Rajasthan Semiconductor Policy 2026
1.
Preamble
India has articulated a national ambition to build a secure, resilient and globally
competitive semiconductor ecosystem. The Government of India’s mission-mode
instruments particularly the Semicon India Programme for fabrication and advanced
packaging and the Design Linked Incentive (DLI) for semiconductor design—provide
the central architecture for catalysing investments, deepening domestic value
addition and advancing technological self-reliance.
Rajasthan recognises that these national programmes deliver maximum impact when
complemented by state-level policy certainty, land-ready sites, reliable utilities,
specialised talent and predictable facilitation. Strategically located along the North-
West manufacturing corridor contiguous to the National Capital Region and served
by the Western Dedicated Freight Corridor and an expanding expressway network,
the State also benefits from a rapidly growing renewable-power base—a critical enabler
for cleanroom-grade, continuous operations.
Building on these structural advantages, this Policy focuses exclusively on
semiconductor value-chain activities: front-end wafer fabrication; advanced
packaging (ATMP/OSAT); compound and power semiconductors, silicon photonics
and sensors; fabless design and prototyping; qualification, reliability and failure
analysis; and enabling inputs such as ultrapure utilities, specialty gases/chemicals
and precision equipment services. It provides a coherent framework of eligibility,
fiscal and non-fiscal support, quality-infrastructure, Centres of Excellence (EDA
access and MPW shuttles), and milestone-linked aftercare.
3471 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
This Preamble affirms Rajasthan’s commitment to establishing a globally
competitive, innovation- driven and sustainable semiconductor hub that creates high-
quality employment, expands domestic value addition, and strengthens national supply-
chain security. The provisions of this Policy shall be read in alignment with applicable
Government of India schemes and with Government Orders issued from time to time
during the notified policy period.
Introduction
Rajasthan enters the semiconductor and electronics era with clear structural
advantages: a central location on India’s industrial corridors, deep and
growing infrastructure, disciplined governance, and a broad, skilled talent base.
Together, these factors de-risk time-to-ground for ATMP/ OSAT, power and
sensor devices, and EMS/ PCBA scale-up while supporting long- term
competitiveness.
1.1
Strategic location
Spanning 3.42 lakh sq. km and bordering five states, Rajasthan sits at the confluence
of DMIC and AKIC with the Western/Eastern Dedicated Freight Corridors.
Proximity to western ports and northern consumption hubs compresses logistics
cycles and makes export operations practical for high-value electronics.
1.2
Multi-modal infrastructure
Roads exceed 3.17 lakh km with 10,790 km of National Highways and new
greenfield expressways (Amritsar–Jamnagar, Delhi–Vadodara) under Bharatmala
and Gati Shakti improving speed and reliability. The North-Western Railway
network (5,800+ km) alongside DFC alignments through Alwar, Jaipur, and
Ajmer supports high-volume shipments and lower turnaround times. Seven
operational airports, including international gateways at Jaipur and Udaipur,
handled ~54 lakh domestic and 3.2 lakh international passengers in 2024—useful
for executive mobility, air freight of high-value components, and service
support.
1.3 Energy advantage
Rajasthan leads India in renewables with ~29.5 GW solar and ~5.2 GW wind (35
GW+ RE total) and ~51 GW overall installed capacity (June 2025). The
Rajasthan Integrated Clean Energy Policy, 2024 targets 125 GW RE by FY
2029-30 (90 GW solar, 25 GW wind/hybrid, 10 GW hydro/PSP/BESS). This
ensures competitive, scalable, and greener power—vital for clean rooms, reliability
labs, and continuous EMS operations.
1.4 Digital & logistics backbone
Planned MMLPs at Jaipur, Bhiwadi, and Udaipur, plus ICDs/CFS facilities near key
RIICO areas, fortify export readiness. RajNET, 10,000+ Wi-Fi hotspots, and
wide e-governance coverage enable digital workflow, vendor integration, and
remote monitoring—practical for Industry 4.0 electronics plants.
1.5 Strategic projects pipeline
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3472
The 9 MMTPA Barmer Refinery & Petrochem complex, three DMIC nodes
(Khushkheda–Bhiwadi– Neemrana, Ajmer–Kishangarh, Jodhpur–Pali–Marwar),
AMRUT 2.0/Smart Cities, and large water security programs (Jal Jeevan Mission,
ERCP/Ramjal Setu) expand urban services, utilities resilience, and industry-grade
infrastructure across districts.
1.6 Economic base with manufacturing depth
Industry contributes 27.16% to GSVA (2024-25), with manufacturing at 42.62% of
industry; IIP reached 157.31 in 2024. Beyond cement, ceramics, and auto-
components, the state is adding defence, ESDM, and green hydrogen. RIICO’s
424+ industrial areas and SEZs host diversified supply chains especially in Alwar/
Bhiwadi (ESDM, automotive)—that matter for electronics and semiconductor-
adjacent growth.
1.7 Industrial ecosystem and investment
Mineral-rich districts (Udaipur, Kota, Bhilwara) support materials industries;
Bhiwadi and Alwar already function as ESDM/auto clusters; Ganganagar and
Kota are scaling agro-processing. Gross Fixed Capital Formation of ~₹4.48 lakh
crore (2024) signals strong investor confidence, while sectoral policies and
incentives lower entry friction.
1.8 Talent pipeline
With 4,600+ higher-education institutions, 74 engineering colleges, 116
polytechnics, 48 MBA institutes, and 3,000+ ITIs, Rajasthan produces over 1
million graduates annually. Flagship skilling (Rajasthan Future Skills Mission)
and top institutions (IIT Jodhpur, IIM Udaipur, MNIT Jaipur, IIIT Kota) create
a continuous funnel for electronics design, production, testing, and
maintenance roles.
