राजè थान राजपğ ͪ

वशेषांक

RAJASTHAN GAZETTE

Extraordinary

साͬ धकार Ĥकाͧ शत

Published by Authority

आषाढ़ 12, शĐवारु, शाके 1948- जलाईु 03, 2026

Asadha 12, Friday, Saka 1948- July 03, 2026

भाग-1(ख)

मह× वपण[ू सरकारȣ आ£ायɅ।

Industries and Commerce (Group-1) Department

Notification

Jaipur, March 03, 2026

No. F5(63)उÙयोग/Ēपु-1/2025 :-

Rajasthan Semiconductor Policy 2026

1.

Preamble

India has articulated a national ambition to build a secure, resilient and globally

competitive semiconductor ecosystem. The Government of India’s mission-mode

instruments particularly the Semicon India Programme for fabrication and advanced

packaging and the Design Linked Incentive (DLI) for semiconductor design—provide

the central architecture for catalysing investments, deepening domestic value

addition and advancing technological self-reliance.

Rajasthan recognises that these national programmes deliver maximum impact when

complemented by state-level policy certainty, land-ready sites, reliable utilities,

specialised talent and predictable facilitation. Strategically located along the North-

West manufacturing corridor contiguous to the National Capital Region and served

by the Western Dedicated Freight Corridor and an expanding expressway network,

the State also benefits from a rapidly growing renewable-power base—a critical enabler

for cleanroom-grade, continuous operations.

Building on these structural advantages, this Policy focuses exclusively on

semiconductor value-chain activities: front-end wafer fabrication; advanced

packaging (ATMP/OSAT); compound and power semiconductors, silicon photonics

and sensors; fabless design and prototyping; qualification, reliability and failure

analysis; and enabling inputs such as ultrapure utilities, specialty gases/chemicals

and precision equipment services. It provides a coherent framework of eligibility,

fiscal and non-fiscal support, quality-infrastructure, Centres of Excellence (EDA

access and MPW shuttles), and milestone-linked aftercare.

3471 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

This Preamble affirms Rajasthan’s commitment to establishing a globally

competitive, innovation- driven and sustainable semiconductor hub that creates high-

quality employment, expands domestic value addition, and strengthens national supply-

chain security. The provisions of this Policy shall be read in alignment with applicable

Government of India schemes and with Government Orders issued from time to time

during the notified policy period.

Introduction

Rajasthan enters the semiconductor and electronics era with clear structural

advantages: a central location on India’s industrial corridors, deep and

growing infrastructure, disciplined governance, and a broad, skilled talent base.

Together, these factors de-risk time-to-ground for ATMP/ OSAT, power and

sensor devices, and EMS/ PCBA scale-up while supporting long- term

competitiveness.

1.1

Strategic location

Spanning 3.42 lakh sq. km and bordering five states, Rajasthan sits at the confluence

of DMIC and AKIC with the Western/Eastern Dedicated Freight Corridors.

Proximity to western ports and northern consumption hubs compresses logistics

cycles and makes export operations practical for high-value electronics.

1.2

Multi-modal infrastructure

Roads exceed 3.17 lakh km with 10,790 km of National Highways and new

greenfield expressways (Amritsar–Jamnagar, Delhi–Vadodara) under Bharatmala

and Gati Shakti improving speed and reliability. The North-Western Railway

network (5,800+ km) alongside DFC alignments through Alwar, Jaipur, and

Ajmer supports high-volume shipments and lower turnaround times. Seven

operational airports, including international gateways at Jaipur and Udaipur,

handled ~54 lakh domestic and 3.2 lakh international passengers in 2024—useful

for executive mobility, air freight of high-value components, and service

support.

1.3 Energy advantage

Rajasthan leads India in renewables with ~29.5 GW solar and ~5.2 GW wind (35

GW+ RE total) and ~51 GW overall installed capacity (June 2025). The

Rajasthan Integrated Clean Energy Policy, 2024 targets 125 GW RE by FY

2029-30 (90 GW solar, 25 GW wind/hybrid, 10 GW hydro/PSP/BESS). This

ensures competitive, scalable, and greener power—vital for clean rooms, reliability

labs, and continuous EMS operations.

1.4 Digital & logistics backbone

Planned MMLPs at Jaipur, Bhiwadi, and Udaipur, plus ICDs/CFS facilities near key

RIICO areas, fortify export readiness. RajNET, 10,000+ Wi-Fi hotspots, and

wide e-governance coverage enable digital workflow, vendor integration, and

remote monitoring—practical for Industry 4.0 electronics plants.

1.5 Strategic projects pipeline

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3472

The 9 MMTPA Barmer Refinery & Petrochem complex, three DMIC nodes

(Khushkheda–Bhiwadi– Neemrana, Ajmer–Kishangarh, Jodhpur–Pali–Marwar),

AMRUT 2.0/Smart Cities, and large water security programs (Jal Jeevan Mission,

ERCP/Ramjal Setu) expand urban services, utilities resilience, and industry-grade

infrastructure across districts.

1.6 Economic base with manufacturing depth

Industry contributes 27.16% to GSVA (2024-25), with manufacturing at 42.62% of

industry; IIP reached 157.31 in 2024. Beyond cement, ceramics, and auto-

components, the state is adding defence, ESDM, and green hydrogen. RIICO’s

424+ industrial areas and SEZs host diversified supply chains especially in Alwar/

Bhiwadi (ESDM, automotive)—that matter for electronics and semiconductor-

adjacent growth.

