[53]

TAMIL NADU

GOVERNMENT GAZETTE

PUBLISHED BY AUTHORITY

DTP—VI-2 (10)

NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.

CONTENTS

No.  10]

CHENNAI, WEDNESDAY, MARCH 11, 2026

Maasi 27, Visuvaavasu, Thiruvalluvar Aandu–2057

Part VI—Section 2

Notifications of interest to a section of the public

issued by Heads of Departments, etc.

© [Regd. No. TN/CCN/467/2012-14.

GOVERNMENT OF TAMIL NADU [R. Dis. No. 197/2009.

2026 [Price: Rs. 42.40 Paise.

Pages.

TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI

Tamil Nadu Electricity Grid Code, 2026

..

..

..

..

..

..

..

54-157

TAMIL NADU GOVERNMENT GAZETTE

54

[Part   VI—Sec. 2

NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.

TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI

Tamil Nadu Electricity Grid Code, 2026

(Notification No. TNERC/GC/01 /2026), Dated: 13-02-2026)

(Lr.No. TNERC/Legal/1369/D.No. 216/2026)

No. VI(2)/13/2026.

In exercise of the powers conferred by Sections 86(1)(h) of the Electricity Act, 2003 (Central Act 36 of 2003)

and all other powers enabling it in this behalf, the Tamil Nadu Electricity Regulatory Commission hereby makes the

Tamil Nadu Electricity Grid Code, 2026 duly repealing the existing Tamil Nadu Electricity Grid Code, 2005 and the

draft of the same having been previously published, as required under sub-section (3) of section 181 of the Act.

Chapter 1 – Short title and Commencement

1.1. Short Title, Commencement and Extent

(a) This Code may be called “Tamil Nadu Electricity Grid Code, 2026”

(b) The provisions of this Code shall come into force from the date of publication in the

Tamil Nadu Government Gazette.

(c) This Code shall apply to State Load Despatch Centre (SLDC) of Tamil Nadu, every user who is connected to

and/uses intra-state transmission system of the State Transmission Utility (STU) and intra-State Transmission Licensees

and the users (Generators & OA consumers) connected with the Distribution System of the Distribution Licensee.

(d) These Regulations shall also be applicable to new connections and equipment procured/provided for new

works / replacements from the date, this Code is made effective.

1.2. Scope

(a) Tamil Nadu Electricity Grid Code (TNEGC) is a document that defines the boundary between STU and Users

and establishes the procedures for operation of facilities connected to the State Transmission System.

(b) The Grid Code shall be complied with by the STU in its capacity as the holder of the State Transmission

Licence and by State Sector Generating Stations (SSGS), IPPs, State Transmission Licensees other than STU,

Distribution Licensees, Open Access customers and any Other User of Intra-State Transmission System and Distribution

System, in the course of generation, transmission and distribution of electricity.

CHAPTER 2 - Preliminary

2.1. Glossary and Definitions

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

1

Act

The Electricity Act 2003 (Central Act No. 36 of 2003).

2

Agency

Means an entity used in this Code to refer to a Licensee / Generating

Station that utilize the Intra State Transmission System.

3

Alert State

means the state in which the operational parameters of the power

system are within their respective operational limits, but a single n-1

contingency leads to violation of system security.

4

Ancillary Services

shall have the same meaning as defined in the Central Electricity

Regulatory Commission (Ancillary Services) Regulations, 2022 and

amendments thereof.

5

Apparatus

means Electrical apparatus and includes all machines, fittings, accessories

and appliances in which conductors are used.

6

Appendix

An Appendix to a chapter of the Grid Code.

7

Area Control Error (ACE)

shall have the same meaning as defined in the IEGC, 2023 and

amendments thereof.

8

Area of Supply

means area designated in the license for carrying out the licensed

activity.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

55

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

9

Automatic Generation Control

(AGC)

means a mechanism that automatically adjusts the generation of a

control area to maintain its interchange schedule plus its share of

frequency response.

10

Automatic Voltage Regulator

(AVR)

means a continuously acting automatic excitation control system to

control the voltage of a generating unit measured at the generator

terminals.

11

Auxiliary Energy Consumption

shall have the same meaning as defined in TNERC (Terms and

Conditions for the determination of Tariff) Regulations and amendments

thereof.

12

Available Capacity

shall have the same meaning as defined in TNERC’s Deviation

Settlement Mechanism Regulations issued in the year 2019 and 2024

and amendments thereof.

13

Available Transfer Capability

(ATC)

means the transfer capability of the inter-control area transmission

system available for scheduling commercial transactions (through

long-term open access, medium-term open access and short-term

open access) in a specific direction, taking into account the network

security. Mathematically, ATC is the Total Transfer Capability less

Transmission Reliability Margin.

14

Backing Down

means reduction of generation from generating unit under abnormal

conditions such as high frequency, low system demand or network

constraints under instructions from SLDC/ SRLDC.

15

Beneficiary

means a person who has a share in a Generating Station.

16

Bilateral Transaction

means a transaction for exchange of energy (MWh) between a specified

buyer and a specified seller, directly or through a trading licensee or

discovered at Power Exchange through anonymous bidding, from a

specified point of injection to a specified point of drawal for a fixed or

varying quantum of power (MW) for any time period during a month.

17

Black Start

means a process of recovery from total or partial blackout of the

State Transmission System.

18

Blackout

means a condition at a specific time where a part or all the operations

of the power system have got suspended.

19

Breakdown

means an occurrence relating to equipment/Transmission /Distribution

facilities of supply system which prevents its normal functioning.

20

Bulk Consumer

shall have the same meaning as defined in CEA Technical Standards

for Connectivity and amendments thereof.

21

Buyer

means a person purchasing electricity through a transaction scheduled

through intra-State transmission system in accordance with this Grid

Code.

22

Capacitor

means an electrical facility provided for generation of reactive power.

23

Captive Generating Plant

(CGP)

shall have the same meaning as defined in the Act.

24

CBIP

Central Board of Irrigation and Power.

25

CEA

Central Electricity Authority.

26

CEA Grid Standards

means the Central Electricity Authority (Grid Standards)

Regulations, 2010 as amended from time to time

27

CEA Technical Standards for

Communication

means the Central Electricity Authority (Technical Standards for

Communication System in Power System Operation) Regulations, 2020

as amended from time to time

28

CEA Technical Standards for

Connectivity

means the Central Electricity Authority (Technical Standards for

Connectivity to the Grid) Regulations, 2007 as amended from time

to time

TAMIL NADU GOVERNMENT GAZETTE

56

[Part   VI—Sec. 2

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

29

CEA Technical Standards for

Construction

means the Central Electricity Authority (Technical Standards for

Construction of Electrical Plants and Electric Lines) Regulations, 2022

as amended from time to time

30

Central Generating (CGS)

Station

shall mean generating stations owned by the companies owned or

controlled by the Central Government.

31

Central Transmission

Utility (CTU)

shall mean utility notified by the Government of India under sub-section

(1) of Section 38 of the Act

32

Centralised Data Collection

Centre (CDCC)

means the centre which is responsible to collect, collate and process

the energy meter data for various applications like energy accounting

and auditing, energy billing, transmission system loss calculations and

power purchase bill reconciliation.

33

CERC

Central Electricity Regulatory Commission

34

Code

Means Tamil Nadu Electricity Grid Code, 2026 inasmuch as this Code

is concerned.

35

Co-generation

means a process, which simultaneously produces two or more forms

of useful energy (including electricity).

36

Cold Start

in relation to steam turbine means start up after a shutdown period

exceeding 72 hours (turbine metal temperatures below approximately

40% of their full load values).

37

Collective Transaction

shall have the same meaning as assigned to it in Central Electricity

Regulatory Commission (Power Market) Regulations, 2021 and

amendments thereof.

38

Commission/ TNERC

shall mean Tamil Nadu Electricity Regulatory Commission.

39

Congestion

means a situation where the demand for transmission capacity or

power flow on any transmission corridor exceeds its Available Transfer

Capability.

40

Connection

means the electric lines and electrical equipments used for connecting

the User’s system to the Intra-State Transmission System.

41

Connection Agreement

means an agreement setting out the terms relating to the Connection

to and / or use of the Intra-State Transmission / Distribution System.

42

Connection Conditions

means the technical conditions to be complied with by any User

having a Connection to the State Transmission System as laid down

in Connection Conditions of this Grid Code and Procedure issued in

this regard by the Commission.

43

Connection point

means a point at which a user’s or Transmission Licensee’s Plant

and/or Apparatus connects to the Intra-State Transmission/ Distribution

System.

44

Connectivity

means the state of getting connected to the intra-State transmission

system by a generating station including a captive generating plant,

a bulk consumer or an Inter-State Transmission licensee, in terms of

the prevailing Regulations/Grid Code/ Procedure issued in this regard

by the Commission.

45

Connectivity Agreement

means an agreement between CTU/STU and any other person(s) setting

out the terms and conditions relating to connection to and/or use of

the Intra-State Transmission System in terms of prevailing Regulations/

Grid Code/Procedure issued in this regard by the Commission.

46

Constituent

means any agency who is a member of the State Electricity System

47

Consumer

shall have the same meaning as defined in the Act.

48

Control Area

means an electrical system bounded by inter-connections (tie lines),

metering and telemetry, which controls its generation and/or load

to maintain its interchange schedule with other control areas and

contributes to regulation of frequency as specified in this Grid Code.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

57

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

49

Control Centre

includes NLDC or RLDC or REMC or SLDC or Area LDC or Sub-

LDC or DISCOMs LDC/SCADA Centre whichever applicable, including

main and backup Centres, as applicable.

50

Data Acquisition System (DAS)

means a system for recording the sequence of operation in time, of

the relays or equipment as well as the measurement of pre-selected

system parameters.

51

Date of Commercial Operation

(COD)

shall have the same meaning as specified in this Grid Code.

52

Declared Capacity (DC)

in relation to a generating station means, the capability to deliver ex-

bus electricity in MW declared by such generating station in relation

to any time-block of the day as defined in the Grid Code or whole

of the day, duly taking into account the availability of fuel or water,

and subject to further qualification as per provisions of the Grid Code.

53

Demand

The demand in MW and MVA of electricity (i.e. both Active and

reactive power).

54

Demand Response

means variation in electricity usage by the end consumers or by a

control area manually or automatically, on stand-alone or aggregated

basis, in response to system requirements as identified by the

concerned LDC.

55

Despatch Schedule

means the ex-power plant net MW and MWh output of a generating

station, for a time block, scheduled to be injected to the Grid from

time to time.

56

Deviation

Deviation in a time-block for a seller means its total actual injection

minus its total scheduled generation and for a buyer means its total

actual drawal minus its total scheduled drawal;

57

Deviation Charges

shall have the same meaning as defined in the Commission’s Deviation

Settlement Mechanism Regulations and amendments thereof issued

from time to time.

58

Deviation Settlement

Mechanism (DSM) Regulations

shall have the same meaning as defined in the TNERC (Deviation

Settlement Mechanism and related matters) Regulations, 2019 and

TNERC (Forecasting, Scheduling and Deviation Settlement and

related matters for wind and solar generation) Regulations, 2024 and

amendments thereof issued from time to time.

59

Disconnection

means the act of physically separating electrical equipments of a User

or EHV Consumer from the State Transmission System.

60

Distribution Licensee/

Distribution Company/DISCOMs

means a Licensee authorised by the Commission to operate and

maintain a distribution system for supplying electricity to the consumers

in his area of supply.

61

Distribution System

means the system of electric lines and electrical equipment at voltage

levels of 33 kV and lower, including part of a State Transmission

System, used for supply of electricity to a single consumer or group

of consumers.

62

Disturbance Recorder (DR)

means a device provided to record the behaviour of the pre-selected

digital and analog values of the system parameters during an Event.

63

Drawal

means the algebraic sum of import and export of electrical energy

and power both active and reactive from the Regional Grid. In respect

of DISCOMs, drawal means algebraic sum of import and export of

electrical energy and power both active and reactive from STU.

64

Drawee Entity

means a consumer or a distribution licensee who has been connected

with the intra-state transmission/distribution system.

65

EHV or Extra High Voltage

Nominal voltage levels of 66 kV and above.

66

EHV Consumer

means a person to whom electricity is provided and who has a

dedicated supply at 66 kV or above.

TAMIL NADU GOVERNMENT GAZETTE

58

[Part   VI—Sec. 2

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

67

Emergency State

means the state in which one or more operational parameters are

outside their operating limit or many of the equipment connected to

the grid are operating above their respective loading limit.

68

Energy Storage System (ESS)

in relation to the electricity system, means a facility where electrical

energy is converted into any form of energy, which can be stored

and subsequently reconverted into electrical energy and injected back

into the grid.

69

Entitlement

means the share of a DISCOMs (in MW and MWh) in the installed

Capacity / output Capability of a Generating Station.

70

Event

means an unscheduled or unplanned occurrence in the grid including

faults, incidents and breakdowns.

71

Event Logging

means a device for recording the chronological sequence of operations

of the relays and other equipment.

72

Ex-Power Plant

means net MW or MWh output of a generating station, after deducting

auxiliary consumption and transformation losses.

73

External interconnection

Electric lines and electrical equipment used for transmission of electricity

between the Inter-State and Intra-State Transmission System.

74

Fault Locator (FL)

means a device installed at the end of a transmission line to measure

or indicate the distance at which a line fault may have occurred.

75

Flexible Alternating Current

Transmission System (FACTS)

means a power electronics-based system and other static equipment

that provide control of one or more AC transmission system parameters

to improve power system stability, enhance controllability and increase

power transfer capability of transmission systems.

76

Forced Outage

means an outage of a generating unit or a transmission facility due

to a fault or any other reasons, which have not been planned.

77

Free Governor Mode of

Operation (FGMO)

means the mode of operation of governor where machines are loaded

or unloaded directly in response to grid frequency, i.e., machine

unloads when grid frequency is more than 50 Hz and loads when grid

frequency is less than 50 Hz. The amount of loading or unloading is

proportional to the governor droop.

78

Frequency Response

Characteristics (FRC)

means automatic, sustained change in the power consumption by load

or output of the generators that occurs immediately after a change

in the load-generation balance of a control area and which is in a

direction to oppose any change in frequency. Mathematically, FRC =

Change in Power (∆P) / Change in Frequency (∆f).

79

Frequency Response

Obligation (FRO)

means the minimum frequency response a control area has to provide

in the event of any frequency deviation.

80

Frequency Response

Performance (FRP)

means the ratio of actual frequency response with frequency response

obligation.

81

Gaming

means an intentional/deliberate mis-declaration of declared capacity

by any seller in order to make an undue commercial gain through

charge for Deviations.

82

Generating Company

shall have the same meaning as defined in sub- section (28) of

Section 2 of the Act.

83

Generating Station

shall have the same meaning as defined in sub- section (30) of

Section 2 of the Act.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

59

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

84

Generating Unit

means

a) a unit of a generating station (other than those covered in sub-

clauses (b) and (c) of this clause) having electrical generator

coupled to a prime mover within a power station together with all

plant and apparatus at the power station which relate exclusively

to operation of that turbo-generator;

b) an inverter along with associated photovoltaic modules and other

equipment in respect of generating station based on solar photo

voltaic technology;

c) a wind turbine generator with associated equipment, in respect of

generating station based on wind energy;

d) in respect of Renewable Hybrid Generating Station (RHGS),

combination of hydro generator under sub-clause (a); or solar

generator under sub-clause (b) or wind generator under sub-clause

(c) of this clause.

85

Generator

means a person or agency who generates electricity and who is

subjected to Grid Code either pursuant to any agreement with STU

or otherwise.

86

Good utility practices

Any of the practices, methods and acts engaged in or approved by

a significant portion of the electric utility industry during the relevant

time period which could have been expected to accomplish the desired

results at a reasonable cost consistent with good business practices,

reliably, safely and with expedition.

87

Governor Droop

in relation to the operation of the governor of a generating unit

means the percentage drop in system frequency, which would cause

the generating unit under governor action to change its output from

no load to full load.

88

Grid Code Review Committee

(GCRC)

means the Committee set up under Chapter-5 (Management of the

Grid Code) of this Grid Code.

89

Grid Contingencies

means abnormal operating conditions brought out by tripping of

generating units, transmission lines, transformers or abrupt load changes

or by a combination of the above leading to abnormal voltage and/

or frequency excursions and/or overloading of network equipment.

90

Grid Disturbance (GD)

means the situation where disintegration and collapse of grid either in

part or full takes place in an unplanned and abrupt manner, affecting

the power supply in a large area of the region.

91

Grid Security

means the power system’s capability to retain a normal state or to

return to a normal state as soon as possible, and which is characterized

by operational security limits.

92

High Voltage (HV)

means the voltage higher than 650 volts but not exceeding 33,000

volts under normal conditions.

93

Hot Start

in relation to steam turbine, means the start up after a shutdown

period of less than 10 hours (turbine metal temperatures below

approximately 80% of their full load values).

94

HVDC

High Voltage Direct Current System.

95

IEC

International Electro Technical Commission, the authority that approves

the electricity industry standards used on an international basis

96

Independent Power Producer

(IPP)

means a generating company not owned or controlled by Central /

State Government/ their joint venture and such generating company

is not classified as a Captive Generating Plant (CGP).

TAMIL NADU GOVERNMENT GAZETTE

60

[Part   VI—Sec. 2

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

97

Indian Electricity Grid Code

(IEGC)

Means regulations framed by Central Electricity Regulatory Commission

under clause (h) of sub-section (1) of Section 79 read with clause

(g) of sub-section (2) of Section 178 of the Act.

98

Indian Standard (IS)

means the standard established and published by the Bureau of Indian

Standards (BIS) and subsequent updations.

99

Inertia

means the contribution to the capability of the power system to

resist changes in frequency by means of an inertial response from a

generating unit, network element or other equipment that is coupled

with the power system and synchronized to the frequency of the

power system.

100

Infirm Power

shall have the same meaning as defined in TNERC – The Power

Procurement from New and Renewable Sources of Energy Regulations,

2008 and amendments thereof.

101

Inter-State Transmission

System (ISTS)

shall have the same meaning as defined in sub- section (36) of

Section 2 of the Act

102

Inter Connecting Transformer

(ICT)

means the transformer connecting EHV lines of different voltage levels.

103

Inter-State Generating Station

(ISGS)

means a central generating station or any other generating station

having a scheme for generation and sale of electricity in more than

one State.

104

Intra-State Transmission

System (InSTS)

shall have the same meaning as defined in sub- section (37) of

Section 2 of the Act.

105

LDC

means Load Despatch Centre

106

Lean Periods

Means periods in a day when electrical demand is at its lowest

107

Licensee

shall have the same meaning as defined in the Act.

108

Load

means the active, reactive or apparent power consumed by a utility/

installation of consumer.

109

Load Crash

means sudden or rapid reduction of electrical load connected to a

system that could be caused due to tripping of major transmission

line(s), feeder(s), power transformer(s) or natural causes like rain, etc.

110

Maximum Continuous Rating

(MCR)

means the maximum continuous output in MW at the generator

terminals guaranteed by the manufacturer at rated parameters.

111

Merit Order

means the order of ranking of available electricity generation in

ascending order from least energy charge to highest energy charge

to be used for deciding despatch instructions to minimize the overall

cost of generation.

112

Minimum Turndown Level

means the minimum output power expressed in percentage of maximum

continuous power rating that the generating unit can sustain continuously,

to be on bar and includes minimum power level as defined in CEA

Flexible Operation Regulations and amendments thereof.

113

Nadir Frequency

means the minimum frequency after a contingency in case of generation

loss and maximum frequency after a contingency in case of load loss.

114

National Grid

The entire inter-connected electric power network of the country, which

would evolve after inter-connection of regional Grids.

115

National Load Despatch Centre

(NLDC)

means the centre established under sub-section (1) of Section 26

of the Act.

116

Near Miss Event

means an incident of multiple failures that has the potential to cause

a grid disturbance, power failure or partial collapse but does not result

in a grid disturbance

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

61

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

117

Net Drawal Schedule at Intra-

State level

means the drawal schedule of a State entity, which is the algebraic

sum of all its transactions through the intra-State transmission system

at Intra-State Transmission System periphery after deducting the

transmission losses

118

Normal State

means the state in which the operational parameters of the power

system are within their respective operational limits and equipment

are within their respective loading limits.

119

On-Bar Declared Capacity

in relation to a generating station means the capability to deliver ex-bus

electricity in MW from the units on-bar declared by such generating

station in relation to any time block of the day or whole of the day,

duly taking into account the availability of fuel and water and subject

to further qualification in the relevant Regulations.

120

Operation

A scheduled or planned action relating to the operation of the power

system.

121

Open Access

shall have the same meaning as defined in TNERC (Grid Connectivity

and Intra-State Open Access) Regulations, 2014 and amendments

thereof.

122

Open Access Customer (OAC)

shall have the same meaning as defined in TNERC (Grid Connectivity

and Intra-State Open Access) Regulations, 2014 and amendments

thereof.

123

Operating range

means the operating range of frequency and voltage as specified in

Chapter-12 of this Grid Code.

124

Operational Parameters

means the parameters for system security as specified by the system

operator including frequency, voltage at station-bus, angular separation,

damping ratio, short circuit level, inertia.

125

Outage

In relation to a Generator/ Transmission/ Distribution facility, means an

interruption of power supply whether manually or by protective relays in

connection with the repair or maintenance of the SSGS/ Transmission

facility or resulting from a breakdown or failure of the Transmission/

Distribution facility/SSGS unit or defect in its Auxiliary system.

126

Peak Period

means that period in a day when electrical demand is at its highest.

127

Permit to Work (PTW)

means the safety documentation issued to any person to allow work

to commence on inter-user boundary after satisfying that all the

necessary safety precautions have been established.

128

Planned Outage

means an outage in relation to a SSGS unit or Power Station Equipment

or Transmission facility, which has been planned and agreed with

SLDC, in advance in respect of the year in which it is to be taken.

129

Pool Account

shall have the same meaning as defined in TNERC (Forecasting,

Scheduling and Deviation Settlement and related matters for wind and

solar generation) Regulations, 2024 and TNERC (Deviation Settlement

Mechanism and related matters) Regulations, 2019 amendments thereof.

130

Pooling Station

shall have the same meaning as defined in TNERC (Forecasting,

Scheduling and Deviation Settlement and related matters for wind

and solar generation) Regulations, 2024 and amendments thereof.

131

Power System

shall have the same meaning as defined in sub- section (50) of

Section 2 of the Act

132

Primary Reserve

means the maximum quantum of power, which will immediately come

into service through governor action of the generator or frequency

controller or through any other resource in the event of sudden

change in frequency.

133

Qualified Coordinating Agency

(QCA)

shall have the same meaning as defined in TNERC (Forecasting,

Scheduling and Deviation Settlement and related matters for wind

and solar generation) Regulations, 2024 and amendments thereof.

TAMIL NADU GOVERNMENT GAZETTE

62

[Part   VI—Sec. 2

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

134

Ramp Rate

means rate of change of a generating station output expressed in

% MW per minute.

135

Rate of Change of Frequency

(df/dt)

means the time derivative of the power system frequency, which

negates short term transients and therefore reflects the actual change

in synchronous network frequency.

136

Reference contingency

means the maximum positive power deviation occurring instantaneously

between generation and demand and considered for estimation of

reserves.

137

Regional Grid

means the important elements of constituent / user systems including

the ISTS which the RLDC supervises.

138

Regional Load Despatch

Centre (RLDC)

means the Centre established under sub-section (1) of Section 27

of the Act.

139

Regional Power Committee

(RPC)

shall have the same meaning as defined in the Act.

140

Renewable Energy Generating

Station (REGS)

means a generating station based on a renewable source of energy

with or without Energy Storage System and shall include Renewable

Hybrid Generating Station.

141

Resilience

means the ability to withstand and reduce the magnitude or duration

of disruptive events, which includes the capability to anticipate, absorb,

adapt to, or rapidly recover from such an event.

142

Restorative State

means a condition in which control action is being taken to reconnect

the system elements and to restore system load.

143

Renewable Hybrid Generating

Station (RHGS)

means a generating station based on hybrid of two or more renewable

source(s) of energy with or without Energy Storage System, connected

at the same inter-connection point.

144

Rotational Load Shedding

means the planned disconnection of consumers on a rotational basis

during periods when there is a significant shortfall of power required

to meet the total demand.

145

Secondary Reserve

means the maximum quantum of power, which can be activated

through secondary control signal by which injection or drawal or

consumption of a Secondary Reserve Ancillary Service provider is

adjusted in accordance with CERC (Ancillary Services) Regulations,

2022 and amendments thereof.

146

Seller

means a person, including a generating station, supplying electricity

through a transaction scheduled in accordance with the appropriate

Regulations.

147

Share

means percentage or MW entitlement of a beneficiary in an ISGS either

notified by Government of India or agreed between the generating

company and beneficiary.

148

Single Line Diagram (SLD)

means Diagrams which are a schematic representation of the HV/ EHV

apparatus and the connections to all external circuits at a Connection

Point incorporating its numbering nomenclature and labelling.

149

Site Common Drawing

Drawing prepared for each connection point which incorporates layout

drawings, electrical layout drawings, common protection/control drawings

and common service drawings

150

Southern Region / Region

means region comprising States and Union Territory of Tamil Nadu,

Andhra Pradesh, Kerala, Karnataka, Telangana and Pondichery for

the integrated operation of the electricity system.

151

SRLDC

means Southern Regional Load Despatch Centre.

152

SRPC

means Southern Regional Power Committee.

153

State

means the State of Tamil Nadu.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

63

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

154

State Entity

means such person who is in the SLDC control area and whose

metering and energy accounting is done at the State level.

155

State Load Despatch Centre

(SLDC)

State Sub Load Centre

(SSLDC)

means the load despatch centre established under section 31 (1)

the Act, operating round the clock for the purpose of managing the

operation of the transmission system and co-ordination of generation

and drawal on a real time basis.

means State’s Sub Load Centre for local control at various places

in Tamil Nadu

156

State Power Committee

means Committee set up under TNERC (Deviation Settlement Mechanism

and related matters) Regulations, 2019 and TNERC (Forecasting,

Scheduling and Deviation Settlement and related matters for wind

and solar generation) Regulations, 2024.

157

State Sector Generating

Station (SSGS)

Means power station within the, except Inter-State Generating Stations

(ISGS) and Independent Power Producer generating stations (IPPs)/

Captive Generating Plant (CGP)/REGS located within the State of

Tamil Nadu in which State has its share.

158

State Transmission System

(STS)

means the system of EHV electric lines (66 kV and above voltage

level) and electrical equipment operated and/or maintained by STU or

any Transmission Licensee for the purpose of transmission of electricity

between Power Stations, External Inter-connections, Distribution Systems

and other users connected to it.

159

State Transmission Utility

(STU)

means the Board or Government Company specified as such by the

State Government under sub-section (1) of section 39 of the Act.

160

Static VAR Compensator

(SVC)

An electrical facility designed for the purpose of generating or absorbing

reactive power.

161

Sub-LDC

means the Load Despatch Centres set up at Chennai, Madurai and

Erode or other places of Tamil Nadu.

162

Supervisory Control and Data

Acquisition (SCADA)

means the combination of transducers, RTU, communication links and

data processing systems, which provides information to SLDC on the

operational state of the State Transmission System.

163

Synchronised

means the condition where an incoming Generating Unit or System

is connected to another System so that the voltage, frequencies and

phase relationships of that Generating Unit or System, as the case

may be, and the System to which it is connected are identical and

the terms “Synchronise” and “Synchronisation” shall be construed

accordingly.

164

System Constraint

means a situation in which there is a need to prepare and activate

a remedial action in order to respect operational security limits.

165

Supply

“Supply” in relation to electricity, means the sale of electricity to a

licensee or consumer.

166

Tertiary Reserve

means the quantum of power, which can be activated in order to

take care of contingencies and to cater to the need for replacing

secondary reserves.

167

Time Block

means block of duration as specified by the Commission for which

energy meters record values of specified electrical parameters with

first time block starting at 0:00 Hours, presently of fifteen (15) minutes

duration.

168

TANTRANSCO

means Tamil Nadu Transmission Corporation Limited

169

TNGECL

means Tamil Nadu Green Energy Corporation Limited.

170

TNPDCL

means Tamil Nadu Power Distribution Corporation Limited.

171

TNPGCL

means Tamil Nadu Power Generation Corporation Limited.

TAMIL NADU GOVERNMENT GAZETTE

64

[Part   VI—Sec. 2

Sl.

No.

Defined Term

Definition

(1)

(2)

(3)

172

Total Transfer Capability (TTC)

means the amount of electric power that can be transferred reliably

over the inter-control area transmission system under a given set of

operating conditions considering the effect of occurrence of the worst

credible contingency.

173

Transmission Licence

means the Licence granted to Transmission Utility by the Commission

under Section 14 of the Act.

174

Transmission Planning Criteria

means the criteria issued by CEA for transmission system planning.

175

Transmission Reliability Margin

(TRM)

means the amount of margin earmarked in the total transfer capability

to ensure that the inter-connected transmission network is secure under

a reasonable range of uncertainties in system conditions.

176

Transmission Service

Agreement (TSA)

means the agreement, contract, memorandum of understanding, or

any such covenants, entered into between the transmission Licensee

and the user of the transmission service/line.

177

Transmission System

The system of EHT electric lines and electrical equipment owned

and / or operated by the STU and other transmission licensees, for

the purpose of the transmission of electricity between power stations,

external interconnections and the distribution system.

178

Trial Operation or Trial Run

shall have the same meaning as specified in this Grid Code, as

applicable.

179

User

means and includes generating company, captive generating plant, energy

storage system, Transmission Licensee including deemed Transmission

Licensee, Distribution Licensee including deemed Distribution Licensee,

solar park developer, wind park developer, wind-solar photo voltaic

hybrid system or bulk consumer which is or whose electrical plant is

connected to the grid at voltage level of 33 kV and above and open

access customer who uses the State Transmission System and who

must comply with the provisions of the Grid Code.

180

Utility

“Utility” means the electrical lines or electrical plant and includes all

lands, buildings, works and materials attached thereto belonging to

any person acting as a generating company or licensee under the

provisions of the Act.

181

Warm Start

means the start up after a shutdown period between 10 hours and

72 hours (turbine metal temperatures between approximately 40% to

80% of their full load values) in relation to steam turbine.

182

WS Seller

means a seller in case of a generating station based on wind or

solar or hybrid of wind-solar resources.

Note:-

(1) Words and expressions used in this Grid Code, that are not defined herein but defined in the Act or

other Regulations of the Commission shall have the meaning as assigned to them under the Act or the said

Regulations of the Commission.

(2) Reference to any Acts, Rules and Regulations shall include amendments or consolidation or re-enactment

thereof.

(3) In case of discrepancy between the Tamil and English version of this Grid Code, the English version

shall prevail. The Commission’s decision shall be final and binding in any dispute arising in this regard.

Chapter 3 - General

3.1. Objectives: The objective of this Code is to define the services rendered by each wing in the overall

electric system and also for identifying the responsibilities and performance factors and measurement points for

each one of them. Further, it facilitates intra-state transmission and Open Access of electricity, with a focus on

the operation, maintenance, development and planning of the Tamil Nadu State Electricity Grid. This Code brings

out a single set of technical requirements encompassing all the Generators, Licensees, and State Transmission

Utility connected to or related to or using the Intra State Transmission System and provides the following:

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

65

a.

To provide clarity and certainty to STU, Distribution Licensee(s), Generating Companies operating

within the State of Tamil Nadu and any Open Access customers connected to Intra-State Transmission System/

distribution system by stating their respective roles, responsibilities and obligations.

b.

The documentation of the principles and procedures, which define the relationship between various

users of the Intra State Transmission System and State Load Despatch Centre as well.

c.

Responsibilities and obligation with respect to the operation of the State Transmission System (STS)

d.

Suitable measures for connectivity with the Grid for all generating plants.

e.

The standards with reference to quality, continuity and reliability of service for compliance by the

Licensees.

f.

Planning of the State Electricity Grid and making arrangements for its operation, maintenance,

development and expansion.

g.

Operation of Grid under normal, abnormal and emergency conditions.

h.

To indicate how generation is to be scheduled and despatched.

i.

Procedures for black start, fast restart, restoration of supply after major disturbances.

j.

Penalty for the non-compliance of this Grid Code, Grid Standards and the lawful directions of SRLDC

and SLDC.

k.

Facilitation for beneficial trading of electricity by defining a common basis of operation of the Intra

State Transmission System and Distribution System applicable to all the users of the system.

l.

To ensure economy and efficiency in the operation of the power system in the State.

m.

