राजè थान राजपğ
ͪवशेषांक
RAJASTHAN GAZETTE
Extraordinary
साͬधकार Ĥकाͧशत
Published by Authority
फाã गुन 27, बधवार
ु
, शाके 1947- माच[ 18, 2026
Phalguna 27, Wednesday, Saka 1947- March 18, 2026
भाग-7
ͪवͧभÛ न ͪवभागɉ मɅ Ĥदायɉ के ͧलए टेÖ डर मांगने कȧ सचनाओं को सिàमͧलत करते हये साव[जǓनक और Ǔनजी
ू
ु
ͪव£ापन आǑद।
राजèथान ͪवÙयतु ͪवǓनयामक आयोग
अͬधसचना
ू
जयपरु, जनवरȣ 21, 2026
संÉया रा.ͪव.ͪव. आयोग/सͬचव/ͪवǓनयम/161:- ͪवÙयतु अͬधǓनयम 2003 (2003 का 36वां) कȧ
धारा 43 से 48, 50, 55 एवं 56 सपǑठत धारा 181 Ùवारा Ĥद× त शिÈतयɉ और उस Ǔनͧमत उसे
समथ[ बनाने वालȣ समèत शािÈतयɉ का Ĥयोग करते हयेु, राजèथान ͪवÙयतु ͪवǓनयामक आयोग, पव[ू
Ĥकाशन के पæचात्, राजèथान ͪवÙयतु ͪवǓनयामक आयोग (ͪवÙयतु Ĥदाय कोड तथा सàबÙध
मामलɅ) ͪवǓनयम, 2021 (इसके पæचात् “मलू ͪवǓनयम’’ के Ǿप मɅ संदͧभ[त) मɅ संशोधन करने के
ͧलये एतÙÙवारा Ǔनàनͧलͨखत ͪवǓनयम बनाता है, अथा[त् :
1.
लघु शȸष[क, ĤयोÏयता तथा Ĥारàभण
(क) ये ͪवǓनयम, “राजèथान ͪवÙयतु ͪवǓनयामक आयोग (ͪवÙयतु Ĥदाय कोड तथा सàबÙध
मामलɅ) (ततीय
ृ
संशोधन) ͪवǓनयम, 2026’’ कहलायɅगे।
(ख) ये ͪवǓनयम राÏय मɅ माǓनत अन£िÜतधाǐरयɉ
ु
सǑहत ͪवतरण अन£िÜतधाǐरयɉ
ु
एवं
उपभोÈताओं के ͧलये ĤयोÏय हɉगɅ।
(ग) ये ͪवǓनयम, इन ͪवǓनयमɉ के शासकȧय राज-पğ मɅ Ĥकाषन कȧ Ǔतͬथ से Ĥव× त
ृ
हɉगɅ।
2.
मलू ͪवǓनयम के ͪवǓनयम 6 मɅ संशोधन
मलू ͪवǓनयम के उप-ͪवǓनयम 6.13 के नीचे एक नया उप-ͪवǓनयम 6.14 Ǔनàनानसार
ु
जोड़ा
जाएगा
“6.14 -एचटȣ/ईएचटȣ उपभोÈताओं को िÙव-İोत ͪवÙयतु आपǓत[
ू
:-
एचटȣ/ईएचटȣ आपǓत[
ू
कȧ आवæयकता रखने वाले आवेदकɉ को, तकनीकȧ åयवहाय[ता तथा सर¢ा
ु
ͪवǓनयमɉ के अनपालन
ु
के अधीन, दो İोतɉ से ͪवÙयतु आपǓत[
ू
Ĥदान कȧ जा सकती है, िजसमɅ
दोनɉ İोतɉ का एक साथ उपयोग अथवा èटɇडबाय İोत के Ǿप मɅ उपयोग सिàमͧलत होगा।
ऐसी िèथǓत मɅ, उपभोÈता को ͩकसी İोत से शÛय
ू
से लेकर अनबंͬधत
ु
माँग तक उपयोग करने कȧ
èवतंğता होगी। ऐसी िèथǓत मɅ, आवेदक Ùवारा दोनɉ İोतɉ हेतु ͪवÙयतु लाइन अथवा ͪवÙयतु संयंğ
457 राजè थान राज-पğ, माच[ 18, 2026 भाग 7
के ͪवèतार से संबंͬधत समèत åयय, शãकɉ
ु
कȧ अनसची
ुू
(अनसची
ुू
-I) मɅ ͪवǑहत शãकɉ
ु
के
अǓतǐरÈत, जमा कराया जाएगा।”
3.
मलू ͪवǓनयम कȧ अनसची
ुू
- I मɅ संशोधन
मलू ͪवǓनयम कȧ ͪवÙयमान अनसची
ुू
-I, 2.2(ख) के नीचे एक नया Ĥावधान Ǔनàनानसार
ु
जोड़ा
जाएगा :-
“ बशतȶ यह ͩक यǑद कोई उपभोÈता दोनɉ İोतɉ के एक साथ उपयोग अथवा èटɇडबाय İोत के
सǑहत िÙव-İोत ͪवÙयतु आपǓत[
ू
के ͧलए आवेदन करता है, तो उससे संयंğ लागत (Plant Cost)
का दोगना
ु
शãक
ु
ͧलया जाएगा।”
आयोग के आदेश Ùवारा,
सͬचव।
RAJASTHAN ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
Jaipur, January 21, 2026
No. RERC/Secy/ Reg161: In exercise of the powers conferred by sections 43 to 48,
50, 55 and 56 read with section 181 of the Electricity Act 2003 (Act 36 of 2003), and all
other powers enabling it in this behalf and after previous publications, the Rajasthan
Electricity Regulatory Commission hereby makes the following Regulations to amend the
Rajasthan Electricity Regulatory Commission (Electricity supply code and connected
matters) Regulations, 2021(hereinafter referred to as “the Principal Regulations”), namely:
1.
Short title, applicability and commencement
a)
These Regulations shall be called ‘The Rajasthan Electricity
Regulatory
Commission
(Electricity
Supply
Code
and
Connected Matters) (Third Amendment), Regulations, 2026.
b)
These Regulations shall apply to distribution licensees
including deemed licensees and consumers in the State.
c)
These Regulations shall come into force from the date of their
publication in the official gazette.
2.
Amendment in Regulation 6 of the Principal Regulations:
A new sub-Regulation 6.14 shall be added below sub-Regulation 6.13 of the
Principlal Regulation as under:
“6.14 – Dual Source Supply to HT/EHT Consumers:-Supply of electricity may
be provided to applicants requiring HT/EHT supply from two sources with
simultaneous use /or standby source, subject to technical feasibility and
458 राजè थान राज-पğ, माच[ 18, 2026 भाग 7
compliance with Safety Regulations. In such case, consumers will be at liberty
to use contracted demand either of the source from zero to contracted demand.
In such case, applicant shall deposit all expenses towards extension of electric
line or electric plant for both sources in addition to charges as prescribed in
the schedule of charges(Schedule-I).”
3.
Amendment in Schedule-I of the Principal Regulations:-
A new proviso shall be added below existing Schedule-I, 2.2(b) of the Principal
Regulation as under:-
“Provided that if consumer applies for dual source of supply with use of both
sources simultaneously/ or standby source, double the plant cost will be
charged.”
By Order of the Commission,
Secretary.
राÏ य केÛ ġȣय मġणालय
ु
, जयपरु।