राजè थान राजपğ

ͪवशेषांक

RAJASTHAN GAZETTE

Extraordinary

साͬधकार Ĥकाͧशत

Published by Authority

आषाढ़ 01, सोमवार, शाके 1948- जनू 22, 2026

Asadha 01, Monday, Saka 1948- June 22, 2026

भाग-1(ख)

मह× वपण[

ू सरकारȣ आ£ायɅ।

Industries and Commerce (Group-1) Department

Notification

Jaipur, May 23, 2026

No.: F.6(2)Industries/I/ 2026 :-Department of Industries and Commerce, Government of Rajasthan

hereby notifies the Scheme for Implementation of Integrated CETPs under Hybrid Annuity Model

(HAM) in Non-RIICO Industrial Areas will come into effect with the date of its publication in the

Gazette.

1. Introduction

India’s industrial expansion has accelerated the growth of manufacturing clusters, driving economic

development while simultaneously increasing the volume and complexity of wastewater generated by

various industrial processes. Managing this wastewater effectively is critical for safeguarding natural

water bodies, meeting regulatory requirements, and ensuring the long-term sustainability of industrial

operations. In this context, Common Effluent Treatment Plants (CETPs) play a pivotal role by

providing a centralized system for the treatment of effluents generated from multiple industrial units

within a cluster.

Rajasthan is a major hub for textile processing industries, with key clusters such as Sanganer’s hand-

block printing, the tie-and-dye centres of Jodhpur and Jaipur, dyeing and printing industries of Pali,

Balotra, Bhilwara and Bikaner’s food and agro-processing units. Wastewater from these clusters is

managed through individual ETPs and cluster-level CETPs. However, most CETPs lack recycling

systems, limiting water reuse, and the majority provide only secondary-level treatment, with only a few

equipped for advanced processes.

Under this scheme, setting up new CETPs with zero liquid discharge under HAM model world be

supported. A corpus fund has been created, which will be equally funded by the State Government and

the Rajasthan State Pollution Control Board (RSPCB). This fund may be expanded in future years

based on need assessments and consultations with the contributing bodies. The scheme primarily

provides one-time grants for establishing CETPs in Non-RIICO industrial areas.

The scheme integrates the entire process for establishing CETPs in Non-RIICO Industrial areas on

Hybrid Annuity Model (HAM) ensuring zero liquid discharge in the treatment process. This approach

ensures a comprehensive environmental management strategy covering liquid industrial waste,

facilitating improved compliance with environmental norms and fostering sustainable industrial

wastewater management practices. This initiative reflects the state's commitment for improving

infrastructure and environmental safeguards in industrial clusters.

2. Implementing Agency

Any State Government department or agency, corporation under the control of State

Government.

3. Operative Period of the Scheme

2958 राजè थान राज-पğ, जनू 22, 2026 भाग 1(ख)

The scheme shall come into effect from the date of its notification in the official Gazette and will

remain in force up to March 31, 2029.

4. Funding under the Scheme

4.1 Funding Pattern for New CETPs

Under this scheme, funding will be provided for establishment of new CETPs in Rajasthan in Non-

RIICO Industrial areas.

4.2 Hybrid Annuity Model (HAM)

HAM is a variation of the DBOT-Annuity model, incorporating a milestone-based payment

mechanism during construction as found in EPC contracts, although this payment covers only the

partial cost of construction. HAM rebalances the financial risks between government and the

Executing Agency. For implementation and subsequently to ensure the effective O&M of project,

State Government and RSPCB will share the financial risk by infusing a part of the project cost

during the construction period and further part amount (in form of annuity) during operation and

maintenance period post completion of construction of CETPs. No interest shall be payable on the

outstanding capex.

This will involve the government grant to the Executing Agency both during the construction

period as well as grant in equal instalment during the concession period, spanning over 20 years.

Further, SPV shall also be contributing to the Executing agency both during the construction period

as well as during the concession period, spanning over 20 years.

The payments will sufficiently cover the expenses incurred by the Executing Agency. The

Executing Agency will take the responsibility for the project's design, construction, funding, and

operation throughout the concession period. Upon the expiration of the concession period, the

project's ownership will be handed to the SPV.

Highlights of HAM model are as follows:

The Executing Agency for the project is chosen through a bidding procedure that is both open

and competitive.

