed by the subsidized category and the

actual payment made by the state government is duly accounted for and utilized for the purpose for which the

subsidy is given subject to final true-up in theARR Petition”

Sd/-

Secretary to the Commission

Note: The Principal Regulations were issued vide Notification No/PSERC/Secy./Regu. 13 published in Punjab

Govt. Gaz.(Extra) dated 7th March, 2005 and further amended vide:

5084

PUNJAB GOVT. GAZ. (EXTRA), DECEMBER 7, 2023 (AGHN 16, 1945 SAKA)

The 1st Amendment to the Principal Regulations issued vide notification No. PSERC/Secy/Regu.28, published

in Punjab Govt. Gaz.(Extra) dated 7th Sept., 2006

The 2nd Amendment to the Principal Regulations issued vide notification No. PSERC/Secy/Regu.69, published

in Punjab Govt. Gaz.(Extra) dated 8th Aug., 2012

The 3rd Amendment to the Principal Regulations issued vide notification No. PSERC/Secy/Regu.81, published

in Punjab Govt. Gaz.(Extra) dated 7th May, 2013

The 4th Amendment to the Principal Regulations issued vide notification No. PSERC/Secy/Regu.92, published

in Punjab Govt. Gaz.(Extra) dated 14th May, 2014

The 5th Amendment to the Principal Regulations issued vide Notification No. PSERC/Secy./Regu. 148 published

in Punjab Govt. Gaz.(Extra) dated 16th March, 2020.

The 6th Amendment to the Principal Regulations issued vide Notification No. PSERC/Secy./Regu. 175 published

in Punjab Govt. Gaz.(Extra) dated 5th June, 2023.

2986/12-2023/Pb. Govt. Press, S.A.S. Nagar