To achieve compliance with the Grid Standards and other relevant Standards, Codes, Regulations

and directions of SLDC by every licensee and others involved in the operation of the power system.

3.2. Structure of the Tamil Nadu Electricity Grid Code:

The Code is structured in distinct chapters as follows:

a) Functional responsibilities of entities connected with the State Grid

b) Management of Grid Code and various Committees

c) Resource Adequacy and System Planning

d) Grid Connectivity conditions

e) Requirement in Grid Operation

f) Scheduling and Despatch

g) Commercial issues and Implementation

h) Non Compliance

i) Metering

j) Cyber Security

k) Data Registration

3.3. General Requirements: The Grid Code contains procedures to permit equitable management of day

to day technical situations in the Electricity Supply System, taking into account a wide range of operational

situations and requirements likely to be encountered under both normal and abnormal conditions. It is nevertheless

necessary to recognize that the Grid Code cannot predict and address all possible operational situations. Users

must therefore understand and accept that, in such unforeseen circumstances, the State Load Despatch Centre

(SLDC) / State Transmission Utility (STU) who has to play a key role in the implementation of the Grid Code

may be required to act decisively for maintaining the Grid regimes for discharging its obligations. Users shall

provide such reasonable co-operation and assistance as the SLDC / STU may request in such circumstances.

TAMIL NADU GOVERNMENT GAZETTE

66

[Part   VI—Sec. 2

3.4. Application of other Codes etc.,

(a) Notwithstanding anything contained herein in the matters concerning intra-state transmission, the provision

of IEGC shall prevail, in case of inconsistency between the IEGC and this Code.

(b) This code shall be read along with the Tamil Nadu Electricity Supply Code, Tamil Nadu Electricity

Distribution Code, Open Access Regulations, Regulations on Deviation Settlement Mechanism and other relevant

provisions of the Act, along with amendments thereon, rules and regulations made thereunder.

(c) Where any of the provisions of this Code is found to be inconsistent with those of the Act, rules or

regulations made there under, notwithstanding such inconsistency, the remaining provisions of this Code shall

remain operative.

(d) Where any dispute arises as to the application or interpretation of any provisions of this Code, it shall

be referred to the Commission whose decision shall be final and binding on the parties concerned.

(e) Wherever extracts of the Electricity Act, 2003, are reproduced, any changes / amendments to the original

Act shall automatically be deemed to be effective under this Code also.

3.5. Code Responsibilities

(a) In discharging its duties under the Grid Code, STU has to rely on information provided by Users / SLDC /

SSLDC regarding their requirements and intentions.

(b) STU shall not be held responsible for any consequences that arise from its reasonable and prudent

actions on the basis of such information.

3.6. Confidentiality

(a) Under the terms of the Grid Code, STU/SLDC will receive information from Users relating to their

intentions in respect of their Generation or Supply businesses.

(b) STU/SLDC shall not, other than as required by the Grid Code, disclose such information to any other

person without the prior written consent of the provider of the information.

3.7. Dispute Settlement Procedures

(a) In the event of any dispute regarding interpretation of any part of the Grid Code provision between any

Users and STU, the matter may be referred to the Commission for its decision. The Commission’s decision shall

be final and binding on all the parties.

(b) In the event of any conflict between any provision of the Grid Code and any contract or agreement

between STU and Users, the provision of the Grid Code shall prevail.

3.8. Communication between STU and Users

(a) All communications between STU and Users shall be in accordance with the provision of the relevant

chapter of the Grid Code and shall be made with the designated nodal officer, appointed by STU.

(b) Unless otherwise specifically required by the Grid Code, all communications shall be in writing, save

where operational timescales require oral communication. Such oral communications shall be confirmed in writing

as soon as practicable.

(c) The voice shall be recorded at SLDC and such record shall be preserved for a reasonable time.

Chapter 4 -Functional Responsibilities of entities connected with the State Grid

4.1. State Transmission Utility

(a) Responsible to undertake transmission of electricity through Intra State Transmission System.

(b) STU shall discharge all functions of planning and coordination relating to intra state transmission

system with

i. Central transmission utility

ii. State Government

iii. Generating Stations

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

67

iv. Regional Power Committee

v. Central Electricity Authority

vi. All Licensees

vii. Any other person notified by the State Government in this behalf

(c) Ensure development of an efficient, coordinated and economical system of Intra-state transmission

lines for smooth flow of electricity from a generating station to the load centers. All the planning works, viz., long

term as well as short term shall be the responsibility of STU only.

(d) Provide non-discriminatory open access to its transmission system for use by

i. any licensee or generating company on payment of the transmission charges or;

ii. any consumer as and when open access is provided by the Commission under subsection(2) of

section 42 of the Act, on payment of the transmission charges and a surcharge thereon as may be specified by

the commission.

iii. be a nodal agency for all long term / medium term open access customers (except when both

injection and drawal points are in distribution system).

(e) The STU shall ensure the power evacuation of the generating stations, for supply to the entities

engaged in distributing electricity and to OA consumers, exchange of power among entities, exchange of power

through inter-connection with CTU.

(f) STU shall be responsible for managing and enforcing the State Grid Code.

(g) STU shall not engage in the business of trading of electricity.

(h) The STU shall also hold meetings with the Users to discuss individual requirements and with the

group of Users for preparing proposals for SPC meeting.

4.2. State Load Despatch Centre (SLDC)

(a) The SLDC shall exercise the powers and discharge the functions as prescribed under sub section (1) of

section 31 of the Act. The SLDC shall be operated by a Government Company, or any Authority or Corporation

established by the State Government, until such company, or Authority, or Corporation is notified by the State

Government, the State Transmission Utility shall operate the State Load Despatch Centre. The SLDC shall be

the apex body to ensure integrated operation of the power system in a State. The SLDC shall:

i. be responsible for optimum scheduling and despatch of electricity within the State, in accordance with

the contracts entered into with the licensees or the generating companies operating in the State.

ii. monitor Grid operation on real time;

iii. keep accounts of the quantity of electricity transmitted through the State Grid and responsible for

data arrangement to help in decision making;

iv. exercise supervision and control over the intra state transmission system and operation of power

plants;

v. be responsible for carrying out real time operations for Grid control and despatch electricity within the

State through secure and economic operation of the State Grid in accordance with the Grid standards and this

Code.

vi. not engage in the business of trading in Electricity.

vii. Certification of Availability of Intra-State Generating Stations and Intra-State Transmission Systems as

and when requested by the utilities.

(b) The SLDC may levy and collect such fee and charges from the generating companies and licensees

engaged in intra state transmission of electricity as may be specified by the commission.

(c) SLDC may give such directions and exercise such supervision and control as may be required for

ensuring the integrated Grid operation and for achieving the maximum economy and efficiency in the operation

of the power system. Every licensee, generating company, generating station, substation and any other person

connected with the operation of the power system shall comply with the direction issued by the SLDC.

TAMIL NADU GOVERNMENT GAZETTE

68

[Part   VI—Sec. 2

(d) State Load Despatch Centre shall discharge the functions assigned to it under the provisions of the Act

and Grid Code in an independent and unbiased manner.

Provided that in event of a State Load Despatch Centre being operated by the State Transmission Utility, as

per first proviso of sub-section (2) of Section 31 of the Act, adequate autonomy shall be provided to the State Load

Despatch Centre to discharge its functions in accordance with the provisions of Tamil Nadu Electricity Grid Code.

(e) The monitoring agency for users shall be the SLDC. The monitoring agency shall track the progress

of compliances of users, and exceptional reporting for non-compliance shall be submitted to the Commission

periodically.

4.3. Transmission Licensees

Every Transmission Licensee shall comply with such technical standards of operation and maintenance of

transmission lines, in accordance with this Code, Grid Standards, as may be specified by the Authority and the

Indian Electricity Grid Code as applicable to the Intra State Transmission System. It shall be the duty of the

transmission licensee

i.

to maintain and operate the transmission system which are licensed to him in the intra state transmission

system and comply with the directions of SRLDC and SLDC as the case may be

ii. provide non-discriminatory open access to its transmission system for use by any licensee or generating

company or other users on payment of the charges as determined by the Commission.

4.4. Tamil Nadu Electricity Regulatory Commission (TNERC)

The functions of TNERC with relevance to TNEGC are:

i. To determine the rate, charges and terms for the use of the transmission facilities of Licensees and

for other statutory purposes and requirements;

ii. To specify the fees and charges payable to SLDC;

iii. To issue directions on matters of non-compliance of TNEGC or to take decisions on any dispute

referred to them;

iv. To issue transmission licenses;

v. To adopt the transmission tariffs for the transmission assets determined through Tariff-Based Competitive

Bidding (TBCB) and Transmission asset monetization in line with the Commission’s Order / Regulations, MoP’s

guidelines, etc. issued from time to time.

vi. To issue amendments to the TNEGC as and when required.

4.5. Government of Tamil Nadu (GoTN)

Government may issue directions to SLDC, to take measures as may be necessary for maintaining smooth

and stable transmission and supply of electricity. SLDC shall abide by such directions if they are consistent with

the provisions of the Act and this Code.

4.6. State Power Committee (SPC)

The following are the primary responsibilities of SPC:

i.

SPC shall issue guidelines for implementation of TNEGC.

ii.

Facilitating the implementation of the rules and procedures developed under the provisions of TNEGC.

iii.

Assessing and recommending the remedial measures for issues that might arise during the course

of implementation of provisions of these regulations, and the rules and procedures developed under the provisions

of TNEGC.

iv.

To undertake regular review of TNEGC and to make suitable recommendations after considering the

Users’ suggestions.

v.

To undertake State level operation analysis for improving grid performance

vi.

To facilitate Intra-State transmission of power.

vii. To facilitate all functions of planning relating to Intra-State transmission system with STU.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

69

viii. To undertake operational planning studies including protection studies for stable operation of the

grid.

ix.

To maintain a centralised database and update the same on a periodic basis containing details of

protection relay setting for various grid elements.

x.

Review the cyber security provisions in the grid.

xi.

To analyse major Grid Disturbances, soon after the occurrence, and to suggest remedial measures

and issue suitable directives to the Users.

xii. To approve load shedding guidelines through under frequency relays.

xiii. In case of open access power and duties as defined in Tamil Nadu Electricity Regulatory Commission

(Grid Connectivity and Intra State Open Access) Regulations, 2014, as amended from time to time.

xiv. Duties assigned under TNERC (Deviation Settlement Mechanism and related matters) Regulations,

2019 and TNERC (Forecasting, Scheduling and Deviation Settlement and related matters for wind and solar

generation) Regulations, 2024.

xv. Any other function as may be directed by the Commission from time to time.

Chapter 5 – Management of State Grid Code

5.1. Management of Grid Code and various Committees

(a) STU is required to implement and comply with the Grid Code and periodically review the same and

its implementation. For the above purpose, a Grid Code Review Committee as per Regulation 5.4 of the Grid

Code, shall be established.

(b) All revisions in the Grid Code shall be proposed by majority votes in the meeting of Grid Code Review

Committee. In the event of equality of votes on proposal, the matter shall be referred to the Commission for

decision. All revision in the Grid Code made by the Grid Code Review Committee shall also be submitted to the

Commission for approval.

(c) The changes/revisions proposed by the Grid Code Review Committee shall be consistent/ compatible

with IEGC and amendments thereof. The Commission may issue directives requiring STU to submit proposal for

revision in the Grid Code and STU shall forthwith comply with such directives within timelines contained therein.

STU shall be responsible for managing and enforcing the State Grid Code. STU shall establish and service the

requirements of the Grid Code Review Committee in accordance with the provisions of Regulation 5.4 of the

Grid Code.

5.2. Grid Code Review Committee

(a) The Commission shall approve the constitution of Grid Code Review Committee through separate order

on receipt of proposal from the SLDC within 30 days from the date of issue of this Code.

(b) STU shall inform all Users in writing, the name and address of the Chairman and Members of the Grid

Code Review Committee within fifteen (15) days of the constitution of the Grid Code Review Committee and any

subsequent changes thereafter.

(c) The Committee, containing of not more than 12 members, shall inter-alia include members from the

various types of generating stations, Transmission Licensee, STU, SLDC and Distribution Licensee.

5.3. Grid Code Review Committee Proceedings

(a) Member Secretary of the Grid Code Review Committee shall be responsible for arranging the meetings

in a timely manner. The procedure to be followed by the Committee in conducting its business shall be formulated

by the Committee and shall be approved by the Commission. The Committee shall meet at least once in a year.

(b) The functions of the Grid Code Review Committee are as follows:

i.

To keep the Grid Code and its implementation under scrutiny and review.

ii.

To propose any revision, if necessary, in the Grid Code consequent of analysis report on major grid

disturbance soon after its occurrence. The recommendations of the Committee may be submitted to Commission

for approval and issuing directives to the Users for taking necessary remedial measures, as may be deemed fit,

to prevent recurrence.

TAMIL NADU GOVERNMENT GAZETTE

70

[Part   VI—Sec. 2

iii.

To consider all requests for amendment to the Grid Code, which any User makes and take action

as per this Code, if found appropriate after consideration.

iv.

To issue guidance on the interpretation and implementation of the Grid Code.

v.

To examine problems/ issues raised by Users.

(c) STU may schedule a meeting with a User or group of Users to discuss the issues in implementation

of this Grid Code and prepare proposals for the Grid Code Review Committee meeting.

(d) If the Committee considers it necessary to discuss any special issue with the Commission, the Committee

may send an appropriate proposal to the Commission along with a copy of Minutes of Meeting (MoM) wherein

the issue was identified. The Commission may take up the issue for consideration in a manner as deemed fit

by the Commission.

5.4. Grid Code Review and Revisions

(i)

Any written request seeking review/modification/amendment of the Grid Code shall be sent to STU. If

the request is sent directly to the Commission, the same shall be forwarded to STU.

(ii)

The Member Secretary of the Committee shall present all proposals for revision of the Grid Code before

the Grid Code Review Committee for its consideration.

(iii) Member Secretary of the Committee shall send to the Commission, the following reports at the conclusion

of each review meeting of the Committee:

i.

A report on the outcome of such review meeting;

ii.

Any proposed revisions to the Grid Code as STU reasonably thinks necessary for the achievement

of the objectives of this Code;

iii.

All written representations or objections from Users arising during the review/consultation process.

(iv) All revisions in the Grid Code shall be made by the Commission.

(v) STU shall convey to all the Users, revisions in the Grid Code after amendment by the Commission.

(vi) STU shall make available a copy of the respective parts of Grid Code in force to any person requesting

it on payment of cost thereof.

(vii) The Commission shall reserve the right to review the Grid Code as and when required.

5.5. Functional Committees

(a) The STU shall be responsible for implementation of Grid Code whereas, the Grid Code Review

Committee shall be responsible for management of Grid Code and for proposing any changes or modifications

in the Grid Code. The STU shall submit the proposal before the Commission for constitution of the following

functional committees and other committees as deemed fit for implementation of the Grid Code within a month

of the publication of this Code:

a)

Load Despatch & System Operation

Code

Operation and Co-ordination Committee (OCC)

b)

Protection Code

Protection Co-ordination Committee (PCC)

c)

Transmission Metering Code

Transmission Metering Committee (TMC)

(b) The Commission shall approve the constitution of Functional Committees through separate order.

(c) The SLDC in coordination with the above committees and stakeholders consultation shall frame the

Codes for Load Despatch & system operation, Protection and Transmission metering within 30 days from the

date of appointment of the Committee concerned and the same shall be submitted within seven days to the

Commission for approval. The Codes shall be consistent with the TNEGC/IEGC/CEA (Installation & Operation of

meters) Regulations, 2019 as amended from time to time.

5.6. Operation and Co-ordination Committee (OCC)

(a) Operation and Co-ordination Committee (OCC) shall deliberate on all technical and operational aspects

of this Grid Code except Protection and Metering Code.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

71

(b) The Committee shall meet at least once in two months.

(c) The procedure to be followed by the Operation and Co-ordination Committee in conducting their business

shall be formulated by the respective Committee and shall be approved by the Grid Code Review Committee.

(d) Operation and Co-ordination Committee (OCC) shall conduct the following functions:

i.

Review of existing inter-connection and equipment for alteration, if necessary, so as to comply with

the Connection Code.

ii.

Deliberation on connectivity criterion for voltage imbalance as specified in the Commission’s Regulations

and amendments thereof and taking remedial measures for cases failing to meet such criterion.

iii.

Review the load management through under frequency, time differential (df/dt) relays and Advanced

Distribution Management System (ADMS) etc.

iv.

Transmission system planning coordination for the State as a whole.

v.

Issues related to energy accounting and scheduling of intra-State energy.

vi.

To discuss and resolve issues pertaining to availability of real time data through Supervisory Control

and Data Acquisition (SCADA).

vii. Review the voice communication facility among SLDC and Users.

viii. Review and analyse the grid disturbances and system restoration procedure.

ix.

Review and finalize Outage Plan of State Transmission System.

x.

Review the installation of Disturbance Recorders, Event Loggers in the State Transmission System.

xi.

Review and study the implementation of free governing / restricted governing mode for all eligible

generating stations.

xii. Review the Licensee’s sub-station equipment failure and replacement of the same within the stipulated

timeframe

xiii. Review the adequacy of manpower for operation and maintenance of the Sub-Station, Lines, etc.

xiv. Any other matter related to technical and operational parameters.

5.7. Protection Co-ordination Committee (PCC)

(a) Protection Co-ordination Committee (PCC) shall ensure implementation of Protection Code by the Users

and discharge their obligations under the Protection Code.

(b) The Committee shall meet at least once in three (3) months.

(c) The procedure to be followed by the Protection Co-ordination Committee in conducting their business

shall be formulated by the respective Committee and shall be approved by the Grid Code Review Committee.

Protection Co-ordination Committee (PCC) shall conduct the following functions:

i.

To keep Protection Code and its implementation under scrutiny and review.

ii.

To consider all the requests for amendment to the Protection Code made by users.

iii.

To issue guidance on the interpretation and implementation of the Protection Code

iv.

Any other matter related to coordination amongst Users in relation to protection and relays.

5.8. Transmission Metering Committee (TMC)

(a) Transmission Metering Committee (TMC) shall ensure implementation of metering system by the Users

and discharge their obligations as per the CEA Metering Regulations and the amendments issued from time to

time and the Commission’s Regulations/Codes/Orders.

(b) The Committee shall meet at least once in three (3) months.

(c) The procedure to be followed by the Transmission Metering Committee in conducting their business

shall be formulated by the respective Committee and shall be approved by the Grid Code Review Committee.

Transmission Metering Committee (TMC) shall conduct the following functions:

TAMIL NADU GOVERNMENT GAZETTE

72

[Part   VI—Sec. 2

i.

To keep Metering system and its working under scrutiny and review.

ii.

To consider all the requests for change/modification to the Metering system, which any user makes.

iii.

To issue guidance on the interpretation and implementation of the CEA Metering Regulations and

the amendments issued from time to time and the Commission’s Regulations/Codes/Orders.

iv.

Review the installation of interface meters already installed at the Generator end and give corrective

steps/suggestive measures in line with the CEA Regulations.

v.

Any other matter related to coordination amongst Users in relation to metering.

5.9. Monitoring of Compliance

(a) State Transmission Utility and State Load Despatch Centre shall be responsible for monitoring the

compliance of Users and State Transmission Licensees with the provisions, contained in the Tamil Nadu Electricity

Grid Code and with the procedures developed under such provisions:

Provided that the State Transmission Utility and/ or State Load Despatch Centre shall not unduly discriminate

against or unduly prefer any User or Transmission Licensee.

(b) If any User fails to comply with any of the provision(s) of the Grid Code, it shall be required to inform

STU without any delay, the reason for its non-compliance and shall remove its non- compliance promptly.

(c) Wrong declaration of capacity, non-compliance of SLDC’s instructions, non-compliance of SLDC’s instructions

for backing down without adequate reasons, non-furnishing data, non-payment of charges such as Deviation

settlement charges, scheduling and system operation charges, Open Access charges, etc. shall constitute non-

compliance of Grid Code and shall be subject to financial penalty as may be decided by the Commission.

(d) In case of persistent non-compliance of the provisions of the Grid Code and/ or with the procedures

developed under such provisions, such matter shall be reported to the Commission by SLDC. Consistent failure

to comply with the Grid Code may lead to disconnection of the User’s plant and/or facilities.

(e) State Load Despatch Centre may give such directions and exercise such supervision and control as may

be required for ensuring the integrated grid operations and for achieving the maximum economy and efficiency in

the operation of power system in the State.

(f)

Every Transmission Licensee and User connected with the operation of the power system shall comply

with the directions issued by the State Load Despatch Centre.

(g) If any dispute arises with reference to the quality of electricity or safe, secure and integrated operation

of the State grid or in relation to any direction given under the provisions of the Tamil Nadu Electricity Grid Code,

it shall be referred to the Commission by SLDC for decision:

Provided that till the time the decision of the Commission is pending, the direction of the State Load Despatch

Centre shall be complied with by the Transmission Licensee or User.

(h) If any Transmission Licensee or any User fails to comply with the directions issued under the Grid Code,

he shall be liable to penalty not exceeding Rs. five (5) Lakh.

(i)

The Commission may order independent third-party compliance audit for any User, as deemed necessary

based on the facts brought to the knowledge of the Commission.

Chapter 6 - Resource Adequacy and System Planning

6.1. Resource Adequacy

The planning of generation and transmission resources shall be to meet the projected demand in compliance

with specified reliability standards for serving the load with optimum generation mix with a focus on integration

of environmental friendly technologies after taking into account the need, inter alia, for flexible resources, storage

systems for energy shift and demand response measures for managing the intermittency and variability of renewable

energy sources.

6.2. Integrated Resource Planning

The integrated resource planning shall include:

(a) Demand forecasting;

(b) Generation resource adequacy planning; and

(c) Transmission resource adequacy planning.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

73

6.3. Demand Forecasting and Generation Resource Adequacy Planning

(a) The provisions related to demand assessment and forecasting and Generation Resource Adequacy

Planning shall be governed by the provisions of the Guidelines for Resource Adequacy Planning Framework for

India, 2022 published by the CEA as amended from time to time, TNERC (Framework for Resource Adequacy)

Regulations,2025 and Regulations/Orders/direction notified/issued by the Commission for Demand Forecasting and

Generation Resource Planning.

(b) In order to ensure optimum and least cost generation resource procurement planning, each distribution

licensee of the State or any agency on its behalf shall give due consideration to the factors such as its share

in the State, regional and national coincident peak, seasonal requirement and possibility of sharing generation

capacity seasonally with other States.

6.4. Transmission resource adequacy planning

(a) STU shall undertake assessment and planning of the Intra-State transmission system as per the provisions

of the Act and shall inter alia take into account:

(i)

Import and export capability across ISTS and STU interface; and

(ii)

Adequate power transfer capability across the Intra-State Transmission System.

(b) The STU shall be responsible for overall planning of STS and shall prepare a perspective rolling

transmission system plan for –

(i)

Short term period i.e. up to 5 years;

(ii)

Medium term period i.e. up to 10 years;

(iii) Long term period i.e. up to 15 years.

Provided that the transmission system plans shall be updated every year to accommodate the revisions in

the load projections and generation capacity additions:

Provided further that State Transmission Utility shall publish on its website the short term transmission system

plans along with updations, if any for STS, by 30th September for each year. The STU shall publish its current

ongoing InSTS plan in its website.

Provided also that such transmission system plans shall also make available to any person upon request.

6.5. System Planning

(a) The System Planning specifies the procedure to be applied by STU in the planning and development

of the State Transmission System and also specifies the method for data submissions by Users to STU for

development of Intra-State Transmission System. The provisions of System Planning are intended to enable STU

to produce a plan in consultation with Users, to provide an efficient, coordinated, secure and economical State

Transmission System to satisfy requirement of future demand.

(b) In accordance with Section 39(2)(b) of the Act, STU shall discharge all functions of planning and

coordination relating to intra-State transmission system with Central Transmission Utility, State Governments,

Generating Companies, Regional Power Committees, Central Electricity Authority (CEA), Licensees and any other

person notified by the State Government in this behalf.

(c) In accordance with Section 39(2)(d) of the Act, STU shall inter-alia provide non-discriminatory open

access to its transmission system for use by:

i.

any Licensee or generating company on payment of the transmission charges; or

ii.

any consumer as and when such open access is provided by the State Commission under sub-

section (2) of Section 42 of the Act, on payment of the transmission charges and a surcharge thereon, as may

be specified by the State Commission.

(d) In accordance with Section 40(c) of the Act, the Transmission Licensee shall inter-alia provide non-

discriminatory open access to its transmission system for use by:

i.

any Licensee or generating company on payment of the transmission charges; or

ii.

any consumer as and when such open access is provided by the State Commission under sub-

section (2) of Section 42 of the Act, on payment of the transmission charges and a surcharge thereon, as may

be specified by the State Commission.

TAMIL NADU GOVERNMENT GAZETTE

74

[Part   VI—Sec. 2

(e) A requirement for reinforcement or extension of the State Transmission System may arise for a number

of reasons, including but not limited to the following:

(i)

Development on a User’s system already connected to the State Transmission System.

(ii)

The introduction of a new Connection point between the User’s system and the State Transmission

System.

(iii) Evacuation system for Generating Stations within or outside the State.

(iv) Reactive Compensation.

(v) A general increase in system capacity (due to addition of generation or system load) to remove

operating constraints and maintain standards of security.

(vi) Transient or steady state stability considerations.

(vii) Cumulative effect of any of the above.

(f)

Accordingly, the reinforcement or extension of the State Transmission System may involve work at an

entry or exit point (Connection point) of a User to the State Transmission System. Since development of all

User’s systems must be planned well in advance to permit consents and way leaves to be obtained and detailed

engineering design/construction work to be completed, STU will require information from Users and vice versa.

To this effect, the Planning Code imposes time scale, for exchange of necessary information between STU and

Users, wherever appropriate, to the confidentiality of such information.

(g) The System Planning Code provides the following:

i.

Defines the procedure for the exchange of information between STU and User in respect of any

proposed User development on the User’s system, which may have an impact on the performance of the User.

ii.

Details the information which STU shall make available to Users in order to facilitate the identification

and evaluation of opportunities for use or connection to State Transmission System.

iii.

Details the information required by STU from Users to enable STU to plan the development of its

Transmission System to facilitate proposed User developments.

iv.

Specifies planning and design standards, which will be applied by STU in planning and development

of the power system.

6.6. Planning Policy

(a) STU would develop a perspective transmission plan for next ten (10) years on annual rolling basis for

Intra-State Transmission System. The perspective transmission plan would be updated every year to take care

of the revisions in load projections and generation capacity additions. The perspective plan shall be submitted to

the Commission for approval.

(b) STU shall carry out annual planning process corresponding to a five (5) year forward term for identification

of major State Transmission System, which shall fit into National Power Plan formulated by Central Government

long-term plan developed by CEA and the five (5) year plan prepared by Central Transmission Utility.

(c) STU shall follow the following steps in planning:

(i)

Based on the provisions of Resource Planning Code, Distribution Licensees shall provide the details

of the Demand forecasting, Generation resource adequacy planning data, methodology and assumptions on which

the forecasts are based, to the Commission and STU. These forecasts would be annually reviewed and updated

by Distribution Licensees.

(ii)

STU shall prepare a transmission plan for the State Transmission System compatible with this

Regulation of the Grid Code including provision for VAR compensation needed in the State Transmission System.

(iii) The reactive power planning exercise shall be carried out by STU in consultation with SRLDC/

SRPC/SLDC/Distribution Licensees for installation of reactive compensation equipments.

(iv) Special attention shall be accorded by STU towards planning of capacitors, reactors, Static Volt Ampere

Reactive Compensator (SVC), Static Volt Ampere Reactive Generator (SVG) and Flexible Alternating Current

Transmission Systems (FACTS) and any other equipment, which is typically used to regulate and control the

voltage within the specified limits.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

75

(v) STU’s planning department shall use load flow, short circuit and transient stability study, relay coordination

study and other techniques for transmission system planning.

(vi) STU’s planning department shall simulate the contingency and system constraint conditions for the system

for transmission system planning.

(vii) The planning criteria shall be as per CEA Manual on Transmission Planning Criteria (Appendix-F) and

amendment thereof.

(d) All the Users shall supply to STU, the desired planning data by 31stMay every year to enable STU to

formulate and finalise the plan by 30thSeptember each year for the next five (5) years.

6.7. Planning Responsibility

(a) The primary responsibility of demand forecasting within Distribution Licensees’ area of supply rests with

the Distribution Licensees. The Distribution Licensees shall determine their peak demand and energy forecasts

for each category for each of the succeeding five (5) years and submit the same annually by 31stMay to STU

along with details of the Demand forecasting, Generation resource adequacy planning, data, methodology and

assumptions on which the forecasts are based along with their proposals for transmission system augmentation.

The demand forecasts shall be updated annually or whenever major changes are made in the existing forecasts

or planning.

(b) State Sector Generating Stations (SSGS) shall provide their generation capacity to STU for evacuating

power from their power stations for each of the succeeding five (5) years along with their proposals for transmission

system augmentation and submit the same annually by 31st March to STU.

(c) STU shall obtain Renewable Capacity Addition plan issued by the Tamil Nadu Green Energy Corporation.

(d) The Distribution Licensee shall provide details of Long-Term Access and Medium-Term Open Access

PPAs signed with ISGS/IPPs/REGS for the succeeding five years to STU annually by 31st May.

(e) The planning for strengthening the State Transmission System for evacuation of power from outside

State stations shall be initiated by STU.

(f)

Operation and Co-ordination Committee consisting of members from Distribution Licensee, STU, Transmission

Licensee, Tamil Nadu Green Energy Corporation and Tamil Nadu Power Generation Corporation shall review and

approve the demand forecasts and the methodology.

6.8. Planning Data

(a) To enable STU to conduct System Studies and prepare perspective plans for electricity demand, generation

and transmission, the Users shall furnish data to STU from time to time as detailed under Data Registration Code

as under:

i.

Standard Planning Data (Generation)/ Standard Planning Data (Distribution) (Appendix-A)

ii.

Detailed Planning Data (Generation)/ Detailed Planning Data (Distribution) (Appendix-B)

(b) To enable Users to co-ordinate planning, design and operation of their plants and systems with the State

Transmission System, they may seek certain salient data of Transmission System as applicable to them, which

STU shall supply from time to time as detailed under Data Registration Code and categorized as:

i.

Standard Planning Data (Transmission) (Appendix-A)

ii.

Detailed Planning Data (Transmission) (Appendix-B)

(c) STU shall also furnish to all the Users, Annual Transmission Planning Report, Power Map and any other

information as the Commission may prescribe.

6.9. Implementation of Transmission Plan

The actual programme for implementation of transmission plan will be determined by STU in consultation with

other Transmission Licensees wherever applicable. The STU/ Transmission Licensees shall ensure the completion

of these works in the required time frame.

TAMIL NADU GOVERNMENT GAZETTE

76

[Part   VI—Sec. 2

Chapter 7 – Grid Connectivity Conditions

7.1. Objective

The objective of this chapter is to ensure the following:

(a) All Users or prospective Users are treated equally.

(b) Any new Connection shall not impose any adverse effects on existing Users, nor shall a new

Connection suffer adversely due to existing Users.

(c) By specifying minimum design and operational criteria, to assist Users in their requirement to comply

with Licence obligations and hence, ensure that a system of acceptable quality is maintained.

(d) The ownership and responsibility for all items of equipment is clearly specified in a schedule (Site

Responsibility Schedule as Appendix-G of this Grid Code) for every site where a Connection is made.

7.2. Grid Connectivity

(a) This code specifies the technical, design and operational criteria for connectivity, procedure and requirements

for physical connection and integration of grid elements, which must be complied with by any User connected to

Intra-State Transmission System (InSTS).

(b) The connectivity to Intra-State Transmission System shall be granted by State Transmission Utility in

accordance with the Grid Code, Tamil Nadu Electricity Regulatory Commission (Grid Connectivity and Intra State

Open Access) Regulations, 2014 and other Regulations/Codes/Orders/Procedures issued by the Commission from

to time.

(c) The applicant who seeks connectivity with the Transmission system shall apply as per the Format

approved by the Commission in the detailed procedure for grant of connectivity to the intra-state transmission

system issued in accordance with the TNERC (Grid connectivity and Intra-State Open Access) Regulations, 2014.

The applicant shall apply for grid connectivity along with the enclosures as prescribed in the format including final

clearance / sanction from TNGECL/TNPDCL/TNPGCL and a compliance report for the generation project.

(d) STU and Users connected to or seeking connection to State Transmission System (STS) shall comply

with the following Act/Regulations and amendments issued from time to time:

i.