Life Cycle Cost serves as the single bid parameter.

The Executing Agency is responsible for ensuring that the project is maintained until the

conclusion of the concession period.

The concession period encompasses both the duration of construction and a fixed period of 20

years for operations.

4.3 Scheme for establishment of Integrated CETPs

For the purpose of availing grant/ assistance under this scheme, the project cost shall be arrived

by considering ₹18 crore per MLD (i.e. 18 crore x capacity of CETP in MLD) or the cost of

project proposed by the SPV, whichever is lower.

For eligible project, financial assistance will be equal to 80% of the approved project cost with

a capping of Rs. 150 crore per project.

Any project cost exceeding the approved grant amount will be borne by the SPVs of

beneficiary industries.

Financial Assistance will be released in equal proportion by State Government and RSPCB (i.e.

Maximum 80% of the approved cost for the purpose of grant).

o During the construction/execution phase i.e. 2 years, 60% of the approved project cost

will be paid with respect to the physical progress. The grant will be released on pro-rata

basis in 3 instalments of 20% each.

o 20% of the approved project cost will be paid over20 Years.

Contribution of SPVs of beneficiaries (20%)

भाग 1(ख) राजè थान राज-पğ, जनू 22, 2026 2959

o During the construction/execution phase 10% of the approved project cost for the

proposed grant has to be borne upfront by the SPV. Letter of Approval of the Scheme

is subject to deposition of Bank guarantee of 3% of project cost by SPV. (the BG will

be adjusted in the upfront 10% contribution of the SPV).

o In case, project requires more funds than permitted under the scheme, same shall be

arranged by operator/SPV

4.4 O&M Cost:

The Operation and Maintenance cost will be paid by user (CETP beneficiary industries) and

will include expenditure towards routine O&M, chemical charges, consumable and electricity

charges etc. The O&M cost to be collected by the SPV of beneficiary industries

4.5Revenue Model

CETP plant shall be established on revenue generating model. The SPV shall recover user

charges from the beneficiary industries.

5. Following Broad categories of project will qualify for funding under the scheme:

The Special Purpose Vehicle (SPV) of the beneficiary industries must have sufficient land area

with proper title.

New CETPs which propose to set up with ZLD (Zero Liquid Discharge) facility for recycling/

reuse of treated water by member units, including installation of RO and reject management

facilities.

Introduction of advance technology to improve effluent quality/reduce sludge quantity.

6. Financial assistance under the scheme shall not be available for the following (Negative List)

a) For procurement of land for the project

b) For meeting recurring or operation and maintenance cost

c) Any liability towards time and cost over runs

d) Retrospective funding

e) Preliminary and pre-operative expenses

f) Consultancy services

g) CETPs which have not formed SPVs as per the guidelines issued by the State Board.

h) Any CETPs for which funding has been approved under the IPDS Scheme of Ministry of

Textiles, Gol, Amended scheme for the establishment of Integrated CETPs and upgradation of

existing CETPs notified by Industries and Commerce (Group-I) Department Government of

Rajasthan vide Letter No.: F.6 Industries/1/2020 Dated 07.07.2023 or its subsequent

amendments and any other scheme.

i) CETPs proposed to be established by Private Industrial Parks/Estates

7. Pre requisites before filing application for financial assistance under the Scheme

a) Application to be filed only by SPV of beneficiary industries registered under Company Act.

b) Submission of DPR through Project Management Agencies (PMA) as per the checklist.

c) Land is in undisputed possession of SPV and converted for the purpose of setting up of CETP

d) Environment Clearance from competent authority has been obtained (if required)

8. The roles and responsibilities of Project Management Agency (PMA) will include the following:

a) Preparation of Detailed Project Report (DPR) and getting the same vetted by the Technical

Evaluation Committee.

b) Assist the SPV in selection of agencies for preparation of bid documents and procurement

procedure to appoint various contractors.

2960 राजè थान राज-पğ, जनू 22, 2026 भाग 1(ख)

c) Monitor the implementation of the project and submit periodical progress reports to RSPCB

and State Government.

d) Ensure timely completion of project and Assist the SPV in achieving financial closure. PMA

will be permitted to work as a contractor in the implementation of the project and also act as

the O&M agency after execution. However, the expert/institution which has evaluated the

DPR as part of the TEC cannot be appointed as PMA.

e) The project report shall have the provision of 3-5% as administrative expenses for hiring of

PMA. These expenses shall be borne by SPV.