1.7 Industrial ecosystem and investment

Mineral-rich districts (Udaipur, Kota, Bhilwara) support materials industries;

Bhiwadi and Alwar already function as ESDM/auto clusters; Ganganagar and

Kota are scaling agro-processing. Gross Fixed Capital Formation of ~₹4.48 lakh

crore (2024) signals strong investor confidence, while sectoral policies and

incentives lower entry friction.

1.8 Talent pipeline

With 4,600+ higher-education institutions, 74 engineering colleges, 116

polytechnics, 48 MBA institutes, and 3,000+ ITIs, Rajasthan produces over 1

million graduates annually. Flagship skilling (Rajasthan Future Skills Mission)

and top institutions (IIT Jodhpur, IIM Udaipur, MNIT Jaipur, IIIT Kota) create

a continuous funnel for electronics design, production, testing, and

maintenance roles.

1.9 Governance as an enabler

Digital platforms—Jan Aadhaar (₹78,300 crore DBT), RajSSO (175+

services), Rajasthan Sampark, Jan Soochna, and the Right to Guaranteed Delivery

of Public Services—embed time- bound delivery and transparency. GIS-based

planning, AI-enabled dashboards, and a three-tier Jansunwai mechanism (2.4 lakh

grievances processed in 2024) reinforce accountability. This governance stack

directly supports EoDB, faster clearances, and predictable operations for

semiconductor and electronics investors.

1.10 Rajasthan’s Readiness for Semiconductor-Adjacent Manufacturing

Rajasthan’s semiconductor-readiness rests on four proven corridors that

generate device demand, embed quality discipline, and offer serviced sites for

rapid ATMP/OSAT scale-up.

► In Neemrana–Ghiloth (Alwar), Japanese anchors (Daikin, Nidec, Tokai

Rika Minda) and white-goods scale (Lloyd) create stable pull for power,

control and sensing ICs while institutionalising lean/ QMS—ideal

conditions for yield-sensitive packaging and final test.

3473 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

► Bhiwadi–Khushkhera–Chopanki–Pathredi hosts the ELCINA EMC (100

acres) and a live ATMP precedent via Sahasra, proving Rajasthan can run

cleanrooms, encapsulation and reliability/test; neighbouring manufacturers

widen local bill-of-materials linkages that de- risk device localisation.

► Jaipur (Sitapura–EPIP/ Kanakpura/ VKI) combines smart-metering and

power- electronics demand with REIL’s PSU-led pilots, enabling early

adoption and justifying RF/EMC, calibration and qualification infrastructure

for semiconductor devices.

► Udaipur (Kaladwas/ Madri/ Pratap Nagar) contributes a reliability

culture through metering, industrial controls and thermal sensing—natural

complements to device qualification and failure analysis.

Together, these electronics manufacturing strengths support the semiconductor industry

by supplying skilled operations talent and providing cluster utilities that can be adapted

to cleanroom shells. Policy priorities: packaging/test parks in EMCs, CoEs with EDA/

MPW and FA labs, JEDEC/ AEC qualification facilities, and time-bound facilitation to

convert today’s demand and process depth into scalable semiconductor capacity.

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3474

2.

Scope of Policy

This Policy covers the semiconductor value chain in Rajasthan—front-end wafer

fabrication; ATMP/ OSAT; compound/ power, sensors and silicon-photonics; fabless

design, prototyping and qualification; enabling utilities, gases/ chemicals and

reliability/

EMI-EMC

labs.

Applies

to

new

and

E/M/D

projects

by

companies/consortia/JVs/SPVs in notified industrial areas. Instruments include

fiscal/non-fiscal incentives, land/ infra facilitation, CoEs and aftercare, aligned to

ISM guidelines.

2.1 Vision

The vision of the Rajasthan Semiconductor Policy 2026 is to position the state as India’s

premier destination for semiconductor manufacturing, design and allied electronics. The

policy seeks a competitive ecosystem attracting investors, enabling self-reliance

through indigenous production, and leveraging Rajasthan’s strategic location,

infrastructure and talent to integrate with global chains.

The State will notify Jodhpur Pali Marwar Industrial Area (JPMIA), Kankani

Industrial Area (Jodhpur) and similar other suitable clusters as Priority

Semiconductor Corridors for fast-track land allotment, utilities co-ordination and

single window facilitation.

2.2 Policy Period

The Rajasthan Semiconductor Policy 2026 shall come into force on the date of its

notification and shall remain in force for a period of five (5) years from that date, or

until a new or revised policy is notified by the Government, whichever is earlier.

2.3 Nodal Department

The office of the Commissioner of Industries and Commerce, Government of Rajasthan,

shall be the nodal department for the implementation of the Rajasthan

Semiconductor Policy 2026. It shall be responsible for processing applications for

incentives, as prescribed under the policy, and for coordinating with relevant State

Government departments and agencies to facilitate the extension of other benefits

envisaged herein. RIICO will be the supporting agency for implementation of this

policy.

2.4 Policy Objectives

This policy aims to build a competitive semiconductor ecosystem spanning

manufacturing, packaging, design and research, leveraging strategic location,

infrastructure and talent to drive self-reliance, exports, technology leadership and

sustainable growth.

2.4.1

Attract anchor investments in fabs, ATMP/OSAT, compound/power and

sensors; develop world-class parks with clean-room-ready sites, reliable utilities

and shared test labs.

2.4.2

Develop a robust fabless design ecosystem via EDA access, MPW shuttles,

prototyping support and IP enablement.

3475 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

2.4.3

Build an

industry–academia

talent

pipeline

via

updated curricula,

apprenticeships and specialised training aligned to semiconductor processes and

qualifications.

2.4.4

Catalyse R&D, technology transfer and co-development with global and

domestic partners, focused on manufacturable, high-reliability devices.