The Electricity Act, 2003 and amendments thereof;

ii.

Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006 and amendments

thereof;

iii.

Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 and

amendments thereof;

iv.

Central Electricity Authority (Grid Standards) Regulations, 2010 and amendments thereof;

v.

Central Electricity Authority (Technical Standards for Communication System in Power System

Operation) Regulations, 2020 and amendments thereof;

vi.

Central Electricity Authority (Cyber Security in Power Sector) Guidelines, 2021;

vii. Tamil Nadu Electricity Regulatory Commission (Grid Connectivity and Intra State Open Access)

Regulations, 2014 and amendments thereof;

viii. Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric

Lines) Regulations, 2022 and amendments thereof;

ix.

Central Electricity Authority (Measures Relating to Safety & Electric Supply) Regulations, 2023 and

amendments thereof;

x.

Central Electricity Authority (Flexible Operation of Coal based Thermal Power Generating Units)

Regulations, 2023 and amendments thereof;

xi.

All relevant Laws/Regulations/Guidelines/Rules/Standards with amendments as specified from time to

time shall be applicable for grant of connectivity.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

77

(e) This Code shall be applicable to generators (including CGPs/Renewable Energy Generating Stations (REGS)),

Energy Storage Systems, Distribution Licensees, Captive Users, Open Access Customers, Intra-State Transmission

Licensees, HT/EHT Consumers of Distribution Companies and all other Users of Intra-State Transmission System.

HT/EHT consumers seeking to avail power from State Distribution Companies shall however route their application

for connectivity through concerned Distribution Licensee.

(f) This Code shall apply to applications made for grant of connectivity to Intra-State Transmission System and

other connectivity related matters, received by STU. The STU shall be the Nodal Agency for grant of connectivity

to Intra-State Transmission System and all other matters connected therewith.

(g) The existing Users, already connected to the Intra-State Transmission System prior to issuance of this

Code shall not be required to make a fresh application for connectivity for the same capacity. However, in case

of any extension or modification of capacity of generating plant (including captive power plant), enhancement of

capacity/load by HT/EHT consumer of Distribution Licensee connected at voltage 33 kV and above and the HT/

EHT consumers of the Distribution Licensee desiring connectivity to higher voltage will be required to make fresh

application for connectivity.

(h) Any new Intra-State Transmission Licensee entering into business of Intra-State Transmission of Electricity

under Section 63 of the Act shall not be required to make an application for connectivity. STU shall connect

transmission system of such Intra-State Transmission Licensee with the existing Intra-State Transmission System as

per agreed terms and conditions stipulated in the bidding documents or the Licence granted by the Commission

and Transmission Service Agreement (TSA) signed by the parties.

(i) The procedure for obtaining connectivity to the intra-state transmission system and distribution system

shall be as per the detailed procedures issued by the Commission in this regard under Tamil Nadu Electricity

Regulatory Commission (Grid Connectivity and Intra State Open Access) Regulations, 2014.

7.3. Responsibilities for operational safety

(a) STU and Users shall be responsible for safety as indicated in Regulation 7 (Site Responsibility Schedule)

of CEA Technical Standards for Connectivity Regulations and amendment thereof.

(b) The format, principles and basic procedure to be used in the preparation of Site Responsibility Schedules

shall be formulated by STU and shall be provided to each User for compliance.

7.4. Single Line Diagrams

(a) Single Line Diagram (SLD) shall be furnished for each Connection Point by the connected User to STU/

SLDC/respective Intra-State Transmission Licensee. These diagrams shall include all HV connected equipment,

location of ABT meters and connections to all external circuits and incorporate numbering, nomenclature and

labelling, etc. The diagram is intended to provide an accurate record of the layout and circuit connections, rating,

numbering and nomenclature of HV apparatus and related plant.

(b) Whenever any equipment is proposed to be changed, then User/ or agency responsible for O&M shall

intimate the necessary changes to respective Intra-State Transmission Licensee and to all concerned.

(c) When the changes are implemented, changed Single Line Diagram (SLD) shall be circulated by User

or agency responsible for O&M to STU/SLDC/respective Intra-State Transmission Licensee.

7.5. Site Common Drawings

(a) Site Common Drawing shall be prepared for each Connection Point and will include site layout, electrical

layout, details of protection and common services drawings. Necessary details shall be provided by Users to STU.

(b) The detailed drawings for the portion of User and respective Intra-State Transmission Licensee at each

Connection Point shall be prepared individually and exchanged between User and respective Intra-State Transmission

Licensee.

(c) If any change in the drawing is found necessary, either by User or respective Intra-State Transmission

Licensee, the details will be exchanged between User and respective Intra-State Transmission Licensee, as soon

as possible.

7.6. System Performance

(a) All equipment connected to the State Transmission System shall be of such design and construction to

enable Intra-State Transmission Licensee to meet the requirements of the Standards of Performance. Distribution

Licensees shall ensure that their loads do not cause violation of these standards.

TAMIL NADU GOVERNMENT GAZETTE

78

[Part   VI—Sec. 2

(b) Any User seeking to establish new or modified arrangement(s) for Grid connection and/or use of

transmission system of STU shall submit the application in the form as may be prescribed by STU.

(c) For every new/modified Connection sought, STU shall specify the Connection Point, technical requirements

and the voltage to be used, along with the metering and protection requirements as specified in the Metering

and Protection Codes of this Grid Code.

(d) STU and SLDC shall jointly carry out a system study six (6) months before the expected date of first

energization of a new power system element to identify operational constraints, if any. In case of constraints,

STU and SLDC shall identify measures for facilitating the integration of the element, subject to grid security.

(e) State Generating Stations and IPPs (including CGPs) shall make available to STU/SLDC, the up-to-date

capability curves for all Generating Units, indicating any restrictions, to allow accurate system studies and effective

operation of the State Transmission System. CGPs shall similarly furnish the net reactive capability that will be

available for Export to/Import from Intra-State Transmission System.

(f) The frequency shall always remain within the band as specified in IEGC.

(g) The User shall however, be subject to the grid discipline of SLDC/SRLDC as per guidelines mutually

agreed with SRPC/SRLDC.

(h) The variation of voltage at the “inter-connection point” may not be more than the limit specified in

Regulation 12.6 of the Grid Code. Distribution Licensees and Open Access Users shall ensure that their loads

do not affect Intra-State Transmission System in terms of causing any:

i)

Imbalance in the phase angle and magnitude of voltage at the inter-connection point beyond the

limits specified by Transmission Performance Standards.

ii)

Harmonics in the system voltage at the inter-connection point beyond the limits specified in the

TNE Supply Code.

STU may direct Distribution Licensees to take appropriate measures to remedy the situation.

(i) In the event of Grid disturbances/ Grid contingencies in the Southern Regional grid, Transmission

Licensees of the State shall not be liable to maintain the system parameters within the normal range of voltage

and frequency.

(j) Insulation coordination of the User’s equipment shall conform to Indian Standards issued by Bureau

of Indian Standards (BIS). If BIS Standards are not available for a particular equipment or material, the standards

defined by STU from time to time shall be followed.

(k) Protection schemes and metering schemes shall be as detailed in the Protection and Metering

Codes of this Grid Code.

7.7. Equipment of Users/ State Transmission System at Connection Points

(a) Sub-station Equipment:

i)

All EHV sub-station equipment shall comply with Bureau of Indian Standards (BIS)/ International

Electro Technical Commission (IEC) Standards/prevailing Code of practice.

ii)

All equipment shall be designed, manufactured and tested and certified in accordance with the

quality assurance requirements as per IEC/BIS standards.

iii)

Each connection between User and STS shall be controlled by a circuit breaker capable of interrupting

at the connection point, the short circuit current as advised by STU in the specific Connection Agreement.

(b) Fault Clearance Time (basic step operation time, i.e., Zone 1 time):

(i)

The fault clearance time of the equipment directly connected to the Intra-State Transmission System

shall be as per the CEA Technical Standards for Construction Regulations and amendments thereof.

(ii)

Back-up protection shall be provided for required isolation/protection in the event of failure of the

primary protection system provided to meet the fault clearance time requirements as defined in Protection Code

of the Grid Code.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

79

(iii) If a Generating Unit is connected to Intra-State Transmission System directly, it shall withstand, until

clearing of the fault by back-up protection on Intra-State Transmission System.

All users connected to Intra-State Transmission System shall provide protection system as specified in

the Protection Code and this shall be made a part of the Connection Agreement.

(c) Generating Units and Power Stations

A Generating Unit shall be capable of continuously supplying its normal rated active/reactive output within the

system frequency and voltage variation range indicated in Chapter 12 of this Grid Code, subject to the design

limitations specified by the manufacturer. A generating unit shall be provided with protection as specified in the

Protection Code, which condition shall be made a part of the Connection Agreement.

(d) Reactive Power Compensation

Reactive Power compensation and/or other facilities should be provided by User of the State Transmission

System including the Distribution Licensee as far as possible close to the load points thereby avoiding the need

for exchange of Reactive Power to/from Intra-State Transmission System and to maintain voltage within the

specified range. Switched Shunt Reactors at 400 kV may be provided to control temporary over-voltage within

the limits and this shall be made a part of the Connection Agreement. The addition of reactive compensation to

be provided by the User shall be indicated by STU in the Connection Agreement for implementation.

(e) Communication Facilities

(i)

Reliable and efficient speech and data communication systems shall be provided in accordance with

CEA Technical Standards for Communication and CERC Communication System Regulations and amendments

thereof by all the users to facilitate necessary communication and data exchange, and supervision/control of the

grid by the SLDC, under normal and abnormal conditions.

(ii)

All Users and Intra-State Transmission Licensees shall provide parameters such as flow, voltage and

status of switches/ transformer taps, etc., in line with interface requirements and other guidelines made available

by SLDC.

(iii) All Users shall provide the required facilities at their respective ends and SLDC and this condition

shall be indicated in the Connection Agreement.

(iv) The associated communication system to facilitate data flow up to appropriate data collection point/

Wide Band node on STU system including inter-operability requirements shall also be established by the concerned

user as specified by STU in the Connectivity Agreement.

(v) The communication system along with data links provided for speech and real time data communication

shall be monitored in real time by all users, STU and SLDC to ensure high reliability of the communication links.

(vi) Unless otherwise agreed in Connection Agreement, the equipment for data transmission and

communication shall be operational and maintained by the user in whose premises they are installed, irrespective

of ownership.

(vii) If real time communication facility and data are not made available by the generators, the SLDC

after 15 days clear notice shall direct the Distribution Licensee to exclude the generator’s output by 10% from

Despatch and deviation settlement processes and if such generator has not made real time communication facility

even after the lapse of 30 days from the date of receipt of the notice issued by the SLDC, the entire output of

the generator shall be excluded from despatch and deviation settlement processes. If the generator has not made

real time communication facility even after the lapse of 45 days from the date of receipt of the notice issued

by the SLDC, further action will be taken by the SLDC as per the provisions of CEA Regulations duly informing

the Commission.

(f) System Recording Instruments

Recording instruments such as Data Acquisition System/Disturbance Recorder/Event Logger/Fault Locator/Wide

Area Management System/ Phasor Measurement Unit  (PMU) (including time synchronization equipment) shall be

provided in the Intra-State Transmission System for recording of dynamic performance of the system. All Users

and STU shall provide all the requisite recording instruments and shall always keep them in working condition.

(g) Procedure for Site Access, Site operational activities and Maintenance Standards

The Connection Agreement will also indicate any procedure necessary for Site access, Site operational activities

and maintenance standard for Intra-State Transmission Licensees equipment at User premises and vice versa.

TAMIL NADU GOVERNMENT GAZETTE

80

[Part   VI—Sec. 2

(h) Schedule of assets of State Transmission Grid

STU shall submit annually to the Commission by 30th September each year a schedule of transmission

assets, which constitute the State Grid, i.e., State Transmission System as on 31st March of that year indicating

ownership on which SLDC has operational control and responsibility.

(i) Connection Point

(i)

State Sector Generating Station (SSGS) Voltage may be 765/400/230/110/66 kV or as agreed with

STU. Unless specifically agreed with STU, the Connection point shall be the outgoing feeder gantry of Power

Station Switchyard.

(ii)

All the terminals, communication and protection equipment owned by SSGS within the perimeter of

the Generator’s site shall be maintained by the SSGS.

(iii) The metering system shall comply with the Transmission Metering Code; provided that, until

the notification and enforcement thereof, the Central Electricity Authority (Installation and Operation of Meters)

Regulations, 2019, as amended from time to time, shall apply. The other User’s equipment shall be maintained

by respective Users. From the outgoing feeders’ gantry onwards, all electrical equipment shall be maintained by

respective Transmission Licensee.

(j) Connectivity point & Voltage level in respect of Distribution Licensee:

The connectivity point of Distribution Licensee shall be on the LV side of the power transformer, i.e., 33 kV

or 22 kV or 11 kV or as agreed with STU. For EHV consumer directly connected to transmission system, voltage

may be 400 kV or 230 kV or 110 kV or 66 kV.

(i)

The Connection point shall be the outgoing feeder gantry/cable termination on transmission tower/pole

at respective Intra-State Transmission Licensee sub-station. Intra-State Transmission Licensee/Distribution Licensee

shall maintain all the terminals, communication and protection for the metering system as per the Metering Code.

(ii)

From the outgoing feeder gantry/transmission line cable terminal structure onwards, all electrical

equipment shall be maintained by respective Distribution Licensee.

Note: The Distribution Licensee shall, within thirty (30) days from the date of notification of this Grid Code,

constitute a Distribution Metering Committee and formulate the Distribution Metering Code in accordance with the

Central Electricity Authority (Installation and Operation of Meters) Regulations, 2019, as amended from time to

time, and other applicable statutory provisions. The Distribution Metering Code so formulated shall be submitted

to the Commission within seven days from the date of framing of Distribution Metering Code for approval prior

to its implementation. The proviso clause specified under the regulation 7.7(i)(iii) shall also be applicable to this

clause (j).

(k) IPPs, CGPs, EHV Consumers and Open Access Users

Voltage may be 400/230/110/33 kV or as agreed with STU. When sub-stations are owned by IPPs, CGPs,

EHV Consumers or the Open access users, the Connection point shall be the outgoing feeder gantry on their

premises.

(l) Connectivity Standards applicable to Wind generation and Solar Generating Station using Inverters

The connectivity standards specifying the technical equipment for wind generators and solar generating stations

using inverters to be synchronized with the grid at 11 kV or above and comply with the connectivity conditions

as specified in CEA Technical Standards for Connectivity Regulations as amended.

(m) Commissioning of Connectivity

(i)

The commissioning of all the new projects shall be governed as per Chapter 9 of this Grid Code.

(ii)

The applicant and all Intra-State Transmission Licensees shall comply with the provisions made in

the Connection Agreement, CEA Technical Standards for Communication Regulations and amendments thereof and

other relevant Regulations of CEA, Commission, TNEGC and IEGC as amended from time to time.

(iii) Special focus shall be made on technical requirements for connectivity to the grid, i.e., voice and

data communication facilities, system recording instruments, responsibilities for safety, cyber security, reactive power

compensation, integration of data with SLDC and STU, SCADA and other provisions.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

81

(iv) Installation of meters, their testing, calibration and reading and all matters incidental thereto shall be

undertaken in conformity with CEA Metering Regulations and amendments thereof, Transmission Metering Code

of this Grid Code and any other additional requirement as may be considered necessary by STU.

(v) The applicant shall intimate timeline for commissioning of works at its end and of dedicated

transmission line up to the point of connectivity at least three months in advance.

(vi) In case of Generating Stations, date of synchronization of Generating Station and Transmission Line

shall be intimated at least one month in advance so that required clearances, charging permission and issue of

unique charging code shall be issued by SLDC in consultation with STU and respective Intra-State Transmission

Licensee. In line with the above, the SLDC shall prepare procedure for first time energization of new or modified

power system elements to intra-State transmission system duly consulting the stakeholders and approval of such

procedure shall be obtained from the Commission within 60 days. In the absence of such procedure of SLDC,

the NLDC procedure shall apply for the elements of 230 kV and above.

(n) Post Connectivity Events

(i)

The Post-connectivity events in relation to Generating Plant, Sub-station, Transmission Line of the

applicant or Intra-State Transmission Licensees shall mean activities pertaining to interchange of power with Intra-

State Transmission System, Operation & Maintenance of such Generating Plant/Sub-station/Transmission Line by

Applicant or Intra-State Transmission Licensee, Operation & Maintenance of dedicated transmission line, Operation

& Maintenance of evacuation system associated with plant generating non-firm power or any other activity as may

be notified by STU.

(ii)

Post connectivity events shall be undertaken in accordance with this Grid Code and relevant

Regulations of CEA/Commission in general and specifically in respect of scheduling, despatch, energy accounting,

DSM accounting and settlement of accounts for Open Access transactions. The aforesaid activities will be taken-

up by SLDC in consultation with STU and Intra-State Transmission Licensees.

(o) Data Requirements

Users shall provide STU with data for this chapter as specified in the Data Registration Code chapter of

this Grid Code. Unless otherwise agreed in Connection Agreement, the equipment for data transmission and

communication shall be operated and maintained by User in whose premises they are installed, irrespective of

ownership.

Chapter 8 – System Security Code

8.1. Introduction

This chapter describes the security aspects to be followed by Intra-State Transmission System Users for grid

security and safety of electrical equipment.

8.2. Objective

The objective of this chapter is that, all Users shall endeavour to operate their respective power system and

generating stations in synchronization with each other at all times, so that the whole State Transmission System

operates as a synchronised system as well as an integrated part of the Southern Regional Grid. The STU shall

endeavour to operate the inter-State links in such a way, that inter-State transfer of power can be achieved

smoothly, whenever required. Security of the power system and safety of power equipment shall enjoy priority

over economically optimal operations.

8.3. System Security Aspects

(a) All Users shall operate their respective power systems in an integrated manner at all times in coordination

with SLDC.

(b) All switching operations, whether manually or automatic, will be based on regulatory provisions of IEGC,

TNEGC, CEA Regulations or any other guidelines issued by appropriate Authority from time to time.

(c) No part of the State Transmission System shall be deliberately isolated from the integrated Grid, except:

(i)

Under an emergency and conditions in which such isolation would prevent a total Grid collapse

and/or enable early restoration of power supply;

(ii)

When serious damage to costly equipment is imminent and such isolation would prevent it;

TAMIL NADU GOVERNMENT GAZETTE

82

[Part   VI—Sec. 2

(iii) For safety of Human Life;

(iv) When such isolation is specifically advised by SLDC; and

(v) On operation of under frequency/islanding scheme as approved by SRPC/SLDC.

(d) Any such isolation shall be reported to SLDC within the next fifteen (15) minutes. All such isolations

shall be restored, as soon as the conditions again permit it. No transmission elements shall be synchronized

without prior consent of SLDC/Sub-LDC. In case of any Grid incidence/disturbance, Grid shall be restored as per

Detailed Operating Procedure of SLDC and instructions given by SLDC during real time operation. No User of

the Grid is allowed to perform any switching operation by their own. The restoration process shall be supervised

by SLDC.

(e) All operational instructions given by SRLDC and SLDC shall have unique codes, which shall be recorded

and maintained as specified in CEA Grid Standards Regulations and amendments thereof. No transmission element

shall be taken into service without obtaining unique code from the SLDC. All Generators including RE and ESS

shall have to obtain unique code before synchronization with the State Grid or while isolating from the Intra-State

Transmission System.

(f)

SLDC, in consultation with SRPC, Users and the SRLDC, shall prepare a list of important elements

in the State grid that are critical for State grid operation and shall make the said list available to all concerned

Users.

(g) An important element of the State Grid as listed at Regulation 8.3(f) of the Grid Code can be taken

out of service only after prior clearance/ approval of SLDC, except in emergencies as per the Detailed Operating

Procedure(s) of SLDC. SLDC shall inform the opening or removal of any such important element (s) of the State

Grid to SRLDC/NLDC/SRPC and the concerned regional entities, who are likely to be affected, as specified in

the Detailed Operating Procedure of NLDC or SRLDC or SLDC.

(h) In case of switching off or tripping of any of the important elements of the State Grid under emergency

conditions or otherwise, it shall be intimated immediately by the Users with available details to SLDC, if the element

is within the control area of SLDC, who in turn shall intimate the SRLDC. The reasons for such switching off

or tripping to the extent determined and the likely time of restoration shall also be intimated within half an hour.

The SLDC and the Users shall ensure restoration of such elements within the estimated time of restoration, as

intimated.

(i)

The isolated, taken out or switched off elements shall be restored as soon as the system conditions

permit. The restoration process shall be supervised by SLDC, in coordination with the SRLDC and NLDC in

accordance with the system restoration procedures of NLDC or SRLDC or SLDC.

(j)

Maintenance of grid elements shall be carried out by respective User in accordance with the provisions

of the CEA Grid Standards Regulations and amendments thereof. Outage of an element that is causing or likely

to cause danger to the grid or sub-optimal operation of the grid shall be monitored by SLDC. SLDC shall report

such outages to SRLDC/SRPC. SLDC shall also issue suitable instructions to restore such elements in a specified

time period.

(k) All generating units shall have their Automatic Voltage Regulators (AVRs), Power System Stabilizers

(PSSs), voltage (reactive power) controllers (Power Plant Controller) and any other requirements in operation, as

per CEA Technical Standards for Connectivity Regulations and amendments thereof. If a generating unit with a

capacity higher than 100 (hundred) MW is required to be operated without its AVR or voltage controller in service,

the generating station shall immediately inform the SLDC of the reasons thereof and the likely duration of such

operation and obtain its permission.

(l)

The tuning of AVR, PSS, Voltage Controllers (PPC) including for low and high voltage ride through

capability of wind and solar generators or any other requirement as per CEA Technical Standards for Connectivity

shall be carried out by the respective generating station:

•

at least once in every five (5) years;

•

based on operational feedback provided by SLDC, after analysis of a grid event or disturbance;

•

in case of major network changes or fault level changes near the generating station as reported

by SLDC; and

•

in case of a major change in the excitation system of the generating station.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

83

(m) Power System Stabilizers (PSSs), AVRs of generating units and reactive power controllers shall be

properly tuned by the generating station as per the plan and the procedure prepared by the concerned SRPC/

SLDC. In case the tuning is not complied with as per the plan and procedure, the SLDC shall issue notice

to the defaulting generating station to complete the tuning within a specified time, failing which the SLDC may

approach the Commission under Section 33(4) of the Act.

(n) SLDC / SPC shall prepare the islanding schemes in accordance with the CEA Grid Standards Regulations

and amendments thereof for identified generating stations, cities and locations and ensure their implementation.

The islanding schemes shall be reviewed and augmented depending on the assessment of critical loads at least

once a year or earlier, if required. All users shall ensure that installation and operation of the protection system

shall comply with the provisions of CEA Grid Standards Regulations and amendments thereof.

(o) Mock drill of the islanding schemes shall be carried out annually by SLDC in coordination with SRLDC

and other Users involved in the islanding scheme. In case, mock drill with field testing is not possible to be

carried out for a particular scheme, simulation testing shall be carried out by SLDC.

(p) All Distribution Licensees, STU and Users shall provide automatic under-frequency relays (UFR) and

df/dt relays for load shedding in their respective systems to arrest frequency decline that could result in grid

failure as per the plan given by SRPC from time to time. The default UFR settings shall be as specified in Table

below or as amended in IEGC from time to time:

Sl.

No.

Stage of UFR Operation

Frequency (Hz)

1.

Stage-1

49.40

2.

Stage-2

49.20

3.

Stage-3

49.00

4.

Stage-4

48.80

Note-1: STU shall plan UFR settings and df/dt load shedding schemes depending on load generation

balance in coordination with SLDC and approval of the SRPC.

Note-2: Pumped storage hydro plants operating in pumping mode or ESS operating in charging mode

shall be automatically disconnected before the first stage of UFR.

Provided that the quantum of load relief under each stage of UFR shall be as indicated by the SRPC to

Tamil Nadu.

(q) The following shall be factored in while designing and implementing the UFR and df/dt relay schemes:

(i)

The under-frequency and df/dt load shedding relays are always functional.

(ii)

Demand disconnection shall not be set with any time delay in addition to the operating time of the

relays and circuit breakers.

(iii) There shall be a uniform spatial spread of feeders selected for UFR and df/dt disconnection.

(iv) SLDC shall ensure that telemetered data of feeders (MW power flow in real time and circuit breaker

status) on which UFR and df/dt relays are installed is available at its control centre. SLDC shall monitor the

combined load in MW of these feeders at all times. SLDC shall share the above data with the SRLDC in real

time and submit a monthly exception report to respective RPC. SLDC shall inform the SRLDC as well as SRPC

on a quarterly basis, durations during the quarter when the combined load in MW of these feeders was below the

level considered while designing the UFR scheme by SLDC/respective RPC. SLDC shall take corrective measures

within a reasonable period and inform the SRLDC and SRPC, failing which suitable action may be initiated by

respective RPC.

(v) SRPC shall undertake a monthly review of UFR and df/dt scheme and may also carry out random

inspection of the under-frequency relays. SRPC shall publish such a monthly review along with an exception

report on its website.

(vi) SLDC shall report the actual operation of UFR and df/dt schemes and load relief to the SRLDC and

SRPC and publish the monthly report on its website.

(r)

SLDC, STU or Users may identify the requirement of System Protection Schemes (SPS) (including

inter-tripping and run-back) in the power system to operate the transmission system within operating limits and

to protect against situations such as voltage collapse, cascade tripping and tripping of important corridors/flow-

TAMIL NADU GOVERNMENT GAZETTE

84

[Part   VI—Sec. 2

gates. Any such SPS at the intra-regional level shall be finalized by the SLDC/SRPC. SPS shall be installed and

commissioned by the concerned Users. SPS shall always be kept in service. If any SPS at the intra-State level

is to be taken out of service, the permission of the SLDC shall be required and the same shall be informed to

SRLDC.

(s) SLDC and Users shall operate in a manner to ensure that the steady state grid voltage as per CEA

Grid Standards Regulations and amendments thereof remains within the following operating range:

Voltage (kV rms)

Nominal

Maximum

Minimum

765

800

728

400

420

380

230

245

207

110

121

99

66

72

60

33

36

30

(t)

SLDC shall take appropriate measures to control the voltage as per its operating procedures.

(u) The concerned Users shall implement defence mechanisms as finalized by the respective RPC/SLDC to

prevent voltage collapse and cascade tripping.

(v) All defence mechanisms shall always be in operation and any exception shall be immediately intimated

by the concerned User to the SLDC along with the reasons and the likely duration of such exception. The

concerned User shall also obtain permission from SLDC.

(w) All Users and SLDC shall take all possible measures to ensure that the grid frequency always remains

within the specified band as specified in IEGC and amended thereof except in an emergency, or when it becomes

necessary to prevent imminent damage to critical equipment, no User shall suddenly reduce its generating unit output

by more than 100 (one hundred) MW without prior permission of the SLDC. Similarly, except in an emergency,

or when it becomes necessary to prevent imminent damage to critical equipment, no User shall cause a sudden

variation in its load by more than 100 (one hundred) MW without the prior permission of the SLDC.

(x) Provision of protections and relay settings shall be coordinated with State Transmission System, as per

plan finalised in Protection Co-ordination Committee.

(y) Each User shall provide adequate and reliable communication facility with SLDC to ensure exchange

of data/information necessary to maintain reliability and security of the grid. Wherever possible, redundancy and

alternate path shall be maintained for communication along important routes, e.g., User to SLDC.

(z) The Users shall send information/data including disturbance recorder/sequential event recorder output,

etc., to SLDC for the purpose of analysis of any grid disturbance/event. No User shall block any data/information

required by SLDC for maintaining reliability and security of the grid and for analysis of an event.

8.4. Special requirements for Solar/Wind generators

SLDC shall make all efforts to evacuate the available solar and wind power and treat them as a must-run

station. However, SLDC may instruct the solar/wind generator to back down generation on consideration of grid

security or if safety of any equipment or personnel is endangered, and Solar/Wind generator shall comply with the

same as per the procedure issued by the Commission in this regard. For this, Data Acquisition System facility/

communication system shall be provided for transfer of information to SLDC:

(i)

SLDC may direct a wind farm to curtail its Reactive Power drawal/injection in case, the security of grid

or safety of any equipment or personnel is endangered.

(ii)

During the wind generator start-up, the wind generator shall ensure that the reactive power drawal shall

not affect the grid performance.

8.5. Management of RE Curtailment

All the entities concerned shall follow the detailed procedure for management of RE curtailment for wind and

solar generation issued by the Commission in this regard.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

85

Chapter 9 - Commissioning and Commercial Operation Code

9.1. Introduction

This chapter covers aspects related to drawal of start-up power and injection of infirm power into the grid,

trial run operation, documents and tests required to be furnished before declaration of COD and requirements

for declaration of COD.

9.2. Drawal of Start Up Power and Injection of Infirm Power

(a) A unit of a generating station including unit of a captive generating plant that has been granted

connectivity to the intra-State Transmission System shall be allowed to interchange power with the grid during

the commissioning period, including testing and full load testing before the COD, after obtaining prior permission

of the SLDC:

Provided that the SLDC while granting such permission shall keep grid security in view.

(b) The period for which such inter-change shall be allowed shall be as follows: -

•

Drawal of start-up power shall not exceed 15 months prior to the expected date of first synchronization

and one year after the date of first synchronization; and

•

Injection of infirm power shall not exceed one year from the date of first synchronization for generating

stations other than REGS and ESS (except Hydro PSP ESS).

•

Injection of infirm power shall not exceed 45 days from the date of first time energisation and integration

approval for REGS and ESS (except Hydro PSP ESS).

(c) Notwithstanding the provisions of the Regulation 9.2(b), the Commission may allow extension of the

period for interchange of power beyond the stipulated period on an application made by the generating station

at least two months in advance of the completion of the stipulated period.

Provided that for REGS and ESS (except Hydro PSP ESS), extension of period for injection of infirm power

beyond the stipulated period may be allowed (a) for a period up to three months by the SLDC on an application(s)

made by such generating station or ESS (except Hydro PSP ESS) to the SLDC along with detailed reasons, at

least 10 days in advance of the completion of the stipulated period, (b) for a period beyond three months, by

the Commission on an application(s) made by such generating station or ESS (except Hydro PSP ESS) along

with detailed reasons, at least 15 days in advance of the completion of the stipulated period.

(d) Drawal of start-up power shall be as per the relevant Regulations/Orders of the Commission.

(e) The charges for deviation for drawal of start-up power or for injection of infirm power shall be governed

by the relevant Deviation Settlement Regulations/Orders of the Commission.

(f)

Start-up power shall not be used by the generating station for construction activities.

(g) The onus of proving that the interchange of infirm power from the unit(s) of the generating station is for

the purpose of pre-commissioning activities, testing and commissioning, shall rest with the generating station, and

the SLDC shall seek such information on each occasion of the interchange of power before COD. For this, the

generating station shall furnish to the SLDC relevant details, such as those relating to the specific commissioning

activity, testing, and full load testing, its duration and the intended period of interchange. The generating station

shall submit a tentative plan for the quantum and time of injection of infirm power on day ahead basis to the

SLDC.

(h) In the case of multiple generating units of the same generating station or multiple generating stations

owned by different entities connected at a common interface point, SLDC shall ensure segregation of firm power

from generating units that have achieved COD from power injected or drawn by generating units, which have not

achieved COD through appropriate accounting of energy.

(i)

SLDC shall stop the drawal of the start-up Power in the following events:

(i)

In case, it is established that the start-up power has been used by the generating station for

construction activity;

(ii)

In the case of default in payment of charges to the utilities, deviation settlement charges, etc.

TAMIL NADU GOVERNMENT GAZETTE

86

[Part   VI—Sec. 2

9.3. Data to be furnished prior to notice of Trial Run

(a) The following details, as applicable, shall be furnished by each generating station entity to the SLDC,

STU and the beneficiaries of the generating station, wherever identified, prior to notice of trial run:

Description

Units

Installed Capacity of generating station

MW

Installed Capacity of generating station

MVA

MCR

MW

Number x unit size

No x MW

Time required for cold start

Minute

Time required for warm start

minute

Time required for hot start

Minute

Time required for combined cycle operation under cold conditions

Minute

Time required for combined cycle operation under warm conditions

Minute

Ramping up capability

% per minute

Ramping down capability

% per minute

Minimum turndown level

% of MCR

Minimum turndown level

MW (ex-bus)

Inverter Loading Ratio (DC/AC capacity)

Name of QCA (where applicable)

Full reservoir level (FRL)

Metre

Design Head

Metre

Minimum draw down level (MDDL)

Metre

Water released at Design Head

M3/ MW

Unit-wise forbidden zones

MW

9.4. Notice of Trial Run

(a) The generating company proposing its generating station or a unit thereof for trial run or repeat of trial

run shall give a notice of not less than seven (7) days to SLDC, STU and the beneficiaries of the generating

stations, including intermediary procurers, wherever identified:

Provided that in case the repeat trial run is to take place within forty-eight (48) hours of the failed trial run,

fresh notice shall not be required.

