GOVERNMENT OF PUNJAB

DEPARTMENT OF POWER

(ENERGY BRANCH)

NOTIFICATION

The 29th August, 2024

No. ENRG/10/74/2024-EV3/2102.-In exercise of the powers conferred by section 12 of the Punjab

Electricity (Duty) Act, 2005 (Punjab Act 9 of 2005) and all other powers enabling him in this behalf, the

Governor of Punjab is pleased to grant hundred percent (100%) Exemption to M/s Special Steel Industries

LLP, having its unit located at Grand Trunk Road, Village Alour, Khanna, Ludhiana, from the payment of

electricity duty (except Social Security Fund) for a period of seven years, under the Detailed Schemes and

Operational Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest subject to the

following conditions, namely:-

CONDITIONS

(i)

The exemption shall be granted to the said Firm for manufacturing of Rounds/Flat Bars, Manufacture of

hot-rolled and cold-rolled Products of steel, as per the conditions contained in the Eligibility Certificate

issued by the Convener-cum-General, Manager, District Level Committee, Ludhiana, vide Endorsement

No. DIC/LDH/7245, dated the 21st December, 2023;

(ii)

the exemption shall be granted from the 03rd April, 2019 to 02nd April, 2026 as per the Eligibility Certificate

dated the 21st December, 2023. However, the date of commercial production of the Unit is certified as

27th December, 2021;

(ii)

in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to the

extent of revised levied rate of electricity duty (except contributions out of electricity duty e.g. Social

Security Fund etc.) shall be applicable to the Unit;

(iv)

The usage of the power by the Firm during the aforesaid period shall be regulated through a transparent

metering arrangement installed or approved by the Punjab State Power Corporation Limited and the Chief

Electrical Inspector to record the consumption of the Unit under exemption;

(v)

the exemption shall not be applicable for the residential area of the said premises and to that effect, an

undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a

residential area in the premises, in that event, a separate meter has to be installed or a separate electricity

( 1013 )

1014

PUNJAB GOVT. GAZ., DECEMBER 27, 2024 (PAUSA 6, 1946 SAKA)

PART I]

connection shall be obtained in order to record the electricity consumption of that residential area, which

shall be excluded from the total electricity consumption of the Unit;

(vi)

it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the purpose

of availing exemption from electricity duty;

(vii) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-cum-

General Manager, District Level Committee, Ludhiana, vide Endorsement No. DIC/LDH/7245, dated the

21st December, 2023;

(viii) In case any exemption claimed in excess is detected at any point of time, it shall be liable for recovery and

penal action under the provisions of the said Act.

To ensure the compliance of the above conditions and proper utilization of incentive, the Auditor of the

office of the Chief Electrical Inspector may inspect the Unit at any time. In case, any violation of any of the

provisions of the said Act and the rules made thereunder and the above conditions is detected, the owner of the

Unit shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption

shall automatically cease for which the owner of the Unit shall be responsible.

RAHUL TEWARI

Chandigarh

Secretary to Government of Punjab,

The 28th August, 2024

Department of Power.