2.4.5

Ensure green manufacturing through renewable power integration, water

efficiency, recycling/ZLD and circular practices across parks.

2.4.6

Guarantee time-bound approvals and compliance ease through single-

window facilitation, risk-based/third-party inspections and predictable aftercare.

2.4.7

Strengthen quality/market access via certification, metrology and EMI/EMC;

deepen value chains; and prepare a pathway for wafer/display fabs through land

banking and project development.

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3476

3.

Definitions

The underlying definitions will provide the clarity and understanding to all the

stakeholder and set uniformity, for proper interpretation and implementation.

General Definitions

“The definitions provided under Points 4.1 to 4.5, for the purpose of this Policy, shall be governed

by Section 9.1.1 (General Definitions) of RIPS 2024, or by the corresponding provisions of the

prevailing RIPS, as applicable. The definitions in effect at the time of publication of this Policy are

as follows:”

3.1 Ancillaries

Ancillaries means an enterprise which uses products and its byproducts in

manufacturing of distinct and different commodities other than products of the

mother unit, is located within 50 km radius of the mother unit and supplies greater

than 50% of their total production to the mother unit annually.

3.2 Enterprise

Enterprise means an industrial undertaking or a business concern or any other

establishment by whatever name called, engaged in manufacturing of India

Semiconductor Mission (ISM) Aligned Project as defined in Sec 5.1 in any manner.

3.3 Existing Enterprise

Existing Enterprise means a manufacturing enterprise that is engaged in commercial

production or operation before or during the operative period of the Policy.

3.4 Exporter

Exporter means the unit bearing Import - Export Code & RCMC with the concerned

EPC/ Board/ Authority/ Organisation.

3.5 New Unit

New unit means a new manufacturing enterprise and includes a unit set up by an

existing enterprise for manufacturing of products as defined in India Semiconductor

Mission Aligned Project as defined in Sec 5.1, having separately identifiable books of

accounts and depositing the taxes and duties leviable under any State Act including

Provident Fund separately.

3.6 Policy

Policy means Rajasthan Semiconductor Policy 2026.

3.7 Government/ State

The Government or the State means the Government of Rajasthan.

3.8 Year

Year means financial year (From 1st April to 31st March).

Incentives Related Definitions

The definitions provided under Points 4.9 to 4.12, for the purpose of this Policy, shall be

governed by Section 9.1.2 (Incentive Related Definitions) of RIPS 2024, or by the corresponding

3477 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

provisions of the prevailing RIPS, as applicable. The definitions in effect at the time of

publication of this Policy are as follows:

3.9 Employment

Employment means employees are on the permanent payroll of the respective

enterprises, i.e., receive wages or salary directly from the enterprise and which will

include contract labour engaged for at least 6 months of the year. The percentage of

contract labour engaged should not exceed 40% of total labour force.

3.10 Expansion

Expansion means the creation of additional capacity for production of goods, either in

the same line of production or through a new product line, by an existing enterprise

at the same or a different site, involving additional investment.

Such expansion shall involve a minimum investment of INR 50 crore for

Manufacturing Enterprises and shall further constitute at least 25% of the existing

investment of the enterprise while resulting in an incremental capacity of not less

than 20%.

3.11 Environmental Projects

Environmental projects shall mean:

3.11.1 Environmental Infrastructure Facilities

a.

Effluent Treatment Plant & Common Effluent Treatment Plant

b.

Establishing "Reuse and Recycling of Industrial Waste, electronic waste &

plastic waste Plant"

c.

Augmentation and technology upgradation of existing ETPs & CETPs

d.

Common spray dryer, common multiple effect evaporator

e.

Implementation of cleaner production technology in place of existing

process such as substitution & optimization of raw material, reduction in

water consumption or energy consumption or waste generation

f.

For environment management project with use of clean, Efficient and

Innovative Pollution Control Equipment

g.

Installation of online Continuous Stack Emission Monitoring Systems

(CEMS)

h.

Setting Up of Environment Management System including setting

up of Environment Management Laboratory

i.

Purchase of new equipment/ system related to safety, occupational health

or for environment compliances for common use of enterprise located in

cluster

j.

Development of Green Estate & Green Buildings for set up/ relocation/

retrofitting of existing polluting industrial units into Green Industrial

Estates

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3478

k.

Green Buildings which obtain green rating under the Indian Green

Building Council (IGBC/ LEED Certification)

3.11.2 Zero Liquid Discharge

Zero Liquid Discharge Based Treatment Plant means an effluent treatment

plant in which the effluent water is either used or fully evaporated and no

effluent is discharged out of factory premises, as certified by the Rajasthan

State Pollution Control Board.

3.11.3 Air Pollution Control Measures

Air Pollution Control Measures will be applicable for those green interventions

which the State deems fit.

3.11.4 Water Conservation Solutions

a.

Wastewater treatment and recycling systems using technologies such

as Activated Sludge Process (ASP), Membrane Bioreactors (MBR),

Reverse Osmosis (RO), etc. to increase supply and use of treated water.

b. Smart Solutions/IoT for Water and Wastewater to reduce dependency

on manpower, enhance business continuity and remote operations

using smart meters/ pumps/ sensors, data analytics, and cloud

solutions.

c.

Adopting rainwater harvesting; restoring water bodies by de-silting

defunct water bodies within the premises.

d.

Zero Liquid Discharge Solutions.

3.11.5 Energy Efficiency Solutions

Energy Efficiency Solutions means industries falling under the Rajasthan Green

Rating system by meeting the eligibility criteria defined in the Green Rating

of Industries in Rajasthan Policy.