(b) The Transmission Licensee proposing its transmission system or an element thereof for trial run shall

give a notice of not less than seven days to the SLDC, STU, Distribution Licensees of the State and the owner

of the inter-connecting system.

(c) The SLDC shall allow commencement of the trial run from the requested date or in the case of any

system constraints, not later than seven (7) days from the proposed date of the trial run. The trial run shall

commence from the time and date as decided and informed by the SLDC.

(d) A generating station shall be required to undergo a trial run in accordance with the below mentioned

Regulation 9.5 after completion of Renovation and Modernization for extension of the useful life of the project as

per the Tariff Regulations.

9.5. Trial Run of Generating Unit

(a)

Trial Run of the Thermal Generating Unit shall be carried out in accordance with the following provisions:

(i) A thermal generating unit shall be in continuous operation at MCR for seventy-two (72) hours on

designated fuel:

Provided that:

1.

short interruption or load reduction shall be permissible with the corresponding increase in duration

of the test;

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

87

2.

interruption or partial loading may be allowed with the condition that the average load during

the duration of the trial run shall not be less than MCR, excluding the period of interruption but including the

corresponding extended period;

3.

cumulative interruption of more than four (4) hours shall call for a repeat of trial run.

(ii) Where, on the basis of the trial run, a thermal generating unit fails to demonstrate the unit capacity

corresponding to MCR, the Generating Company has the option to de-rate the capacity of the generating unit or

to go for a repeat trial run. If the Generating Company decides to de-rate the unit capacity, the de-rated capacity

in such cases shall not be more than 95% of the demonstrated capacity, to cater for primary response.

(b)

Trial Run of Hydro Generating Unit shall be carried out in accordance with the following provisions:

(i)

A hydro generating unit shall be in continuous operation at MCR for twelve (12) hours:

Provided that -

1.

short interruption or load reduction shall be permissible with a corresponding increase in duration

of the test;

2.

interruption or partial loading may be allowed with the condition that the average load during the

duration of trial run shall not be less than MCR excluding the period of interruption but including the corresponding

extended period;

3.

cumulative interruption of more than four (4) hours shall call for a repeat of trial run;

4.

if it is not possible to demonstrate the MCR due to insufficient reservoir or pond level or insufficient

inflow, COD may be declared, subject to the condition that the same shall be demonstrated immediately when

sufficient water is available after COD:

Provided that if such a generating station is not able to demonstrate the MCR when sufficient water is

available, the generating company shall de-rate the capacity in terms of below mentioned Regulation 9.5(b)(ii)

and such de-rating shall be effective from COD.

(ii) Where, on the basis of the trial run, a hydro generating unit fails to demonstrate the unit capacity

corresponding to MCR, the Generating Company shall have the option to either de-rate the capacity or go for

a repeat trial run. If the Generating Company decides to de-rate the unit capacity, the de-rated capacity in such

cases shall not be more than 90% of the demonstrated capacity to cater for primary response.

(c)

Trial Run of Solar/ Wind/ ESS/ PSP/ Hybrid Generating Station:

(i)

Trial run of the solar inverter unit(s) connected at State Transmission system shall be performed for a

minimum capacity of 5 MW:

Provided that in the case of a project having a capacity of more than 5 MW, the trial run for the balance

capacity shall be performed in a maximum of four instalments with a minimum capacity of 5 MW:

(ii)

Successful trial run of a solar inverter unit(s) covered under the above Regulation 9.5(c)(i) shall mean

the flow of power and communication signal for not less than four hours on a cumulative basis between sunrise

and sunset in a single day with the requisite metering system, power plant controller, telemetry and protection

system in service. The Generating Company shall record the output of the unit(s) during the trial run and shall

corroborate its performance with the temperature and solar irradiation recorded at site during the day and plant

design parameters: Provided that:

(iii) the output below the corroborated performance level with the solar irradiation of the day shall call for

a repeat of the trial run;

(iv) if it is not possible to demonstrate the rated capacity of the plant due to insufficient solar irradiation,

COD may be declared subject to the condition that the same shall be demonstrated immediately when sufficient

solar irradiation is available after COD, within one year from the date of COD:

Provided that if such a generating station is not able to demonstrate the rated capacity when sufficient solar

irradiation is available after COD, the generating company shall de-rate the capacity in terms of below mentioned

Regulation 9.5(c)(ix).

(v) Trial run of a wind turbine(s) connected at State Transmission system shall be performed for a minimum

capacity of 5 MW:

TAMIL NADU GOVERNMENT GAZETTE

88

[Part   VI—Sec. 2

Provided that in the case of a project having a capacity of more than 5 MW, the trial run for wind turbine(s)

above the capacity of 5 MW shall be performed in batch sizes of not less than 5 MW:

(vi) Successful trial run of a wind turbine(s) covered under the above Regulation 9.5(c)(v) shall mean the

flow of power and communication signal for a period of not less than four (4) hours on a cumulative basis in a

single day during periods of wind availability with the requisite metering system, power plant controller, telemetry,

and protection system in service. The Generating Company shall record the output of the unit(s) during the trial

run and corroborate its performance with the wind speed recorded at the site(s) during the day and plant design

parameters:

Provided that-

(i)

the output below the corroborated performance level with the wind speed of the day shall call for

a repeat of the trial run;

(ii)

if it is not possible to demonstrate the rated capacity of the plant due to insufficient wind velocity,

COD may be declared subject to the condition that the same shall be demonstrated immediately when sufficient

wind velocity is available after COD, within one year from the date of COD:

Provided that if such a generating station is not able to demonstrate the rated capacity when sufficient wind

velocity is available after COD, the Generating Company shall de-rate the capacity in terms of below mentioned

Regulation 9.5(c)(x).

(vii) Successful trial run of a standalone Energy Storage System (ESS) connected at State Transmission

system shall mean one (1) complete cycle of charging and discharging of energy as per the design capabilities

with the requisite metering, telemetry and protection system being in service.

(viii) Successful trial run of a Pumped Storage Plant (PSP) connected at State Transmission system shall

mean one (1) complete cycle of turbo-generator and pumping motor mode as per the design capabilities up to

the rated water drawing levels with the requisite metering, telemetry and protection system being in service.

Provided that if it is not possible to demonstrate the design capabilities up to the rated water drawing levels

due to insufficient reservoir levels, the COD may be declared after demonstrating the capabilities at available

water drawing levels, subject to the condition that design capabilities up to the rated water drawing levels shall

be demonstrated immediately when sufficient reservoir level is available after COD.

Provided further that if such a generating station is not able to demonstrate the design capabilities when

sufficient water is available, the generating company shall have the option to either go for a repeat trial run or

de-rate the capacity. If the generating company decides to de-rate the unit capacity in terms of Regulation 9.5(b)

(ii), such de-rating shall be effective from the COD.

(ix) Successful trial run of a hybrid system connected at State Transmission system shall mean successful

trial run of each individual source of the hybrid system in accordance with the applicable provisions of this Grid

Code.

(x) Where, on the basis of the trial run, solar/ wind/ ESS/ PSP/ hybrid generating station connected at

State Transmission system fails to demonstrate its rated capacity, the Generating Company shall have the option

to either go for a repeat trial run or de-rate the capacity subject to a minimum aggregated de-rated capacity of

5 MW and above, as the case may be.

(xi) In the case of Wind/Solar/ESS/Hybrid Generating Station projects having installed capacity of 50 MW or

more, the trial run may be performed in instalments, with a minimum capacity of 20% of the proposed capacity

for each instalment.

(xii) Notwithstanding the provisions contained in the Grid Code, where Power Purchase Agreement provides

for a specific capacity that can be declared COD, trial run shall be allowed for such capacity in terms of such

Power Purchase Agreement.

(d)

Trial Run of Intra-State Transmission System

Trial run of a transmission system or an element thereof shall mean successful energisation of the transmission

system or the element thereof at its nominal system voltage through inter-connection with the grid for a continuous

twenty-four (24) hours flow of power and communication signal from the sending end to the receiving end and

with the requisite metering system, telemetry and protection system:

Provided that under exceptional circumstances and with the prior approval of STU and SLDC, a transmission

element can be energized at lower nominal system voltage level:

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

89

Provided further that the STU and SLDC may allow anti-theft charging where the transmission line is not

carrying any power.

9.6. Documents and Tests Prior to Declaration of Commercial Operation

(a) Notwithstanding the requirements in other standards, codes and contracts, for ensuring grid security, the

tests as specified in the following Regulations shall be scheduled and carried out in coordination with SLDC and

STU by the Generating Company or the Transmission Licensee, as the case may be, and relevant reports and

other documents as specified shall be submitted to SLDC and STU before a certificate of successful trial run is

issued to such a Generating Company or the Transmission Licensee, as the case may be.

(b) All thermal generating stations having a capacity of more than 200 MW and hydro generating stations

having a capacity of more than 25 MW shall submit documents confirming the enablement of automatic operation

of the plant from the appropriate Load Despatch Centre by integrating the controls and telemetering features of

their system into the automatic generation control in accordance with CEA Technical Standards for Construction

Regulations and CEA Technical Standards for Connectivity Regulations and amendments thereof.

9.7. Documents and Tests Required for Thermal (coal/lignite) Generating Stations

(a) The Generating Company shall submit the following documents from the Original Equipment Manufacturer

(OEM), namely

(i)

Start-up curve for boiler and turbine including starting time of unit in cold, warm and hot conditions,

(ii)

capability curve of generator,

(iii) design ramp rate of boiler and turbine.

(b) The following tests shall be performed:

(i)

Operation at a load of fifty-five (55) percent of MCR as per the CEA Technical Standards for

Construction Regulations for a sustained period of four (4) hours.

(ii)

Ramp-up from Fifty-five (55) percent of MCR to MCR at a ramp rate of at least one (1) percent

of MCR per minute, in one step or two steps (with stabilization period of 30 minutes between two steps), and

sustained operation at MCR for one (1) hour.

(iii) Demonstrate overload capability with the valve wide open as per the CEA Technical Standards for

Construction Regulations and sustained operation at that level for at least five (5) minutes.

(iv) Ramp-down from MCR to fifty-five (55) percent of MCR at a ramp rate of at least one (1) percent

of MCR per minute, in one or two steps (with stabilization period of 30 minutes between two steps).

(v) Primary response through injecting a frequency test signal with a step change of ± 0.1 Hz at 55%,

60%, 75% and 100% load.

(vi) Reactive power capability as per the generator capability curve as provided by OEM considering

over-excitation and under-excitation limiter settings and prevailing grid condition.

9.8. Documents and Tests Required for Hydro Generating Stations including Pumped Storage Hydro

Generating Station

(a) The Generating Company shall submit documents from the OEM for the turbine characteristics curve

indicating the operating zone(s) and forbidden zone(s). In order to demonstrate the operating flexibility of the

generating unit, it shall be operated below and above the forbidden zone(s).

(b) The following tests shall be performed considering the water availability and head:

(i)

Primary response through injecting a frequency test signal with a step change of ± 0.1 Hz for

various loadings within the operating zone.

(ii)

Reactive power capability as per the generator capability curve considering over- excitation and

under-excitation limiter settings.

(iii) Black start capability, wherever feasible.

(iv) Operation in synchronous condenser mode, wherever designed.

TAMIL NADU GOVERNMENT GAZETTE

90

[Part   VI—Sec. 2

9.9. Documents and Test Required for Gas Turbine based Generating Stations

(a) The Generating Company shall submit documents from the OEM for (i) starting time of the unit in cold,

warm and conditions (ii) design ramp rate.

(b) The following tests shall be performed:

(i)

Primary response through injecting a frequency test signal with a step change of ± 0.1 Hz for

various loadings within the operating zone.

(ii)

Reactive power capability as per the generator capability curve considering over- excitation and

under-excitation limiter settings.

(iii) Black start capability up to 100 MW capacity, wherever feasible.

(iv) Operation in synchronous condenser mode, wherever designed.

9.10. Documents and Tests Required for the Generating Stations based on wind and solar resources

(a) The Generating Company shall submit a certificate confirming compliance with CEA Technical Standards

for Connectivity Regulations, in accordance with Regulation 9.6 of the Grid Code.

(b) The Type test report for Fault Ride through Test (LVRT and HVRT) for units commissioned after the

specified date as per CEA Technical Standards for Connectivity Regulations and amendments thereof, mandating

LVRT and HVRT capability shall be submitted.

(i) Failure of Generator to comply with the Low Voltage Ride through (LVRT) / High Voltage Ride through

(HVRT) requirements as specified in 9.10(b) shall constitute a violation of Grid Security.

(ii) Upon detection and verification of such non-compliance, the State Load Despatch Centre (SLDC) shall

issue a Notice to the concerned Generator, directing to take necessary corrective action and ensure compliance

within a period of thirty (30) days from the date of receipt of such Notice.

(iii) In the event of failure or repeated non-compliance beyond the aforesaid notice period, the SLDC

shall file a petition before the Commission within 15 days from the date of expiry of notice period for appropriate

remedy for the Grid indiscipline caused by such wind and solar generators.

(c) The following tests shall be performed at the point of inter-connection:

(i)

Frequency response of machines as per the CEA Technical Standards for Connectivity Regulations.

(ii)

Reactive power capability as per OEM rating at the available irradiance or the wind energy, as the

case may be:

Provided that the Generating Company may submit offline simulation studies for the specified tests, in case

testing is not feasible before COD, subject to the condition that tests shall be performed within a period of one

year from the date of achieving COD.

9.11. Documents and Tests Required for Energy Storage Systems

(a) The ESS shall submit a certificate confirming compliance with the CEA Technical Standards for Connectivity

Regulations, in accordance with Regulation 9.18 of the Grid Code.

(b) The following tests shall be performed at the point of inter-connection:

(i)

Power output capability in MW and energy output capacity in MWh.

(ii)

Frequency response of ESS.

(iii) Ramping capability as per design.

9.12. Documents and Tests Required for HVDC Transmission System

(a) The Transmission Licensee shall submit technical details including operating guidelines such as filter

bank requirements at various operating loads and monopolar/ or bipolar configuration, reactive power controller,

run-back features, frequency controller, reduced voltage mode of operation, circuit design parameters and power

oscillation damping, as applicable.

(b) The following tests shall be performed:

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

91

(i)

Minimum load operation.

(ii)

Ramp rate.

(iii) Overload capability, subject to grid condition.

(iv) Black start capability in the case of Voltage Source Convertor (VSC) HVDC, wherever feasible.

(v) Dynamic Reactive Power Support (in the case of VSC based HVDC).

9.13. Documents and Tests Required for SVC or STATCOM

(a) The Transmission Licensee shall submit technical particulars including a single line diagram, V/I characteristics,

the rating of coupling transformer, the rating of each VSC, MSR and MSC branch, different operating modes, the

IEEE standard Model, Power Oscillation Damping (POD) enabled and tuned (if not, then reasons for the same)

and the results of an offline simulation-based study to validate the performance of POD.

(b) The following tests shall be performed to validate the full reactive power capability of SVC and STATCOM

in both directions, i.e., absorption as well as injection mode:

(i)

POD performance test;

(ii)

dynamic performance testing:

Provided that the Transmission Licensee may submit offline simulation studies for the specified tests, in case

the conduct of tests is not feasible before COD, subject to the condition that tests shall be performed within a

period of one year from the date of achieving COD.

9.14. Certificate of Successful Trial Run

(a) In case any objection is raised by a beneficiary in writing to the SLDC with a copy to all concerned

regarding the trial run within two (2) days of completion of such trial run, the SLDC shall, within five (5) days of

receipt of such objection, in coordination with the concerned entity and the beneficiaries, decide if the trial run

was successful or if there is a need for a repeat trial run.

(b) After completion of a successful trial run and receipt of documents and test reports as per this Grid

Code, the SLDC shall issue a certificate to that effect to the concerned generating station, ESS, or Transmission

Licensee, as the case may be, with a copy to their respective beneficiary(ies) and the STU and RPC, within

three days.

9.15. Declaration by Generating Company and Transmission Licensee

(a) Thermal Generating Station -

The Generating Company shall certify that:

(i)

The generating station or unit thereof meets the relevant requirements and provisions of the CEA

Technical Standards for Construction Regulations, CEA Technical Standards for Connectivity Regulations, CEA

Technical Standards for Communication Regulations, CEA Safety Regulations, CEA Flexible Operation Regulations

and this Grid Code, as applicable.

(ii)

The main plant equipment and auxiliary systems including the balance of the plant such as the

fuel oil system, coal handling plant, DM plant, pre-treatment plant, fire-fighting system, ash disposal system and

any other site-specific system have been commissioned and are capable of full load operation of the units of the

generating station on a sustained basis.

(iii) Permanent electric supply system including emergency supplies and all necessary instrumentation,

control and protection systems and auto loops for full load operation of the unit have been put into service.

(b) The certificates required under the above Regulation 9.15(a) shall be signed by the authorized signatory

not below the rank of CMD or CEO or MD of the Generating Company and shall be submitted to the SLDC

and to the Member Secretary of the concerned State Power Committee (SPC) before the declaration of COD.

9.16. Hydro Generating Station

(a) The Generating Company shall certify that:

(i)

The generating station or unit thereof meets the requirement and relevant provisions of the CEA

Technical Standards for Construction Regulations, CEA Technical Standards for Connectivity Regulations, CEA

Technical Standards for Communication Regulations, CEA Safety Regulations and this Grid Code, as applicable.

TAMIL NADU GOVERNMENT GAZETTE

92

[Part   VI—Sec. 2

(ii)

The main plant equipment and auxiliary systems including the drainage de-watering system, primary

and secondary cooling system, LP and HP air compressor and fire fighting system have been commissioned and

are capable of full load operation of units on a sustained basis.

(iii) Permanent electric supply systems including emergency supplies and all necessary Instrumentation,

Control and Protection Systems and auto loops for full load operation of the unit are put into service.

(b) The certificates required under the above Regulation 9.16(a) shall be signed by the authorized signatory

not below the rank of CMD or CEO or MD of the Generating Company and shall be submitted to the SLDC

and to the Member Secretary of the concerned RPC before the declaration of COD.

9.17. Transmission System

The Transmission Licensee shall submit a certificate signed by the authorized signatory not below the rank of

CMD or CEO or MD of the Company to the concerned SLDC and to the STU before declaration of COD that the

transmission line, sub-station and communication system conform to the CEA Technical Standards for Construction

Regulations, CEA Technical Standards for Connectivity Regulations, CEA Technical Standards for Communication

Regulations, CEA Safety Regulations and this Grid Code and are capable of operation to their full capacity.

9.18. Wind, Solar, Storage and Hybrid Generating Stations

The generating station based on wind and solar resources, ESS, and hybrid generating station shall submit

a certificate signed by the authorized signatory not below the rank of CMD or CEO or MD to the SLDC and to

the STU before declaration of COD, that the said generating station or the ESS as the case may be, including

main plant equipment such as wind turbines or solar inverters or auxiliary systems, as the case may be, has

complied with all relevant provisions of CEA Technical Standards for Connectivity Regulations, CEA Technical

Standards for Communication Regulations, CEA Safety Regulations and this Grid Code.

9.19. Declaration of Commercial Operation and Commercial Operation Date (COD)

(a) A generating station or unit thereof or a transmission system or an element thereof or ESS may declare

commercial operation as follows and inform SLDC, STU and its beneficiaries:

(i)

Thermal Generating Station or a unit thereof

1.

The commercial operation date in the case of a unit of the thermal generation station shall be the date

declared by the Generating Company after a successful trial run at MCR or de-rated capacity as per Regulation

9.5(a)(ii) of the Grid Code, as the case may be, and submission of a declaration as per Regulation 9.15(a) of

the Grid Code.

2.

In the case of the generating station, the COD of the last unit of the generating station shall be

considered as the COD of the generating station.

(ii) Hydro Generating Station

1.

The commercial operation date in the case of a unit of the hydro generating station including a pumped

storage hydro generating station shall be the date declared by the generating station after a successful trial run

at MCR or de-rated capacity as per Regulation 9.5(b)(ii) of the Grid Code, as the case may be, and submission

of a declaration as per Regulation 9.16 of the Grid Code.

2.

In the case of the generating station, the COD of the last unit of the generating station shall be

considered as the COD of the generating station.

(iii) Transmission System

1.

The commercial operation date in the case of an Intra-State Transmission System or an element thereof

shall be the date declared by the Transmission Licensee on which the Transmission System or an element thereof

is in regular service at 0000 hours after successful trial operation for transmitting electricity and communication

signals from the sending end to the receiving end as per Regulation 9.5(d) of the Grid Code and submission of

a declaration as per Regulation 9.17 of the Grid Code:

Provided that the commercial operation date of a transmission element shall be declared only after a successful

trial run of the last element of the said transmission system:

Provided further that where only some of the transmission elements of the transmission system have

achieved a successful trial run seeks commercial operation of such elements, the commercial operation date of

such transmission elements of the transmission system may be declared by the Transmission Licensee as per

this Grid Code:

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

93

Provided also that where only some of the transmission element(s) of the transmission system have achieved

a successful trial run and if the operation of such transmission elements is certified by the STU and concerned

Regional Power Committee(s) for improving the performance, safety and security of the grid, the commercial

operation date of such transmission element(s) of the transmission system may be declared by the Transmission

Licensee as per this Grid Code:

Provided also that in case a transmission system or an element thereof executed under regulated tariff

mechanism is prevented from regular service on or after the scheduled COD for reasons not attributable to the

Transmission Licensee or its supplier or its contractors but is on account of the delay in commissioning of the

concerned generating station or in commissioning of the upstream or downstream transmission system of other

Transmission Licensee or downstream distribution system of Distribution Licensee, the Transmission Licensee shall

approach the Commission through an appropriate petition along with a certificate from the STU to the effect

that the transmission system is complete as per the applicable CEA Standards, for approval of the commercial

operation date of such transmission system or an element thereof:

Provided also that in the case of Intra-State Transmission System executed through Tariff Based Competitive

Bidding, the Transmission Licensee may declare deemed COD of the Intra-State Transmission System in accordance

with the provisions of the Transmission Service Agreement after obtaining (a) a certificate from the STU to the

effect that the transmission system is complete as per the specifications of the bidding guidelines and applicable

CEA Standards, and (b) no load charging certificate from the respective SLDC, where no load charging is possible.

2.

The COD of a transmission element of the transmission system under Tariff Based Competitive Bidding

(TBCB) shall be declared only after the declaration of the COD of all the pre-required transmission elements as

per the Transmission Services Agreement (TSA):

Provided that in case any transmission element is required in the interest of the power system as certified

by the STU and Long-Term Transmission Customer (LTTC), the COD of the said transmission element may be

declared prior to the declaration of the COD of its pre-required transmission elements.

(iv) Communication System

Date of commercial operation in relation to a communication system or an element thereof shall mean the

date declared by the Transmission Licensee from 0000 hours of which a communication system or element thereof

shall be put into service after completion of the site acceptance test including transfer of voice and data to the

respective control centres as certified by State Load Despatch Centre.

(v)

Generating Stations based on Wind and Solar resources; ESS and Hybrid Generating Station

1.

The commercial operation date in the case of units of a renewable generating station aggregating to

5 MW and above or such other limit as specified in Regulation 9.5(c) of the Grid Code, shall mean the date

declared by the generating station after undergoing a successful trial run as per Regulation 9.5(c) of the Grid

Code, submission of declaration as per Regulation 9.18 of the Grid Code, and subject to fulfilment of other

conditions, if any, as per PPA.

2.

In the case of a generating station as a whole, the commercial operation date of the last unit of the

generating station shall be considered as the COD of the generating station.

(b) On declaration of commercial operation date, scheduling of the generating station or unit thereof

shall start from 0000 hours of D+2 (where D is the date when a generating station intimates the commercial

operation of the generating station or unit thereof) or the commercial operation date declared by the generating

station or unit thereof, whichever is later.

Chapter 10 – Operational Planning Code

10.1. Introduction

This chapter describes the process by which, SLDC shall carry out the operational planning and demand

control procedures to permit reduction in demand for any reason.

10.2. Objective

The detailed provision is required to enable SLDC to achieve a reduction in demand to avoid operating

problems on all or part of the State Transmission System. SLDC shall utilise Demand Control in a manner, which

does not unduly discriminate against any one or group of customers.

10.3. Operating Philosophy

(a) All Intra-State Users shall at all times function in coordination to ensure integrity, stability and resilience

of the grid and achieve economy and efficiency in the operation of power system

TAMIL NADU GOVERNMENT GAZETTE

94

[Part   VI—Sec. 2

(b) Operation of the State grid shall be monitored by SLDC.

(c) Detailed Operating Procedures for State grid shall be developed, maintained and updated by the SLDC,

consistent with the Detailed Operating Procedures of SRLDC.

(d) SLDC shall have qualified operating personnel manning the control room round the clock.

(e) Every generating station and transmission sub-station of 66 kV and above shall have a control room

manned by qualified operating personnel round the clock. Alternatively, the same may be operated round the

clock from a remotely located control room, subject to the condition that such remote operation does not result

in a delay in the execution of any switching instructions and information flow:

Provided that a Transmission Licensee owning a transmission line but not owning the connected sub-station,

shall have a coordination centre functioning round the clock, manned by qualified personnel for operational

coordination with SLDC and equipped to carry out the operations as directed by SLDC.

(f)

Qualified Coordinating Agency (QCA) shall have coordination centres functioning round the clock, manned

by qualified personnel for operational coordination with SLDC and generating stations. ESS and Bulk Consumers,

which are State entities, shall have coordination centres functioning round the clock and manned by qualified

personnel for operational coordination with SLDC.

10.4. Demand Estimation

The demand estimation shall be done by the DISCOM(s)/STU in accordance with the provisions of the Grid

Code and Resource Adequacy Regulations. SLDC/STU shall be provided with a copy of the same as and when

it is finalized.

10.5. Demand Control

(a) Primarily the need for demand control would arise on account of the following conditions:

(i)

Variations in demand from the estimated or forecasted values, which cannot be absorbed by the grid;

(ii)

Unforeseen generation/ transmission outages resulting in reduced power availability; and

(iii) Heavy reactive power demand causing low voltages.

(b) SLDC shall match the consolidated demands of the DISCOM(s) with consolidated generation availability

from SSGS, ISGS, IPP/CGP and other sources and exercise Demand Control to ensure that there is a balance

between the energy availability and the DISCOMs demand plus losses plus the required reserve.

(c) SLDC would maintain a historical database for the purpose of Demand Estimation and shall be equipped

with the state-of-the-art tools such as Energy Management System (EMS) for short-term demand estimation to

plan in advance, as to how the load would be met without overdrawing from the grid.

(d) SLDC shall advise STU for planning of automatic load shedding and rotational load shedding schemes

through installation of Under Frequency Relays and df/dt relays.

(e) The particulars of feeders or group of feeders at STU sub-station, which shall be tripped under under-

frequency load shedding scheme whether manually or automatic on rotational basis or otherwise, will be available

at the sub-station for information of the consumer(s).

(f)

Demand control can also be exercised by SLDC through direct circuit breaker tripping using RTUs or

under frequency detection by SLDC SCADA or through telephonic instructions. Demand shed by operation of

under frequency relays shall not be restored without specific directions from SLDC.

(g) Rotational load shedding schemes through installation of Under Frequency Relays and df/dt relays shall

be prepared, in accordance with the instructions/guidelines issued by SRLDC/SRPC.

10.6. Demand Disconnection

(a) All Users/Distribution Licensees shall restrict their drawal from the grid, within the net drawal schedule.

(b) Distribution Licensees shall ensure that requisite load shedding is carried out in its control area, so that

there is no over drawal.

(c) The SLDC through respective Distribution Licensees shall also formulate and implement state-of-the-art

demand management schemes for automatic demand management like rotational load shedding, demand response

etc., to reduce over drawal in order to comply with Regulation 10.6(a) and Regulation 10.6(b) of the Grid Code.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

95

(d) In order to maintain the frequency within the stipulated band and maintain the network security, the

interruptible loads shall be arranged in four groups, viz., load for scheduled power cuts/load shedding, load for

unscheduled load shedding, load to be shed through under frequency relays/df/dt relays and load to be shed

under any System Protection Scheme identified at RPC level. These loads shall be grouped in such a manner,

that there is no overlapping between different groups of loads. In case of certain contingencies and/or threat to

system security, the SRLDC may direct SLDC to decrease drawal of its control area by a certain quantum. Such

directions shall immediately be acted upon by Users/ Distribution Licensees.

(e) SLDC shall devise standard instantaneous message formats in order to give directions in case of

contingencies and /or threat to the system security to reduce deviation from the schedule by the Users/ Distribution

Licensees/ Injecting Utility at different over drawal/ Under drawal/ Over-Injection/Under Injection conditions depending

upon the severity. SLDC shall also ensure immediate compliance of these directions and any violation of SLDC’s

directions shall be intimated to the Commission through monthly report.

(f)

All Users/Distribution Licensee shall comply with direction of SLDC and carry out requisite load shedding

or backing down of generation in case of congestion in transmission system to ensure safety and reliability of

the system. The procedure for application of measures to relieve congestion in real time as well as provisions

of withdrawal of congestion shall be in accordance with detailed procedure in accordance with Central Electricity

Regulatory Commission (Measures to relieve congestion in real time operation) Regulations, 2009 and amendments

thereof or any relevant guidelines/ Regulations issued by appropriate Authority/ Commission.

(g) The measures taken by Users/Distribution Licensee shall not be withdrawn as long as the frequency

remains at a level lower than the limits or congestion continues, unless specifically permitted by the SRLDC/

SLDC.

10.7. Load Crash

(a) In the event of load crash in the system due to weather disturbance or any other reasons, the situation

would be controlled by SLDC by the following methods:

(i)

Backing down of hydel stations for short period immediately;

(ii)

Lifting of the load restrictions, if any;

(iii) Exporting the power to neighbouring regions;

(iv) Backing down of thermal stations with a time lag of 5-10 minutes for short period;

(v) Closing down of hydel units (subject to non-spilling of water and effect on irrigation); and

(vi) Backing down of Renewable Energy Power Plants.

The above methodology shall be reviewed by Operation and Co-ordination Committee from time to time.

(b) While implementing the above, the system security aspects should not be violated as per relevant

provisions under IEGC and State Grid Code.

Chapter 11 - Schedule and Despatch Code

11.1. Introduction

This chapter deals with the procedure for scheduling, injection and drawal of power by the Users through

Intra-State Transmission System and the modalities for exchange of information and sets out the responsibilities

of each User and SLDC in Scheduling and Despatch of energy.

11.2. Objective

The objective of this chapter is to deal with the procedures to be adopted for scheduling of ISGS, SSGS,

IPPs, Joint Ventures, CGPs, Open Access Customers and REGS in detail and responsibility of SLDC in preparing

and issuing daily schedule of despatch/ drawal of generators and DISCOMs/Users respectively.

11.3. General Principles of Scheduling

(a) All the scheduling will be done on 15-minute time block basis. For the purpose of scheduling, each day

starting from 0000 hours (IST) to 2400 hours (IST) is divided into 96 time blocks each of 15 minutes duration.

SLDC shall compile and intimate each DISCOM/buyer, the drawal schedule and to each SSGS and IPPs, CGPs,

etc. the generation schedule in advance:

TAMIL NADU GOVERNMENT GAZETTE

96

[Part   VI—Sec. 2

(b) Users shall submit the following documents before commencement of scheduling of power:

i)

Documents in support of the connectivity and open access by Seller or Buyer, as applicable.

ii)

Copies of valid contracts signed by Sellers and Buyers, for transactions other than collective

transactions.

iii)

Copy of allocation order, in case power is allocated by the State Government.

(c) The State Load Despatch Centre shall be responsible for optimum scheduling and despatch of electricity,

monitoring of real time grid operations through secure and economic operation of the State grid and management

of the reserves including energy storage systems and demand response within its State control area, supervision

and control over the intra-State transmission system, processing of interface energy meter data and coordinating

the accounting and the settlement of State pool account, as may be specified by the Commission.

(d) The Users connected exclusively to the intra-State transmission system shall be under the control area

jurisdiction of SLDC for scheduling and despatch of electricity.

(e) Unless otherwise decided by the Commission, the Users that have already declared COD as on the

date of coming into force of this Grid Code, shall continue to remain under the control area of the SLDC or the

SRLDC, as the case may be, as existing before the date of coming into force of this Grid Code.

