Notification
Jaipur, May 23, 2026
No.: F.6(2)Industries/I/ 2026 :-Department of Industries and Commerce, Government of Rajasthan
hereby notifies the Scheme for Implementation of Integrated CETPs under Hybrid Annuity Model
(HAM) in Non-RIICO Industrial Areas will come into effect with the date of its publication in the
Gazette.
1. Introduction
India’s industrial expansion has accelerated the growth of manufacturing clusters, driving economic
development while simultaneously increasing the volume and complexity of wastewater generated by
various industrial processes. Managing this wastewater effectively is critical for safeguarding natural
water bodies, meeting regulatory requirements, and ensuring the long-term sustainability of industrial
operations. In this context, Common Effluent Treatment Plants (CETPs) play a pivotal role by
providing a centralized system for the treatment of effluents generated from multiple industrial units
within a cluster.
Rajasthan is a major hub for textile processing industries, with key clusters such as Sanganer’s hand-
block printing, the tie-and-dye centres of Jodhpur and Jaipur, dyeing and printing industries of Pali,
Balotra, Bhilwara and Bikaner’s food and agro-processing units. Wastewater from these clusters is
managed through individual ETPs and cluster-level CETPs. However, most CETPs lack recycling
systems, limiting water reuse, and the majority provide only secondary-level treatment, with only a few
equipped for advanced processes.
Under this scheme, setting up new CETPs with zero liquid discharge under HAM model world be
supported. A corpus fund has been created, which will be equally funded by the State Government and
the Rajasthan State Pollution Control Board (RSPCB). This fund may be expanded in future years
based on need assessments and consultations with the contributing bodies. The scheme primarily
provides one-time grants for establishing CETPs in Non-RIICO industrial areas.
The scheme integrates the entire process for establishing CETPs in Non-RIICO Industrial areas on
Hybrid Annuity Model (HAM) ensuring zero liquid discharge in the treatment process. This approach
ensures a comprehensive environmental management strategy covering liquid industrial waste,
facilitating improved compliance with environmental norms and fostering sustainable industrial
wastewater management practices. This initiative reflects the state's commitment for improving
infrastructure and environmental safeguards in industrial clusters.
2. Implementing Agency
Any State Government department or agency, corporation under the control of State
Government.
3. Operative Period of the Scheme
2958 राजè थान राज-पğ, जनू 22, 2026 भाग 1(ख)
The scheme shall come into effect from the date of its notification in the official Gazette and will
remain in force up to March 31, 2029.
4. Funding under the Scheme
4.1 Funding Pattern for New CETPs
Under this scheme, funding will be provided for establishment of new CETPs in Rajasthan in Non-
RIICO Industrial areas.
4.2 Hybrid Annuity Model (HAM)
HAM is a variation of the DBOT-Annuity model, incorporating a milestone-based payment
mechanism during construction as found in EPC contracts, although this payment covers only the
partial cost of construction. HAM rebalances the financial risks between government and the
Executing Agency. For implementation and subsequently to ensure the effective O&M of project,
State Government and RSPCB will share the financial risk by infusing a part of the project cost
during the construction period and further part amount (in form of annuity) during operation and
maintenance period post completion of construction of CETPs. No interest shall be payable on the
outstanding capex.
This will involve the government grant to the Executing Agency both during the construction
period as well as grant in equal instalment during the concession period, spanning over 20 years.
Further, SPV shall also be contributing to the Executing agency both during the construction period
as well as during the concession period, spanning over 20 years.
The payments will sufficiently cover the expenses incurred by the Executing Agency. The
Executing Agency will take the responsibility for the project's design, construction, funding, and
operation throughout the concession period. Upon the expiration of the concession period, the
project's ownership will be handed to the SPV.
Highlights of HAM model are as follows:
The Executing Agency for the project is chosen through a bidding procedure that is both open
and competitive.
Life Cycle Cost serves as the single bid parameter.
The Executing Agency is responsible for ensuring that the project is maintained until the
conclusion of the concession period.
The concession period encompasses both the duration of construction and a fixed period of 20
years for operations.