3.11.6 Air Quality/ Emission Reduction Measures

Air Quality/ Emission Reduction Measures will be applicable for those

green interventions which the State deems fit.

3.12 Term Loan

Term Loan means term loan taken by enterprise from Financial Institutions or State

Financial Institutions or Banks recognised by Reserve Bank of India.

3.13 Pari-Passu Payment

The pro rata payment by Nodal Agency to be released after the corresponding share

to be mobilised by applicant/ Project Company along with other sources in the No-

Lien Account (NLA). The deposits in the No-Lien Account (NLA) shall be utilised

only for authorised expenditure for the approved project.

3479 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

4.

Semiconductor Manufacturing Package

4.1

Eligibility for Semiconductor Manufacturing Package

Companies incorporated in India (including subsidiaries/ JVs/ SPVs of global

firms), Indian consortia, and project-specific SPVs are eligible. Applicants must

demonstrate technical competence, financial capacity, and access to proven process

technology (including via ToT/ licensing).

ISM-aligned projects: Projects that have been approved by, Government of India schemes

for:

4.1.1 Semiconductor Fabs (any wafer size, any node)

4.1.2 Display Fabs (TFT-LCD Gen-8 and above; AMOLED Gen-6 and above)

4.1.3 Compound

Semiconductor/

Silicon

Photonics/

Sensor

Fabs/

Discrete

Semiconductors

4.1.4 Semiconductor Packaging: ATMP/ OSAT

4.1.5 Any successor scheme notified by GoI/ ISM State incentives will mirror/ stack over

GoI support and will be activation-linked to GoI sanction (pari passu disbursal).

4.2

General Eligibility Criteria

4.2.1

New Units

All new units under Semiconductor Manufacturing Package are eligible for

benefits under this Policy unless expressly excluded in specific provisions.

4.2.2

Existing Units (E/ M/ D)

Existing

industrial

units

undertaking

Expansion/

Modernisation/

Diversification (E/M/D) under Semiconductor Manufacturing Package are

also eligible.

4.3

Eligible Fixed Capital Expenditure (EFCI)

4.3.1

Semiconductor Fabs (Si CMOS and other wafer fabs)

State fiscal support shall be computed on the Project Cost as defined in Section

2.12 of the Government of India file ‘Guidelines for Modified Scheme for

setting up of Semiconductor Fabs in India,’ No. W-38/21/2022-IPHW dated

29.05.2023, as amended from time to time (including any successor

guidelines/notifications). The State will adopt all inclusions/ exclusions

contained therein.

4.3.2

Display Fabs (TFT-LCD Gen-8+; AMOLED Gen-6+)

State fiscal support shall be computed on the Project Cost as defined in Section

2.12 of the GoI file “Guidelines for Modified Scheme for setting up of Display

Fabs in India,” No. W-38/21/2022-IPHW dated 29.05.2023, as amended

from time to time (including any successor guidelines/ notifications). The

State will adopt all inclusions/ exclusions contained therein.

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3480

4.3.3

Compound/ Silicon Photonics/ Sensors/ Discrete & ATMP/OSAT.

State fiscal support shall be computed on Capital Expenditure (Capex) as

defined in Section 2.11 of the GoI file “Revised Guidelines for effective

functioning of the Modified Scheme for setting up of Compound

Semiconductors / Silicon Photonics / Sensors Fab / Discrete Semiconductors

Fab and Semiconductor ATMP/OSAT facilities in India,” No. W-38/21/2022-

IPHW dated 30.06.2023, as amended from time to time (including any

successor guidelines/notifications). The State will adopt all inclusions/

exclusions contained therein.

4.3.4

Alignment and Verification

a. Definitions in Clauses 5.3.1 to 5.3.3 shall auto-align with any future

GoI amendments/ successor schemes;

b. State support will be milestone-linked and, where applicable, activation-

linked to GoI sanction and released pari passu with verified

capitalisation;

c. The period for computing eligible capital expenditure shall commence

from the issuance of EC however the total computation period shall be as

per the relevant India Semiconductor Mission (ISM) guidelines, as

amended from time to time. For projects evaluated directly by the State

when the GoI window is closed or not availed, the computation period

shall be as per RIPS 2024 or as approved by the Appropriate Sanctioning

Committee.

d. State Empowered Committee may evaluate proposals and issue an in-

principle State Activation Note to enable preliminary facilitation,

pending sanction by Government of India. Final Financial support

would however remain contingent upon sanction by Government of

India

e. For projects evaluated directly by the State, the same GoI definitions of

Project Cost/ Capex shall apply.

Incentives under Semiconductor Manufacturing Package

4.4 Exemptions and Reimbursements

4.4.1 Exemption from payment of 100% electricity duty for 7 years.

4.4.2 Exemption from payment of 75% stamp duty and reimbursement of 25% stamp

duty.

4.4.3 Exemption from payment of 75% conversion charge and reimbursement of 25%

conversion charge.

4.5 Capital Subsidy

The State shall provide a capital subsidy equivalent to 60% of the capital subsidy

sanctioned by the Government of India under the relevant India Semiconductor Mission

3481 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

scheme, calculated on the same eligible cost base and subject to GoI ceilings; disbursal

shall be linked to GoI approval and released pari passu with GoI tranches against

verified milestones and capitalisation with subject to the following ceiling:

4.5.1 Semiconductor Fabs: As per the decision of State Empowered Committee (SEC)

under customised incentive packages.

