336

PUNJAB GOVT. GAZ., FEBRUARY 28, 2025 (PHGN 9, 1946 SAKA)

PART I]

Published by Authority

No. 9]

CHANDIGARH, FRIDAY, FEBRUARY 28, 2025 (PHALGUNA 9, 1946 SAKA)

PART I

Punjab Government Notifications and Orders

GOVERNMENT OF PUNJAB

DEPARTMENT OF POWER

(ENERGY BRANCH)

NOTIFICATION

The 31st January, 2025

No. ENRG/10/19/2025-EV3/45l.- In exercise of the powers conferred by section 12 of the Punjab

Electricity (Duty) Act, 2005 (Punjab Act 9 of 2005), and all other powers enabling him in this behalf, the

Governor of Punjab is pleased to grant hundred percent (100%) exemption to M/s Rudra Agro having its

manufacturing unit located at Village Badinpur, Peer Gajju Shah Road, Mandi Gobindgarh, Tehsil Amloh,

District Fatehgarh Sahib, from the payment of electricity duty (except Social Security Fund) for a period of

ten years, in terms of the Detailed Schemes and Operational Guidelines, 2018 (Industrial and Business

Development Policy, 2017) in public interest subject to the following conditions, namely:-

CONDITIONS

(i)

the exemption shall be granted to the said Firm for manufacturing of Fortified Rice, as per the conditions

contained in the Eligibility Certificate issued by the Convener, District Level Committee, Fatehgarh Sahib,

vide Endorsement No.DIC/MGG/1858-1865, dated the 02nd December, 2024;

(ii)

the exemption shall be granted from the 19th August, 2021 to 18th August, 2031 as per the Eligibility

Certificate dated the 02nd December, 2024. However, the date of commercial production of the Unit is

certified as 16th June, 2021 and 12th February, 2022 for Phase-l and Phase-ll respectively;

(iii)

in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to the

extent of revised levied rate of electricity duty (except contributions out of electricity duty e.g. Social

Security Fund etc.) shall be applicable to the Unit;

(iv)

the usage of the power by the Firm during the aforesaid period shall be regulated through a transparent

metering arrangement installed or approved by the Punjab State Power Corporation Limited and the

Chief Electrical Inspector to record the consumption of the Unit under exemption;

(v)

the exemption shall not be applicable for the residential area of the said premises and to that effect, an

undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a

( 336 )

PART I]

PUNJAB GOVT. GAZ., FEBRUARY 28, 2025 (PHGN 9, 1946 SAKA)

337

residential area in the premises, in that event, a separate meter has to be installed or a separate electricity

connection shall be obtained in order to record the electricity consumption of that residential area, which

shall be excluded from the total electricity consumption of the Unit;

(vi)

it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the purpose

of availing exemption from electricity duty;

(vii) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener,

District- Level Committee, Fatehgarh Sahib, vide Endorsement No. DIC/MGG/1858-1865, dated the

02nd December, 2024; and

(viii) in case any exemption claimed in excess is detected at any point of time, it shall be liable for recovery and

penal action under the provisions of the said Act.

To ensure the compliance of the above conditions and proper utilization of incentive, the Auditor of the

office of the Chief Electrical Inspector may inspect the Unit at any time. In case, any violation of any of the

provisions of the said Act and the rules made thereunder and the above conditions is detected, the owner of the

Unit shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption

shall automatically cease for which the owner of the Unit shall be responsible.

Sd/-

AJOY KUMAR SINHA,

Chandigarh

Principal Secretary to Government of Punjab,

The 28th January, 2025

Department of Power.

3323$2-2025/Pb. Govt. Press, S.A.S. Nagar