1.9 Governance as an enabler
Digital platforms—Jan Aadhaar (₹78,300 crore DBT), RajSSO (175+
services), Rajasthan Sampark, Jan Soochna, and the Right to Guaranteed Delivery
of Public Services—embed time- bound delivery and transparency. GIS-based
planning, AI-enabled dashboards, and a three-tier Jansunwai mechanism (2.4 lakh
grievances processed in 2024) reinforce accountability. This governance stack
directly supports EoDB, faster clearances, and predictable operations for
semiconductor and electronics investors.
1.10 Rajasthan’s Readiness for Semiconductor-Adjacent Manufacturing
Rajasthan’s semiconductor-readiness rests on four proven corridors that
generate device demand, embed quality discipline, and offer serviced sites for
rapid ATMP/OSAT scale-up.
► In Neemrana–Ghiloth (Alwar), Japanese anchors (Daikin, Nidec, Tokai
Rika Minda) and white-goods scale (Lloyd) create stable pull for power,
control and sensing ICs while institutionalising lean/ QMS—ideal
conditions for yield-sensitive packaging and final test.
3473 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
► Bhiwadi–Khushkhera–Chopanki–Pathredi hosts the ELCINA EMC (100
acres) and a live ATMP precedent via Sahasra, proving Rajasthan can run
cleanrooms, encapsulation and reliability/test; neighbouring manufacturers
widen local bill-of-materials linkages that de- risk device localisation.
► Jaipur (Sitapura–EPIP/ Kanakpura/ VKI) combines smart-metering and
power- electronics demand with REIL’s PSU-led pilots, enabling early
adoption and justifying RF/EMC, calibration and qualification infrastructure
for semiconductor devices.
► Udaipur (Kaladwas/ Madri/ Pratap Nagar) contributes a reliability
culture through metering, industrial controls and thermal sensing—natural
complements to device qualification and failure analysis.
Together, these electronics manufacturing strengths support the semiconductor industry
by supplying skilled operations talent and providing cluster utilities that can be adapted
to cleanroom shells. Policy priorities: packaging/test parks in EMCs, CoEs with EDA/
MPW and FA labs, JEDEC/ AEC qualification facilities, and time-bound facilitation to
convert today’s demand and process depth into scalable semiconductor capacity.
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3474
2.
Scope of Policy
This Policy covers the semiconductor value chain in Rajasthan—front-end wafer
fabrication; ATMP/ OSAT; compound/ power, sensors and silicon-photonics; fabless
design, prototyping and qualification; enabling utilities, gases/ chemicals and
reliability/
EMI-EMC
labs.
Applies
to
new
and
E/M/D
projects
by
companies/consortia/JVs/SPVs in notified industrial areas. Instruments include
fiscal/non-fiscal incentives, land/ infra facilitation, CoEs and aftercare, aligned to
ISM guidelines.
2.1 Vision
The vision of the Rajasthan Semiconductor Policy 2026 is to position the state as India’s
premier destination for semiconductor manufacturing, design and allied electronics. The
policy seeks a competitive ecosystem attracting investors, enabling self-reliance
through indigenous production, and leveraging Rajasthan’s strategic location,
infrastructure and talent to integrate with global chains.
The State will notify Jodhpur Pali Marwar Industrial Area (JPMIA), Kankani
Industrial Area (Jodhpur) and similar other suitable clusters as Priority
Semiconductor Corridors for fast-track land allotment, utilities co-ordination and
single window facilitation.
2.2 Policy Period
The Rajasthan Semiconductor Policy 2026 shall come into force on the date of its
notification and shall remain in force for a period of five (5) years from that date, or
until a new or revised policy is notified by the Government, whichever is earlier.
2.3 Nodal Department
The office of the Commissioner of Industries and Commerce, Government of Rajasthan,
shall be the nodal department for the implementation of the Rajasthan
Semiconductor Policy 2026. It shall be responsible for processing applications for
incentives, as prescribed under the policy, and for coordinating with relevant State
Government departments and agencies to facilitate the extension of other benefits
envisaged herein. RIICO will be the supporting agency for implementation of this
policy.
2.4 Policy Objectives
This policy aims to build a competitive semiconductor ecosystem spanning
manufacturing, packaging, design and research, leveraging strategic location,
infrastructure and talent to drive self-reliance, exports, technology leadership and
sustainable growth.
2.4.1
Attract anchor investments in fabs, ATMP/OSAT, compound/power and
sensors; develop world-class parks with clean-room-ready sites, reliable utilities
and shared test labs.
2.4.2
Develop a robust fabless design ecosystem via EDA access, MPW shuttles,
prototyping support and IP enablement.
3475 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
2.4.3
Build an
industry–academia
talent
pipeline
via
updated curricula,
apprenticeships and specialised training aligned to semiconductor processes and
qualifications.
2.4.4
Catalyse R&D, technology transfer and co-development with global and
domestic partners, focused on manufacturable, high-reliability devices.
2.4.5
Ensure green manufacturing through renewable power integration, water
efficiency, recycling/ZLD and circular practices across parks.
2.4.6
Guarantee time-bound approvals and compliance ease through single-
window facilitation, risk-based/third-party inspections and predictable aftercare.
2.4.7
Strengthen quality/market access via certification, metrology and EMI/EMC;
deepen value chains; and prepare a pathway for wafer/display fabs through land
banking and project development.