4.5.2 Display Fabs/ Compound Semiconductor/ Silicon Photonics/ Sensor Fabs/ Discrete

Semiconductors/ Semiconductor Packaging: INR 100 Cr

4.6 Interest Subvention

5% Interest Subvention on term loan taken from Financial Institutions or State

Financial Institutions or Banks recognised by the Reserve Bank of India, for making an

investment in plant & machinery or equipment/ plant related apparatus (constituting a

part of the EFCI), for a period of 5 years subject to 2.5% of the EFCI distributed

equally over 5 years.

Special Incentives

The Special Incentives aim to boost large-scale manufacturing investments and integrated

supply chains by offering flexible land payment terms for eligible projects and rewarding

mother-ancillary ecosystems, fostering collaboration, reducing operational costs, and

strengthening industrial linkages to create competitive, self-sustaining manufacturing hubs

within the state.

4.7 Flexible Land Payment

Eligible enterprises shall be eligible to avail land basis following payment schedule:

Particulars

Payment Schedule

25% of land cost + Bank Guarantee of an

amount

equivalent to 75% of the land cost for 3 years

Upfront

75% of land cost

Distributed equally over 10 annual

instalments at an interest rate of 8%

Land cost support shall only be available:

4.7.1

Once per eligible Manufacturing Enterprise making a new investment; and

4.7.2

Only on land leased from RIICO; and

4.7.3 Only if the land is purchased specifically for the purpose of establishing manufacturing

project in respect of which the enterprise is seeking incentives under this Policy.

Add-On Incentives Driven by State Priorities

The Add-On Incentives driven by State priorities shall be provided to promote

sustainable growth, competitiveness, and innovation by offering targeted benefits for

green initiatives, freight support, skill development, and intellectual property creation,

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3482

thereby encouraging enterprises to align operations with environmental goals, export

growth, workforce upskilling, and innovation.

4.8

Add-On Green Incentives

Eligible Enterprises availing Asset Creation Incentive can avail the following up to a

maximum of INR 12.5 crores:

4.8.1 Reimbursement of 50% of the cost of Environmental Projects.

4.8.2 100% electricity duty exemption for captive renewable energy generation for 7

years.

4.8.3 50% consent fee waiver for industries under the Rajasthan Green Rating System.

4.9

Add-On Skill and Training Incentives

Eligible Enterprises shall be eligible for reimbursement of 50% of the total cost of

employee training, up to a maximum of INR 10,000 per worker per month, for a

maximum of 6 months, as a one-time incentive.

OR

Reimbursement of 50% of the total cost of employee training, up to INR 100,000 per

employee per annum, for a maximum of 20 employees per Enterprise, as a one-time

incentive.

4.10 Add-On IP Creation Incentive

An Intellectual Property (IP) creation incentive of 50% of the expenditure incurred

towards obtaining patents, copyrights, trademarks, and registration of geographical

indications shall be provided, subject to an overall ceiling of INR 1 crore. This

incentive shall be applicable only for granted patents and can be availed within 3

years of the commencement of business.

Other Incentives

4.11 Inclusion of Group Captive Investment in EFCI

Eligible Enterprises investing in captive renewable power plants shall be eligible to

include 51% of the said investment in their EFCI.

OR

Eligible Enterprises entering into group captive power agreements (12+ years) will

be eligible to Include 100% of their said investment in their EFCI.

4.12 Quality Certification Incentive

To drive operational excellence and global market access in semiconductor fabs,

ATMP/ OSAT, compound/ power devices, sensors, fabless and EMS units, the State

will reimburse 50% of eligible costs for quality, safety, environmental, information-

security, product and supply-chain certifications/ qualifications, capped at INR 1 crore

per unit within five years from COD. Eligible heads include first-time and surveillance

audits, certification/registration, lab accreditation and mandated testing/qualification

3483 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

(e.g., ISO 9001/14001/45001/50001, IATF 16949, ISO/IEC 27001, IEC 62443,

ANSI/ESD S20.20, ISO/IEC 17025, BIS-CRS, IECEE CB, CE, UL, FCC,

RoHS/REACH, AEC-Q100/101, JEDEC). Certifications must be issued by accredited

bodies (NABCB/NABL, IAF-MLA, CB Scheme NCBs).

4.13 Employment Generation Incentive

The Employment Generation Subsidy in the form of reimbursement of 50% of

employers’ contribution towards EPF and ESI shall be granted for a period of 3

years with annual incentive ceiling of INR 2 Cr:

4.13.1 For women employees, employees belonging to Scheduled Caste (SC), Scheduled

Tribe (ST), Person with disability (PwD); and

4.13.2 For all employees if the Enterprise is providing more than 75% direct

employment to persons domiciled in Rajasthan

Provided further that the Employment Generation Subsidy shall not be granted for

those employees for which employer is receiving reimbursement under any other

Policy of Government of India or Government of Rajasthan. This shall only be

granted to applicable categories as laid out in the policy.

4.14 Maximum Extent of Subsidy

The aggregate of all fiscal incentives/ subsidies/ reimbursements from the Government

of India and the Government of Rajasthan over the entire benefit period, shall not

exceed one hundred and twenty-five percent (125%) of the Eligible Fixed Capital

Investment (EFCI) as defined in this Policy, unless otherwise approved by the

Appropriate Sanctioning Committee.

Non-Fiscal Incentives

4.15 Mission-Critical Infrastructure (Essential Service)

Semiconductor manufacturing and allied clean-room utilities shall be notified as

‘Essential Services’ under the State ESMA, subject to orders of the competent

authority, to safeguard uninterrupted operations, maintenance and logistics.

4.16 Water Supply

The State shall endeavour for reliable water supply at the project site, including

facilitation for treated/ ultra-pure water, recycling/ ZLD options and requisite

permissions through the nodal agencies.

4.17 Open Access Power

Eligible units may procure power through Open Access in accordance with the

Electricity Act, applicable rules and RERC regulations, including green/ open access.

