Energy Department

Notfication

Jaipur, July 23, 2025

Partial amendment in RoW compensation policy issued by Energy

Department, GoR on 08.11.2024

No.F.12(31)Energy/2024/02647 .-Partial amendment in policy regarding

payment of crop compensation and compensation towards land use in regard to

Right of Way (RoW) for installation of 132kV and above transmission lines in

the state of Rajasthan" published by Department of Energy, Govt. of Rajasthan

in Gazette of Rajasthan on dt. 08.11.2024 is hereby proposed in regard to

installation of 400kV and above transmission lines asfollows:-

Pointno.II(4)isherebysubstitutedasunder:-

Tower Base compensation: Compensation for the tower base area shall

be of 200% of the land value as per DLC rates and additional 200%

compensation will be given for these lines due to more risk factor

involved in these linesowing to induction effects due to strong electric

and magnetic field generated by these lines. The tower basearea shall be

the area enclosed by the four legs of the tower at ground level, plus an

additional one (1) meter extension on each side.

Pointno.II(5)isherebysubstitutedasunder:-

RoW Corridor compensation: The compensation amount for Right-of-

Way (RoW) corridor shall be as follows:-

i.

30% of the land value in rural areas.

ii.

45% of the land value for municipalities and all other urban planning areas

notified by the State Government.

iii.

60% of the land value in municipal corporations and metropolitan areas

notified by the State Government.

Land value will be calculated as per DLC rates. Land within the RoW

corridor, as defined in Schedule VII of the Central Electricity Authority

(Technical Standards for Construction of Electrical Plants and Electric

Lines)

Regulations,

2022

(Annexure-A),

shall

be

eligible

for

compensation. This compensation will address the potential diminution of

land value due to the presence of overhead lines or underground cables

143 राजस् थान राज-पत्र, अगस् त 05, 2025 भाग 7

within the RoW corridor. No construction activityofany kind would be

permitted with in the RoWofthetransmissio nline.

This amendment shall be applicable for all implementing agencies

(Transmission licensee) and for both Intra and Inter-State transmission lines. All

other conditions of the policy will remain the same.

This amendment in the policy shall become effective from the date of

publication of notification in Rajasthan Government Gazette.

Sourabh Swami,

Joint Secretary, Energy.