(f)

The Generating Station(s) shall declare ex-bus Declared Capacity limited to 100% MCR less auxiliary

power consumption on day ahead basis without fail. If any of the generating Station(s) fail to provide such

schedule, the SLDC may issue notice to such generating Station(s) to comply with the scheduling procedure and

if such generating Station(s) fail to do so, the SLDC shall file appropriate petition before the Commission and

the Commission shall take decision on case to case basis.

(g) The hydro generating stations may declare ex-Bus Declared Capacity more than 100% MCR less auxiliary

power consumption limited to overload capability during the high inflow periods. The high inflow period for this

purpose shall be notified by SLDC.

(h) The State Load Depatch Centre shall periodically check that the generating station is not manipulating

the declaration of the Declared Capacity with the intent of making undue money through Fixed Charges or DSM.

(i)

The SSGS, IPPs and any other thermal generating station shall be required to demonstrate the declared

capability/capacity of its generating station as and when asked by the SLDC. In the event of the SSGS and IPPs

failing to demonstrate the declared capability, the capacity charges due to the generator shall be reduced as a

measure of penalty.

(j)

The quantum of penalty for the first mis-declaration for any duration/block in a day shall be the charges

corresponding to two days’ fixed charges. For the second mis-declaration the penalty shall be equivalent to fixed

charges for four days and for subsequent mis-declarations, the penalty shall be multiplied in the geometrical

progression over a period of a month.

(k) DISCOM(s) will give their requisitions on day ahead/Real time basis to the SLDC and SLDC shall operate

on real time basis as per individual Merit Order furnished by the DISCOM(s), i.e., in ascending order of the cost

of energy (i.e., variable cost) of generating stations excluding hydro, nuclear and REGS.

Notwithstanding anything contained in the clause (k), in the absence of any requisition from the DISCOM(s),

the SLDC shall operate on real time basis as per the Merit Order Despatch or as it deems fit and appropriate

in the given circumstances based on the available data.

(l)

The drawal schedule of any DISCOM issued by SLDC, considering economic operation of State grid

would be sum of ex-power plant schedules from different SSGS/IPPs/JVs, share from ISGS and any bilateral

exchange agreed by the DISCOMs and drawal/ injection on behalf of Open Access customers.

(m) The generation schedule of each SSGS shall be sum of the requisitions made by the Distribution

Licensee(s), restricted to their entitlement and subjected to maximum and minimum value criteria or any other

technical constraints indicated by SLDC.

(n) All the Intra State Users shall endeavour to maintain their Drawals/injections in such a manner that

they do not violate the limits on deviation volume as specified in the relevant Regulations/Orders issued by the

Commission.

(o) The following specific points would be taken into consideration, while preparing the schedules:

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

97

(i)

SLDC to check that the resulting power flows do not give rise to any transmission constraint. In

case of any constraints, SLDC has to moderate the schedule to the required extent, under intimation to concerned

Distribution Licensees and generating stations.

(ii)

SLDC to check that schedules are operationally reasonable particularly in terms of Ramping up /

Ramping down rates and ratio between minimum and maximum generation levels. SLDC to moderate the schedule

to the required extent under intimation to concerned Distribution Licensees. The ramping up / ramping down rates

in respect of different categories of stations would be as follows:

1.

Coal or lignite fired plants shall declare a ramp up or ramp down rate of not less than 1%

of ex-bus capacity corresponding to MCR on bar per minute;

2.

Gas power plants shall declare a ramp up or ramp down rate of not less than 3% of ex-bus

capacity corresponding to MCR on bar per minute;

3.

Hydro power plants shall declare a ramp up or ramp down rate of not less than 10% of

ex-bus capacity corresponding to MCR on bar per minute;

4.

Renewable Energy generating stations shall declare a ramp up or ramp down rate as per CEA

Technical Standards for Connectivity Regulations.

(p) Wind/ Solar generators, Hybrid of Wind and Solar Generating Stations and Energy Storage System

(ESS) shall mandatorily provide to SLDC, in a format as specified by SLDC, the technical specifications of their

plants at the beginning and whenever there is any change. The data relating to power system parameters and

weather-related data as applicable shall also be mandatorily provided by such generators to SLDC in real time.

(q) For calculating the net drawal schedule of DISCOMs, the transmission losses shall be apportioned in

proportion to their drawal schedule.

(r)

In addition to the above, the generators have to follow the provisions of the TNERC (Deviation Settlement

Mechanism and related matters) Regulations, 2019 and TNERC (Forecasting, Scheduling and Deviation Settlement

and related matters for wind and solar generation) Regulations, 2024 and amendments thereof issued from time

to time

[Note:- Commission vide Order No. 1-1 of 2024, dated 20-02-2024 has ordered that the Hydro Generating

Stations including the Pumped storage power plant of the TNGECL (formerly TANGEDCO) are exempted under

the purview of the Deviation Settlement Mechanism. This exemption for these power plants shall be continued

until further orders from the Commission. However, these Generating Power Plants shall declare the Declared

Capacity to the SLDC.]

11.4. Responsibilities of State Load Despatch Centre

The SLDC, in discharge of its functions under the Act and for stable, smooth and secure operation of the

integrated grid, shall be responsible for the following within its control area:

(a) Forecasting demand for its control area for each time block on day-ahead and intra-day basis;

(b) Forecasting of generation from wind/solar generators, Hybrid of Wind and Solar Generating Stations and

Energy Storage System (ESS) under its jurisdiction for each time block on day-ahead and intra-day basis:

Provided that such forecasts may be used by the wind /solar generators, Hybrid of Wind and Solar Generating

Stations and Energy Storage System (ESS) at their own risk and discretion along with all commercial liabilities

arising out of it;

(c) Scheduling and despatch for the entities in the State control area in accordance with contracts;

(d) SLDC shall certify the Declared Capacity of generating stations/units, which is under the purview of

SLDC and shall be binding on all the participants;

(e) Balancing demand and supply to minimize Area Control Error (ACE) for the State;

(f)

Maintaining and despatching reserves as shall be decided by SRPC as per guidelines of central agencies;

(g) Declaring Total Transfer Capability (TTC) and Available Transfer Capability (ATC) in respect of import

and export of electricity of its control area with inter-State transmission systems in coordination with the Central

Transmission Utility, State Transmission Utility and SRLDC and revising the same from time to time based on

grid conditions. Assessment of TTC and ATC shall be done on a continuous basis at least Eleven (11) months

TAMIL NADU GOVERNMENT GAZETTE

98

[Part   VI—Sec. 2

(M-12) in advance with addition of new elements (commissioned or to be commissioned). SLDC shall submit

morning peak, evening peak, day and night off-peak node-wise load data (MW and MVAR) for 66 kV and above

for the preparation of scenarios for computation of TTC and ATC by SRLDC and NLDC. STU in co-ordination

with Distribution Licensee(s) and generating stations shall submit this data to SLDC by 5th of M-12 month and

may revise on M-6 (by 5th day) and M-1 (by 5th day) months. TTC and ATC calculations for the State shall be

done based on procedure for the transfer capability assessment methodology published by NLDC.

11.5. Scheduling Process

(a) By 6 AM on ‘D-1’ day, each Intra-State SSGS/IPPs/CGPs/REGS/other generators connected with the

intra-state transmission system will intimate SLDC, station-wise ex-power plant MW and MWH capabilities foreseen

for the next day ‘D’, i.e., between 0000 hours to 2400 hours, at 15-minute intervals in the formats prescribed by

SLDC. The Generating Stations shall submit the following information:

(i)

Generating Station based on coal, gas and lignite:

1.

Time block-wise On-bar Declared Capacity (MW) for on-bar units.

2.

Time block-wise Off-bar Declared Capacity (MW) for off-bar units.

3.

Time block-wise Ramp up rate (MW/ min) for on-bar capacity.

4.

Time block-wise Ramp down rate (MW/min) for on-bar capacity.

5.

MWh capability for the day.

6.

Minimum turndown level (MW) and in percentage (%) of ex-bus capacity on-bar.

Note:- Declared Capacity shall be given as per unit wise/plant wise as requested by SLDC.

(ii)

Generating Station based on hydro energy:

1.

Time block-wise ex-bus declared capacity.

2.

MWh capability for the day.

3.

Ex-bus peaking capability in MW and MWh.

4.

Time block-wise Ramp up rate (MW/min) for on-bar capacity.

5.

Time block-wise Ramp down rate (MW/min) for on-bar capacity.

6.

Unit-wise/plant-wise forbidden zones in MW and percentage (%) of ex-bus installed capacity.

7.

Minimum MW and duration corresponding to requirement of water release for irrigation, drinking

water and other considerations.

8.

Unit-wise/plant-wise maximum MW along with probable combination of unit maximum in case

adequate water is not available.

Note:- Declared Capacity shall be given as per unit wise/plant wise as requested by the SLDC.

(iii) The renewable energy generating station based on wind/ solar, hybrid of wind and solar, individually or

represented by a lead generator or QCA, shall submit aggregate available capacity of the pooled generation and

aggregate schedule along with contract-wise breakup for each time block for 0000 hours to 2400 hours of the

‘D’ day, by 6 AM on ‘D-1’ day. The source-wise/Pooling sub-station wise breakup of aggregate available capacity,

schedules of the pooled generation shall also be furnished as per the Deviation Settlement Mechanism Regulations

and the procedures issued by the Commission.

(iv) ESS including pumped storage plant, individually or represented by the lead ESS or QCA on their behalf,

shall submit aggregate available capacity of the pooled generation and aggregate schedule along with contract-wise

breakup for each time-block for 0000 hours to 2400 hours of the ‘D’ day, by 6 AM on ‘D-1’ day. The source-wise/

Pooling sub-station wise breakup of aggregate available capacity, schedules of the pooled generation shall also be

furnished as per the Deviation Settlement Mechanism Regulations and the procedures issued by the Commission.

(v) The availability declaration/declared quantum by generating station shall have a resolution of two decimal

(0.01) MW and three decimal (0.001) MWh.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

99

(b) The entitlement of each Beneficiary or Buyer, from generating stations, shall be in accordance with

Regulation 49.1(b) of Indian Electricity Grid Code and amendments thereof.

(c) SRLDC shall declare share of each Beneficiary or Buyer for 0000 hours to 2400 hours of ‘D’ day,

by 7 AM on ‘D-1’ day.

(d) SLDC will compile the generator-wise availability for ISGS/ other agreements /SSGS/ IPPs/REGS

entitlement of each Beneficiary or Buyer for ‘D’ day at 15-minute interval and shall intimate the same to the

Distribution Licensee(s) including Deemed Licensees by 07:15AM on ‘D-1’ day.

(e) By 07:45 AM of ‘D-1’ day, the Distribution Licensee(s) including Deemed Licensees will furnish requisition

to SLDC in each ISGS, other agreements, Intra-State, SSGS/ IPPs/ REGS for 0000 hours to 2400 hours of ‘D’

day.

(f)

By 8 AM of ‘D-1’ day, SLDC shall convey the requisition of the State to SRLDC from ISGS/other

agreements/SSGS/ IPPs/ REGS for 0000 hours to 2400 hours of ‘D’ day.

(g) The SLDC on behalf of the intra-State entities while furnishing time block-wise requisition under this Grid

Code, subject to technical constraints, duly factor in merit order of the generating stations with which intra-State

entities has entered into contract(s) for drawal of power:

Provided that the renewable energy generating stations shall not be subjected to merit order despatch, and

subject to technical constraints shall be requisitioned first followed by requisition from other generating stations

in merit order.

(h) SRLDC shall check if drawal schedules as requisitioned can be allowed based on available transmission

capability:

Provided that in case of constraint in transmission system, the available transmission corridor shall be allocated

in proportion depending upon the transmission constraint, whether it is within the region or from outside the region,

as the case may be. The same shall be intimated by 8:15 AM on ‘D-1’ day.

(i)

The Intra-State Entity shall revise their requisition for drawal schedule based on availability of transmission

corridors by 8:30 AM on ‘D-1’ day.

(j)

SRLDC shall issue initial drawal schedules and injection schedules for the State by 9 AM on ‘D-1’ day.

SRLDC shall convey the generating station-wise drawal schedule of the State by 9:00 AM on ‘D-1’ day.

(k) The SLDC shall issue initial despatch/drawl schedules at 9.15 AM on ‘D-1’ day for the intra-state entities

under SLDC purview.

(l)

In case a generating station under the purview of SRLDC other than REGS intends to replace its

schedule by power supplied from REGS, it shall intimate the quantum and source of power in the SRLDC/NLDC

website by which it intends to replace the power already scheduled by 9:15 AM on ‘D-1’ day.

(m) SRLDC and subsequently SLDC, shall incorporate the request from the above said generating station

and finalize the injection and drawal schedules by 9:45 AM on ‘D-1’ day.

(n) SLDC shall issue modified depatch/drawl schedules at 10 AM on ‘D-1’ day for the intra-state entities

under SLDC purview if there are any changes in the intra-state entities.

(o) SRLDC shall release the balance corridors after finalisation of schedules for day ahead collective

transactions.

(p) Power Exchange(s) shall open bidding window for day ahead collective transactions from 10:00 AM to

11:00 AM of ‘D-1’ day. NLDC shall validate the same from system security point and inform the Power Exchange(s)

with revisions required, if any, due to transmission congestion or any other system constraint by 12:15 PM of

‘D-1’ day. The Power Exchange(s) shall submit the final trade schedules to NLDC for regional entities and to

SLDC for intra-State entities by 1:00 PM of ‘D-1’ day.

(q) SRLDC shall release balance corridors after finalisation of schedules under day ahead collective transactions

by 1:00 PM of ‘D-1’ day.

(r)

SRLDC/ SLDC shall process exigency applications received till 1:00 PM of ‘D-1’ day for ‘D’ day by 2:00

PM of ‘D-1’ day.

TAMIL NADU GOVERNMENT GAZETTE

100

[Part   VI—Sec. 2

(s) SRLDC, and subsequently SLDC, shall update the availability of balance transmission corridors, if any,

after finalisation of schedules for exigency applications by 2:00 PM of ‘D-1’ day on its website. The balance

transmission corridor may be utilised by way of revision of schedule, under any contract for exigency applications

or in real time market on first-come-first-served basis.

(t)

SLDC shall issue depatch/drawl schedules for State entities at 22:45 hours on ‘D-1’ day as final revision

before real-time market operation.

(u) All the entities participating in the real-time market may place their bids and offers on the Power

Exchange(s) for purchase and sale of power. The window for trade in real-time market for ‘D’ day shall open

from 22:45 hours to 23:00 hours of ‘D-1’ for the delivery of power for the first two time-blocks of 1st hour of

‘D’ day, i.e., 0000 hours to 0030 hours, and will be repeated every half an hour thereafter. NLDC shall indicate

to the Power Exchange(s) the available margin on each of the transmission corridors before the gate closure.

The Power Exchange(s) shall clear the real-time bids from 23:00 hours till 23:15 hours of ‘D-1’ day based on

the available transmission corridor and the buy and sell bids for the real time market (RTM) for the specified

duration and intimate the cleared bids to NLDC by 23:15 hours, for scheduling.

(v) NLDC shall finalise schedules under real time market (RTM) by 23:30 hours of ‘D-1’ day and SRLDC,

subsequently SLDC, shall publish the final schedules for depatch by 23:35 hours of ‘D-1’day. Subsequently, the

SLDC shall publish the schedules during intra-say operations.

(w) Scheduling process for the inter-state entities liable to change as per the IEGC and its relevant regulations.

Subsequently, SLDC shall change the scheduling process by incorporating the changes in the inter-state entities

whenever, there is change in scheduling timeline.

(x) The scheduled finalized by SLDC shall have the following:

• Ex-power plant generation schedule of SSGS/IPPs and other State generators including wind/solar

generators, Hybrid of wind and solar Generating Stations and Energy Storage System (ESS).

• Drawal schedule of State Distribution Licensees including Deemed Licensees.

11.6. Rules for revision in schedule

(a) In the event of a situation arising due to bottleneck in evacuation of power due to transmission constraint

in a block, SLDC shall revise the schedule, which shall become effective from the next time block.

(b) In case of any grid disturbance, the scheduled generation of all the generating stations and scheduled

drawal shall be deemed to be equal to their actual generation/ drawal for all the time blocks affected by grid

disturbance. The certificate of grid disturbance and its duration shall be declared by the SLDC or SRLDC and

the same will be binding on all intra-State transmission system Users:

Provided that in case, SLDC observes that there is a need for revision of schedule in the interest of State

Grid Security for better system operation and to facilitate integration of RE power into the grid, SLDC may do

so on its own and in such cases, the revised schedule shall become effective from next time block.

(c) Revision of Declared Capacity and schedule shall be allowed on account of forced outage of a unit of

an intra-State generating station or ESS (as an injecting entity) only in case of bilateral transactions and not in

case of collective transaction. Such generating station or ESS (as injecting entity) or the electricity trader or any

other agency selling power from the unit of the generating station or ESS shall immediately intimate the outage of

the unit along with the requisition for revision of Declared Capacity, schedule and the estimated time of restoration

of the unit, to SLDC. The schedule of beneficiaries, sellers and buyers of power from this generating unit shall

be revised on a pro-rata basis for all bilateral transactions. The revised Declared Capacity and schedules shall

become effective from 6th time block, counting the time block in which revision is advised by the generators to

be the first one. The revised declared capacity shall be considered based on the ramp-up rate of the generating

stations.

Provided that the generating station or ESS (as injecting entity) or Trading Licensee or any other agency

selling power from a generating station, or unit(s), or ESS, may revise its estimated restoration time only once

in a day.

Provided further that the SLDC shall inform the revised schedule to the seller and the buyer. The original

schedule shall become effective in the 6th time block from the estimated time of restoration of the unit.

Provided further that in case of inter-state transactions, the revision of schedule shall be carried out as per

the provisions of the IEGC as amended from time to time.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

101

(d) The generating station (other than lignite, gas based thermal generating station, and hydro generating

station) or ESS (as an injecting entity) shall be allowed a maximum of 4 (four) revisions of Declared Capacity

and schedule in a day subject to a maximum of 60 (sixty) revisions during a month, due to reasons such as a

partial outage of the unit or variation of fuel quality or any other technical reason to be recorded in writing:

Provided that SLDC may allow upward revision of DC beyond the above limit keeping in view of grid

requirements.

(e) The generating station based on lignite, gas, or hydro generating station shall be allowed 6(six) revisions

of Declared Capacity and schedule in a day subject to a maximum of 120 (One hundred twenty) revisions during

a month, due to reasons such as a partial outage of the unit or water availability for hydro generating stations

or fuel quality or variations in the supply of gas for gas generating stations or any other technical reason to be

recorded in writing:

Provided that SLDC may allow upward revision of DC beyond the above limit keeping in view grid requirements.

(f)

In case of requirement of revision of schedule due to forecasting error, a WS Seller may revise its

schedule only in case of bilateral transactions and not in case of collective transaction. Such revision of schedule

shall become effective from 6th time block, counting the time block in which the revision is informed by WS seller

to be the first one.

(g) In case of requirement of revision of Declared Capacity due to forecasting error, a Run-of-River generating

station may request for revision of its Declared Capacity and schedule only in case of bilateral transactions and

not in case of collective transaction. Such revision shall become effective from 6th time block, counting the time

block in which the revision is informed to SLDC to be the first one.

(h) If a revision is received from any ISGS stations, RLDC will flash the information in real-time basis

containing all the relevant information needed to revise the schedule based on which SLDC will process the

revision in parallel. The implementation time of revision will be same for both RLDC and SLDC.

(i)

SLDC, on behalf of intra-State drawee entities may revise their schedules, which shall become effective

from 6th time block, counting the time block in which the revised schedule is issued by SLDC to be the first

one:

Provided that scheduled transactions under short term open access once scheduled cannot be revised.

(j)

After the operating day is over at 24:00 hours, the schedule finally implemented during the ‘D’ day

(taking into account all before-the-fact changes in Despatch Schedule of Electricity Generating Stations and Drawal

Schedule of the other Intra-State Entities) shall be issued by SLDC within three (3) days or on receipt of SRLDC

implemented schedule. Further, the implemented schedule may be revised by SLDC, if Ex-post facto revision in

implemented schedule is made by SRPC/TNSPC. These Schedules shall form the basis for commercial accounting.

The average ex-bus capability for each SSGS and IPPs shall also be worked out based on all before-the-fact

advice to SLDC.

(k) The SLDC shall prepare detailed procedure for the scheduling as per this grid code within 60 days of

notification of these regulations duly consulting the stakeholders and submit it to the Commission for approval.

11.7. Scheduling from alternate source of power by a generating station

(a) A generating station may supply power from alternate source in case of forced outage of unit(s). This

facility shall also be available to a generating station other than REGS replacing its scheduled generation by

REGS, irrespective of whether such identified sources are located within or outside the premises of the generating

station.

(b) The methodology for scheduling of power from alternate sources covered under forced outage of unit(s)

shall be as per the following steps:

(i)

The generating station may enter into contract with alternate supplier under bilateral transaction or

collective transaction.

(ii)

In case of bilateral transaction, the generating station shall request SLDC to schedule power from

such alternate supplier to its beneficiaries, which shall become effective from 6th time block.

(iii) The power scheduled from alternate supplier shall be reduced from the schedule of the generating

station.

(iv) In case, alternate supply is arranged through collective transactions, the transacted quantum shall

be reduced from the scheduled generation of the generating station.

TAMIL NADU GOVERNMENT GAZETTE

102

[Part   VI—Sec. 2

(v) The generating station shall not be required to pay the transmission charges and losses for such

purchase of power to supply to the buyer from alternate sources.

(c) The methodology for scheduling of power from alternate sources for a generating station other than

REGS replacing its scheduled generation by power supplied from REGS shall be as per the following steps:

(i)

The generating station shall enter into contract with REGS for supply of power from alternate

sources.

(ii)

The generating station shall request SLDC to schedule power from such alternate source to its

beneficiaries, which shall become effective from 6th time block.

(iii) The power scheduled from alternate source shall be reduced from the schedule of the generating

station.

(iv) The generating station shall not be required to pay the transmission charges and losses for such

purchase and supply from alternate sources to the buyer.

(d) In case of a generating station whose tariff is determined by the Commission under Section 62 of the

Act, supply of power by such generating station to its buyer from an alternate source, shall be subject to the

Commission’s Regulations/Orders issued from time to time.

(e) In case of a generating station other than whose tariff is determined by the Commission under Section

62 of the Act, supply of power by such generating station to its buyer from an alternate source shall be in

accordance with the contract with the buyer and in the absence of a specific provision in the contract, in terms

of mutual consent including on sharing of net savings between the generating station and the buyer.

11.8. Minimum Turndown Level for operation of Thermal Generating Stations

(a) The technical minimum level for operation in respect of thermal generating units connected to STU network

and which is in the control area of SLDC shall be 55% of the MCR of the said unit or such other minimum

power level as specified in the CEA Flexible Operation Regulations as amended from time to time, whichever is

lower:

Provided that the Commission may, through an order, fix a different minimum turndown level of operation in

respect of specific unit(s) of a thermal generating station:

Provided further that such generating station on its own option may declare a minimum turndown level below

the minimum turndown level specified in this Regulation:

Provided also that the thermal generating stations whose tariffs are determined under Section 62 or Section

63 of the Act, shall be compensated for part load operation, i.e., for generation below the normative level of

operation, in terms of the provisions of the contract entered into by such generating stations with the beneficiaries

or buyers, or in the absence of such provision in the contract, as per the mechanism specified in the applicable

Tariff Regulations or to be specified by the Commission separately.

(b) The SSGS having 100% installed capacity tied up/contracted with DISCOM(s) of the State through

long-term PPA and whose tariff is determined by the Commission, may be directed by SLDC to operate below

normative plant availability factor but at or above technical minimum. In such cases, SSGS shall be compensated

as per the provisions of the TNERC (Terms and conditions for determination of Tariff) (Amendment) Regulations,

2025 or other Regulations as notified by the Commission from time to time on monthly basis duly supported by

relevant data verified by SLDC.

(i)

In case the scheduled generation of the Coal/Lignite based generating stations falls below the

technical minimum schedule, the concerned generating stations shall have the option to go for reserve shut

down and in such cases, start-up fuel cost over and above seven (7) start/stop in a year shall be considered

as additional compensation based on the provisions of the TNERC (Terms and conditions for determination of

Tariff) (Amendment) Regulations, 2025 or other Regulations as notified by the Commission from time to time.

(ii)

Compensation for Station Heat Rate and Auxiliary Energy Consumption shall be worked out in terms

of energy charges.

(iii) The compensation so computed shall be borne by the entity who has caused the plant to be

operated at schedule lower than corresponding to Normative Plant Availability Factor up to technical minimum

based on the compensation mechanism finalized by SLDC, which shall be guided by the mechanism finalized by

SRPC.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

103

(iv) No compensation for Heat Rate degradation and Auxiliary Energy Consumption shall be admissible,

if the actual Station Heat Rate and/ or actual Auxiliary Energy Consumption are lower than normative Station

Heat Rate and / or normative Auxiliary Energy Consumption applicable to unit or generating station in a month

or after annual reconciliation at the end of year.

(v) There shall be reconciliation of compensation at the end of financial year taking into due consideration

of actual weighted average operational parameters of station heat rate, auxiliary energy consumption and secondary

oil consumption.

(c) In case of generating stations other than SSGS, wherein the 100% installed capacity is not tied up with

DISCOM(s) of the State or whose tariff for only partial/contracted capacity is determined by the Commission, such

generating station may have to appropriately factor in the above provisions in their PPAs entered with DISCOM(s)

for sale of power, in order to claim compensation for operating at the technical minimum schedule.

11.9.

Data Registration

User shall provide SLDC with data for this chapter as specified in Data Registration Code.

Chapter 12 - Frequency and Voltage Management Code

12.1. Introduction

This chapter describes the method by which all Users of the State Transmission System shall coordinate with

SLDC and STU in contributing towards effective control of the system frequency and managing the EHV voltage

of the State Transmission System.

State Transmission System normally operates in synchronism with the Southern Region Grid and SRLDC has

the overall responsibility of the integrated operation of the Southern Regional Power System. The constituents

of the Region are required to follow the instructions of SRLDC for backing down generation, regulating loads,

MVAr drawal, etc., to meet the objective. SLDC shall accordingly instruct Generating Units to regulate generation/

export and hold reserves of active and reactive power within their respective declared parameters. SLDC shall

also regulate the load as may be necessary to meet the objective.

12.2. Objective

The objectives of this chapter are as follows:

•

To define the responsibilities of all Users in contributing to frequency and voltage management.

•

To define the actions required to enable SLDC and STU to maintain State Transmission System voltages

and frequency within acceptable levels in accordance with IEGC/State Grid Code.

12.3. Frequency Management

(a) The rated frequency of the system shall be 50.000 Hz and shall normally be regulated within the

allowable band of 49.900-50.050 Hz in line with IEGC. The frequency shall be measured with a resolution of

+/- 0.001 Hz by SLDC and such frequency data measured every second shall be archived by SLDC.

(b) Falling frequency

SLDC shall take appropriate action to issue instructions, in co-ordination with SRLDC to arrest the falling

frequency and restore it, within permissible range. Such instructions may include despatch instruction to generators

under control area of SLDC and/or instruction to DISCOMs/Users to reduce load demand manually and/or through

automatic load shedding.

(c) Rising Frequency

SLDC shall take appropriate action to issue instructions to the generators under its control in co-ordination

with SRLDC, to arrest the rising frequency and restore frequency within permissible range. SLDC shall also issue

instructions to DISCOMs/ Users in coordination with SRLDC to lift Load shedding, if any persist.

12.4. Reserve

(a) There shall be reserves as under:

(i)

Primary, Secondary and Tertiary reserves:

1.

Primary, Secondary and Tertiary reserves shall be deployed for the purpose of frequency control,

reducing area control error and relieving congestion.

TAMIL NADU GOVERNMENT GAZETTE

104

[Part   VI—Sec. 2

2.

The response under Primary reserve shall be provided as per this Grid Code.

3.

Secondary reserves including automatic generation control and demand response shall be

deployed in the control area as may be notified by the Commission separately indicating the date from which

such deployment of Secondary reserves shall be effective.

4.

Tertiary reserves shall be deployed in the control area as may be notified by the Commission

separately indicating the date from which such deployment of Tertiary reserves shall be effective.

(ii)

Black Start reserves:

Generating stations having black start capability, ESS, and HVDC Station based on VSC, shall be identified

by NLDC and RLDCs in consultation with SLDC at the inter-State level and by SLDC at the State level, to act

as black start reserves.

(iii) Voltage Control reserves:

Voltage Control reserves shall be deployed for controlling the voltage at a bus or sub-system through reactive

power injection or drawal.

(b) The mechanism of procurement and deployment of Primary Reserves Ancillary Service (PRAS) shall be

as specified in this Grid Code or by separate order.

(c) The mechanism of procurement, deployment and payment of Secondary Reserve Ancillary Service and

Tertiary Reserve Ancillary Service shall be as may be notified by the Commission.

(d) The primary response of the generating units shall be verified by SLDC during grid events. The concerned

generating station shall furnish the requisite data to SLDC within two days of notification of reportable event.

12.5. Control Hierarchy

(a) Inertia

The power system shall be operated at all times with a minimum inertia to be stipulated by NLDC so that

the minimum nadir frequency post reference contingency stays above the threshold set for under frequency load

shedding (UFLS). To maintain the minimum inertia, the NLDC may, if required, bring quick start synchronous

generation on bar and reschedule generation including curtailment of wind, solar and wind-solar hybrid generation,

in coordination with the respective RLDC and SLDC. The compensation for such quick start synchronous generation

shall be included in the procedure to be prepared by SLDC in line to NLDC and approved by the appropriate

Commission.

(b) Primary Control

(i)

Primary control is local automatic control in a generating unit or energy storage system or demand

side resource for the purpose of adjusting its active power output or consumption, as the case may be, in

response to frequency excursion. Primary control is the immediate automatic control implemented through turbine

speed governors or frequency controllers.

(ii)

Primary control shall be provided by the Primary Reserves Ancillary Service (PRAS).

(iii) The minimum quantum of PRAS required for reference contingency shall be declared by NLDC in

consultation with SLDC at the start of each financial year.

(iv) The generating stations and units thereof shall have electronically controlled governing systems or

frequency controllers in accordance with the CEA Technical Standards for Connectivity Regulations and are mandated

to provide PRAS. The generating stations and units thereof with governors shall be under Free Governor Mode

of Operation.

(v) NLDC in consultation with SLDC may also identify other resources such as ESS and demand

resource to provide PRAS for which PRAS providers shall be compensated in accordance, as may be notified

by the Commission.

(vi) The minimum All India target frequency response characteristics (FRC) shall be estimated and

based on such target FRC, the frequency response obligation of each control area shall be assessed by NLDC

in consultation with SLDC, giving due consideration to generation and load within each control area and details

as given in Table below. The same shall be informed to all control areas by 15th of March every year for the

next financial year.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

105

(vii) All the generating units shall have their governors or frequency controllers in operation all the time

with droop settings as specified in the CEA Technical Standards for Connectivity Regulations. The primary response

requirement of various types of generating units shall be as mentioned below:

Fuel/ Source

Minimum unit size/

Capacity

Up to

Coal/Lignite Based

200 MW and above

±5% of MCR

Hydro

25 MW and above

±10% of MCR

Gas based

Gas Turbine above 50 MW

±5% of MCR (corrected for

ambience temperature)

WS Seller

Capacity of Generating

station more than 10 MW and

connected at 33 kV and above

As per CEA Technical Standards

for Connectivity Regulations.

Provided that:

i)

WS Sellers commissioned after the date as specified in CEA Technical Standards for Connectivity

Regulations, shall have the option to provide primary response individually through ESS or through a common

ESS installed at its pooling station.

ii)

Nuclear generating stations and hydro generating stations (with pondage up to 3 hours or Run of

the river projects) shall be exempt from mandatory primary response. They may provide the primary response to

the extent possible, considering the safety and security of machines and humans.

(viii) All generating stations mentioned in above table shall have the capability of instantaneously picking up

to a minimum of 105% of their operating level and up to 105% or 110% of their MCR, as the case may be,

when the frequency falls suddenly and thus providing primary response whenever conditions arise.

(ix) Any generating station not complying with the above requirements shall be kept in operation (synchronized

with the regional grid) only after obtaining the permission of SLDC.