4.18 Power Banking for RE/ Green Power

Power banking shall be permitted as per RERC guidelines and relevant DISCOM

procedures, enabling scheduling flexibility for renewable/ green energy.

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3484

4.19 Grid Redundancy & Reliability

The Government shall coordinate with transmission/ distribution utilities to build

N-1/N-2 redundancy and ensure high-reliability supply adequate for FAB/ ATMP

facilities, including dual feeds where feasible.

4.20 24×7/ Three-Shift Operations & Women’s Employment

Units may operate 24×7 with three shifts, including employment of women in all

shifts, subject to compliance with applicable central/ state labour laws and

mandatory safety, transport and security measures.

4.21 Self-Certification & Risk-Based/ Third-Party Inspection

Eligible units shall be covered under a self-certification regime to the extent

permissible under law, in lieu of routine inspections under the Factories Act,

Maternity Benefit Act, Shops & Establishments Act, Contract Labour (R&A) Act,

Payment of Wages Act, Minimum Wages Act, and Employment Exchanges (CNV)

Act. Inspections may be undertaken upon specific complaint, accident,

court/competent authority direction, or as required by statute.

3485 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

5.

Administration

The State shall formulate and notify the necessary procedural guidelines to facilitate

the effective implementation of the Rajasthan Semiconductor Policy 2026 across all

relevant departments, agencies, and institutional mechanisms.

5.1 Implementation and Interpretation Authority

All the related Departments shall implement the policy. The Department of

Industries and Commerce shall act as the nodal coordinating, monitoring, and

implementing department. Any matter pertaining to interpretation of any clause/

section of the policy shall be referred to Department of Industries and Commerce,

Government of Rajasthan. The decision of the Department of Industries and

Commerce in such matters shall be final.

5.2 Review or Modification of the Policy

The State Government reserves the right to review or modify the Policy as and when

needed in public interest. However, Forms released as part of the Policy may be

modified, changed, added, or deleted by the Department of Industries and Commerce as

and when needed for the sake of convenience in implementation of the Policy.

5.3 Revision of the Policy by the State Government

The Government may revise the Policy, in full or in part, prospectively or

retrospectively, to keep harmony with the provisions of the State Goods and

Services Tax Act and Rules made there under.

5.4 Application Process for Incentives and Benefits

The RajNivesh portal, managed by the Bureau of Investment Promotion (BIP), shall

serve as the single-point digital interface for facilitating all investment-related

applications under this Policy. The portal enables end-to-end, time-bound processing

of clearances, approvals, and submissions, ensuring transparency, efficiency, and

ease of doing business.

Steps will be taken for issuance of Entitlement Certificates within 30 days, and

disbursal of approved incentives within 60 days of achievement of milestones.

5.5 Institutional Mechanism

The following institutional framework outlines the mechanism for effective

implementation of the Rajasthan Semiconductor Policy 2026 across all concerned

stakeholders

5.5.1

State Level Sanctioning Committee

The State Level Sanctioning Committee (SLSC) shall have jurisdiction over

all Enterprises investing more than INR 25 crores and Enterprise(s) making

investments in more than one district. In cases requiring review by the State

Level Sanctioning Committee, the decision of the State Level Sanctioning

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3486

Committee shall be final. Detailed guidelines regarding this provision to be

separately notified. The constitution of State Level Sanctioning Committee

(SLSC) shall be as follows:

State Level Sanctioning Committee (SLSC)

Secretary-in-charge

Department of Industries and Commerce

Chairman

Secretary-in-charge

Finance (Revenue) or nominee of Finance Department not below the

rank of Joint Secretary

Member

Commissioner

Commercial Taxes Department

Member

Managing Director

RIICO

Member

Commissioner

Investments and NRIs (BIP)

Member

Commissioner

Department of Industries and Commerce

Member Secretary

5.5.2

State Empowered Committee (SEC)

State Empowered Committee (SEC) is authorised, to consider and approve

customised incentive packages for eligible enterprises.

State Empowered Committee

Chief Secretary

Chairman

Additional Chief Secretary

(Finance) or an officer nominated by them, not below the rank of

Secretary Member

Member

Secretary-in-charge

Environment and Forest Department Member

Member

Secretary-in-charge

Urban Development and Housing Department Member

Member

Secretary-in-charge

Department of Industries and Commerce

Member

Commissioner

Department of Industries and Commerce

Member

Secretary-in-charge

Labour and Employment Department

Member

Secretary-in-charge

Mines and Petroleum Department

Member

Additional Chief Secretary

Member

3487 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

Principal Secretary to Chief Minister

Secretary-in-charge

Revenue Department

Member

Managing Director

RIICO

Member

Secretary-in-charge

Energy Department

Member

Secretary-in-charge

Tourism Department

Member

Commissioner

Investments and NRIs (BIP)

Member Secretary

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3488

6.

Terms and Conditions

This policy clearly sets out the provisions, terms, and conditions to be followed, and

outlines the rights, responsibilities, and limitations of all parties involved.

6.1 Transfer of Benefits in Case of Transfer of Business

6.1.1 When the ownership of a unit of an Enterprise availing benefit of the Policy is

entirely transferred in any manner, then the remaining benefits of such unit under

the Policy, if any, shall be transferred to the transferee Enterprise on fulfilment of

any statutory levy.

6.1.2 For availing such remaining benefits, the transferee Enterprise shall submit a duly

completed application as part of the attached forms and manner as may be

prescribed, to the Member Secretary of the appropriate Sanctioning Committee

along with proof of transfer of ownership of unit and original Entitlement

Certificate(s) issued to the transferor Enterprise, within ninety days of such

transfer.

