TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI
TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI
Amendment to the
Amendment to the Tamil Nadu Electricity Regulatory Commission (Renewable Energy
Purchase Obligation) Regulations, 2010 .. .. ..
.. .. ..
132-134
132-134
132
TAMIL NADU GOVERNMENT GAZETTE
[Part VI—Sec. 2
NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.
TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI.
Amendment to the Tamil Nadu Electricity Regulatory Commission (Renewable Energy Purchase Obligation)
Regulations, 2010
(Notifi cation No. TNERC/RPO/19 – 5 dated 24th July 2020)
(Lr.No. TNERC/Legal/2050/2020, dated: 28th July 2020)
No. VI(2)/35/2020.
In exercise of the powers conferred by Sections 61(h),66 and 86(1)(e) read with section 181 of the Electricity
Act,2003 (Central Act 36 of 2003) and all other powers enabling it in this behalf, the Tamil Nadu Electricity Regulatory
Commission hereby makes the following amendment to the Tamil Nadu Electricity Regulatory Commission (Renewable
Energy Purchase Obligation) Regulations,2010, the draft of the same having been previously published as required by
sub-section (3) of Section 181 of the said Act.
Aඕඍඖඌඕඍඖග
In the said regulations, in regulation 3, in sub-regulation (1A),
(a) in the Table after Sl.No.3, in column (1) and the entries relating thereto in columns (2) to (4), the following
shall respectively be inserted, namely :-
“
4.
2018-19
14.00%
5.00%
5.
2019-20
14.00%
5.00%
6.
2020-21
18.25%
8.00%
7.
2021-22
21.00%
10.50%
”
(b) the existing ‘Explanation’ under the Table shall be renumbered as Explanation (1), and after Explanation (1) ,
as so renumbered, the following Explanation shall be added , namely:-
“(2) The applicability of the Renewable Purchase Obligations specifi ed in sub-regulation (1A) to the Obligated
entities other than the Distribution Licensees shall be subject to the outcome of the writ petitions pending before the
Hon’ble High Court,Madras.”
(By order of the Tamil Nadu Electricity Regulatory Commission)
Chennai-600 008,
S.CHINNARAJALU,
27th July 2020.
Secretary
Tamil Nadu Electricity Regulatory Commission.
EXPLANATORY STATEMENT
The Commission has been mandated to fi x Renewable Energy Purchase Obligation (RPO) under Section 86(1)(e) of
the Electricity Act,2003. Accordingly, the Commission has notifi ed the RPO until FY 2017-18 in its RPO Regulations.
Distribution Licensee, Open Access Consumers and Captive Consumers are the obligated entities under the above
Regulation. The RPO fi xed by the Commission for FY 2017-18 continues to be applicable for further period until any
revision is eff ected by the Commission as per the Commission’s RPO Regulations.
The Ministry of Power in consultation of Ministry of New and Renewable Energy has in the order dt.14-6-2018
notifi ed a long term growth trajectory of Renewable Energy Purchase Obligations (RPO) for Solar and Non Solar for
consideration of State Electricity Regulatory Commissions to notify RPO in their respective States. In consideration to
Aug. 12, 2020]
TAMIL NADU GOVERNMENT GAZETTE
133
the order of Ministry of Power and in aiding acceleration of growth of clean energy sources, the RPO growth trajectory
for the fi nancial years 2019-20, 2020-21 and 2021-22 is proposed to be specifi ed under the RPO Regulations. The
RPO target specifi ed will be applicable to the Distribution licensee only at present and however the enforcement of
RPO as per the percentage specifi ed in the Regulations to the other obligated entities will be subject to the outcome
of the writ petitions pending before the Hon’ble High Court, Madras.
(By the order of the Tamil Nadu Electricity Regulatory Commission)
Chennai-600 008,
S.CHINNARAJALU,
27th July 2020.
Secretary
Tamil Nadu Electricity Regulatory Commission.
STATEMENT SHOWING EXISTING PROVISION AND PROVISION AS AMENDED
Tamil Nadu Electricity Regulatory Commission (Renewable Energy Purchase Obligation) Regulations, 2010
Existing provision
(1)
Provision as amended
(2)
3. Renewable Purchase Obligation.-
(1) Every obligated entity shall purchase not less than
defi ned minimum percentage of its consumption of energy
from renewable energy sources under the Renewable
Purchase Obligation (RPO) during a year as specifi ed
below:
xxx
(1A) The following percentage of Renewable Purchase
Obligation is fi xed:
S l .
No.
Year
Minimum Quantum
of total renewable
purchase obligation
in percentage
(in terms of energy
in kWh)
Minimum quantum
of solar renewable
purchase obligation
in percentage out of
the total renewable
purchase obligation
mentioned in column
(3 )(in terms of
energy in kWh)
(1)
(2)
(3)
(4)
1
2015-16
9.50%
0.50%
2
2016-17
11.50%
2.50%
3
2017-18
14.00%
5.00%
Explanation:
The
Renewable
Purchase
Obligations
specifi ed for the year 2011-12 in sub-regulation (1) shall be
applicable for the years 2012-13, 2013-14 and 2014-15 to
the Distribution Licensee.
3. Renewable Purchase Obligation.-
(1) Every obligated entity shall purchase not less than
defi ned minimum percentage of its consumption of
energy from renewable energy sources under the
Renewable Purchase Obligation (RPO) during a year
as specifi ed below:
xxx
xxx
Sl.
No.
Year
Minimum Quantum
of total renewable
p u r c h a s e
obligation
in
percentage
(in
terms of energy in
kWh)
Minimum quantum of
solar renewable purchase
obligation in percentage
out of the total renewable
purchase
obligation
mentioned in column (3)
(in terms of energy in kWh)
(1)
(2)
(3)
(4)
1
2015-16
9.50%
0.50%
2
2016-17
11.50%
2.50%
3
2017-18
14.00%
5.00%
4.
2018-19
14.00%
5.00%
5.
2019-20
14.00%
5.00%
6.
2020-21
18.25%
8.00%
7.
2021-22
21.00%
10.50%
Explanation:(1) The Renewable Purchase Obligations specifi ed
for the year 2011-12 in sub-regulation (1) shall be applicable
for the years 2012-13, 2013-14 and 2014-15 to the Distribution
Licensee.
134
TAMIL NADU GOVERNMENT GAZETTE
[Part VI—Sec. 2
Existing provision
(1)
Provision as amended
(2)
(2) xxx
(3) xxx
(2) The applicability of the Renewable Purchase Obligations
specifi ed in sub-regulation (1A) to the Obligated entities other
than the Distribution Licensees shall be subject to the outcome of
the writ petitions pending before the Hon’ble High Court, Madras.
(2) No change
(3) No change
(By the order of the Tamil Nadu Electricity Regulatory Commission)
Chennai-600 008,
S.CHINNARAJALU,
27th July 2020.
Secretary,
Tamil Nadu Electricity Regulatory Commission.