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3476
3.
Definitions
The underlying definitions will provide the clarity and understanding to all the
stakeholder and set uniformity, for proper interpretation and implementation.
General Definitions
“The definitions provided under Points 4.1 to 4.5, for the purpose of this Policy, shall be governed
by Section 9.1.1 (General Definitions) of RIPS 2024, or by the corresponding provisions of the
prevailing RIPS, as applicable. The definitions in effect at the time of publication of this Policy are
as follows:”
3.1 Ancillaries
Ancillaries means an enterprise which uses products and its byproducts in
manufacturing of distinct and different commodities other than products of the
mother unit, is located within 50 km radius of the mother unit and supplies greater
than 50% of their total production to the mother unit annually.
3.2 Enterprise
Enterprise means an industrial undertaking or a business concern or any other
establishment by whatever name called, engaged in manufacturing of India
Semiconductor Mission (ISM) Aligned Project as defined in Sec 5.1 in any manner.
3.3 Existing Enterprise
Existing Enterprise means a manufacturing enterprise that is engaged in commercial
production or operation before or during the operative period of the Policy.
3.4 Exporter
Exporter means the unit bearing Import - Export Code & RCMC with the concerned
EPC/ Board/ Authority/ Organisation.
3.5 New Unit
New unit means a new manufacturing enterprise and includes a unit set up by an
existing enterprise for manufacturing of products as defined in India Semiconductor
Mission Aligned Project as defined in Sec 5.1, having separately identifiable books of
accounts and depositing the taxes and duties leviable under any State Act including
Provident Fund separately.
3.6 Policy
Policy means Rajasthan Semiconductor Policy 2026.
3.7 Government/ State
The Government or the State means the Government of Rajasthan.
3.8 Year
Year means financial year (From 1st April to 31st March).
Incentives Related Definitions
The definitions provided under Points 4.9 to 4.12, for the purpose of this Policy, shall be
governed by Section 9.1.2 (Incentive Related Definitions) of RIPS 2024, or by the corresponding
3477 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
provisions of the prevailing RIPS, as applicable. The definitions in effect at the time of
publication of this Policy are as follows:
3.9 Employment
Employment means employees are on the permanent payroll of the respective
enterprises, i.e., receive wages or salary directly from the enterprise and which will
include contract labour engaged for at least 6 months of the year. The percentage of
contract labour engaged should not exceed 40% of total labour force.
3.10 Expansion
Expansion means the creation of additional capacity for production of goods, either in
the same line of production or through a new product line, by an existing enterprise
at the same or a different site, involving additional investment.
Such expansion shall involve a minimum investment of INR 50 crore for
Manufacturing Enterprises and shall further constitute at least 25% of the existing
investment of the enterprise while resulting in an incremental capacity of not less
than 20%.
3.11 Environmental Projects
Environmental projects shall mean:
3.11.1 Environmental Infrastructure Facilities
a.
Effluent Treatment Plant & Common Effluent Treatment Plant
b.
Establishing "Reuse and Recycling of Industrial Waste, electronic waste &
plastic waste Plant"
c.
Augmentation and technology upgradation of existing ETPs & CETPs
d.
Common spray dryer, common multiple effect evaporator
e.
Implementation of cleaner production technology in place of existing
process such as substitution & optimization of raw material, reduction in
water consumption or energy consumption or waste generation
f.
For environment management project with use of clean, Efficient and
Innovative Pollution Control Equipment
g.
Installation of online Continuous Stack Emission Monitoring Systems
(CEMS)
h.
Setting Up of Environment Management System including setting
up of Environment Management Laboratory
i.
Purchase of new equipment/ system related to safety, occupational health
or for environment compliances for common use of enterprise located in
cluster
j.
Development of Green Estate & Green Buildings for set up/ relocation/
retrofitting of existing polluting industrial units into Green Industrial
Estates
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3478
k.
Green Buildings which obtain green rating under the Indian Green
Building Council (IGBC/ LEED Certification)
3.11.2 Zero Liquid Discharge
Zero Liquid Discharge Based Treatment Plant means an effluent treatment
plant in which the effluent water is either used or fully evaporated and no
effluent is discharged out of factory premises, as certified by the Rajasthan
State Pollution Control Board.
3.11.3 Air Pollution Control Measures
Air Pollution Control Measures will be applicable for those green interventions
which the State deems fit.
3.11.4 Water Conservation Solutions
a.
Wastewater treatment and recycling systems using technologies such
as Activated Sludge Process (ASP), Membrane Bioreactors (MBR),
Reverse Osmosis (RO), etc. to increase supply and use of treated water.
b. Smart Solutions/IoT for Water and Wastewater to reduce dependency
on manpower, enhance business continuity and remote operations
using smart meters/ pumps/ sensors, data analytics, and cloud
solutions.
c.
Adopting rainwater harvesting; restoring water bodies by de-silting
defunct water bodies within the premises.
d.
Zero Liquid Discharge Solutions.
3.11.5 Energy Efficiency Solutions
Energy Efficiency Solutions means industries falling under the Rajasthan Green
Rating system by meeting the eligibility criteria defined in the Green Rating
of Industries in Rajasthan Policy.
3.11.6 Air Quality/ Emission Reduction Measures
Air Quality/ Emission Reduction Measures will be applicable for those
green interventions which the State deems fit.
3.12 Term Loan
Term Loan means term loan taken by enterprise from Financial Institutions or State
Financial Institutions or Banks recognised by Reserve Bank of India.