6.1.3 The Member Secretary of the appropriate Sanctioning Committee shall register the

application and place the completed application before the appropriate

Sanctioning Committee within forty-five days from the receipt of the application

unless specifically extended for reasons to be recorded in writing.

6.1.4 Where the application has been filed beyond the time period as provided in

Section 7.1.2 the appropriate Sanctioning Committee having been satisfied

with the genuineness of cause of delay may condone the delay in filing of the

application from the prescribed date of application.

6.1.5 In case the committee approves the transfer of ownership, the Member Secretary

shall amend the entitlement certificate(s) by making an endorsement in the said

certificate(s) as under; “The benefit under this certificate is hereby transferred

to M/s…

, and the said Enterprise is entitled to avail the benefits mentioned

in this certificate for a period from …… to ”

6.1.6 After such endorsement, the Member Secretary shall forward it to all concerned

immediately but not later than fifteen days from the date of the decision taken by

the committee in its meeting, unless specifically extended for reasons to be

recorded in writing.

6.1.7 Where the committee is of the opinion that the transferee Enterprise is not eligible

to avail the remaining benefits of the Policy, it shall provide an opportunity of

being heard to such Enterprise and shall record the reasons of rejection. The

decision of the Committee shall be communicated by the Member Secretary of the

appropriate Sanctioning Committee to the Enterprise, and all concerned

immediately but not later than thirty days from the date of decision taken by the

committee in its meeting, unless specifically extended for reasons to be recorded

in writing.

6.2 Extent and Period of Benefits

3489 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

6.2.1 Period of Benefit: The period of benefit wherever applicable, shall be counted

from the date of the issuance of the concerned Entitlement Certificate (EC) for

that incentive, unless otherwise specified in the Policy. The period of validity

of that EC will be 10 years in case of Capital Subsidy.

6.2.2 Extent of Interest Subvention: The Interest Subvention shall be in addition

to any other incentive available under any other Scheme of Government of

India. The Enterprise availing Interest Subvention under any other Scheme/

package of State Government shall not be eligible for availing benefit

under the Policy.

6.2.3 The Interest Subvention shall be allowed on the term loan taken from State

Financial Institutions/ Financial Institution/ Bank recognised by Reserve

Bank of India for making investment in plant & machinery and/ or

equipment or apparatus. Provided that the total benefit availed under

Interest Subvention shall not exceed the total interest liability from such

term loan on the Enterprise.

6.2.4 The Interest Subvention shall be available only for interest levied by the

Financial Institution/ Bank. Penal interest or other charges shall not be

reimbursed.

6.2.5 Interest Subvention shall be granted for the duration specified in the

eligibility certificate or until the loan is fully repaid, whichever is earlier. In

the event of the loan being transferred to another State Financial Institution,

Financial Institution, or Bank recognised by the Reserve Bank of India, the

Subvention may continue for the remaining period, subject to the approval

of the appropriate Sanctioning Committee.

6.2.6 In cases of transfer of loan, principal amount needs to remain the same

between one bank recognised by RBI/ FI/ SFI to other.

6.2.7 The Interest Subvention shall be given to the Enterprise which pays regular

instalments and interest to the Financial Institution/Bank. If the Enterprise

becomes a defaulter, it will not get interest subvention for the default

period and such defaulting period will be deducted from five years period

as mentioned in the eligibility certificate.

6.2.8 The Interest Subvention shall be allowed only in a case where the Enterprise

is engaged in manufacturing in which interest subvention is claimed except

where it is engaged in manufacturing of seasonal goods.

6.2.9 In cases where the eligible loan amount for interest subsidy approved by the

appropriate sanctioning committee is less than total term loan disbursed by

the bank(s)/ FI(s), the amount of interest subsidy shall be calculated

proportionately based on repayment of the eligible amount vis-a-vis total

sanctioned loan amount.

6.2.10 An Enterprise availing benefits under this Policy shall comply with all

statutory laws and regulations of the State of Rajasthan applicable to the

Enterprise. Non-compliance may entail cancellation/ withdrawal of the

benefits under the Policy.

7.3

Appeal

भाग 1(ख) राजè थान राज-पğ, जलाईु 03, 2026 3490

7.3.1

The State Level Sanctioning Committee shall be empowered to hear and

decide appeals against the orders of the District Level Sanctioning Committee.

7.3.2

The State Empowered Committee constituted under Section 3 of the

Rajasthan Enterprises Single Window Enabling and Clearance Act 2011 shall

be empowered to hear and decide appeals against the order of State Level

Sanctioning Committee.

7.3.3

The application for appeal shall be filed within a period of 90 days from the

date of communication of the decision.

7.4

Revision by the State Government:

7.4.1

The Department of Industries and Commerce may suo motu or otherwise

revise an order passed by any Sanctioning Committee if it is found to be

erroneous and prejudicial to the interest of the State, after affording an

opportunity of being heard to the beneficiary enterprise.

7.4.2 No order under this Section shall be passed by the State Government after the

expiry of a period of three years after the date by which the benefits under

the Policy are fully availed of.

7.5 Penal Clause

7.5.1

New investments must achieve commercial production within 36 months of

availing stamp duty exemption. In case an entity fails to reach commercial

production within 36 months from availing stamp duty exemption, the

following actions will apply:

a.

Claw back of 50% of applicable stamp duty exemption.

b. A deflator of 0.98 per year will be applicable for all incentives under the

policy.

7.6 Other Terms and Conditions

7.6.1

An Enterprise availing benefits under this Policy shall comply with all

statutory laws and regulations of the State of Rajasthan applicable to the

Enterprise. Non-compliance may entail cancellation/withdrawal of the benefits

under the Policy.

