160

PUNJAB GOVT. GAZ., APRIL 5, 2024 (CHTR 16, 1946 SAKA)

PART I]

Published by Authority

No. 14]

CHANDIGARH, FRIDAY, APRIL 5, 2024 (CHAITRA 16, 1946 SAKA)

PART I

Punjab Government Notifications and Orders

( 160 )

GOVERNMENT OF PUNJAB

DEPARTMENT OF POWER

(ENERGY BRANCH)

NOTIFICATION

The 28th July, 2022

No.10/64/2022-EV4/2716.-In exercise of the powers conferred by section 12 of the Punjab Electricity

(Duty) Act, 2005 (Punjab Act No.9 of 2005) and all other powers enabling him in this behalf, the Governor of

Punjab is pleased to grant hundred percent (100%) exemption to M/s Gupta Motor Store, having its new

manufacturing Unit located at Village Hamjeri, Patran, District Patiala from the payment of electricity duty

(except Social Security Fund) for a period of seven years, in terms of the Detailed Scheme and Operational

Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest subject to the following

conditions. namely:-

CONDITIONS

(i)

the exemption shall be granted to the said Firm for manufacturing of PVC Panel as per the conditions

contained in the Eligibility Certificate issued by the Convener- cum-General Manager, District Level

Committee, District Industries Centre, Patiala vide Endorsement No. DIC/PTL/IBDP-17/ED/2194,

dated the 09th June, 2022;

(ii)

the exemption shall be granted for the period from the 22nd February, 2018 to 21st February, 2025 as

per the Eligibility Certificate dated 09th June, 2022. However, the date of commercial production of the

Unit is certified as 01st December, 2018;

(iii)

in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to

the extent of revised levied rate of electricity duty (except contributions out of electricity duty e. g.

Social Security Fund etc.) shall be applicable to the Unit;

(iv)

the usage of the power by the Firm during the aforesaid period shall be regulated through a transparent

metering arrangement installed or approved by the Punjab State Power Corporation Limited and the

PART I]

PUNJAB GOVT. GAZ., APRIL 5, 2024 (CHTR 16, 1946 SAKA)

161

Chief Electrical Inspector to record the consumption of the Unit under exemption;

(v)

the exemption shall not be applicable for the residential area of the said premises and to that effect, an

undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a

residential area in the premises in that event a separate meter has to be installed or a separate electricity

connection shall be obtained in order to record the electricity consumption of that residential area, which

shall be excluded from the total electricity consumption of the Unit;

(vi)

it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the

purpose of availing exemption from electricity duty;

(vii)

the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-

cum-General Manager, District Level Committee, District Industries Centre, Patiala vide Endorsement

No. DIC/PTL/IBDP-17/ED/2194, dated the 09th June, 2022; and

(viii)

in case any excess claimed exemption is detected at any point of time, it shall be liable for recovery and

penal action under the provisions of the said Act.

To ensure the compliance of the above conditions and proper utilization of incentive the Auditors of the

office of the Chief Electrical Inspector may inspect the Unit at any time. In case, any violation of any of the

provisions of the said Act and the rules made thereunder and the above conditions, is detected, the owner of the

Unit shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption

shall automatically cease for which the owner of the unit shall be responsible.

Sd/-

TEJVEER SINGH,

Chandigarh

Principal Secretary to Government of Punjab,

The 26th July, 2022

Department of Power.

3076/4-2024/Pb. Govt. Press, S.A.S. Nagar