राजè थान राजपğ
ͪवशेषांक
RAJASTHAN GAZETTE
Extraordinary
साͬधकार Ĥकाͧशत
Published by Authority
भाġ 03, मंगलवार, शाके 1948- अगè त 25, 2026
Bhadra 03, Tuesday, Saka 1948- August 25, 2026
भाग-7
ͪवͧभÛ न ͪवभागɉ मɅ Ĥदायɉ के ͧलए टेÖ डर मांगने कȧ सचनाओं को सिàमͧलत करते हये साव[जǓनक और Ǔनजी
ू
ु
ͪव£ापन आǑद।
Energy Department
NOTIFICATION
Jaipur, August 17, 2026
No.F.20(40) Energy/2025/04269 :-The State Government, vide Notification No.
F.20(62) Energy/2024 dated 04.12.2024, issued the Rajasthan Integrated Clean Energy
Policy, 2024, which was subsequently amended vide Notification dated 25.07.2025. In this
connection, the following clauses of the aforesaid Policy are hereby inserted/replaced as
follows, with immediate effect:
1. New Clause 15.13 (Section-A) inserted below clause 15.12:
The provisions of Clause 15.11 shall mutatis mutandis apply to an RE
Park/Solar Park for transfer of the entire registered capacity of such park.
2. Clause 16.2.6 (Section-A) replaced with following:
The land may be allotted for the establishment of Renewable Energy
Projects/Renewable Energy Parks/Green Hydrogen Projects/Green Hydrogen
Parks with or without storage having capacity of not less than 1000 MW, and in
cases where Developers/Power Producers do not presently have connectivity
from the Central Transmission Utility (CTU)/State Transmission Utility (STU)
for the land identified in accordance with the provisions of prevailing
landrevenue rules.
RREC will make recommendation to Revenue Department forallotment of land
for establishing RE/Green HydrogenProjects/Parks etc. on deposition of Land
Security @ Rs. 1 Lac/MWin form of DD/RTGS or through E-grass/IFMS 3.0 of
RevenueManagement System in designated Budget Head in favour of
StateGovernment. The land so recommended shall not be more than
themaximum limit of land as prescribed under clause 16.3 (section-A)of this
policy.
Revenue Department will issue necessary allotment order for rightto use of the
land as an advance possession, as per applicableprovision of Rajasthan Land
Revenue (Allotment of land for settingup of Power Plant based on Renewable
Energy Sources) Rules,2007 as amended from time to time.
The Security Deposit (SD) deposited with the State Governmentshall be
refunded to the Developer upon commissioning of theproject, in proportion
भाग 7 राजè थान राज-पğ, अगè त 25, 2026 269
tothe capacity commissioned, based on therecommendation of RRECL by
Revenue Department as per the rules.
The Developers/Power Producers who have already applied and/ordeposited the
Security Deposit with RREC as per the EnergyDepartment, GoR Notification
dated 25.07.2025 shall have theoption to migrate their application for allotment
of land under theseprovisions within two months, along with the deposition of
theapplicable Security Deposit, if not deposited from the effective dateof
notification of this policy provision. In case of withdrawal ofapplication towards
set apart of the land by Developer/PowerProducers, the SD will be refunded to
Developer/Power Producerby RREC.
RREC will send the proposal accordingly to Revenue Department.
Any violation of the provisions of this policy & Rajasthan LandRevenue
(Allotment of land for setting up of Power Plant based onRenewable Energy
Sources) Rules, 2007 shall lead to withdrawal ofallotment of the land and also
forfeiture of Land Security amount.
3. Clause 16.3 (Section-A) replaced with following
For setting up of Power Plants based on different technologies, maximum
land area which can be allotted to the Developer/ Power Producer will be as
under:
S.
N
o.
Technology
Maximum land area
for Solar Plant
For Wind-Solar
Hybrid Plant
i SPV on Crystalline Technology. 2.0Hect./MW
ii SPV on Crystalline Technology
with tracker.
2.0Hect./MW
iii SPV on Thin Film/Amorphous
Technology with or without
tracker.
2.0 Hect./MW
iv Solar Thermal (CSP)-
Parabolic Trough /Tower/Other
Technology with and without
storage
a) Up to PLF of 21%:
3.0 Hect./MW
b) For every 1%
increase in PLF,
0.15 Hect./MW
additional land will
be allotted.
Land
shall
be
allotted
according
to
individual
capacity
of
solar
and
wind
component of the
project subject to
condition
that
maximum
ceiling
limit of overall land
for Hybrid project
will be 2.5 Ha/MW
of declared capacity
of Hybrid Project.
v Maximum land area for Wind
Plant
2.0 Hect/MW
Provided that 10% of the total area of land allotted shall be reserved bythe
allottee for the purpose of tree plantation.
270 राजè थान राज-पğ, अगè त 25, 2026 भाग 7
Note: For power projects with storage system, additional land will beallotted as
per the rules prescribed by the Revenue Department,GoR.
New Clause 16.4.5 Stamp Duty (Section-A) inserted below clause 16.4.4.
The applicable stamp duty on execution of lease deed/sub lease deed etc.will be
payable by Developer/Power Producer as per prevalent Act/Rules.
4. Clause 6.3 (Section-B) replaced with following:
In order to encourage storage capacity to supply reliable power, newRE projects
integrated with BESS at STU/Discom Network under with minimum capacity
of X/2 MWh (where "X" is the installed capacity of RE project) shall be
exempted 50% from registration charges for the RE capacity and on installation
of BESS beyond X/2 MWh capacity, registration charges shall be exempted up
to 100% on pro rata basis corresponding to the storage capacity added.
5. Clause 8(d) (Section-B) replaced with following:
Each Developer of PSP will deposit non-refundable registration charge of Rs.
10 Lac per project with RREC.
BESS (Stand alone or integrated with RE) will deposit following registration
charges:
BESS size ≤ 2 MWh
Rs. 5,000/-
BESS size > 2 MWh
& ≤100 MWh
Rs. 10,000 per MWh
BESS size > 100
MWh
Rs. 10 Lac per project
However, the aforesaid registration charges will not be applicable only for
BESS required to be installed with RE Project as per clause 6.4 (section-B).
6. Clause 1.12 (iii) (Section-E) replaced with following:
The Power Evacuation facilities granted by DISCOMs/RVPN as per the grid
connectivity procedure/guidelines of DISCOMs/RVPN, will be utilized by
Developers/ Power Producers within 2 years from the date of approval,
otherwise
power
evacuation
approval
may
be
allocated
to
otherDevelopers/Power Producers on priority basis.
By Order,
Manoj Kumar Mittal,
Dy. Secretary to Government.
राÏ य केÛ ġȣय मġणालय
ु
, जयपरु।