7.6.2

An Enterprise availing benefits under the Policy shall be subject to the

conditions, procedures, instructions, clarifications, or amendments issued

from time to time under the Policy.

7.6.3

Benefits under the Policy can only be availed if, and as long as there is, and

for the period/ s, consent to establish and consent to operate, wherever

applicable, from the Central/ Rajasthan State Pollution Control Board is

effective.

7.6.4

In case of breach of any of the conditions mentioned anywhere in the

Policy, the benefits availed under the Policy shall be withdrawn by the

appropriate Sanctioning Committee and, on its recommendation, the

3491 राजè थान राज-पğ, जलाईु 03, 2026 भाग 1(ख)

concerned Department shall recover the benefits availed by the Enterprise

along with interest @ 18% per annum from the date from which the benefits

have been availed.

7.6.5

Rectification by authority competent to disburse subsidy: Authority

competent to disburse subsidy can claw back any wrongly disbursed subsidy

with an interest of 9% per annum. However, no order for such claw back

shall be passed without providing the Enterprise an opportunity to be heard.

No order for such claw back shall be passed after the completion of 3 years

from the end of the entitlement period.

7.6.6

Rectification of mistake by State Level Sanctioning Committee or District

Level Sanctioning Committee:

a.

With a view to rectify any mistake apparent on record, the State Level

Sanctioning Committee may either suo moto or on an application in this

behalf, rectify any order passed by it or the District Level Sanctioning

Committee.

b. A mistake shall include an order which was valid when it was made

and is subsequently rendered invalid by an amendment of the Policy

having retrospective operation or by a judgment of the Supreme Court, or

the Rajasthan High Court.

c.

No application for rectification shall be filed under this Section after the

expiry of a period of three years from the date of the order sought to be

rectified.

d.

An application under this Section shall be presented to the Member

Secretary of the State Level Sanctioning Committee. The Member

Secretary shall place such application before the State Level Sanctioning

Committee and the State Level Sanctioning Committee shall dispose of

such application.

e.

No order of rectification shall be made after the expiry of four years

from the date of the order.

7.6.7

Entitlement Certificate for Stamp Duty Exemption will be valid for 2 years or

till the expiry of the Policy's operative period.

7.6.8

Provisions for e-governance: To enable electronic delivery of services

under the Policy, notwithstanding anything contrary contained anywhere in

the Policy, the Government Department responsible for the grant of benefit

or issuance of Entitlement Certificate (EC), requires that an application or any

communication, order, certificate, or disbursement of payment relating to

benefits under the Policy shall be made or issued in electronic form. Further,

to facilitate e-governance, the Government Department may change the

procedure mentioned in the Policy to such extent that it is not inconsistent or

incompatible with electronic forms of communication and payment, and

such change shall not invalidate any action for the mere reason that it is

repugnant to the procedural provisions of the Policy.

7.

Abbreviations

Abbreviatio

n

Expansion

Brief context

AEC

Automotive Electronics Council

Automotive device qualification (e.g.,

Q100/ Q101)

AKIC

Amritsar–Kolkata

Industrial

Corridor

National industrial corridor

ATMP

Assembly, Testing, Marking &

Packaging

Semiconductor back-end manufacturing

BESS

Battery Energy Storage System

Electrical energy storage

CoE

Centre of Excellence

Shared

labs/

design/

qualification

platform

DFC

Dedicated Freight Corridor

High-capacity rail freight routes

DISCOM

Distribution Company

Electricity distribution utility

DMIC

Delhi–Mumbai Industrial Corridor

National industrial corridor

EC

Entitlement Certificate

State approval for availing incentives

EDA

Electronic Design Automation

Design tool suites for chips

EHS

Environment, Health & Safety

Operational compliance domain

EMI/EMC

Electromagnetic

Interference/

Compatibility

Product/ lab conformity scope

EMS

Electronics Manufacturing Services Contract

manufacturing

(boards/modules)

ESMA

Essential Services Maintenance Act

Essential services notification basis

FA

Failure Analysis

Device/ package defect analysis

IP

Intellectual Property

Patents/designs/trademarks

ISM

India Semiconductor Mission

GoI

mission

administering

semiconductor

schemes

JEDEC

JEDEC

Solid

State

Technology

Assoc.

Device/ test/ reliability standards

LRN

Loan Registration Number

Banking/term-loan reference

MPW

Multi-Project Wafer

Shared shuttle for prototyping

NLA

No-Lien Account

Dedicated

account

for

pari-passu

disbursals

OSAT

Outsourced

Semiconductor

Assembly

& Test

Third-party packaging/test services

PCBA

Printed Circuit Board Assembly

SMT/through-hole board build

PSU

Public Sector Undertaking

Government-owned enterprise

PwD

Persons with Disabilities

Inclusion category

R&A

Regulation & Abolition

Contract Labour Act context

3493 राजè थान राज-पğ, जलाई ु03, 2026 भाग 1(ख)

RajNivesh

Single-Window System (Rajasthan)

Time-bound clearances & approvals

RE

Renewable Energy

Green power sources

RERC

Rajasthan Electricity Regulatory

Commission

State power regulator

RIPS-2024

Rajasthan

Investment

Promotion

Scheme 2024

State umbrella incentives framework

VKI

Vishwakarma Industrial Area

Jaipur industrial area

ZLD

Zero Liquid Discharge

Water/wastewater compliance regime

By the order of the Governor,

Mahipal Kumar,

Deputy Secretary to Government.

राÏ य केÛ ġȣय मġणालयु,जयपर।ु