3.13 Pari-Passu Payment
The pro rata payment by Nodal Agency to be released after the corresponding share
to be mobilised by applicant/ Project Company along with other sources in the No-
Lien Account (NLA). The deposits in the No-Lien Account (NLA) shall be utilised
only for authorised expenditure for the approved project.
3479 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
4.
Semiconductor Manufacturing Package
4.1
Eligibility for Semiconductor Manufacturing Package
Companies incorporated in India (including subsidiaries/ JVs/ SPVs of global
firms), Indian consortia, and project-specific SPVs are eligible. Applicants must
demonstrate technical competence, financial capacity, and access to proven process
technology (including via ToT/ licensing).
ISM-aligned projects: Projects that have been approved by, Government of India schemes
for:
4.1.1 Semiconductor Fabs (any wafer size, any node)
4.1.2 Display Fabs (TFT-LCD Gen-8 and above; AMOLED Gen-6 and above)
4.1.3 Compound
Semiconductor/
Silicon
Photonics/
Sensor
Fabs/
Discrete
Semiconductors
4.1.4 Semiconductor Packaging: ATMP/ OSAT
4.1.5 Any successor scheme notified by GoI/ ISM State incentives will mirror/ stack over
GoI support and will be activation-linked to GoI sanction (pari passu disbursal).
4.2
General Eligibility Criteria
4.2.1
New Units
All new units under Semiconductor Manufacturing Package are eligible for
benefits under this Policy unless expressly excluded in specific provisions.
4.2.2
Existing Units (E/ M/ D)
Existing
industrial
units
undertaking
Expansion/
Modernisation/
Diversification (E/M/D) under Semiconductor Manufacturing Package are
also eligible.
4.3
Eligible Fixed Capital Expenditure (EFCI)
4.3.1
Semiconductor Fabs (Si CMOS and other wafer fabs)
State fiscal support shall be computed on the Project Cost as defined in Section
2.12 of the Government of India file ‘Guidelines for Modified Scheme for
setting up of Semiconductor Fabs in India,’ No. W-38/21/2022-IPHW dated
29.05.2023, as amended from time to time (including any successor
guidelines/notifications). The State will adopt all inclusions/ exclusions
contained therein.
4.3.2
Display Fabs (TFT-LCD Gen-8+; AMOLED Gen-6+)
State fiscal support shall be computed on the Project Cost as defined in Section
2.12 of the GoI file “Guidelines for Modified Scheme for setting up of Display
Fabs in India,” No. W-38/21/2022-IPHW dated 29.05.2023, as amended
from time to time (including any successor guidelines/ notifications). The
State will adopt all inclusions/ exclusions contained therein.
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3480
4.3.3
Compound/ Silicon Photonics/ Sensors/ Discrete & ATMP/OSAT.
State fiscal support shall be computed on Capital Expenditure (Capex) as
defined in Section 2.11 of the GoI file “Revised Guidelines for effective
functioning of the Modified Scheme for setting up of Compound
Semiconductors / Silicon Photonics / Sensors Fab / Discrete Semiconductors
Fab and Semiconductor ATMP/OSAT facilities in India,” No. W-38/21/2022-
IPHW dated 30.06.2023, as amended from time to time (including any
successor guidelines/notifications). The State will adopt all inclusions/
exclusions contained therein.
4.3.4
Alignment and Verification
a. Definitions in Clauses 5.3.1 to 5.3.3 shall auto-align with any future
GoI amendments/ successor schemes;
b. State support will be milestone-linked and, where applicable, activation-
linked to GoI sanction and released pari passu with verified
capitalisation;
c. The period for computing eligible capital expenditure shall commence
from the issuance of EC however the total computation period shall be as
per the relevant India Semiconductor Mission (ISM) guidelines, as
amended from time to time. For projects evaluated directly by the State
when the GoI window is closed or not availed, the computation period
shall be as per RIPS 2024 or as approved by the Appropriate Sanctioning
Committee.
d. State Empowered Committee may evaluate proposals and issue an in-
principle State Activation Note to enable preliminary facilitation,
pending sanction by Government of India. Final Financial support
would however remain contingent upon sanction by Government of
India
e. For projects evaluated directly by the State, the same GoI definitions of
Project Cost/ Capex shall apply.
Incentives under Semiconductor Manufacturing Package
4.4 Exemptions and Reimbursements
4.4.1 Exemption from payment of 100% electricity duty for 7 years.
4.4.2 Exemption from payment of 75% stamp duty and reimbursement of 25% stamp
duty.
4.4.3 Exemption from payment of 75% conversion charge and reimbursement of 25%
conversion charge.
4.5 Capital Subsidy
The State shall provide a capital subsidy equivalent to 60% of the capital subsidy
sanctioned by the Government of India under the relevant India Semiconductor Mission
3481 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
scheme, calculated on the same eligible cost base and subject to GoI ceilings; disbursal
shall be linked to GoI approval and released pari passu with GoI tranches against
verified milestones and capitalisation with subject to the following ceiling:
4.5.1 Semiconductor Fabs: As per the decision of State Empowered Committee (SEC)
under customised incentive packages.
4.5.2 Display Fabs/ Compound Semiconductor/ Silicon Photonics/ Sensor Fabs/ Discrete
Semiconductors/ Semiconductor Packaging: INR 100 Cr
4.6 Interest Subvention
5% Interest Subvention on term loan taken from Financial Institutions or State
Financial Institutions or Banks recognised by the Reserve Bank of India, for making an
investment in plant & machinery or equipment/ plant related apparatus (constituting a
part of the EFCI), for a period of 5 years subject to 2.5% of the EFCI distributed
equally over 5 years.