For the purpose of this scheme, any agency/institution recognized by MoEF & CC or Ministry of

Textile (MoT), Government of India, or by the state Government for the purpose shall be engaged as

Project Management Agency by the SPV. The SPV will ensure that DPR is prepared as per the

prescribed checklist annexed with the guidelines. TEC will not accept incomplete DPR which are not as

per the Check list

9. Technical Evaluation Committee (TEC)

Projects received for financial assistance will be evaluated for its technical/financial feasibility and

its practical utility by the Technical Evaluation Committee comprising the following members:

i. Commissioner Industries and Commerce – Chairman

ii. Chief Environmental Engineer (RSPCB) – Member

iii. Nominee of Department of Environment, GoR – Member

iv. GM (E.M.), RIICO – Member

v. Concerned Regional Officer, RSPCB – Member

vi. Concerned General Manager, DICC – Member

vii. Concerned Unit Head, RIICO – Member

viii. Additional/Joint Commissioner Industries and Commerce – Member Secretary

TEC may invite any other expert as special invitee, if required Members/Institutions

recognized/empanelled by MoEF & CC or Ministry of Textile (MoT), Government of India or by the

state Government for the purpose will be engaged by the SPV who will evaluate the DPR and present to

TEC. The Expert Member/Institution will also assist the TEC during disbursement of funds. In case an

expert member/ agency is involved in the evaluation process, SPV shall pay a fees in form of level

10. State Level Approval Committee (SLAC)

Projects forwarded by TEC will be examined and approved by State Level Approval Committee.

The SLAC will consist of the following:

1. Chief Secretary - Chairman

2. Addl. Chief Secretary/Pr. Secretary (Industries & Commerce)-Member

3. Addl. Chief Secretary/Principal Secretary (Finance) - Member

4. Addl. Chief Secretary/Principal Secretary (Environment) - Member

5. Managing Director (RIICO) - Member

6. Member Secretary (RSPCB)Member

7. Commissioner Industries and Commerce- Member Secretary

Besides the above, the SLAC may invite concerned SPV or any other technical expert/government

official as special invitee depending on the need.

11. Timelines for project approvals/appraisals

Evaluation of the Project by TEC and forwarding its recommendations to the SLAC-30 days

after receipt of the complete proposal as per the check list from the SPV.

Approval of the project by SLAC Within 30 days after receipt of evaluation report from TEC.

भाग 1(ख) राजè थान राज-पğ, जनू 22, 2026 2961

12. Minimum Eligibility Criteria for the Bidders:

After final approval of the project, the SPV will call for the bids. To ensure that only reputed

and qualified agencies take part in the bidding process, following minimum eligibility

criteria is laid down for the bidders.

The agency should have minimum experience of 5 years in Design, Engineering, Supply,

Installation, Testing and Commissioning of CETPs of similar types for which bids are

being invited

It should have completed minimum 3 similar project of at least 50% capacity at the time of

publication of the bid.

Any experience in Operation & Maintenance (O&M) of CETPs will be desirable

Average turnover of the agency for past three years should be equal to bid estimated.

cost for the project for which bids are being invited.

It should be a limited company/firm Registered in India.

The bidder should not have any history or on-going litigation/blacklisted for bidding by any

entity (Private or Government).

13. Project Monitoring during Implementation of the Project:

SPV will be responsible for timely implementation of the project. It will file monthly progress

report in the format prescribed by the Technical Evaluation Committee (TEC), Concerned

Regional Officer. RSPCB and Unit Head, RIICO and GM, DIC will jointly inspect the CETP to

physically assess the progress of implementation every quarter. SLAC will also review the

progress from time to time.

14. Submission of Utilization Certificate:

SPV will submit Utilization Certificate (UC) in the prescribed format before release of the next

instalment. The Industries (Group-1) Department shall be the Administrative Department of the

Scheme.

This bears the approval of Finance Department vide ID No. 162600855 dated 08.05.2026.

By order of the Governor,

Mahipal Kumar,

Deputy Secretary to the Government,

राÏ य केÛ ġȣय मġणालय

ु

,जयपर।

ु