4.3 Scheme for establishment of Integrated CETPs
For the purpose of availing grant/ assistance under this scheme, the project cost shall be arrived
by considering ₹18 crore per MLD (i.e. 18 crore x capacity of CETP in MLD) or the cost of
project proposed by the SPV, whichever is lower.
For eligible project, financial assistance will be equal to 80% of the approved project cost with
a capping of Rs. 150 crore per project.
Any project cost exceeding the approved grant amount will be borne by the SPVs of
beneficiary industries.
Financial Assistance will be released in equal proportion by State Government and RSPCB (i.e.
Maximum 80% of the approved cost for the purpose of grant).
o During the construction/execution phase i.e. 2 years, 60% of the approved project cost
will be paid with respect to the physical progress. The grant will be released on pro-rata
basis in 3 instalments of 20% each.
o 20% of the approved project cost will be paid over20 Years.
Contribution of SPVs of beneficiaries (20%)
भाग 1(ख) राजè थान राज-पğ, जनू 22, 2026 2959
o During the construction/execution phase 10% of the approved project cost for the
proposed grant has to be borne upfront by the SPV. Letter of Approval of the Scheme
is subject to deposition of Bank guarantee of 3% of project cost by SPV. (the BG will
be adjusted in the upfront 10% contribution of the SPV).
o In case, project requires more funds than permitted under the scheme, same shall be
arranged by operator/SPV
4.4 O&M Cost:
The Operation and Maintenance cost will be paid by user (CETP beneficiary industries) and
will include expenditure towards routine O&M, chemical charges, consumable and electricity
charges etc. The O&M cost to be collected by the SPV of beneficiary industries
4.5Revenue Model
CETP plant shall be established on revenue generating model. The SPV shall recover user
charges from the beneficiary industries.
5. Following Broad categories of project will qualify for funding under the scheme:
The Special Purpose Vehicle (SPV) of the beneficiary industries must have sufficient land area
with proper title.
New CETPs which propose to set up with ZLD (Zero Liquid Discharge) facility for recycling/
reuse of treated water by member units, including installation of RO and reject management
facilities.
Introduction of advance technology to improve effluent quality/reduce sludge quantity.
6. Financial assistance under the scheme shall not be available for the following (Negative List)
a) For procurement of land for the project
b) For meeting recurring or operation and maintenance cost
c) Any liability towards time and cost over runs
d) Retrospective funding
e) Preliminary and pre-operative expenses
f) Consultancy services
g) CETPs which have not formed SPVs as per the guidelines issued by the State Board.
h) Any CETPs for which funding has been approved under the IPDS Scheme of Ministry of
Textiles, Gol, Amended scheme for the establishment of Integrated CETPs and upgradation of
existing CETPs notified by Industries and Commerce (Group-I) Department Government of
Rajasthan vide Letter No.: F.6 Industries/1/2020 Dated 07.07.2023 or its subsequent
amendments and any other scheme.
i) CETPs proposed to be established by Private Industrial Parks/Estates
7. Pre requisites before filing application for financial assistance under the Scheme
a) Application to be filed only by SPV of beneficiary industries registered under Company Act.
b) Submission of DPR through Project Management Agencies (PMA) as per the checklist.
c) Land is in undisputed possession of SPV and converted for the purpose of setting up of CETP
d) Environment Clearance from competent authority has been obtained (if required)
8. The roles and responsibilities of Project Management Agency (PMA) will include the following:
a) Preparation of Detailed Project Report (DPR) and getting the same vetted by the Technical
Evaluation Committee.
b) Assist the SPV in selection of agencies for preparation of bid documents and procurement
procedure to appoint various contractors.
2960 राजè थान राज-पğ, जनू 22, 2026 भाग 1(ख)
c) Monitor the implementation of the project and submit periodical progress reports to RSPCB
and State Government.
d) Ensure timely completion of project and Assist the SPV in achieving financial closure. PMA
will be permitted to work as a contractor in the implementation of the project and also act as
the O&M agency after execution. However, the expert/institution which has evaluated the
DPR as part of the TEC cannot be appointed as PMA.
e) The project report shall have the provision of 3-5% as administrative expenses for hiring of
PMA. These expenses shall be borne by SPV.