Special Incentives
The Special Incentives aim to boost large-scale manufacturing investments and integrated
supply chains by offering flexible land payment terms for eligible projects and rewarding
mother-ancillary ecosystems, fostering collaboration, reducing operational costs, and
strengthening industrial linkages to create competitive, self-sustaining manufacturing hubs
within the state.
4.7 Flexible Land Payment
Eligible enterprises shall be eligible to avail land basis following payment schedule:
Particulars
Payment Schedule
25% of land cost + Bank Guarantee of an
amount
equivalent to 75% of the land cost for 3 years
Upfront
75% of land cost
Distributed equally over 10 annual
instalments at an interest rate of 8%
Land cost support shall only be available:
4.7.1
Once per eligible Manufacturing Enterprise making a new investment; and
4.7.2
Only on land leased from RIICO; and
4.7.3 Only if the land is purchased specifically for the purpose of establishing manufacturing
project in respect of which the enterprise is seeking incentives under this Policy.
Add-On Incentives Driven by State Priorities
The Add-On Incentives driven by State priorities shall be provided to promote
sustainable growth, competitiveness, and innovation by offering targeted benefits for
green initiatives, freight support, skill development, and intellectual property creation,
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3482
thereby encouraging enterprises to align operations with environmental goals, export
growth, workforce upskilling, and innovation.
4.8
Add-On Green Incentives
Eligible Enterprises availing Asset Creation Incentive can avail the following up to a
maximum of INR 12.5 crores:
4.8.1 Reimbursement of 50% of the cost of Environmental Projects.
4.8.2 100% electricity duty exemption for captive renewable energy generation for 7
years.
4.8.3 50% consent fee waiver for industries under the Rajasthan Green Rating System.
4.9
Add-On Skill and Training Incentives
Eligible Enterprises shall be eligible for reimbursement of 50% of the total cost of
employee training, up to a maximum of INR 10,000 per worker per month, for a
maximum of 6 months, as a one-time incentive.
OR
Reimbursement of 50% of the total cost of employee training, up to INR 100,000 per
employee per annum, for a maximum of 20 employees per Enterprise, as a one-time
incentive.
4.10 Add-On IP Creation Incentive
An Intellectual Property (IP) creation incentive of 50% of the expenditure incurred
towards obtaining patents, copyrights, trademarks, and registration of geographical
indications shall be provided, subject to an overall ceiling of INR 1 crore. This
incentive shall be applicable only for granted patents and can be availed within 3
years of the commencement of business.
Other Incentives
4.11 Inclusion of Group Captive Investment in EFCI
Eligible Enterprises investing in captive renewable power plants shall be eligible to
include 51% of the said investment in their EFCI.
OR
Eligible Enterprises entering into group captive power agreements (12+ years) will
be eligible to Include 100% of their said investment in their EFCI.
4.12 Quality Certification Incentive
To drive operational excellence and global market access in semiconductor fabs,
ATMP/ OSAT, compound/ power devices, sensors, fabless and EMS units, the State
will reimburse 50% of eligible costs for quality, safety, environmental, information-
security, product and supply-chain certifications/ qualifications, capped at INR 1 crore
per unit within five years from COD. Eligible heads include first-time and surveillance
audits, certification/registration, lab accreditation and mandated testing/qualification
3483 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
(e.g., ISO 9001/14001/45001/50001, IATF 16949, ISO/IEC 27001, IEC 62443,
ANSI/ESD S20.20, ISO/IEC 17025, BIS-CRS, IECEE CB, CE, UL, FCC,
RoHS/REACH, AEC-Q100/101, JEDEC). Certifications must be issued by accredited
bodies (NABCB/NABL, IAF-MLA, CB Scheme NCBs).
4.13 Employment Generation Incentive
The Employment Generation Subsidy in the form of reimbursement of 50% of
employers’ contribution towards EPF and ESI shall be granted for a period of 3
years with annual incentive ceiling of INR 2 Cr:
4.13.1 For women employees, employees belonging to Scheduled Caste (SC), Scheduled
Tribe (ST), Person with disability (PwD); and
4.13.2 For all employees if the Enterprise is providing more than 75% direct
employment to persons domiciled in Rajasthan
Provided further that the Employment Generation Subsidy shall not be granted for
those employees for which employer is receiving reimbursement under any other
Policy of Government of India or Government of Rajasthan. This shall only be
granted to applicable categories as laid out in the policy.
4.14 Maximum Extent of Subsidy
The aggregate of all fiscal incentives/ subsidies/ reimbursements from the Government
of India and the Government of Rajasthan over the entire benefit period, shall not
exceed one hundred and twenty-five percent (125%) of the Eligible Fixed Capital
Investment (EFCI) as defined in this Policy, unless otherwise approved by the
Appropriate Sanctioning Committee.
Non-Fiscal Incentives
4.15 Mission-Critical Infrastructure (Essential Service)
Semiconductor manufacturing and allied clean-room utilities shall be notified as
‘Essential Services’ under the State ESMA, subject to orders of the competent
authority, to safeguard uninterrupted operations, maintenance and logistics.
4.16 Water Supply
The State shall endeavour for reliable water supply at the project site, including
facilitation for treated/ ultra-pure water, recycling/ ZLD options and requisite
permissions through the nodal agencies.
4.17 Open Access Power
Eligible units may procure power through Open Access in accordance with the
Electricity Act, applicable rules and RERC regulations, including green/ open access.