(x) All generating stations, including the WS Seller as mentioned in the above table, shall have the capability

of reducing output at least by 5% or 10%, as applicable, of their operating level and up to 5% or 10% of

their MCR, as applicable, limited to the minimum turndown level when the frequency rises above the reference

frequency and thus, providing primary response, whenever conditions arise. Any generating station not complying

with the above requirements shall be kept in operation (synchronized with the regional grid) only after obtaining

permission from SLDC.

(xi) The normal governor action shall not be suppressed in any manner through load limiter, Automatic

Turbine Run-up System (ATRS), turbine supervisory control or coordinated control system, and no time delays

shall be deliberately introduced. In the case of a renewable energy generating unit, a reactive power limiter or

power factor controller or voltage limiter shall not suppress the primary frequency response within its capabilities.

The inherent dead band of a generating unit or frequency controller shall not exceed +/- 0.03 Hz. The governor

shall be set with respect to a reference frequency of 50.000 Hz and response outside the dead band shall be

with respect to a total change in frequency.

(xii) The thermal and hydro generating units shall not resort to Valve Wide Open (VWO) operation to make

available margin for providing governor action.

(xiii) The Primary Reserves Ancillary Service (PRAS) shall start immediately when the frequency deviates

beyond the dead band as specified in above Regulation 12.5(b)(x) and shall be capable of providing its full PRAS

capacity obligation within 45 seconds and sustaining at least for the next five (5) minutes.

(xiv) Each control area shall assess its frequency response characteristics and share the assessment with the

concerned SRLDC along with high resolution data of at least one (1) second for generating stations and energy

storage systems and ten (10) seconds for the State control area.

(xv) The SRLDC shall calculate actual frequency response characteristics of all the control areas within its

region. The performance of each control area in providing frequency response characteristics shall be calculated

for each reportable event as per IEGC.

(xvi) NLDC in consultation with RLDCs/SLDCs shall calculate the actual frequency response characteristics

at national level by factoring in the FRC of all regions and shall also calculate the FRC for cross-border control

areas.

TAMIL NADU GOVERNMENT GAZETTE

106

[Part   VI—Sec. 2

(xvii) NLDC, RLDC and SLDC shall grade the median Frequency Response Performance annually, considering

at least ten (10) reportable events. In case the median Frequency Response Performance is less than 0.75 as

calculated, NLDC, RLDCs, SLDCs, as the case may be, after analysing the FRP, shall direct the concerned

entities to take corrective action. All such cases shall be reported to the concerned RPC for its review.

(c) Secondary Control and Tertiary Control shall be such as may be notified by the Commission separately.

12.6. Voltage Management

(a) Users using the State Transmission System shall make all possible efforts to ensure that the grid voltage

always remains within the limits specified in IEGC and amended thereof. The specified limits of voltage specified

in IEGC are reproduced below:

Voltage (kV rms)

Nominal

Maximum

Minimum

765

800

728

400

420

380

230*

245*

207*

110

121

99

33

36

30

* As per CEA Manual on Transmission Planning Criteria and updated thereof.

(b) STU and/or SLDC shall carry out load flow studies based on operational data available from time to

time, to predict where voltage problems may be encountered and to identify appropriate measures to ensure that

voltages remain within the defined limits. On the basis of these studies, SLDC shall instruct the generators within

its control area to maintain specified voltage level at interconnecting points. SLDC and STU shall co-ordinate

with the DISCOM(s) to determine voltage level at the inter-connection points. SLDC shall continuously monitor

400/220/110 kV voltage levels at strategic sub-stations.

(c) SLDC shall take appropriate measures to control State Transmission System voltages, which may

include but not be limited to transformer tap changing, capacitor/ reactor switching including capacitor switching by

DISCOM(s) at 33kV sub-stations, operation of Hydro unit as synchronous condenser and use of MVAr reserves with

the generators within its control area within technical limits agreed to between STU and Generators. Generators

shall inform SLDC of their reactive reserve capability promptly on request.

(d) SSGS and IPPs shall make available to SLDC, the up-to-date capability curves for all Generating Units,

indicating any restrictions, to allow accurate system studies and effective operation of the State Transmission

System. CGPs shall similarly furnish the net reactive capability that will be available for Export to/ Import from

State Transmission System.

(e) DISCOM(s) and Open Access Users shall participate in voltage management by providing local VAR

compensation (as far as possible in low voltage system close to load points) such that they do not depend upon

EHV grid for reactive support.

12.7. Reactive Power management

(a) All Users shall endeavour to maintain the voltage at the inter-connection point in the range specified in

the Grid Code.

(b) All generating stations shall be capable of supplying reactive power support so as to maintain power

factor at the point of inter-connection within the limits of 0.95 lagging to 0.95 leading as per the CEA Technical

Standards for Connectivity Regulations and amendments thereof.

(c) The distribution licensees, OA and bulk consumers shall ensure the following:

i.

They shall maintain neutral grounding of their installation and shall isolate the installation whose

neutral grounding is imperfect; and

ii.

They shall switch off capacitor banks if voltage exceed 105% of nominal system voltage and shall

switch off shunt reactors if voltage goes below 95% of nominal voltage

(d) All generating stations connected to the grid shall generate or absorb reactive power as per instructions

of SLDC, within the capability limits of the respective generating units, where capability limits shall be as specified

by the OEM.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

107

(e) The reactive interchange of Users shall be measured and monitored by SLDC/ SRLDC.

(f)

SLDC/SRLDC may direct the Users about reactive power set-points, voltage set-points and power factor

control to maintain the voltage at inter-connection points.

(g) SLDC shall assess the dynamic reactive power reserve available at various sub-stations or generating

stations under any credible contingency on a regular basis based on technical details and data provided by Users,

as per the procedure specified by NLDC/ SLDC.

(h) SLDC shall take appropriate measures to maintain the voltage within limits, inter-alia, using the following

facilities, but not limited to and the facility owner shall abide by the instructions of NLDC, RLDCs and SLDCs:

(i)

Shunt reactors,

(ii)

Shunt capacitors (excluding HVDC automatic control),

(iii) Thyristor-Controlled Series Capacitor (TCSC),

(iv) Voltage Sourced Converter (VSC) based High Voltage Direct Current (HVDC),

(v) Synchronous/non-synchronous generator voltage control including inverter based reactive power

support,

(vi) Synchronous condenser,

(vii) Static VAR compensators (SVC), STATCOM and other FACTS devices,

(viii) Transformer tap change: generator transformer and inter-connecting transformer,

(ix) HVDC power order or HVDC controller selection to optimise filter bank.

(i)

Reactive power facility shall be in operation at all times and shall not be taken out without the permission

of SLDC.

(j)

Periodic or seasonal tap changing of inter-connecting transformers and generator transformers shall be

carried out to optimize the voltages, subject to technical feasibility, and wherever necessary, other options such

as tap staggering may be carried out in the network.

(k) Hydro and gas generating units having this capability shall operate in synchronous condenser mode

operation as per instructions of the SRLDC or SLDC. Standalone synchronous condenser units shall operate as

per the instructions of SRLDC or SLDC.

(l)

Any commercial settlement for reactive power shall be governed as per the regulatory framework specified

in Appendix-J.

(m) If voltage is outside the limit as specified in Regulation 12.6(a) of the Grid Code and the means of

voltage control set out in Regulation 12.7(h) of the Grid Code are exhausted, SLDC shall take all reasonable

actions necessary to restore the voltages so as to be within the relevant limits including switching ON or OFF

of lines considering the security of the system.

(n) Notwithstanding the above, SLDC may direct the State entities to curtail VAr drawal/injection in case the

security of grid or safety of any equipment is endangered.

(o) In general, the State entities shall endeavour to minimize the VAr drawal at an interchange point when

the voltage at that point is below 95% of rated voltage, and shall not return VAr when the voltage is above

105%. Transformer taps at the respective drawal points may be changed to control the VAr interchange only as

per the instructions of SLDC.

(p) Switching in/out of 400 kV bus and line reactors in the intra-state transmission grid shall be carried out

as per instructions of SRLDC/SLDC. Tap changing of all identified transformers shall be carried out as per SLDC

instructions.

(q) All the Inverter Based Resources (IBRs) covering wind, solar and energy storage shall ensure that they

have the necessary capability, as per CEA Connectivity Standards, all the time including non-operating hours

and night hours for solar. The active power consumed by these devices for purpose of providing reactive power

support, when operating under synchronous condenser/night-mode, shall not be charged under deviations and shall

be treated as transmission losses in the ISTS. For IBRs of capacity 10 MW and below not coming directly to the

point of interconnection but through the pooling at the Power Park Developer end, the Power Park Developer or

the QCA shall act as aggregator for the Reactive Energy Charges for payments to and from the Pool Account

TAMIL NADU GOVERNMENT GAZETTE

108

[Part   VI—Sec. 2

at SLDC level. The de-pooling of Reactive Energy charges amongst the individual wind and solar shall be done

by the Power Park Developer or QCA or aggregator.

12.8. General

Close co-ordination between Users and SLDC and STU shall exist at all times for the purposes of effective

frequency and voltage management.

Chapter 13 - Monitoring of Generation and Drawal Code

13.1. Introduction

The monitoring of generating stations output and active and reactive reserve capacity is important to evaluate

the performance of generation stations. The monitoring of scheduled drawal is important to ensure that STU,

Transmission Licensees and DISCOM(s) contribute towards improving system performance and observe grid discipline.

13.2. Objective

The objective of this chapter is to define the responsibilities of generating stations in monitoring of generating

unit reliability and performance and DISCOM(s)/Users compliance with the scheduled drawal to assist SLDC in

managing voltage and frequency.

13.3. Monitoring Procedure

(i)

SLDC shall continuously monitor generating unit outputs and bus voltages for effective operation of the

State Transmission System and ensure that declared availability of generating stations are realistic.

(ii)

SLDC can instruct a generating station to demonstrate its declared availability, in case SLDC has a

reason to believe that declared availability of generating station does not match with actual availability or declared

output does not match the actual output.

(iii) SLDC shall inform the generating stations, in writing, if continued monitoring demonstrates an apparent

persistent or material mismatch between the despatch instructions and the generating unit output or breach of

the Connection Conditions. Continued discrepancies shall be resolved in Grid Code Review Committee meeting

with a view to either improve performance in future, providing more realistic declarations or initiate appropriate

actions for any breach of Connectivity Conditions.

(iv) Generating stations shall provide to SLDC hourly generation summation outputs whenever telemetry data

is not available through SCADA/ RTU equipment. Generating stations shall also provide any other logged readings

that SLDC requires, for monitoring and reporting purposes.

13.4. Generating Unit Trippings

(i)

Generating stations shall immediately inform the tripping of a generating unit, with reasons, to SLDC in

accordance with the operational event/accident reporting Regulation. SLDC shall keep a written log of all such

trippings, along with reasons, with a view demonstrating the effect on system performance and identifying the

need for remedial measures.

(ii)

The operating log books/log records of the generating station and EHV sub-stations shall be available

for review by SLDC. These books/records shall keep record of machine operation, outage/tripping of transmission

elements and maintenance.

13.5. Monitoring of Drawal

(i)

SLDC shall continuously monitor actual MW drawal by DISCOM(s) against that scheduled by use of

SCADA equipment. STU shall request SRLDC and adjacent States as appropriate to provide any additional data,

if required to enable this monitoring to be carried out.

(ii)

SLDC shall also monitor the actual MVAr drawal to the extent possible. This will be used to assist in

voltage management of the State Transmission System.

13.6. Data Requirement

Users shall submit data to SLDC as listed in Data Registration Code, termed as Monitoring of Generation.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

109

Chapter 14 - Outage Planning Code

14.1. Introduction

This chapter describes the process by which STU carries out the planning of State Transmission System

Outages, including interface co-ordination with Users. Outage planning shall be done by SLDC for the grid elements

in a coordinated and optimal manner, keeping in view the system operating conditions and grid security. The

coordinated generation and transmission outage plan for the State grid shall take into consideration all the available

generation resources, demand estimates, transmission constraints, and factor in water for irrigation requirements,

if any. To optimize the transmission outages of the State grid, to avoid grid operation getting adversely affected

and to maintain system security standards, the outage plan shall also take into account the generation outage

schedule and the transmission outage schedule.

14.2. Objective

The objective of this chapter is to define the process, which will allow STU to optimise its transmission

system outage, while maintaining the system security to the extent possible.

14.3. Annual Outage Planning and Process

(a) Each User shall provide their operational planning data including outage programme as per Appendix-C

for ensuing financial year to SLDC for preparing an overall outage plan for State Transmission System, as a

whole. SLDC shall be responsible for analysing the outage schedules of Users and preparing a draft annual

outage Plan for State Transmission System in co-ordination with Outage Plan prepared for the region by SRPC.

SLDC is authorised to defer the planned outage in case of any of the following events:

(i) Major grid disturbance;

(ii)

System Isolation;

(iii) Black out in the State;

(iii) Any other event in the system that may have an adverse impact on system security by the proposed

outage.

(b) Annual outage plan shall be prepared in advance for the financial year by SLDC in consultation with STU

and DISCOMs and reviewed during the year on Bi-Monthly basis. Annual outage plan shall be prepared in such a

manner as to minimize the overall downtime, particularly where multiple entities are involved in the outage of any

grid elements. The outage planning of hydro generating stations, REGS and ESS and its associated evacuation

network shall be planned with a view to extract maximum generating from these sources. Example: Outage of wind

generator should be planned during lean wind season, whereas outage of solar, if required, should be planned

during the rainy season, and outage of hydro power plant should be planned in the lean water season.

(c) Generating stations connected to State grid shall furnish their proposed outage programme for the

next financial year in writing by 15th September of each year. The outage programme shall contain details like

identification of unit, reason for outage, generation availability affected due to such outage, outage start date and

duration of outage.

(d) SLDC shall also obtain from STU, the proposed outage programme for transmission lines, equipment

and sub-stations, etc., for next financial year by 15thSeptember each year. STU outage programmes shall contain

identification of lines/ sub-stations, reason for outage, outage start date and duration of outage.

(e) Scheduled outage of 400 kV transmission elements and other inter-State lines shall be effected only

with the approval of SRPC in coordination with SLDC.

(f)

The above annual outage plan shall be reviewed by SLDC on bi-monthly basis in Operation and

Co-Ordination Committee meeting in coordination with all parties concerned, to chalk out the outage of State

transmission system and adjustments made wherever found to be necessary.

(g) SLDC shall submit Load Generation Balance Report (LGBR) for its control area to SRPC Secretariat

in writing for the next financial year by 31st October of each year. These shall contain identification of each

generating unit/transmission line/ ICT, etc., the preferred date for each outage and its duration and where there

is flexibility, the earliest start date and latest finishing date. The annual plans for managing deficits/ surplus in

respective control areas shall clearly be indicated in the LGBR submitted by SLDC.

(h) The RPC Secretariat shall be primarily responsible for finalization of LGBR and the annual outage plan

for the following financial year by 31st December of each year.

TAMIL NADU GOVERNMENT GAZETTE

110

[Part   VI—Sec. 2

14.4. Schedule for availing of shutdowns

(a) SLDC would review on daily basis the outage schedule for the next two days and in case of any

contingency, defer any planned outage as deemed fit, clearly stating the reasons thereof. The revised dates in

such cases would be finalized in consultation with User.

(b) Each User and STU shall obtain the final approval from SLDC prior to availing an outage.

14.5. Demand and Load Management

(a) The demand and load shall be managed for ensuring grid security.

(b) SLDC, in coordination with STU and Distribution Licensee(s), shall develop Automatic Demand Management

scheme with emergency controls at SLDC.

(c) Whenever the power system is in an alert state or emergency state as assessed by SLDC:

(i)

the respective Distribution Licensee or bulk consumer under the control area of the State shall abide

by the directions of SLDC to secure the system and extreme measures like load shedding may be carried out

as a last resort.

(ii)

SLDC may direct Distribution Licensees or bulk consumers directly connected to STU, to restrict

drawal from the grid or curtail load to ensure the stability of the grid:

Provided that load shedding shall be resorted to after the demand response option has been exhausted.

(iii) The load disconnected, if any, shall be restored as soon as possible on clearance from SLDC, after

the system has been normalized.

14.6. Post-Despatch Analysis

(a) Operational analysis

(i)

SLDC shall analyse the following:

1.

Pattern of demand met, under drawals and over drawals, frequency profile, voltage and tie-line flows,

angular spread, area control error, reserve margin, load and RE forecast errors, ancillary services despatched,

transmission congestion and (n-1) violations;

2.

Generation mix in terms of source and station-wise generation;

3.

Irregular pattern in any of the system parameters mentioned in Regulation 14.6(a)(i)(1) and Regulation

14.6(a)(i)(2) of the Grid Code and reasons thereof; and

4.

Extreme weather events or any other event affecting grid security.

(ii) Such analysis shall be disclosed by SLDC on its website.

(iii) SLDC shall prepare a quarterly report that shall bring out the system constraints, reasons for not

meeting the requirements, if any, of security standards and quality of service, along with details of actions taken,

including by those responsible for causing disturbances in the system parameters.

(iv) SLDC shall also provide such a report to SRPC.

(v) For the purpose of analysis and reporting, telemetered data shall be archived with a granularity of

not more than five (5) minutes and higher granularity for special events. Such data shall be stored by SLDC for

at least fifteen (15) years and reports shall be stored for twenty-five (25) years for operational analysis.

(b) Event reporting

(i)

Event reporting shall make available adequate data to facilitate event analysis:

1.

Immediately following an event (grid disturbance or grid incidence as defined in the CEA Grid Standards

Regulation and amendments thereof) in the system, the concerned User or SLDC shall inform SRLDC through

voice message.

2.

Written flash report shall be submitted to SLDC by the concerned User within the timeline specified in

Table below.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

111

3.

Disturbance Recorder (DR), station Event Logger (EL) and Data Acquisition System (DAS) shall be

submitted within the timeline specified in Table below.

4.

SLDC shall report the event (grid disturbance or grid incidence) to CEA, RPC and all regional entities

within twenty-four (24) hours of receipt of the flash report.

5.

After a complete analysis of the event, the User shall submit a detailed report in the case of grid

disturbance or grid incidence within one (1) week of the occurrence of event to SLDC.

(ii)

SLDC shall prepare a draft report of each grid disturbance or grid incidence including simulation

results and analysis, which shall be discussed and finalized at the Protection sub-committee of RPC as per the

timeline specified in Table below.

Sl.

No.

Grid Event^

(Classification)

Flash report

submission

deadline

(Users/ SLDC)

Disturbance

record and

station event

log submission

deadline (Users/

SLDC)

Detailed report

and data

submission

deadline (Users/

SLDC)

Draft report

submission

deadline

(RLDC/

NLDC)

Discussion

in protection

committee meeting

and final report

submission

deadline (RPC)

1

GI-1/GI-2

8 hours

24 hours

+7 days

+7 days

+60 days

2

Near miss event

8 hours

24 hours

+7 days

+7 days

+60 days

3

GD-1

8 hours

24 hours

+7 days

+7 days

+60 days

4

GD-2/GD- 3

8 hours

24 hours

+7 days

+21 days

+60 days

5

GD-4/GD- 5

8 hours

24 hours

+7 days

+30 days

+60 days

^The classification of Grid Disturbance (GD)/Grid Incident (GI) shall be as per the CEA Grid Standards

(iii) Categorisation of grid incidents and grid disturbance based on severity of trippings.- The categorisation

of grid incidents and grid disturbances shall be as follows:-

1.

Categorisation of grid incidents in increasing order of severity,-

Category GI-1 - Tripping of one or more power system elements of the grid like a generator, transmission

line, transformer, shunt reactor, series capacitor and Static VAR Compensator, which requires re-scheduling of

generation or load, without total loss of supply at a sub-station or loss of integrity of the grid at 110 kV;

Category GI-2 - Tripping of one or more power system elements of the grid like a

generator, transmission line, transformer, shunt reactor, series capacitor and Static VAR Compensator, which

requires re-scheduling of generation or load, without total loss of supply at a sub-station or loss of integrity of

the grid at 230 kV and above.

2.

Categorization of grid disturbance in increasing order of severity,-

Category GD-1

When less than ten percent of the antecedent generation or load

in a State grid is lost.

Category GD-2

When ten percent. to less than twenty percent of the antecedent

generation or load in a State grid is lost.

Category GD-3

When twenty percent to less than thirty percent. of the antecedent

generation or load in a State grid is lost.

Category GD-4

When thirty percent to less than forty percent of the antecedent

generation or load in a State grid is lost.

Category GD-5

When forty percent or more of the antecedent generation or load

in a State grid is lost.

Explanation: For the purpose of categorization of grid disturbances, percentage loss of generation or load,

whichever is higher shall be considered.

(iv) The implementation of the recommendations of the final report shall be monitored by the Protection sub-

committee of the RPC. NLDC shall disseminate the lessons learnt from each event to all the RPCs for necessary

action in the respective regions.

TAMIL NADU GOVERNMENT GAZETTE

112

[Part   VI—Sec. 2

(v) Any additional data such as single line diagram (SLD) of the station, protection relay settings, HVDC

transient fault record, switchyard equipment and any other relevant station data required for carrying out analysis

of an event by RPC, NLDC, RLDC and SLDC, shall be furnished by the Users including RLDC and SLDC, as

the case may be, within forty- eight (48) hours of the request. All Users shall also furnish high-resolution analog

data from various instruments including power electronic devices like HVDC, FACTS, renewable generation (inverter

level or WTG level) on the request of RPC, NLDC, RLDC and SLDC.

(vi) Triggering of STATCOM, TCSC, HVDC run-back, HVDC power oscillation damping, generating station

power system stabilizer and any other controller system during any event in the grid shall be reported to SLDC,

if connected to an intra-State system. The transient fault records and event logger data shall be submitted to the

SLDC within twenty-four (24) hours of the occurrence of the incident. Generating stations shall submit one (1)

second resolution active power and reactive power data recorded during oscillations to SLDC within twenty-four

(24) hours of the occurrence of the oscillations.

(vii) A monthly report on events of unintended operation or non-operation of the protection system shall be

prepared and submitted by each User to SLDC within the first week of the subsequent month.

Chapter 15 - Contingency Planning Code

15.1. Introduction

This chapter describes the steps in the recovery process to be followed by all Users in the event of total

or partial blackouts of the State Transmission System or Regional System.

15.2. Objective

The objective of this chapter is to define the responsibilities of all Users to achieve the fastest recovery

in the event of blackout of State Transmission System or Regional System, taking into account essential loads,

Generator capabilities and system constraints.

15.3. Contingency Planning Procedure

(a) SLDC shall prepare contingency plan to efficiently handle the following two types of contingencies:

(i)

Partial system black out in the State due to multiple tripping of the transmission lines emanating

from power stations/sub-station; and

(ii)

Total black out in the State/Region.

(b) In case of partial black out in the system/State, priority should be given for early restoration of power

station units, which are tripped. Start-up power for the power station shall be extended through shortest possible

line and within shortest possible time from adjoining sub-station/power station where the supply is available.

Synchronising facility at all power stations and 400/230kV sub-station shall be available.

(c) In case of total regional black out, SLDC In-charge shall co-ordinate and follow the instructions of

SRLDC for early restoration of the entire grid. After total collapse, for each power station, to avoid damage to

the turbine, survival power is required. To meet the survival power, the diesel generating (DG) sets of sufficient

capacity shall be available at each power station. Start-up power to the thermal station shall be given by the

hydel stations and inter-State supply, if available. All possible efforts shall be made to extend the hydel supply to

the thermal power stations through shortest transmission network to avoid high voltage problem due to low load

condition. For safe and fast restoration of supply, STU shall formulate the proper sequence of operation for major

generating units, intra-State transmission lines, transformers and load within the State in consultation with SRPC.

The sequence of operation shall include closing/tripping of circuit breakers, isolators, on-load tap-changers, etc. In

emergency situations, the Distribution Licensee may approach a nearby captive power plant to get the extremely

important energy requirement at the earliest. The STU shall formulate the proper sequence of operations in this

regard.

15.4. Restoration Procedure

(a) The procedure for restoration of State Transmission System shall be prepared by SLDC for the following

contingency (Total system black out, Partial System Blackout and Synchronisation of System Islands and System

Split) and shall be in conformity to the System Restoration Procedure of the Southern Region specified under

IEGC. SLDC shall review and update the restoration procedure every year.

(b) The restoration process shall take into account the generator capabilities and the operational constraints

of Regional and State Transmission System with the object of achieving normalcy in the shortest possible time.

All Users must be aware of the steps to be taken during major grid disturbance and system restoration process.

These steps shall be followed by all the Users to ensure consistent, reliable and quick restoration.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

113

(c) Detailed procedures for restoration post partial and total blackout of each User system within the

State shall be prepared by the concerned User in coordination with SLDC. The concerned User shall review

the procedure every year and update the same. The User shall carry out a mock trial run of the procedure for

different sub-systems including black-start of generating units along with grid forming capability of inverter based

generating station and Voltage Source Converters (VSC) based HVDC black-start support at least once a year

under intimation to SLDC / SRLDC. Diesel generator sets and other standalone auxiliary supply source to be

used for black start shall be tested on a weekly basis and the User shall send the test reports to the concerned

SLDC, SRLDC on a quarterly basis.

(d) Simulation studies shall be carried out by each User in coordination with SLDC / SRLDC for preparing,

reviewing and updating the restoration procedures considering the following:

(i)

Black start capability of the generator;

(ii)

Ability of black start generator to build cranking path and sustain island;

(iii) Impact of block load switching in or out;

(iv) Line/transformer charging;

(v) Reduced fault levels; and

(vi) Protection settings under restoration condition.

(e) The thermal and nuclear generating stations shall prepare themselves for house load operation as per

design. The concerned User and SLDC shall report the performance of house load operation of a generating

station in the event where such operation was required.

(f)

SLDC shall identify the generating stations with black start facility, grid forming capability of inverter

based generating stations, house load operation facility, inter-State or inter-regional ties, synchronizing points and

essential loads to be restored on priority.

(g) During the restoration process following a blackout, SLDC is authorized to operate with reduced security

standards for voltage and frequency and may direct the implementation of any such operational setting as necessary,

in order to achieve the fastest possible recovery of the grid.

(h) Any entity extending black start support by way of injection of power as identified in Regulation 15.4(f)

of the Grid Code shall be paid for actual injection @ 110 % of the normal rate of charges for deviation.

15.5. Real Time Operation

(a) System state

Power system shall be categorized under normal, alert, emergency, extreme emergency and restoration state

depending on the type of contingencies and value of operational parameters of the power system by RLDC,

NLDC or SLDC, as the case may be.

(i) Normal state

Power system shall be categorized under normal state when the power system is operating with operational

parameters within their respective operational limits and equipment is within their respective loading limits. Under

normal state, the power system is secure and capable of maintaining stability under contingencies defined in the

CEA Transmission Planning Criteria and updated thereof.

(ii) Alert state

Power system shall be categorized under alert state when the power system is operating with operational

parameters within their respective operational limits, but a single contingency (‘N-1’) leads to a violation of security

criteria. The power system remains intact under such alert state. However, whenever the power system is under

alert state, the system operator shall take corrective measures to bring it back to a normal state.

(iii) Emergency state

Power system shall be categorized under emergency state when the power system is operating with operational

parameters outside their respective operational limits or equipments are above their respective loading limits.

Emergency state can arise out of multiple contingencies or any major grid disturbance in the system. The power

system remains intact under such emergency state. However, whenever the power system is under emergency

state, it is the responsibility of the system operator to bring back the power system to alert/normal and shall

take corrective measures such as:

TAMIL NADU GOVERNMENT GAZETTE

114

[Part   VI—Sec. 2

• extreme measures such as load shedding, generation unit tripping, line tripping or closing,

• emergency control action such as HVDC Control, Excitation Control, HP-LP Bypass, tie line flow rescheduling

on critical lines, and

• automated action such as system protection scheme, load curtailment scheme and generation run-back

scheme.

(iv) Extreme emergency state

Power system shall be categorized under extreme emergency state if the control actions taken during the

emergency state are not able to bring the system either to an alert state or a normal state and operational

parameters are outside their respective operational limits or equipment are critically loaded. Extreme emergency

state may arise due to high impact low frequency events like natural disasters. The power system may or may

not remain intact (splitting may occur) and extreme events like generation plant tripping, bulk load shedding, under

frequency load shedding (UFLS) and under voltage load shedding (UVLS) operation may occur.

(v) Restorative state

Power system shall be categorized under restorative state when control action is being taken to reconnect

the system elements and restore system load. The power system transits from a restorative state to

either an alert state or a normal state, depending on the system conditions.

(b) SLDC shall maintain the grid in the normal state by taking suitable measures. In case, the power system

moves away from the normal state, appropriate measures shall be taken to bring the system back to the normal

state. In case the power system has moved to an extreme emergency state, SLDC shall take emergency action

and initiate restorative measures immediately.

(c) Procedure to be followed during an event:

(i)

In case of an event on the intra-State transmission system that may significantly impact the inter-

State transmission system, SLDC shall immediately inform the SRLDC;

(ii)

any warning in respect of system security issued by NLDC/ SRLDC/ SLDC, shall be taken note

of immediately by the concerned Users who shall take the necessary action to withstand the said event or to

minimize its effect.

(d) Operational coordination:

(i)

For operational coordination, each intra-State Transmission Licensee, generating station and QCA

shall have a control centre or coordination centre for round the clock coordination.

(ii)

Any planned operation activity in the Intra-State Transmission system [such as generating unit

synchronization or de-synchronization, transmission element opening or closing (including breakers), protection

system outage, System Protection Schemes (SPS) outage and testing, etc.] shall be done by taking operational

code from SLDC. The operational code shall have validity period of sixty (60) minutes from the time of issue. In

case such operation activity does not take place within the validity period of the code, the entity shall obtain a

fresh operational code from SLDC.

15.6. Special Considerations

(a) During the restoration process, normal standards of voltage and frequency shall not apply.

(b) Distribution Licensees with essential loads will separately identify non-essential components of such loads,

which may be kept off during system contingencies. Distribution Licensees shall draw up an appropriate schedule

with corresponding load blocks in each case. The non-essential loads can be put on only when system normally

is restored, as advised by SLDC.

(c) All Users shall pay special attention in carrying out the procedures so that secondary collapse due to

undue haste or inappropriate loading is avoided.

(d) Despite the urgency of the situation, careful prompt and complete logging of all operations and operational

messages shall be ensured by all Users to facilitate subsequent investigation into the incident and the efficiency

of the restoration process. Such investigation shall be conducted promptly after the incident.

(e) All communication channels required for restoration process shall be used for operational communication

only, till grid normalcy is restored.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

115

Chapter 16 - Inter-User Boundary Safety Code

16.1. Introduction

This chapter sets down the requirements for maintaining safe working practices associated with inter-user

boundary operations. It lays down the procedure to be followed when work is required to be carried out on

electrical equipment that is connected to another User’s system.

16.2. Objective

The objective of this chapter is to achieve agreement and consistency on the principles of safety as specified

in the CEA safety Regulations as amended from time to time.

16.3. Designated Officers

STU and all Users shall nominate authorized persons responsible for the co-ordination of safety across the

Company boundary. These persons shall be referred to as Designated Officer(s).

16.4. Procedure

(a) STU shall issue a list of Designated Officers (names, designations and telephone numbers) to all Users

who have a direct inter-user boundary with STU. This list shall be updated promptly whenever there is change

of name, designation or telephone number.

(b) All Users with a direct inter-user boundary with STU or other User’s system shall issue a similar list of

their Designated Officer to STU or other User, which shall be updated promptly whenever there is a change to

the Designated Officer list.

(c) Whenever work across an inter-user boundary between STU and any other User or between two Users

is to be carried out, the Designated Officer of the User (which may be STU), wishing to carry out work shall

personally contact the other relevant Designated Officer. If the Permit to Work (PTW) cannot be obtained personally,

the designated officers shall contact through telephone and exchange code words to ensure correct identification

of both parties.

(d) In case the work extends over more than one shift, the Designated Officer shall ensure that the relief

Designated Officer is fully briefed on the nature of the work and the code words in operation.

(e) The Designated Officers shall co-operate to establish and maintain the precautions necessary for the

required work to be carried out in a safe manner. Both the established isolation and the established earth shall

be locked in position, where such facilities exist, and shall be clearly identified.

(f)

Work shall not commence until the Designated Officer of the User, wishing to carry out the work, is

satisfied that all the safety precautions have been established. This Designated Officer shall issue agreed safety

documentation (PTW) to the working party to allow work to commence. The PTW in respect of specified EHV

lines and other inter-connections shall be issued with the consent of SLDC.

(g) When work is completed and safety precautions are no longer required, the Designated Officer who has

been responsible for the work being carried out shall make direct contact with the other Designated Officer to

return the PTW and removal of those safety precautions. Return of PTW in respect of specified EHV lines and

inter-connections shall be informed to SLDC.