For the purpose of this scheme, any agency/institution recognized by MoEF & CC or Ministry of
Textile (MoT), Government of India, or by the state Government for the purpose shall be engaged as
Project Management Agency by the SPV. The SPV will ensure that DPR is prepared as per the
prescribed checklist annexed with the guidelines. TEC will not accept incomplete DPR which are not as
per the Check list
9. Technical Evaluation Committee (TEC)
Projects received for financial assistance will be evaluated for its technical/financial feasibility and
its practical utility by the Technical Evaluation Committee comprising the following members:
i. Commissioner Industries and Commerce – Chairman
ii. Chief Environmental Engineer (RSPCB) – Member
iii. Nominee of Department of Environment, GoR – Member
iv. GM (E.M.), RIICO – Member
v. Concerned Regional Officer, RSPCB – Member
vi. Concerned General Manager, DICC – Member
vii. Concerned Unit Head, RIICO – Member
viii. Additional/Joint Commissioner Industries and Commerce – Member Secretary
TEC may invite any other expert as special invitee, if required Members/Institutions
recognized/empanelled by MoEF & CC or Ministry of Textile (MoT), Government of India or by the
state Government for the purpose will be engaged by the SPV who will evaluate the DPR and present to
TEC. The Expert Member/Institution will also assist the TEC during disbursement of funds. In case an
expert member/ agency is involved in the evaluation process, SPV shall pay a fees in form of level
10. State Level Approval Committee (SLAC)
Projects forwarded by TEC will be examined and approved by State Level Approval Committee.
The SLAC will consist of the following:
1. Chief Secretary - Chairman
2. Addl. Chief Secretary/Pr. Secretary (Industries & Commerce)-Member
3. Addl. Chief Secretary/Principal Secretary (Finance) - Member
4. Addl. Chief Secretary/Principal Secretary (Environment) - Member
5. Managing Director (RIICO) - Member
6. Member Secretary (RSPCB)Member
7. Commissioner Industries and Commerce- Member Secretary
Besides the above, the SLAC may invite concerned SPV or any other technical expert/government
official as special invitee depending on the need.
11. Timelines for project approvals/appraisals
Evaluation of the Project by TEC and forwarding its recommendations to the SLAC-30 days
after receipt of the complete proposal as per the check list from the SPV.
Approval of the project by SLAC Within 30 days after receipt of evaluation report from TEC.
भाग 1(ख) राजè थान राज-पğ, जनू 22, 2026 2961
12. Minimum Eligibility Criteria for the Bidders:
After final approval of the project, the SPV will call for the bids. To ensure that only reputed
and qualified agencies take part in the bidding process, following minimum eligibility
criteria is laid down for the bidders.
The agency should have minimum experience of 5 years in Design, Engineering, Supply,
Installation, Testing and Commissioning of CETPs of similar types for which bids are
being invited
It should have completed minimum 3 similar project of at least 50% capacity at the time of
publication of the bid.
Any experience in Operation & Maintenance (O&M) of CETPs will be desirable
Average turnover of the agency for past three years should be equal to bid estimated.
cost for the project for which bids are being invited.
It should be a limited company/firm Registered in India.
The bidder should not have any history or on-going litigation/blacklisted for bidding by any
entity (Private or Government).
13. Project Monitoring during Implementation of the Project:
SPV will be responsible for timely implementation of the project. It will file monthly progress
report in the format prescribed by the Technical Evaluation Committee (TEC), Concerned
Regional Officer. RSPCB and Unit Head, RIICO and GM, DIC will jointly inspect the CETP to
physically assess the progress of implementation every quarter. SLAC will also review the
progress from time to time.
14. Submission of Utilization Certificate:
SPV will submit Utilization Certificate (UC) in the prescribed format before release of the next
instalment. The Industries (Group-1) Department shall be the Administrative Department of the
Scheme.
This bears the approval of Finance Department vide ID No. 162600855 dated 08.05.2026.
By order of the Governor,
Mahipal Kumar,
Deputy Secretary to the Government,
राÏ य केÛ ġȣय मġणालय
ु