4.18 Power Banking for RE/ Green Power
Power banking shall be permitted as per RERC guidelines and relevant DISCOM
procedures, enabling scheduling flexibility for renewable/ green energy.
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3484
4.19 Grid Redundancy & Reliability
The Government shall coordinate with transmission/ distribution utilities to build
N-1/N-2 redundancy and ensure high-reliability supply adequate for FAB/ ATMP
facilities, including dual feeds where feasible.
4.20 24×7/ Three-Shift Operations & Women’s Employment
Units may operate 24×7 with three shifts, including employment of women in all
shifts, subject to compliance with applicable central/ state labour laws and
mandatory safety, transport and security measures.
4.21 Self-Certification & Risk-Based/ Third-Party Inspection
Eligible units shall be covered under a self-certification regime to the extent
permissible under law, in lieu of routine inspections under the Factories Act,
Maternity Benefit Act, Shops & Establishments Act, Contract Labour (R&A) Act,
Payment of Wages Act, Minimum Wages Act, and Employment Exchanges (CNV)
Act. Inspections may be undertaken upon specific complaint, accident,
court/competent authority direction, or as required by statute.
3485 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
5.
Administration
The State shall formulate and notify the necessary procedural guidelines to facilitate
the effective implementation of the Rajasthan Semiconductor Policy 2026 across all
relevant departments, agencies, and institutional mechanisms.
5.1 Implementation and Interpretation Authority
All the related Departments shall implement the policy. The Department of
Industries and Commerce shall act as the nodal coordinating, monitoring, and
implementing department. Any matter pertaining to interpretation of any clause/
section of the policy shall be referred to Department of Industries and Commerce,
Government of Rajasthan. The decision of the Department of Industries and
Commerce in such matters shall be final.
5.2 Review or Modification of the Policy
The State Government reserves the right to review or modify the Policy as and when
needed in public interest. However, Forms released as part of the Policy may be
modified, changed, added, or deleted by the Department of Industries and Commerce as
and when needed for the sake of convenience in implementation of the Policy.
5.3 Revision of the Policy by the State Government
The Government may revise the Policy, in full or in part, prospectively or
retrospectively, to keep harmony with the provisions of the State Goods and
Services Tax Act and Rules made there under.
5.4 Application Process for Incentives and Benefits
The RajNivesh portal, managed by the Bureau of Investment Promotion (BIP), shall
serve as the single-point digital interface for facilitating all investment-related
applications under this Policy. The portal enables end-to-end, time-bound processing
of clearances, approvals, and submissions, ensuring transparency, efficiency, and
ease of doing business.
Steps will be taken for issuance of Entitlement Certificates within 30 days, and
disbursal of approved incentives within 60 days of achievement of milestones.
5.5 Institutional Mechanism
The following institutional framework outlines the mechanism for effective
implementation of the Rajasthan Semiconductor Policy 2026 across all concerned
stakeholders
5.5.1
State Level Sanctioning Committee
The State Level Sanctioning Committee (SLSC) shall have jurisdiction over
all Enterprises investing more than INR 25 crores and Enterprise(s) making
investments in more than one district. In cases requiring review by the State
Level Sanctioning Committee, the decision of the State Level Sanctioning
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3486
Committee shall be final. Detailed guidelines regarding this provision to be
separately notified. The constitution of State Level Sanctioning Committee
(SLSC) shall be as follows:
State Level Sanctioning Committee (SLSC)
Secretary-in-charge
Department of Industries and Commerce
Chairman
Secretary-in-charge
Finance (Revenue) or nominee of Finance Department not below the
rank of Joint Secretary
Member
Commissioner
Commercial Taxes Department
Member
Managing Director
RIICO
Member
Commissioner
Investments and NRIs (BIP)
Member
Commissioner
Department of Industries and Commerce
Member Secretary
5.5.2
State Empowered Committee (SEC)
State Empowered Committee (SEC) is authorised, to consider and approve
customised incentive packages for eligible enterprises.
State Empowered Committee
Chief Secretary
Chairman
Additional Chief Secretary
(Finance) or an officer nominated by them, not below the rank of
Secretary Member
Member
Secretary-in-charge
Environment and Forest Department Member
Member
Secretary-in-charge
Urban Development and Housing Department Member
Member
Secretary-in-charge
Department of Industries and Commerce
Member
Commissioner
Department of Industries and Commerce
Member
Secretary-in-charge
Labour and Employment Department
Member
Secretary-in-charge
Mines and Petroleum Department
Member
Additional Chief Secretary
Member
3487 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
Principal Secretary to Chief Minister
Secretary-in-charge
Revenue Department
Member
Managing Director
RIICO
Member
Secretary-in-charge
Energy Department
Member
Secretary-in-charge
Tourism Department
Member
Commissioner
Investments and NRIs (BIP)
Member Secretary
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3488
6.
Terms and Conditions
This policy clearly sets out the provisions, terms, and conditions to be followed, and
outlines the rights, responsibilities, and limitations of all parties involved.
6.1 Transfer of Benefits in Case of Transfer of Business
6.1.1 When the ownership of a unit of an Enterprise availing benefit of the Policy is
entirely transferred in any manner, then the remaining benefits of such unit under
the Policy, if any, shall be transferred to the transferee Enterprise on fulfilment of
any statutory levy.
6.1.2 For availing such remaining benefits, the transferee Enterprise shall submit a duly
completed application as part of the attached forms and manner as may be
prescribed, to the Member Secretary of the appropriate Sanctioning Committee
along with proof of transfer of ownership of unit and original Entitlement
Certificate(s) issued to the transferor Enterprise, within ninety days of such
transfer.
