PART I]
PUNJAB GOVT. GAZ., DECEMBER 27, 2024 (PAUSA 6, 1946 SAKA)
1019
Published by Authority
No. 52]
CHANDIGARH, FRIDAY, DECEMBER 27, 2024 (PAUSA 6 , 1946 SAKA)
PART I
Punjab Government Notifications and Orders
GOVERNMENT OF PUNJAB
DEPARTMENT OF POWER
(ENERGY BRANCH)
NOTIFICATION
The 28th October, 2024
No. ENRG/10/105/2024-EV3/2812.- In exercise of the powers conferred by section 12 of the Punjab
Electricity (Duty) Act, 2005 (Punjab Act 9 of 2005) and all other powers enabling him in this behalf, the Governor
of Punjab is pleased to grant hundred percent (100%) Exemption to M/s Neelkanth Industries, having its
manufacturing unit located at Manwala Road, Opposite A.P. Solvex, Dhuri, Sangrur, from the payment of
electricity duty (except Social Security Fund) for a period of seven years, under the Detailed Schemes and
Operational Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest subject to the
following conditions, namely:-
CONDITIONS
(i)
The exemption shall be granted to the said Firm for manufacturing of PVC Pipes and Fitting, as per the
conditions contained in the Eligibility Certificate issued by the Convener-cum-General Manager, District
Level Committee, Sangrur, vide Endorsement No. DIC/SNG/561-567, dated the 27th June, 2024;
(ii)
the exemption shall be granted from the 09th September, 2022 to 08th September, 2029 as per the Eligibility
Certificate dated the 27th June, 2024. However, the date of commercial production of the Unit is certified
as 25th October, 2022;
(iii)
in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to the
extent of revised levied rate of electricity duty (except contributions out of electricity duty e.g. Social
Security Fund etc.) shall be applicable to the Unit;
(iv)
the usage of the power by the Firm during the aforesaid period shall be regulated through a transparent
metering arrangement installed or approved by the Punjab State Power Corporation Limited and the Chief
Electrical Inspector to record the consumption of the Unit under exemption;
(v)
the exemption shall not be applicable for the residential area of the said premises and to that effect, an
undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a
residential area in the premises, in that event, a separate meter has to be installed or a separate electricity
( 1019)
1020
PUNJAB GOVT. GAZ., DECEMBER 27, 2024 (PAUSA 6, 1946 SAKA)
PART I]
connection shall be obtained in order to record the electricity consumption of that residential area, which
shall be excluded from the total electricity consumption of the Unit;
(vi)
it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the purpose
of availing exemption from electricity duty;
(vii ) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-cum-
General Manager, District Level Committee, Sangrur, vide Endorsement No. DIC/SNG/561-567, dated
the 27th June, 2024; and
(viii) In case any exemption claimed in excess is detected at any point of time, it shall be liable for recovery and
penal action under the provisions of the said Act.
To ensure the compliance of the above conditions and proper utilization of incentive, the Auditor of the
office of the Chief Electrical Inspector may inspect the Unit at any time. In case, any violation of any of the
provisions of the said Act and the rules made thereunder and the above conditions is detected, the owner of the
Unit shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption
shall automatically cease for which the owner of the Unit shall be responsible.
RAHUL TEWARI,
Chandigarh
Secretary to Government of Punjab,
The 28th October, 2024
Department of Power.
3275/ 12-2024/Pb. Govt. Press, S.A.S. Nagar