(h) The equipment shall only be considered as suitable for return to service when all safety precautions are

confirmed as removed, by direct communication using code word contact between the two Designated Officers

and return of agreed safety documentation from the working party has taken place.

(i)

STU/SLDC shall develop an agreed written procedure for inter-user boundary safety and continually

update it.

(j)

Any dispute concerning inter-user boundary safety shall be resolved at an appropriate higher level of

authority.

16.5. Special Consideration

(a) For inter-user boundary between STU and other Users circuits, all Users shall comply with the agreed

safety rules, which must be in accordance with the extant Rules and amendments thereof.

(b) All equipment on inter-user boundary between STU and other Users circuits, which may be used for

the purpose of safety co-ordination and establishment of isolation and earthing, shall be permanently and clearly

TAMIL NADU GOVERNMENT GAZETTE

116

[Part   VI—Sec. 2

marked with an identification number or name, that number or name being unique in that sub-station. This

equipment shall be regularly inspected and maintained in accordance with manufacturer’s specification.

(c) Each Designated Officer shall maintain a legibly written safety log, in chronological order, of all operations

and messages relating to safety co-ordination sent and received by them. All safety logs shall be retained for a

period of not less than five (5) years.

16.6. Boundaries between Systems of Entities

(a) Boundary between a Generating station and the Transmission System

The boundary shall be the line isolator of the feeder, which injects power into the transmission system.

The isolator shall be in the jurisdiction of the generating company.

(b) Boundary between the Transmission System and the Distribution system

The boundary shall be the line isolator of the outgoing feeder injecting power into the distribution system.

The line isolator shall be in the jurisdiction of the transmission licensee. Alternatively the boundary may be the

isolator between the LV side circuit breaker of the Extra High Tension (EHT) Transformer and the 33 / 22 / 11

kV bus–bars at the EHT Sub–Station. The actual boundary shall be decided jointly by the transmission licensee

and the distribution licensee.

(c) In respect of case (i) and (ii) above, at particular inter-connections both parties may jointly agree on a

different boundary. In such an event the written agreement shall be submitted to the RPC /STU.

(d) Boundaries between Transmission/Distribution Licensee and Captive Generators, Co-generators and

HV consumers

The boundary between the transmission/Distribution licensee and Captive Generators, Co-generators and HV

consumers is the isolator in the consumer’s or Captive Generators or Co-generators system, which is also the

point of commencement or injection of supply.

(e) Boundaries between Inter-State Transmission System and Intra State Transmission System

For the Southern Regional Transmission System, the inter-state transmission link to the intra state system

shall be in accordance with the mutual agreement between CTU and the STU. In such an event the written

agreement shall be submitted to the RPC.

Chapter 17 – Reports

17.1. Periodic reports

(a) Daily and monthly reports covering performance of the State grid shall be prepared by the SLDC and

published on SLDC website. The monthly report shall cover the performance of the State grid for the previous

month. The monthly report shall contain the following:

(i)

Frequency profile.

(ii)

Maximum and minimum frequency recorded daily and daily frequency variation index (FVI).

(iii) Voltage profile.

(iv) Voltage profile of selected sub-stations.

(v) Major Generation and Transmission Outages.

(vi) Transmission Constraints.

(vii) Instances of persistent / significant non-compliance of Grid Code.

(viii) Grid Security events, leading to curtailment along with reasons.

(b) Other Reports/Forms

The SLDC shall also upload a quarterly report on its website, which shall bring out the system constraints,

reasons for not meeting the requirements, if any, of security standards and quality of service, along with details

of various actions taken by different Users and the Users responsible for causing the constraints.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

117

(c) These reports shall also be submitted to the Commission within a week from the due date of issue of

the reports.

17.2. Operational Event/Accident Reporting

(a) Introduction

This chapter describes the reporting procedure, of reportable events in writing in the State Transmission System.

(b) Objective

The objective of this chapter is to define the incidents to be reported, the reporting route to be followed

and the information to be supplied to ensure a consistent approach for reporting of incidents and accidents on

the Intra-State Transmission System.

(c) Reportable Incidents

Any of the following events that could affect the State Transmission System requires reporting:

(i)

Exceptionally high / low system voltage or frequency.

(ii)

Serious equipment problem, i.e., major circuit breaker, transformer or bus-bar etc.

(iii) Loss of Generating Unit.

(iv) Instance of Black Start.

(v) Tripping of Transmission Line, Interconnecting transformer (ICT) and capacitor banks

(vi) Major fire incidents.

(vii) Major failure of protection.

(viii) Equipment and transmission line overload.

(ix) Accidents-fatal and non-fatal.

(x) Load Crash / Loss of Load.

(xi) Violation of Security Standards.

(xii) Grid indiscipline.

(xiii) Non-compliance of SLDC instructions.

(xiv) Excessive drawal deviations.

(xv) Minor equipment alarms.

The last two reportable incidents are typical examples of those, which are of lesser consequence, but still

affect the State Transmission System and can be reasonably classed as minor. They will require corrective action

but may not warrant management reporting until these are repeated for sufficient time.

(d)

Reporting Procedure/Forms

(i)

All reportable incidents occurring in lines and equipment of 66 kV and above affecting the State

Transmission System shall promptly be communicated by the User whose equipment has experienced the incident

(the Reporting User) to any other significantly affected Users and to SLDC.

(ii)

Within one (1) hour of being informed by the Reporting User, SLDC may ask for a written report on

any incident as per Appendix-H.

(iii) In case of minor incident, the Reporting User shall submit an initial written report within two (2) hours

and comprehensive report within twenty-four (24) hours of the submission of the initial written report, whereas, in

other cases, the Reporting User shall submit a report within five (5) working days to SLDC.

(iv) SLDC may call for a report from any User on any reportable incident affecting other Users and STU,

in case the same is not reported by such User whose equipment might have been the source of the reportable

incident. This shall not relieve any User from the obligation to report events in accordance with IE Rules.

TAMIL NADU GOVERNMENT GAZETTE

118

[Part   VI—Sec. 2

(v) The format of such a report will be as agreed to by the Grid Code Review Committee, but will typically

contain the following information:

1.

Location of incident.

2.

Date and time of incident.

3.

Plant or equipment involved.

4.

Details of relay indications with nature of fault implications.

5.

Supplies interrupted and duration if applicable.

6.

Amount of generation lost if applicable.

7.

Brief description of incident.

8.

Estimated time to return to service.

9.

Name of originator.

10. Possibility of alternate arrangement of supply

11. Single line diagram

12. All relevant system data including copies of records of all recording instruments including Disturbance

Recorder, Event Logger, Data Acquisition System (DAS), etc.

(e) Major Failure

Following a major failure, SLDC and other Users shall co-operate to inquire into and establish the cause of

such failure and produce appropriate recommendations. The SLDC shall report the major failure to the Commission

immediately for information and shall submit the enquiry report to the Commission within two (2) months of the

incident.

(f)

Accident Reporting

Reporting of accidents shall be in accordance with the relevant Rules/ Regulations/ Grid Code. In both fatal

and non-fatal accidents, the report shall be sent to the Electrical Inspector in the specified form.

Chapter 18 - Protection Code

18.1. Introduction

The chapter covers the protection protocol, protection settings and protection audit plan of electrical systems

to be adopted in order to safeguard the State Transmission System and User’s system from faults.

18.2. Objective

The objective of this chapter is to define the minimum protection requirements for any equipment connected

to the State Transmission System and thereby minimize the disruption due to faults.

18.3. General Principles

(a) There should be a uniform protection protocol for the Users of the State grid:

(i) for proper co-ordination of protection system in order to protect the equipment/system from abnormal

operating conditions, isolate the faulty equipment and avoid unintended operation of protection system;

(ii) to have a repository of protection system, settings and events at State level;

(iii) specifying timelines for submission of data;

(iv) to ensure healthiness of recording equipment including triggering criteria and time synchronization; and

(v) to provide for periodic audit of protection system.

(b) STU shall be guided by the advice of SRPC / SRLDC for the following:

(i)

Planning for upgrading and strengthening protection system based on analysis of grid disturbance

and partial/total blackout in State Transmission System.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

119

(ii)

Planning of Islanding and system split schemes and installation of Under Frequency Relays and df/

dt relays.

(c) Under-Frequency relay for load shedding, relays provided for islanding scheme, disturbance recorder, and

fault locator installed at various sub-stations shall be tested and calibrated. All Users shall ensure correct and

appropriate settings of protection equipments.

(d) Protection settings shall not be altered or protection bypassed and/or disconnected without consultation and

agreement of all affected Users. In the case where protection is bypassed and/or disconnected, by agreement, then

the cause must be rectified, and the protection restored to normal condition as quickly as possible. If agreement

has not been reached, the electrical equipment will be removed from service forthwith.

(e) No item of electrical equipment shall be allowed to remain connected to the State Transmission System

unless it is covered by minimum specified protection aimed at reliability, selectivity, speed and sensitivity.

18.4. Protection Co-ordination

A Protection Coordination Committee (PCC) shall be constituted as per this Grid Code and shall be responsible

for all the protection coordination functions. STU shall be responsible for arranging periodical meetings of the

Protection Coordination Committee. STU shall investigate any malfunction of protection or other unsatisfactory

protection issues. Users shall take prompt action to correct any protection malfunction or issue as discussed and

agreed to, in the periodical meetings.

18.5. Protection Protocol

(a) All Users connected to the State grid shall provide and maintain effective protection system having

the reliability, selectivity, speed and sensitivity to isolate the faulty section and protect element(s) as per CEA

Technical Standards for Connectivity Regulations, CEA Grid Standards Regulations, CEA Technical Standards for

Communication Regulations, CEA Technical Standards for Construction Regulations and amendments thereof and

any other applicable CEA standards specified from time to time.

(b) Back-up protection system shall be provided to protect an element in the event of failure of the primary

protection system.

(c) Protection Coordination Committee (PCC) shall develop the protection protocol and revise the same, after

review from time to time, in consultation with the stakeholders in the State, and in doing so shall be guided by

the principle that minimum electrical protection functions for equipment connected with the grid shall be provided

as per CEA Technical Standards for Connectivity Regulations, CEA Grid Standards Regulations, CEA Technical

Standards for Communication Regulations, CEA Technical Standards for Construction Regulations, CEA Safety

Regulations and amendments thereof and any other CEA standards specified from time to time.

(d) The protection protocol in a particular system may vary depending upon operational experience. Changes

in protection protocol, as and when required, shall be carried out after deliberation and approval of the Protection

Coordination Committee (PCC).

(e) Violation of the protection protocol of the State shall be brought to the notice of Protection Coordination

Committee (PCC) by SLDC.

18.6. Protection Settings

(a) Protection Coordination Committee (PCC) shall undertake a review of the protection settings, assess the

requirement of revisions in protection settings and revise protection settings in consultation with the stakeholders

of the State from time to time and at least once in a year. The necessary studies in this regard shall be carried

out by the Protection Coordination Committee (PCC). The data including base case (peak and off-peak cases)

files for carrying out studies shall be provided by SLDC and STU to Protection Coordination Committee (PCC).

(b) All Users connected to the grid shall:

(i)

furnish the protection settings implemented for each element to Protection Coordination Committee

(PCC) in a format to be prescribed by Protection Coordination Committee (PCC);

(ii)

obtain approval of Protection Coordination Committee (PCC) for any revision in settings and

implementation of new protection system;

(iii) intimate to Protection Coordination Committee (PCC) about the changes implemented in protection

system or protection settings within a fortnight of such changes;

TAMIL NADU GOVERNMENT GAZETTE

120

[Part   VI—Sec. 2

(iv) ensure correct and appropriate settings of protection as specified by Protection Coordination Committee

(PCC); and

(v) ensure proper coordinated protection settings.

(c) Protection Coordination Committee (PCC) shall:

(i)

maintain a centralized database and update the same on periodic basis in respect of State containing

details of relay settings for grid elements connected to 66 kV and above. SLDC shall also maintain such database.

(ii)

carry out detailed system studies once in a year, for protection settings and advise modifications /

changes, if any, to STU and all Users. The data required to carry out such studies shall be provided by SLDC,

STU and Users, as the case may be.

(iii) provide the database access to STU and SLDC and to all Users of the State. The database shall

have different access rights for different Users.

(d) The changes in the network and protection settings of grid elements connected to 66 kV and above

shall be informed to Protection Coordination Committee (PCC) by SLDC and STU, as the case may be.

18.7. Protection Audit Plan

(a) Generating Stations shall conduct internal audit of their protection systems annually and any shortcomings

identified shall be rectified and informed to Protection Coordination Committee (PCC) and SLDC. The audit report

along with action plan for rectification of deficiencies detected if any, shall be shared with Protection Coordination

Committee (PCC) and SLDC.

(b) All Users except those under Regulation 18.7(a) of the Grid Code and having sub-stations at voltage level

230 kV and above shall conduct internal audit of their protection systems annually and third-party protection audit

of each sub-station once in five (5) years. The audit report along with action plan for rectification of deficiencies

detected if any, shall be shared with Protection Coordination Committee (PCC) and SLDC.

(c) All Users except those under Regulation 18.7(a) of the Grid Code and having sub-stations at voltage level

66 kV / 110 kV shall conduct internal audit of their protection systems once in three (3) years. The audit report

along with action plan for rectification of deficiencies detected if any, shall be shared with Protection Coordination

Committee (PCC) and SLDC.

(d) After analysis of any event, Protection Coordination Committee (PCC) shall identify a list of sub-stations/

generating stations where third-party protection audit is required to be carried out and accordingly advise the

respective Users to complete third-party audit within three months.

(e) The third-party protection audit report shall contain information sought in the format enclosed as

Appendix–I. The protection audit reports along with action plan for rectification of deficiencies detected, if any,

shall be submitted to Protection Coordination Committee (PCC) and SLDC within a month of submission of third-

party audit report. The necessary compliance to such protection audit report shall be followed up regularly in

Protection Coordination Committee (PCC) meetings.

(f)

Annual audit plan for the next financial year shall be submitted by the Users to Protection Coordination

Committee (PCC) and SLDC by 31st October. The Users shall adhere to the annual audit plan and report

compliance of the same to Protection Coordination Committee (PCC) and to SLDC for record purposes.

(g) Users shall submit the following protection performance indices of previous month to Protection Coordination

Committee (PCC) and SLDC on monthly basis for 66 kV and above system, which shall be reviewed by the

Protection Coordination Committee (PCC):

The Dependability Index defined as D =Nc/ (Nc+Nf);

The Security Index defined as S =Nc/(Nc+Nu); and

The Reliability Index defined as R =Nc/ (Nc+Ni);

where,

Nc is the number of correct operations at internal power system faults;

Nf is the number of failures to operate at internal power system faults;

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

121

Nu is the number of unwanted operations; and

Ni is the number of incorrect operations and is the sum of Nf and Nu.

(h) Each User shall also submit the reasons for performance indices less than unity of individual

element-wise protection system to Protection Coordination Committee (PCC) and action plan for corrective measures.

The action plan will be followed up regularly by the Protection Coordination Committee (PCC).

(i)

In case any User fails to comply with the protection protocol specified by Protection Coordination

Committee (PCC) or fails to undertake remedial action identified by the Protection Coordination Committee (PCC)

within the specified timelines, Protection Coordination Committee (PCC) / STU may approach the Commission

with all relevant details for suitable directions.

18.8. System Protection Scheme (SPS)

(a) System Protection Scheme (SPS) for identified system shall have redundancies in measurement of input

signals and communication paths involved up to the last mile to ensure security and dependability.

(b) For the operational System Protection Scheme (SPS), SLDC in consultation with Protection Coordination

Committee (PCC) shall perform regular load flow and dynamic studies and mock testing for reviewing System

Protection Scheme parameters and functions, at least once in a year. SLDC shall share the report of such studies

and mock testing including any short comings to Protection Coordination Committee (PCC). The data for such

studies shall be provided by STU/SLDC to the Protection Coordination Committee (PCC).

(c) The Users and SLDC shall report about the operation of System Protection Scheme (SPS) immediately

and detailed report shall be submitted within three days of operation to Protection Coordination Committee (PCC)

in the format specified by Protection Coordination Committee (PCC).

(d) The performance of System Protection Scheme (SPS) shall be assessed as per the protection performance

indices specified in this Grid Code. In case, the System Protection Scheme (SPS) fails to operate, the concerned

User shall take corrective actions and submit a detailed report on the corrective actions taken to Protection

Coordination Committee (PCC) within a fortnight.

18.9. Recording Instruments

(a) All Users shall keep the recording instruments (disturbance recorder and event logger) in proper working

condition.

(b) The disturbance recorders shall have time synchronization and a standard format for recording analog

and digital signals, which shall be included in the guidelines issued by Protection Coordination Committee (PCC).

(c) The time synchronization of the disturbance recorders shall be corroborated with the PMU data or

SCADA event loggers by SLDC. Disturbance recorders, which are non-compliant shall be listed out for discussion

at Protection Coordination Committee (PCC) meeting.

18.10.

Calibration and Testing

(a) The protection scheme shall be tested at each 765 kV, 400 kV and 230 kV sub-station by STU once

in a year or immediately after any major fault, whichever is earlier. However, in case of 66 kV / 110 kV, the

same shall be carried out once in every three years or immediately after any major fault, whichever is earlier.

Setting, co-ordination, testing and calibration of all protection schemes pertaining to generating units/stations shall

be the responsibility of respective Generator. The periodic testing shall be carried out on power system elements

for ascertaining the correctness of mathematical models used for simulation studies as well as ensuring desired

performance during an event in the system.

(b) All equipment owners shall submit a testing plan for the next year to the STU/SLDC/SRPC by 31st

October to ensure proper coordination during testing as per the schedule. In case of any change in the schedule,

the owners shall inform the STU/SLDC/SRPC in advance.

(c) The tests shall be performed once every five (5) years or whenever major retrofitting is done. If any

adverse performance is observed during any grid event, then the tests shall be carried out even earlier, if so,

advised by SLDC or SRLDC or NLDC or SRPC, as the case may be.

(d) The owners of the power system elements shall implement the recommendations, if any, suggested in

the test reports in consultation with STU, SLDC, SRPC, NLDC, CEA and CTU.

TAMIL NADU GOVERNMENT GAZETTE

122

[Part   VI—Sec. 2

(e) The overall co-ordination between Users and STU shall be decided in the meeting of Protection Co-

ordination Committee. The Protection Co-ordination Committee shall review the testing and calibration as and when

needed.

(f)

The following tests shall be carried out on the respective power system elements:

Power System Elements

Tests

Applicability

Synchronous Generator

(1) Real and Reactive Power Capability

assessment.

(2) Assessment of Reactive Power Control

Capability as per CEA Technical Standards for

Connectivity Regulations

(3) Model Validation and verification test for the

complete Generator and Excitation System

model including PSS.

(4) Model Validation and verification of Turbine/

Governor and Load Control or Active Power/

Frequency Control Functions.

(5) Testing of Governor performance and

Automatic Generation Control.

Individual Unit of

rating 100MW and

above for Coal/

lignite, 50MW and

above gas turbine

and 25 MW and

above for Hydro.

Non synchronous

Generator (Solar/Wind)

(1) Real and Reactive Power Capability for

Generator

(2) Power Plant Controller Function Test

(3) Frequency Response Test

(4) Active Power Set Point change test.

(5) Reactive Power (Voltage / Power Factor / Q)

Set Point change test

Applicable as per

CEA Technical

Standards for

Connectivity

Regulations.

HVDC/FACTS Devices

(1) Reactive Power Controller (RPC) Capability

for HVDC/FACTS

(2) Filter bank adequacy assessment based on

present grid condition, in consultation with

NLDC.

(3) Validation of response by FACTS devices as

per settings.

To all ISTS HVDC

as well as Intra-

State HVDC/

FACTS,

as applicable

18.11.

Capacity Building and Certification

Capacity building, skill up-gradation, and certification of the personnel deployed in Generating Stations, Load

Despatch Centres and EHV Sub-stations shall be done periodically under an institutional framework through

accredited certifying agency(ies).

18.12.

Data Requirements

Users shall provide STU with data for this chapter as specified in Appendix-D of Data Registration Code.

Chapter 19 - Transmission Metering Code and Distribution Metering Code

19.1. Introduction

The Transmission Metering Code and Distribution Metering Code prescribes a uniform policy in respect of

electricity metering for State Transmission Utility (STU), Distribution Licensee, Generating Companies and metering of

all Users of State Transmission System including Open Access customers as per the Act using State Transmission

Utility and any new system interfacing with State Transmission Utility system in the State of Tamil Nadu.

19.2. Objective

The objective of the Code is to define minimum acceptable metering standards for appropriate metering of

the system parameters for the purpose of accounting, commercial billing and settlement of electrical energy and

also provide information that will help to optimize the system planning.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

123

19.3. Scope

(a) The scope of the Code covers the practices that shall be employed and the facilities that shall be

provided for the measurement and recording of various parameters like active/reactive/apparent power/energy,

power factor, voltage, frequency, etc.

(b) The Code also specifies the requirement for calibration, testing and commissioning of metering equipment,

viz., energy meters with associated accessories, current transformers, and voltage transformers. The Code indicates

the technical features of various elements of the metering, data communication, testing and calibration system,

the procedure for assessment of consumption in case of defective and stuck-up meters and also lays down the

guidelines for resolution of disputes between different parties.

19.4. Reference Standards/ Regulations

(a) All interface meters, consumer meters and energy accounting meters shall comply with the relevant

standards of Bureau of Indian Standards (BIS). If BIS Standards are not available for particular equipment or

material, International Electro-Technical Commission (IEC) Standards, CBIP Technical Report or any other equivalent

standard shall be followed. Whenever an international Standard or IEC Standard is followed, necessary corrections

or modifications shall be made, as required for nominal system frequency, nominal system voltage, ambient

temperature, humidity, and other conditions prevailing in India before actual adoption of the said Standard.

(b) All the meters of Users and systems interfacing with STU systems shall be installed and operated as

per CEA Metering Regulations and amendments thereof.

19.5. Ownership

The ownership of meters shall be in accordance with CEA Metering Regulations and amendments thereof.

19.6. Other Technical Requirements for Metering

(a)

Data Display Capabilities - Instantaneous Values:

The meter shall be capable to record and display (on demand) at least the following instantaneous parameters/

information:

(i)

Three rms line voltages/currents

(ii)

System frequency (Hz)

(iii) Power factor with sign of lag/lead.

(iv) Watt hour- Import/Export

(v) VAr - Lead/Lag

(vi) VA - Import/Export

(vii) Maximum Demand (Import/Export) during the month in Watt & VA with date and time;

(viii) Meter Serial Number

(b)

Data Storage Capabilities - Cumulative Values:

The meter shall be capable to record, store and display (on demand) at least following cumulative parameters.

At least five (5) registers shall be provided for each parameter, out of which one (1) register shall record energy

for 24 hours in a day whereas other four (4) registers shall record Time of Day (TOD) energy during morning

peak, morning off-peak, evening peak and evening off-peak durations:

(i)

Watt hour - Import/Export

(ii)

VAr hour - Lead/Lag while Watt hour - Import

(iii) VAr hour - Lead/Lag while Watt hour - Export

(iv) VA hour – Import/Export

(v) VAr hour during low voltage (V<97%)

(vi) VAr hour during high voltage (V>103%)

TAMIL NADU GOVERNMENT GAZETTE

124

[Part   VI—Sec. 2

(c)

Data Logging Capabilities1 - Integrated Values:

The meter shall have sufficient memory to store any combination of at least ten (10) parameters listed in

Regulation 19.6(a) and Regulation 19.6(b) of the Grid Code over minimum forty (40) days at a logging interval

of fifteen (15) minutes. The State Transmission Utility shall be able to select these parameters locally through

optical port using CMRI and/or remotely through communication port and/or Mobile App. At least following essential

parameters shall be logged at an interval of 15 minutes:

(i)

Watt hour - Import/ Export

(ii)

VAr - Lead/Lag while Watt - Import

(iii) VAr - Lead/Lag while Watt - Export

(iv) VAr hour during low voltage (V<97%)

(v) VAr hour during high voltage (V>103%)

(vi) Average frequency (Hz)

(vii) Average three phase voltage.

(d)

Other Parameters2:

Each meter shall also store the values of active energy (Import), active energy (Export), reactive energy (lag)

and reactive energy (lead) separately during active energy (import) and active energy (export) conditions recorded

at 24:00 hours on last day of the month for a period of at least twelve (12) months. The User shall be able to

program time and day at which value of energy to be stored in the memory.

(e)

Events and Abnormalities Logging Capabilities3:

The meter shall be able to log date and time stamped events captured with a resolution of at least one (1)

second. Sufficient memory shall be provided to store at least last 100 events in the meter on First-In-First-Out

(FIFO) basis as following, but not limited to:

(i)

Missing potential (VT supply missing)

(ii)

CT/VT Polarity reversal

(iii) Current unbalances (magnitude as well as phase unbalance) in any one of the phases or more than

one phase

(iv) Voltage imbalance (magnitude as well as phase imbalance) in any one of the phases or more than one

phase

(v) Supply interruptions along with the duration of each interruption

(vi) Tamper information/anomaly occurrence/anomaly restoration.

(vii) Meter internal setup/program change information

1In case of operational metering, the number of parameters and their logging intervals shall be decided by

the Licensee as per their operational requirements.

2This Regulation may not be applicable for operational metering.

3In case of advanced metering, the meter needs to store time stamped events with at least 1ms resolution

for meeting operational needs.

(f)

Real Time Clock (RTC) and Calendar

The meter shall have in-built Quartz crystal based accurate Real Time Clock. The meter shall display real time

in 24 hours format (hh:mm:ss). Meter shall also display the date as per Indian calendar in dd-mm-yyyy format.

Thirty (30) years calendar with automatic leap year adjustment shall be provided in the meter. The accuracy of

the clock and calendar shall be better than one minute per year.

(g)

Time Synchronization

All meters shall have facility for time synchronisation locally and/or remotely through a Global Positioning

System (GPS) or through the central computer (at CDCC) using the same port used for remote data communication.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

125

(h)

Data Retention

The logged data shall be stored in a non-volatile memory of meter with a minimum retention period of ten

(10) years without any battery back-up.

(i)

Data Concentration and Network Integration

The local network of all meters installed in a sub-station shall be formed using modem/multiplexer/data

concentrator/LAN hub switch. This local network shall be integrated with communication network using appropriate

standard protocol. Communication network may be based on Radio frequency, Microwave, Public Switched Telephone

Network (PSTN), Power Line Carrier Communication (PLCC), Very Small Aperture Terminal (VSAT) network, Optical

Fibre Cable (OFC), GSM, Radio or any other means of telemetry.

(j)

Pulse Output

High intensity Light Emitting Diodes (LED) shall be provided on front of the meter for test calibration and

accuracy check of Wh and VArh measurements.

(k)

Display

The meter shall have a minimum of 7 digits Alpha-numeric Liquid Crystal Display (LCD) or Light Emitting

Diode (LED) type display with bright back-light and automatic back-light time out feature. A touch key pad or push

buttons shall be provided on the meter front for switching ON the display and for changing from one indication

to next. Two separate push buttons shall be provided, one for scrolling and other for MD resetting.

(l)

Data Security

The metering system should have the following facilities:

(i)

Data encryption (coding) capability,

(ii)

Mechanical seals and locks, i.e., sealing provision for terminal block, meter cover, MD reset button

and all communication ports,

(iii) Message authentication algorithm capability/multi-level password protection,

(iv) Independent security across communication channels.

(m) Self-Diagnostics Feature

The meter shall have self-diagnostics feature to scan the healthiness of internal components and circuitry.

On detection of any exception or fault, meter shall display the message immediately.

(n)

Communication Ports

The meter shall have at least the following communication ports:

(i)

One optically isolated infra-red communication port (optical port) for local communication as per IEC

1107.

(ii)

One galvanically isolated Ethernet (LAN) port or RS485 serial port or RS232 serial port for remote

communication.

(o)

Communication Protocol

For communication by meter with external devices, meter supplier shall implement industry standard open

protocol(s) like MODBUS RTU, MODBUS, TCP/IP, IEC 870-5-102, IEEE 1377, DNP 3.0, Device Language Message

Specification (DLMS) or any other industry standard protocol. In case of proprietary protocol, the meter supplier

shall furnish the protocol software and details of protocol followed by him. Any variation in the standard protocol

for optimizing communication resources shall be detailed.

(p)

Reprogramming of the meter

Utility shall be able to select the display parameters, logging parameters, timings of TOD registers, billing

dates, logging interval or any other parameter locally using CMRI through optical and/or remotely using meter

reprogramming software installed at CDCC through communication port(s).

(q)

Data Downloading

Utility shall be able to download the logged data locally using CMRI through optical port and/ or remotely

using meter interrogation software installed at CDCC through communication port(s). Any interrogation/read operation

TAMIL NADU GOVERNMENT GAZETTE

126

[Part   VI—Sec. 2

shall not delete or alter any stored meter data.

(r)

Ratio and Phase Angle Correction Feature

The meter shall have facility to correct the ratio error and phase angle error of external CTs and VTs

connected to it.

(s)

External Auxiliary Supply

(i)

The meters shall be capable of powered up with 230 V AC auxiliary supply and 110V or 220V DC

supply of sub-station so that metering cores of VT are never loaded. The meter will normally be powered up by

AC auxiliary supply and will be switched over automatically to DC supply only when AC auxiliary supply fails.

(ii)

If any external supply is not available, self-powered type meter can be provided which derives internal

power consumption from VT signal itself. In case of failure of main power supply or VT supply, meters shall be

capable of being read locally using CMRI and/or remotely through communication network. Suitable maintenance-

free dry battery shall be provided internally for this purpose.

(t)

The Interface meters shall be of open protocol conforming to IS 15959 and of point 0.2S accuracy class. The accuracy

class of Current transformers (CTs) and voltage transformers (VTs) shall not be inferior to that of associated meters. The

meters shall have a non-volatile memory in which following shall be automatically stored:

(i)

Average frequency for each successive 15-minutes block, as a two-digit code (00 to 99 for frequency

from 49.0 to 51.0 Hz)

(ii)

Net Wh transmitted during each successive 15-minutes block, upto the second decimal, with plus/minus

sign.

(iii) Cumulative Wh transmittal at each midnight, in six digits including one decimal.

(iv) Cumulative VArh transmittal for voltage high condition, at each midnight, in six digits including one

decimal.

(v) Cumulative VArh transmittal for voltage low condition, at each midnight, in six digits including one decimal.

(vi) Date and time blocks of failure of VT supply on any phase, as a star (*) mark.

(vii) The interface meters shall have the provision of recording of energy in 15-minutes time block as well as

in 5-minutes time block as configured through software. In addition to the existing provisions of interface meters,

the meters shall also have a provision of frequency resolution of 0.01Hz and they must be capable of recording

Voltage and Reactive Energy at every 5-minutes and have feature of auto-time synchronization through GPS.

(viii) The respective Transmission Licensee shall be responsible for procurement and installation of Interface

Energy Meters and AMR facility. The cost of Interface Energy Meter, providing AMR facility and AMC charges,

shall be recovered from the user of the State Grid for whom Interface Energy Meter (s) is installed. Respective

Transmission Licensee shall also be responsible for replacement of faulty meters and AMR facility at the cost of

respective entity.

(ix) The periodic calibration of Interface Meters to ensure correctness and completeness of data is to

be done by the respective Users.

(x) The installation, operation, calibration and maintenance of Interface Energy Meters (IEMs) with

automatic remote meter reading (AMR) facility shall be in accordance with the CEA Metering Regulations and

subsequent amendments thereof.

19.7. Minimum Technical Requirement for Current Transformer (CT)

(a) Single-phase type current transformers shall be used for 3 phase 4 wire and 3 phase 3 wire and 2

phase 2 wire measurement system. The secondary current rating of the CTs shall be 1 ampere or 5 amperes

depending upon the total circuit burden.

(b) Either dedicated set of current transformers or dedicated core of current transformers shall be provided

for metering and wherever feasible, CTs (or their cores) feeding to main meters and check meters shall be

separate. The errors of the current transformers shall be checked in the laboratory or at site. However, if such

facilities are not available, CT test certificates issued by Government test house or Government recognized test

agency shall be referred to.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

127

(c) The rated burden of CT shall be kept close to the circuit burden as per the requirements of the

respective Metering Code to ensure minimum error. Total burden connected to each current transformer shall not

exceed the rated burden of CT.