6.1.3 The Member Secretary of the appropriate Sanctioning Committee shall register the
application and place the completed application before the appropriate
Sanctioning Committee within forty-five days from the receipt of the application
unless specifically extended for reasons to be recorded in writing.
6.1.4 Where the application has been filed beyond the time period as provided in
Section 7.1.2 the appropriate Sanctioning Committee having been satisfied
with the genuineness of cause of delay may condone the delay in filing of the
application from the prescribed date of application.
6.1.5 In case the committee approves the transfer of ownership, the Member Secretary
shall amend the entitlement certificate(s) by making an endorsement in the said
certificate(s) as under; “The benefit under this certificate is hereby transferred
to M/s…
, and the said Enterprise is entitled to avail the benefits mentioned
in this certificate for a period from …… to ”
6.1.6 After such endorsement, the Member Secretary shall forward it to all concerned
immediately but not later than fifteen days from the date of the decision taken by
the committee in its meeting, unless specifically extended for reasons to be
recorded in writing.
6.1.7 Where the committee is of the opinion that the transferee Enterprise is not eligible
to avail the remaining benefits of the Policy, it shall provide an opportunity of
being heard to such Enterprise and shall record the reasons of rejection. The
decision of the Committee shall be communicated by the Member Secretary of the
appropriate Sanctioning Committee to the Enterprise, and all concerned
immediately but not later than thirty days from the date of decision taken by the
committee in its meeting, unless specifically extended for reasons to be recorded
in writing.
6.2 Extent and Period of Benefits
3489 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
6.2.1 Period of Benefit: The period of benefit wherever applicable, shall be counted
from the date of the issuance of the concerned Entitlement Certificate (EC) for
that incentive, unless otherwise specified in the Policy. The period of validity
of that EC will be 10 years in case of Capital Subsidy.
6.2.2 Extent of Interest Subvention: The Interest Subvention shall be in addition
to any other incentive available under any other Scheme of Government of
India. The Enterprise availing Interest Subvention under any other Scheme/
package of State Government shall not be eligible for availing benefit
under the Policy.
6.2.3 The Interest Subvention shall be allowed on the term loan taken from State
Financial Institutions/ Financial Institution/ Bank recognised by Reserve
Bank of India for making investment in plant & machinery and/ or
equipment or apparatus. Provided that the total benefit availed under
Interest Subvention shall not exceed the total interest liability from such
term loan on the Enterprise.
6.2.4 The Interest Subvention shall be available only for interest levied by the
Financial Institution/ Bank. Penal interest or other charges shall not be
reimbursed.
6.2.5 Interest Subvention shall be granted for the duration specified in the
eligibility certificate or until the loan is fully repaid, whichever is earlier. In
the event of the loan being transferred to another State Financial Institution,
Financial Institution, or Bank recognised by the Reserve Bank of India, the
Subvention may continue for the remaining period, subject to the approval
of the appropriate Sanctioning Committee.
6.2.6 In cases of transfer of loan, principal amount needs to remain the same
between one bank recognised by RBI/ FI/ SFI to other.
6.2.7 The Interest Subvention shall be given to the Enterprise which pays regular
instalments and interest to the Financial Institution/Bank. If the Enterprise
becomes a defaulter, it will not get interest subvention for the default
period and such defaulting period will be deducted from five years period
as mentioned in the eligibility certificate.
6.2.8 The Interest Subvention shall be allowed only in a case where the Enterprise
is engaged in manufacturing in which interest subvention is claimed except
where it is engaged in manufacturing of seasonal goods.
6.2.9 In cases where the eligible loan amount for interest subsidy approved by the
appropriate sanctioning committee is less than total term loan disbursed by
the bank(s)/ FI(s), the amount of interest subsidy shall be calculated
proportionately based on repayment of the eligible amount vis-a-vis total
sanctioned loan amount.
6.2.10 An Enterprise availing benefits under this Policy shall comply with all
statutory laws and regulations of the State of Rajasthan applicable to the
Enterprise. Non-compliance may entail cancellation/ withdrawal of the
benefits under the Policy.
7.3
Appeal
भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3490
7.3.1
The State Level Sanctioning Committee shall be empowered to hear and
decide appeals against the orders of the District Level Sanctioning Committee.
7.3.2
The State Empowered Committee constituted under Section 3 of the
Rajasthan Enterprises Single Window Enabling and Clearance Act 2011 shall
be empowered to hear and decide appeals against the order of State Level
Sanctioning Committee.
7.3.3
The application for appeal shall be filed within a period of 90 days from the
date of communication of the decision.
7.4
Revision by the State Government:
7.4.1
The Department of Industries and Commerce may suo motu or otherwise
revise an order passed by any Sanctioning Committee if it is found to be
erroneous and prejudicial to the interest of the State, after affording an
opportunity of being heard to the beneficiary enterprise.
7.4.2 No order under this Section shall be passed by the State Government after the
expiry of a period of three years after the date by which the benefits under
the Policy are fully availed of.
7.5 Penal Clause
7.5.1
New investments must achieve commercial production within 36 months of
availing stamp duty exemption. In case an entity fails to reach commercial
production within 36 months from availing stamp duty exemption, the
following actions will apply:
a.
Claw back of 50% of applicable stamp duty exemption.
b. A deflator of 0.98 per year will be applicable for all incentives under the
policy.
