338
PUNJAB GOVT. GAZ., FEBRUARY 28, 2025 (PHGN 9, 1946 SAKA)
PART I]
Published by Authority
No. 9]
CHANDIGARH, FRIDAY, FEBRUARY 28, 2025 (PHALGUNA 9, 1946 SAKA)
PART I
Punjab Government Notifications and Orders
GOVERNMENT OF PUNJAB
DEPARTMENT OF POWER
(ENERGY BRANCH)
NOTIFICATION
The 31st January, 2025
No. ENRG/10/20/2025-EV3/458.- In exercise of the powers conferred by section 12 of the Punjab
Electricity (Duty) Act, 2005 (Punjab Act 9 of 2005), and all other powers enabling him in this behalf, the
Governor of Punjab is pleased to grant hundred percent (100%) exemption to M/s Gurdaspur Medicity,
having its manufacturing unit located at Opposite Meritorious School, Gurdaspur, District Gurdaspur,
from the payment of electricity duty (except Social Security Fund) for a period of ten years, under the Detailed
Schemes and Operational Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest
subject to the following conditions, namely:-
CONDITIONS
(i)
the exemption shall be granted to the said Firm for Hospital Activities, as per the conditions contained in
the Eligibility Certificate issued by the Convener-cum-General Manager, District Level Committee,
Gurdaspur, vide Endorsement No.3525-33, dated the 19th December, 2024;
(ii)
the exemption shall be granted from the 17th November, 2023 to 16th November, 2033 as per the Eligibility
Certificate dated the 19th December, 2024. However, the date of commercial production of the Unit is
certified as 01st December, 2023;
(iii)
in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to the
extent of revised levied rate of electricity duty (except contributions out of electricity duty e.g. Social
Security Fund etc.) shall be applicable to the Unit;
(iv)
the usage of the power by the Firm during the aforesaid period shall be regulated through a transparent
metering arrangement installed or approved by the Punjab State Power Corporation Limited and the
Chief Electrical Inspector to record the consumption of the Unit under exemption;
(v)
the exemption shall not be applicable for the residential area of the said premises and to that effect, an
undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a
( 338 )
PART I]
PUNJAB GOVT. GAZ., FEBRUARY 28, 2025 (PHGN 9, 1946 SAKA)
339
residential area in the premises, in that event, a separate meter has to be installed or a separate electricity
connection shall be obtained in order to record the electricity consumption of that residential area, which
shall be excluded from the total electricity consumption of the Unit;
(vi)
it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the purpose
of availing exemption from electricity duty;
(vii) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-
cum-General Manager, District Level Committee, Gurdaspur, vide Endorsement No. 3525-33, dated the
19th December, 2024; and
(viii) in case any exemption claimed in excess is detected at any point of time, it shall be liable for recovery and
penal action under the provisions of the said Act.
To ensure the compliance of the above conditions and proper utilization of incentive, the Auditor of the
office of the Chief Electrical Inspector may inspect the Unit at any time.In case, any violation of any of the
provisions of the said Act and the rules“made thereunder and the above conditions is detected, the owner of the
Unit shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption
shall automatically cease for which the owner of the Unit shall be responsible.
Sd/-
AJOY KUMAR SINHA,
Chandigarh
Principal Secretary to Government of Punjab,
The 28th January, 2025
Department of Power.
3323$2-2025/Pb. Govt. Press, S.A.S. Nagar