7.6 Other Terms and Conditions
7.6.1
An Enterprise availing benefits under this Policy shall comply with all
statutory laws and regulations of the State of Rajasthan applicable to the
Enterprise. Non-compliance may entail cancellation/withdrawal of the benefits
under the Policy.
7.6.2
An Enterprise availing benefits under the Policy shall be subject to the
conditions, procedures, instructions, clarifications, or amendments issued
from time to time under the Policy.
7.6.3
Benefits under the Policy can only be availed if, and as long as there is, and
for the period/ s, consent to establish and consent to operate, wherever
applicable, from the Central/ Rajasthan State Pollution Control Board is
effective.
7.6.4
In case of breach of any of the conditions mentioned anywhere in the
Policy, the benefits availed under the Policy shall be withdrawn by the
appropriate Sanctioning Committee and, on its recommendation, the
3491 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)
concerned Department shall recover the benefits availed by the Enterprise
along with interest @ 18% per annum from the date from which the benefits
have been availed.
7.6.5
Rectification by authority competent to disburse subsidy: Authority
competent to disburse subsidy can claw back any wrongly disbursed subsidy
with an interest of 9% per annum. However, no order for such claw back
shall be passed without providing the Enterprise an opportunity to be heard.
No order for such claw back shall be passed after the completion of 3 years
from the end of the entitlement period.
7.6.6
Rectification of mistake by State Level Sanctioning Committee or District
Level Sanctioning Committee:
a.
With a view to rectify any mistake apparent on record, the State Level
Sanctioning Committee may either suo moto or on an application in this
behalf, rectify any order passed by it or the District Level Sanctioning
Committee.
b. A mistake shall include an order which was valid when it was made
and is subsequently rendered invalid by an amendment of the Policy
having retrospective operation or by a judgment of the Supreme Court, or
the Rajasthan High Court.
c.
No application for rectification shall be filed under this Section after the
expiry of a period of three years from the date of the order sought to be
rectified.
d.
An application under this Section shall be presented to the Member
Secretary of the State Level Sanctioning Committee. The Member
Secretary shall place such application before the State Level Sanctioning
Committee and the State Level Sanctioning Committee shall dispose of
such application.
e.
No order of rectification shall be made after the expiry of four years
from the date of the order.
7.6.7
Entitlement Certificate for Stamp Duty Exemption will be valid for 2 years or
till the expiry of the Policy's operative period.
7.6.8
Provisions for e-governance: To enable electronic delivery of services
under the Policy, notwithstanding anything contrary contained anywhere in
the Policy, the Government Department responsible for the grant of benefit
or issuance of Entitlement Certificate (EC), requires that an application or any
communication, order, certificate, or disbursement of payment relating to
benefits under the Policy shall be made or issued in electronic form. Further,
to facilitate e-governance, the Government Department may change the
procedure mentioned in the Policy to such extent that it is not inconsistent or
incompatible with electronic forms of communication and payment, and
such change shall not invalidate any action for the mere reason that it is
repugnant to the procedural provisions of the Policy.
7.
Abbreviations
Abbreviatio
n
Expansion
Brief context
AEC
Automotive Electronics Council
Automotive device qualification (e.g.,
Q100/ Q101)
AKIC
Amritsar–Kolkata
Industrial
Corridor
National industrial corridor
ATMP
Assembly, Testing, Marking &
Packaging
Semiconductor back-end manufacturing
BESS
Battery Energy Storage System
Electrical energy storage
CoE
Centre of Excellence
Shared
labs/
design/
qualification
platform
DFC
Dedicated Freight Corridor
High-capacity rail freight routes
DISCOM
Distribution Company
Electricity distribution utility
DMIC
Delhi–Mumbai Industrial Corridor
National industrial corridor
EC
Entitlement Certificate
State approval for availing incentives
EDA
Electronic Design Automation
Design tool suites for chips
EHS
Environment, Health & Safety
Operational compliance domain
EMI/EMC
Electromagnetic
Interference/
Compatibility
Product/ lab conformity scope
EMS
Electronics Manufacturing Services Contract
manufacturing
(boards/modules)
ESMA
Essential Services Maintenance Act
Essential services notification basis
FA
Failure Analysis
Device/ package defect analysis
IP
Intellectual Property
Patents/designs/trademarks
ISM
India Semiconductor Mission
GoI
mission
administering
semiconductor
schemes
JEDEC
JEDEC
Solid
State
Technology
Assoc.
Device/ test/ reliability standards
LRN
Loan Registration Number
Banking/term-loan reference
MPW
Multi-Project Wafer
Shared shuttle for prototyping
NLA
No-Lien Account
Dedicated
account
for
pari-passu
disbursals
OSAT
Outsourced
Semiconductor
Assembly
& Test
Third-party packaging/test services
PCBA
Printed Circuit Board Assembly
SMT/through-hole board build
PSU
Public Sector Undertaking
Government-owned enterprise
PwD
Persons with Disabilities
Inclusion category
R&A
Regulation & Abolition
Contract Labour Act context
3493 राजè थान राज-पğ, जलाई ु03, 2026 भाग 1(ख)
RajNivesh
Single-Window System (Rajasthan)
Time-bound clearances & approvals
RE
Renewable Energy
Green power sources
RERC
Rajasthan Electricity Regulatory
Commission
State power regulator
RIPS-2024
Rajasthan
Investment
Promotion
Scheme 2024
State umbrella incentives framework
VKI
Vishwakarma Industrial Area
Jaipur industrial area
ZLD
Zero Liquid Discharge
Water/wastewater compliance regime
By the order of the Governor,
Mahipal Kumar,
Deputy Secretary to Government.