19.8. Minimum Technical Requirement for Voltage Transformers (VT)

(a) Either Electromagnetic Voltage Transformers (EVT) or Capacitive Voltage transformer (CVT) may be used

for metering purpose. Generally, term VT is used to cover either EVT or CVT. The secondary voltage per phase

shall be 110/√3 volts or 415/√3 volts. The VTs shall be connected to main and check meters and shall preferably

be dedicated to the metering. Fuses of proper rating shall be provided at appropriate locations in the VT circuit.

(b) The errors of the VTs shall be checked in the laboratory or at site. However, if such facilities are not

available, VT test certificates issued by Government test house or Government recognized test agency shall be

referred to.

(c) The burden of VT connected to a circuit shall be close to the burden of the circuit as specified in the

respective Metering Code to ensure minimum error and total burden connected to each VT shall not exceed the

rated burden of VT. Percentage voltage drop in VT leads shall be within the permissible limits as per relevant

standards.

19.9. Location and Application of Metering System

(a)

Non-conventional Energy Sources

All the Main meters, Check meters and Standby meters, if required will be installed at location specified in

CEA Metering Regulations and subsequent amendments thereof. However, in case of RE generators where pooling

of generation is at common pooling station, meters shall be installed at outgoing feeders of pooling stations.

(b)

Metering between State Transmission Utility –Distribution Licensee

(i)

For measurement of power delivered by State Transmission Utility to Distribution Licensee, Main metering

shall be provided on the LV side of EHV Power Transformer, i.e., 33 kV side of 220/33 kV and 110/33kV, and

11kV side of 110/11kV transformers installed in EHV sub-stations. The standby metering shall be provided on

the HV side of EHV Power Transformer, i.e., 230/33 kV, 110/33kV and 110/11kV transformers installed in EHV

sub-stations. Operational meters shall also be provided on all outgoing 33kV and 11kV feeders for energy audit

on feeder and reconciliation of energy with respect to energy measured on LV side of EHV Power Transformer.

(ii)

EHV consumers and other Distribution Licensees directly connected with EHV sub-station of respective

State Transmission Licensee, shall provide Main and Check meter in their premises and Standby meter at sub-

station of respective Transmission Licensee. In case of railway traction, main and check meter shall be provided

on traction sub-station (TSS) and standby meter shall be at respective Transmission Licensee’s sub-station.

(c)

Metering between two Distribution Licensees

The energy metering shall be provided at such points of the power lines connecting any two Distribution

Systems owned by different Distribution Licensees so that the measured energy gives correct measurement of

consumption by either Distribution Licensee. If installation of metering at tapped points is not feasible, it shall be

provided at both the ends of feeder to which tapped feeder is connected.

(d)

Sub-station Auxiliary Consumption Metering

The auxiliary consumption of STU sub-stations shall be recorded on LV side of station auxiliary transformers.

If such transformer(s) is feeding other local load (colony quarters, street lights, etc.) apart from sub-station auxiliary

load, separate metering shall be provided on individual feeders. Except uni-directional kWh, other data logging/

billing capabilities/energy registers/other features may not be required for this application.

(e)

Open Access Customer (OAC)

In case of Generator availing/seeking open access, the metering equipment shall be installed on outgoing

feeders emanating from the generating station.

In case of CGP having parallel operation, permission and connected through dedicated feeder with grid but

not the consumer of DISCOMs and availing/seeking open access to sell power, the metering equipment shall

be installed in Transmission Licensee’s premises. If the CGP is connected through tapped feeder, the metering

equipment shall be installed at CGP end.

In case of EHV/HV consumer having contract demand/standby support with DISCOMs and availing/seeking

open access, metering equipment shall be installed in the premises of Open Access Consumer.

TAMIL NADU GOVERNMENT GAZETTE

128

[Part   VI—Sec. 2

In case of EHV/HV consumer with CGP having contract demand/standby support with DISCOMs and availing/

seeking open access, metering equipment shall be installed in the premises of Open Access Consumer.

In case of any Distribution Licensee availing/seeking open access, metering equipment shall be installed at

each supply point interfacing with transmission network.

(f)

In addition to provisions of Regulations 19.9(a) to 19.9(e), the location and application of metering system

shall be as per CEA Metering Regulations as amended.

19.10. Data Collection Systems and Data Downloading

All concerned Intra-State entities (in whose premises the Special Energy Meters are installed) shall provide

Automatic Meter Reading (AMR) facility for transmitting ABT meter data to SLDC remotely. If the weekly data of

Special Energy Meter is not received through AMR system installed at SLDC, the same may be downloaded and

transmitted to the SLDC by the owner of the ABT meter or entities who have been authorized to take energy

meter reading.

19.11. Testing Arrangements

(a) The test terminal blocks shall be provided on all meters to facilitate testing of meters. Meter testing shall

be carried out as per relevant IS with electronic reference standard meter of accuracy class as given therein.

For site testing, meter testing equipment with one class higher accuracy than meter under test may be used as

per relevant IS.

(b) Separate test terminal blocks for testing of main and check meters shall be provided so that when

one meter is under testing, the other meter continues to record actual energy during testing period. Where only

one/main meter exists, an additional meter shall be put in circuit during the testing period of the main meter so

that while the main meter is under testing, the other meter can record energy during the period of meter under

testing.

19.12. System for Joint Inspection, Testing and Calibration

(a) The metering system located at metering points between Generating Companies, State Transmission Utility

and Distribution Licensees shall be regularly inspected, tested and calibrated jointly by both the agencies involved

for despatch and receipt of energy at least once in 5 years or whenever the energy and other quantity recorded

by the meter are abnormal or inconsistent with electrically adjacent meters or as mutually agreed. Since the static

tri-vector meters are calibrated through software at the manufacturers’ works, only accuracy of the meters and

functioning shall be verified during joint inspection and certified jointly by both the agencies. In case of any doubt

or defect, the meter shall be replaced then and there or calibrated. In later case, error correction as determined

will be applied to the meter reading for the purpose of billing contingency referred as in Regulation 19.16 of the

Grid Code and comprising their readings. To cover for loss of time, spare meters shall always be kept available

with the agency to whom the meter/metering point belongs. After testing, the meter shall be properly sealed and

a joint report shall be prepared giving details of testing work carried out, details of old seals removed and new

seals affixed, test results, further action to be taken, if any, etc. The User in whose premises the meter is located

shall be responsible for proper security, protection of the metering equipment and sealing arrangement.

(b) Joint inspection shall also be carried out as and when difference in meter readings (so corrected) exceeds

the sum of maximum error as per accuracy class of main and check meter. The meters shall be jointly tested/

calibrated on all loads and power factors as per relevant standards through static phantom load.

19.13. Meter Sealing Provision

(a) Metering system shall be jointly sealed by the authorized representatives of the concerned parties as

per the procedure agreed upon.

(b) No seal, applied pursuant to this Metering Code, shall be broken or removed except in the presence

of or with the prior consent of the agency affixing the seal or on whose behalf the seal has been affixed unless

it is necessary to do so in circumstances where

(i)

both main and check meters are malfunctioning or there occurs a fire or similar hazard and such

removal is essential and such consent cannot be obtained immediately

(ii)

such action is required for the purpose of attending to the meter failure. In such circumstances,

verbal consent shall be given immediately, and it must be confirmed in writing forthwith.

(c) Each party shall control the issue of its own seals and sealing pliers and shall keep proper register/

record of all such pliers and the authorized persons to whom these are issued.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

129

(d) Sealing of the metering system shall be carried out in such a manner so as not to hamper downloading

of the data from the meter using CMRI or a remote meter reading system.

19.14. Access to Equipment and Data

Each constituent of the agency (Utility) on request with advance notice, shall grant full right to install metering

equipment for other agency’s employees, agents/duly authorized representative for inspecting, testing, calibrating,

sealing, replacing the damaged equipment, collecting the data, joint reading recording, and other functions necessary

and as mutually agreed.

19.15. Operation and Maintenance of the Metering System

(a) The maintenance of the meters shall be the exclusive responsibility of the owner of the meters.

(b) The operation and maintenance of the metering system includes proper installation, regular maintenance

of the metering system, checking of errors of the CTs, VTs and meters, proper laying of cables and protection

thereof, cleaning of connections/ joints, checking of voltage drop in the CT/VT leads, condition of meter box and

enclosure, condition of seals, regular/daily reading meters and regular data retrieved through CMRI and DPS,

attending any breakdown/fault on the metering system, etc.

19.16. Procedure for Assessment of Consumption in case of Defective and/or stuck-up Meter

(a) Whenever a meter goes defective, the consumption recorded by the check meter shall be referred

for a period agreed mutually. The details of the malfunctioning along with date, time and snap-shot parameters

along with load survey shall be retrieved from the main meter. The exact nature of the mal-functioning shall be

brought out after analysing the data so retrieved and the consumption/losses recorded by the main meter shall

be assessed accordingly.

(b) If main as well as check metering systems become defective, the assessment of energy consumption

for the outage period shall be done as per the provisions of the TNE Supply Code or as mutually agreed by

the concerned parties or at the level of Transmission Metering Committee.

19.17. Mechanism for Dispute Resolution

Any disputes relating to inter-utility metering between State Transmission Utility and any Generating Company/

Distribution Licensees/Transmission Licensees/Users shall be settled in accordance with procedures prescribed under

relevant Power Purchase Agreements (PPA)/Connection Agreement or relevant Agreement, as the case may be.

In case of unresolved dispute, the matter may be referred to the Commission.

19.18. Implementation of Transmission Metering Code and Distribution Metering Code

(a) For existing metering system not complying with this Codes, State Transmission Utility and Distribution

Licensee shall submit a time-bound action plan to the Commission for replacement of the metering equipment in

a phased manner keeping in view the emerging and future requirements like development of open power market,

Act requirements, other tariff structures (two-part tariff etc.), Quality of Supply monitoring, remote monitoring/control,

etc.

(b) For any new procurement of metering system, this code shall be applicable immediately.

19.19. Dynamic Code

(a) To have a dynamic Code is very valuable aspect because there is continuous and very fast up gradation

in the technology of metering and communication, therefore the Code needs to be reviewed periodically as decided

by the Commission.

(b) If any of the provisions of the prevailing Metering Code of this TN State Grid Code is inconsistent with

any of the provisions of CEA Metering Regulations as amended from time to time, the provisions of Regulations

made by CEA shall prevail.

Chapter 20 - Cyber Security Code

20.1. General

(a) This chapter deals with measures to be taken to safeguard the State grid from spyware, malware, cyber-

attacks, network hacking, procedure for security audit from time to time, up-gradation of system requirements and

keeping abreast of latest developments in the area of cyber-attacks and cyber security requirements.

(b) All Users, SLDC, STU and other important third party agencies such as QCAs, Forecasting service

providers, etc. as considered by the STU/SLDC shall have in place, a Cyber Security framework in accordance

TAMIL NADU GOVERNMENT GAZETTE

130

[Part   VI—Sec. 2

with Information Technology Act, 2000, CEA Technical Standards for Connectivity Regulations, CEA (Cyber Security

in Power Sector) Guidelines, 2021 and any such Regulations issued from time to time, by an appropriate authority

to identify the critical cyber assets and protect them so as to support reliable operation of the grid.

20.2. Cyber Security Audit

All Users, SLDC and STU, shall conduct Cyber Security Audit as per the guidelines mentioned in the CEA

(Cyber Security in Power Sector) Guidelines, 2021 and any other guidelines issued by an appropriate Authority.

20.3. Mechanism of Reporting

(a) All entities shall immediately report to the appropriate government agencies in accordance with the

Information Technology Act, 2000, as amended from time to time, and CEA (Cyber Security in Power Sector)

Guidelines, 2021, in case of any cyber- attack.

(b) SLDC and the Commission shall also be informed by such entities in case of any instance of cyber-

attack.

20.4. Cyber Security Coordination Forum

(a) The sectoral CERT (Computer Emergency Response Team) for wings of power sector, as notified by

Government of India, from time to time, shall form a Cyber Security Coordination Forum with members from all

concerned utilities and other statutory agencies to coordinate and deliberate on the cyber security challenges and

gaps at appropriate level. A sub-committee of the same shall be formed at the regional level.

(b) The sectoral CERT shall lay down rules of procedure for carrying out their activities.

Chapter 21 - Data Registration Code

21.1. Introduction

This chapter contains list of data required by STU and SLDC, which is to be provided by Users and data

required by Users to be provided by STU at times specified in the Grid Code. Other chapters of the Grid Code

contain the obligation to submit the data and define the times, when such data is to be provided by Users.

21.2. Objective

The objective of this chapter is to list all the data required to be provided by Users to STU and vice versa,

in accordance with the provisions of the Grid Code.

21.3. Responsibility

(a) All Users are responsible for submitting up-to-date data to STU/ SLDC in accordance with the provisions

of the Grid Code.

(b) All Users shall provide STU and SLDC with the name, address and telephone number of the person

responsible for sending data.

(c) STU shall inform all Users and SLDC, the name, address and telephone number of the person responsible

for receiving data.

(d) STU shall provide up-to-date data to Users as provided in the relevant schedule of the Grid Code.

(e) Responsibility for the correctness of data rests with the concerned User providing the data.

21.4. Data Categories and Stages in Registration

Data required to be exchanged has been listed in the appendices of this chapter under various categories

with cross-reference to the concerned chapters.

21.5. Changes to User’s Data

Whenever there is any change/modification in the data submitted by User that is registered with STU, the

User must promptly notify STU of such changes. STU on receipt of intimation of the changes shall promptly

correct the database accordingly. This shall also apply to any data compiled by STU regarding to its own system.

21.6. Methods of submitting Data

(a) The data shall be furnished to SLDC/STU in the standard formats. However, in cases where standard

formats are not enclosed, the same would be developed by SLDC/ STU in consultation with Users.

(b) Where a computer data link exists between a User and SLDC/ STU, data may be submitted via link.

Other modes of data transfer, such as pen drive may be utilised, if SLDC/ STU gives its prior written consent.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

131

21.7. Special Considerations

(a) STU and SLDC and any other User may at any time make reasonable request for extra data as

necessary.

(b) STU shall supply data, required/requested by SLDC for system operation, from data bank to SLDC.

Chapter 22 – Miscellaneous

22.1. Power to Relax

The Commission for reasons to be recorded in writing, may relax any of the provisions of the Grid Code

on its own motion or on an application made before it by an interested person.

22.2. Power to Remove Difficulty

If any difficulty arises in giving effect to the provisions of this Grid Code, the Commission may, by order,

make such provisions not inconsistent with the provisions of the Act or provisions of other regulations specified

by the Commission, as may appear to be necessary for removing the difficulty in giving effect to the objectives

of the Grid Code.

22.3. Repeal and Savings

(a) Save as otherwise provided in this Grid Code, the “Tamil Nadu Electricity Grid Code” notified by the

Commission vide Notification No.TNERC/GC/13/1, dated 19.10.2005 along with all amendments thereto shall stand

repealed from the date of commencement of this Code.

(b) Notwithstanding anything contained contrary to any other regulations of the Commission for the time

being in force, the procedure for scheduling and Despatch of power shall be as per this Code only.

(c) Nothing in this Grid Code shall be deemed to limit or otherwise affect the inherent powers of the

Commission to make such orders as may be necessary for ends of justice or to prevent abuse of the process

of law.

(d) Nothing in this Grid Code shall bar the Commission from adopting, in conformity with the provisions

of the Act, a procedure which is at variance with any of the provisions of this Grid Code, if the Commission,

in view of the special circumstances of a matter or class of matters and for reasons to be recorded in writing,

deems it necessary or expedient for dealing with such a matter or class of matters.

(e) Nothing in this Grid Code shall, expressly or impliedly, bar the Commission dealing with any matter or

exercising any power under the Act for which no Regulations have been framed and the Commission may deal

with such matters, power and functions in a manner it thinks fit.

22.4. Issue of Suo-moto Orders and Directions

The Commission may from time-to-time issue suo-moto orders and practice directions with regard to

implementation of this Grid Code and matters incidental or ancillary thereto, as the case may be.

22.5. Treatment of this Grid Code in Contract

The provisions of this Grid Code or any amendments thereof shall not be treated under ‘Change in law’ in

any of the agreements entered into by any of the Users covered under this Grid Code.

(By Order of the Commission)

Chennai-600 032,

S. JOHN SUNDARARAJ,

17th February 2026.

Secretary (in-charge),

Tamil Nadu Electricity Regulatory Commission.

TAMIL NADU GOVERNMENT GAZETTE

132

[Part   VI—Sec. 2

APPENDIX

Appendix A: Standard Planning Data

Standard Planning Data consist of details, which are expected to be normally sufficient for STU to investigate

the impact on the State Transmission System due to User development. Standard planning data covering (a)

preliminary project planning

REFERENCE TO:

CHAPTER - 6 RESOURCE ADEQUACY AND SYSTEM PLANNING CODE

CHAPTER - 7 CONNECTION CODE

A-1 STANDARD PLANNING DATA (GENERATION)

For SSGS – Thermal

A.1.1 THERMAL (COAL / GAS/FUEL LINKED)

A.1.1.1 GENERAL

i

Site

Give location map to scale showing roads, railway lines, Transmission

lines, canals, pondage and reservoirs if any.

ii

Coal linkage/ Fuel (Like Liquefied

Natural Gas, Naphtha etc.) linkage

Give information on means of coal transport / carriage. In case of other

fuels, give details of source of fuel and their transport.

iii

Water Sources

Give information on availability of water for operation of the Power

Station.

iv

Environmental

State whether forest or other land areas are affected.

v

Site Map (To Scale)

Showing area required for Power Station coal linkage, coal yard, water

pipe lines, ash disposal area, colony etc.

vi

Approximate period of construction

A.1.1.2 CONNECTION

i

Point of Connection

Give single line diagram of the proposed Connection with the system.

ii

Step up voltage for Connection (kV)

A.1.1.3 STATION CAPACITY

i

Total Power Station capacity (MW)

State whether development shall be carried out in phases and if

so, furnish details.

ii

No. of units & unit size (MW)

A.1.1.4 GENERATING UNIT DATA

i

Steam Generating Unit

State type, capacity, steam pressure, steam temperature etc.

ii

Steam turbine

State type, capacity

iii

Generator

Type

Rating (MVA)

Speed (RPM)

Terminal voltage (kV)

Rated Power Factor

Reactive Power Capability

(MVAr) in the range 0.95 of leading and 0.85 lagging

Short Circuit Ratio

Direct axis (saturated) transient reactance (% on MVA rating)

Direct axis (saturated) sub-transient reactance ( % on MVA rating)

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

133

Auxiliary Power Requirement

MW and MVAr Capability curve

iv

Generator Transformer

Type

Rated capacity (MVA) Voltage Ratio (HV/LV)

Tap change Range (+ % to - %)

Percentage Impedance (Positive Sequence at Full load)

A.1.2 HYDRO ELECTRIC

For SSGS – Hydro

A.1.2.1 GENERAL

Site

Give location map to scale showing roads, railway

lines, and transmission lines.

Site map (To scale)

Showing proposed canal, reservoir area, water conductor

system, fore-bay, power house etc.

Submerged Area

Give information on area submerged, villages submerged,

submerged forest land, agricultural land etc.

Whether storage type or run of river type

Whether catchment receiving discharges from other

reservoir or power plant.

Full reservoir level

Minimum draw down level.

Tail race level

Design Head

Reservoir level versus energy potential curve Restraint,

if any, in water discharges Approximate period of

construction

A.1.2.2 CONNECTION

i

Point of Connection

Give single line diagram proposed Connection with the

Transmission System.

ii

Step up voltage for Connection (kV)

A.1.2.3 STATION CAPACITY

i

Total Power Station capacity (MW)

State whether development is carried out in phases

and if so furnish details.

ii

No. of units & unit size (MW)

A.1.2.4 GENERATING UNIT DATA

i

Operating Head

(in Metres)

a. Maximum

b. Minimum

c. Average

Hydro Unit

Capability to operate as synchronous condenser Water head versus

discharges curve (at full and part load) Power requirement or water

discharge while operating as synchronous condenser

ii

Turbine

State Type and capacity

TAMIL NADU GOVERNMENT GAZETTE

134

[Part   VI—Sec. 2

iii

Generator

Type

Rating (MVA)

Speed (RPM)

Terminal voltage (kV)

Rated Power Factor

Reactive Power Capability (MVAr) in the range 0.95 of leading and 0.85

of lagging

MW & MVAr capability curve of generating unit

Short Circuit Ratio

Direct axis transient (saturated) reactance (% on rated MVA)

Direct axis sub-transient (saturated) reactance (% on rated MVA)

Auxiliary Power Requirement (MW)

iv

Generator - Transformer

a. Type

b. Rated Capacity (MVA)

c. Voltage Ratio HV/LV

d. Tap change Range (+% to -%)

e. Percentage Impedance (Positive Sequence at Full Load).

A.2 STANDARD PLANNING DATA (TRANSMISSION) For STU and Transmission Licensees

Note: The compilation of the data is the internal matter of STU, and as such STU shall make arrangements

for getting the required data from different Departments of STU/other transmission licensees (if any) to update its

Standard Planning Data in the format given below:

i

Name of line (Indicating Power Stations and sub-stations to be connected).

ii

Voltage of line (kV).

iii

No. of circuits.

iv

Route length (km).

v

Conductor sizes.

vi

Line parameters (PU values).

a. Resistance/km

b. Inductance/km

c. Susceptance/ km (B/2)

vii

Approximate power flow expected- MW & MVAr.

viii

Terrain of the route- Give information regarding nature of terrain i.e. forest land, fallow land, agricultural and

river basin, hill slope etc.

ix

Route map (to scale) - Furnish topographical map showing the proposed route showing existing power lines

and telecommunication lines.

x

Purpose of Connection- Reference to Scheme, wheeling to other States etc.

xi

Approximate period of Construction.

A.3. STANDARD PLANNING DATA (DISTRIBUTION) For DISCOMs and Distribution Licensees

A.3.1 GENERAL

i

Area Map (to scale)

Marking the area in the map of Tamil Nadu for which Distribution

License is applied.

ii

Consumer Data

Furnish categories of consumers, their numbers and connected loads.

iii

Furnish categories of consumers,

their numbers and connected loads.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

135

A.3.2 CONNECTION

i

Points of Connection

Furnish single line diagram showing points of Connection

ii

Voltage of supply at points of

Connection

iii

Names of Grid Sub-Stations feeding

the points of Connection

A.3.3 LINES AND SUB-STATIONS

i

Line Data

Furnish lengths of line and voltages within the Area.

ii

Sub-station Data

Furnish details of 33/11kV sub-station, 11/0.4kV sub-stations, capacitor

installations

A.3.4 LOADS

i

Loads drawn at points of Connection.

ii

Details of loads fed at EHV, if any. Give name of consumer, voltage of supply, contract demand and name of

Grid Sub-station from which line is drawn, length of EHV line from Grid Sub-station to consumer’s premises.

iii

Reactive Power compensation installed

A.3.5 DEMAND DATA (FOR ALL LOADS 1 MW AND ABOVE)

i

Type of load

State whether furnace loads, rolling mills, traction loads, other

industrial loads, pumping loads etc.

ii

Rated voltage and phase

iii

Electrical loading of equipment

State number and size of motors, types of drive and control

arrangements.

iv

Power Factor

v

Sensitivity of load to voltage and frequency of

supply.

vi

Maximum Harmonic content of load.

vii

Average and maximum phase unbalance of

load

viii

Nearest sub-station from which load is to be fed

ix

Location map to scale

Showing location of load with reference to lines and sub-

stations in the vicinity

A.3.6 LOAD FORECAST DATA

Peak load and energy forecast for each category of loads for each of the succeeding 5 years. Details of

methodology and assumptions on which forecasts are based.

If supply is received from more than one sub-station, the sub-station wise break up of peak load and energy

projections for each category of loads for each of the succeeding 5 years along with estimated Daily load curve.

Details of loads 1 MW and above.

Name of prospective consumer.

Location and nature of load/complex.

Sub-Station from which to be fed.

Voltage of supply.

Phasing of load.

TAMIL NADU GOVERNMENT GAZETTE

136

[Part   VI—Sec. 2

Appendix B: Detailed Planning Data

REFER TO:

CHAPTER – 6 RESOURCE ADEQUACY ANDSYSTEM PLANNING CODE

CHAPTER – 7 CONNECTION CODE

B.1 DETAILED PLANNING DATA (GENERATION)

PART-I FOR ROUTINE SUBMISSION

B.1.1 THERMAL POWER STATIONS

For SSGS – Thermal

B.1.1.

GENERAL

1.

Name of Power Station.

2.

Number and capacity of Generating Units (MVA).

3.

Ratings of all major equipments (Boilers and major accessories, Turbines, Alternators,

Generator Unit Transformers etc.).

4.

Single line Diagram of Power Station and switchyard.

5.

Relaying and metering diagram.

6.

Neutral Grounding of Generating Units.

7.

Excitation control- (What type is used? e.g. Thyristor, Fast Brushless Excitors)

8.

Earthing arrangements with earth resistance values.

B.1.1.

PROTECTION AND METERING

i.

Full description including settings for all relays and protection systems on the

Generating Unit, Generator unit Transformer, Auxiliary Transformer

motor of major equipments listed, but not limited to, under Sec. 3.

ii.

Full description including settings for all relays installed on all outgoing feeders from

Power Station switchyard, Tie circuit breakers, and incoming circuit

iii.

Full description of inter-tripping of circuit breakers at the point or points of Connection

with the Transmission System.

iv.

Most probable fault clearance time for electrical faults on the User’s.

v.

Full description of operational and commercial metering schemes.

B.1.1.

SWITCHYARD

In relation to interconnecting transformers:

i

Rated MVA.

ii

Voltage Ratio

iii

Vector Group.

iv

Positive sequence reactance for maximum, minimum, normal Tap. (% on MVA).

v

Positive sequence resistance for maximum, minimum, normal Tap. (% on MVA).

vi

Zero sequence reactance (% on MVA).

vii

Tap changer Range (+% to -%) and steps.

viii

Type of Tap changer. (off/on load).

In relation to switchgear including circuit breakers, isolators on all circuits connected to the points of Connection:

i

Rated voltage (kV).

ii

Type of circuit breaker (MOCB/ABCB/SF6).

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

137

iii

Rated short circuit breaking current (kA) 3 phase.

iv

Rated short circuit breaking current (kA) 1 phase.

v

Rated short circuit making current (kA) 3 phase.

vi

Rated short circuit making current (kA) 1-phase.

vii

Provisions of auto reclosing with details.

(a) Lightning Arresters -

(b)Technical data

(c) Communication –

(d) Details of Communications equipment installed at points of connections.

(e) Basic Insulation Level (kV)

i. Bus bar.

ii. Switchgear.

iii. Transformer Bushings

iv. Transformer windings.

B.1.1.4 GENERATING UNITS

Parameters of Generator

i.

Rated terminal voltage (kV).

ii.

Rated MVA.

iii.

Rated MW.

iv.

Speed (rpm) or number of poles.

v.

Inertia constant H (MW sec./MVA).

vi.

Short circuit ratio.

vii.

Direct axis synchronous reactance Xd (% on MVA).

viii.

Direct axis (saturated) transient reactance (% on MVA) X’d.

ix.

Direct axis (saturated) sub-transient reactance (% on MVA) X”d.

x.

Quadrature axis synchronous reactance (% on MVA) Xq.

xi.

Quadrature axis (saturated) transient reactance (% on MVA) X’q.

xii.

Quadrature axis (saturated) sub-transient reactance (% on MVA) X”q.

xiii.

Direct axis transient open circuit time constant (sec) T’do.

xiv.

Direct axis sub-transient open circuit time constant (sec) T”do.

xv.

Quadrature axis transient open circuit time content (sec) T’qo.

xvi.

Quadrature axis transient open circuit time constant (sec) T”qo.

xvii.

Stator Resistance (Ohm) Ra.

xviii.

Stator leakage reactance (Ohm) X1.

xix.

Stator time constant (Sec).

xx.

Rated Field current (A).

xxi.

Neutral grounding details.

xxii.

Open Circuit saturation characteristics of the Generator for various terminal voltages giving the compounding

current to achieve this.

xxiii

MW and MVAr Capability curve.

B.1.1.5

Parameters of excitation control system:

i

Type of Excitation

ii

Maximum field Voltage

iii

Minimum field voltage

iv

Rated Field Voltage.

TAMIL NADU GOVERNMENT GAZETTE

138

[Part   VI—Sec. 2

v

Details of excitation loop in block diagrams showing transfer functions of individual elements using I.E.E.E.

symbols.

vi

Dynamic characteristics of over - excitation limiter.

vii

Dynamic characteristics of under-excitation limiter

B.1.1.6

Parameters of governor:

i.

Governor average gain (MW/Hz).

ii.

Speeder motor setting range.

iii.

Time constant of steam or fuel Governor valve.

iv.

Governor valve opening limits.

v.

Governor valve rate limits.

vi.

Time constant of Turbine.

vii.

Governor block diagram showing transfer functions of individual elements using I.E.E.E. symbols.

B.1.1.7

Operational parameters:

i.

Minimum notice required to synchronise a Generating Unit from de-synchronisation

ii.

Minimum time between synchronizing different Generating Units in a Power Station.

iii.

The minimum block load requirements on synchronizing.

iv.

Time required for synchronizing a Generating Unit for the following conditions:

a. Hot

b. Warm

c. Cold

v.

Maximum Generating Unit loading rates for the following conditions:

a. Hot

b. Warm

c. Cold

vi.

Minimum load without oil support (MW).

B.1.1.8 GENERAL STATUS

i

Detailed Project report.

ii

Status Report

(a) Land

(b) Coal

(c) Water

(d) Environmental clearance

(e) Rehabilitation of displaced persons

iii

Techno-economic approval by Central Electricity Authority (CEA).

iv

Approval of State Government/Government of India.

v

Financial Tie-up.

B.1.1.9 CONNECTION

i. Reports of Studies for parallel operation with the State Transmission System.

(a)

Short Circuit studies

(b)

Stability Studies.

(c)

Load Flow Studies.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

139

ii. Proposed Connection with the State Transmission System.

(a)

Voltage

(b)

No. of circuits

(c)

Point of Connection.

B.1.2 HYDRO - ELECTRIC STATIONS

For SSGS – Hydro

B.1.2.1 GENERAL

i

Name of Power Station.

ii

No and capacity of units. (MVA)

iii

Ratings of all major equipment.

a) Turbines (HP)

b) Generators (MVA)

c) Generator Transformers (MVA)

d) Auxiliary Transformers (MVA)

iv

Single line diagram of Power Station and switchyard.

v

Relaying and metering diagram.

vi

Neutral grounding of Generator.

vii

Excitation control.

viii

Earthing arrangements with earth resistance values.

ix

Reservoir Data.

a) Salient features

b) Type of Reservoir

i. Multipurpose

ii. For Power

c) Operating Table with

i. Area capacity curves and

ii. Unit capability at different net heads

B.1.2.2 PROTECTION

i

Full description including settings for all relays and protection systems installed on the Generating Unit,

Generator transformer, auxiliary transformer and electrical motor of major equipment included, but not limited to

those listed, under Sec. 3 (General).

ii

Full description including settings for all relays installed on all outgoing feeders from Power Station

switchyard, tiebreakers, and incoming breakers.

iii

Full description of inter-tripping of breakers at the point or points of Connection with the Transmission System.

iv

Most Probable fault clearance time for electrical faults on the User’s System.

B.1.2.3 SWITCHYARD

(a) Interconnecting transformers:

i

Rated MVA

ii

Voltage Ratio

iii

Vector Group

iv

Positive sequence reactance for maximum, minimum and normal Tap.(% on MVA).

TAMIL NADU GOVERNMENT GAZETTE

140

[Part   VI—Sec. 2

v

Positive sequence resistance for maximum, minimum and normal Tap.(% on MVA).

vi

Zero sequence reactance (% on MVA)

vii

Tap changer range (+% to -%) and steps.

viii

Type of Tap changer (off/on load).

ix

Neutral grounding details.

(b) Switchgear (including circuit breakers, Isolators on all circuits connected to the points of Connection).

i

Rated voltage (kV).

ii

Type of Breaker (MOCB/ABCB/SF6).

iii

Rated short circuit breaking current (kA) 3 phase.

iv

Rated short circuit breaking current (kA) 1 phase.

v

Rated short circuit making current (kA) 3 phase.

vi

Rated short circuit making current (kA) 1 phase.

vii

Provisions of auto reclosing with details.

(c) Lightning Arresters Technical data

(d) Communications -

Details of Communications equipment installed at points of connections.

(e) Basic Insulation Level (kV)

i

Bus bar.

ii

Switchgear.

iii

Transformer Bushings

iv

Transformer windings.

B.1.2.4 GENERATING UNITS

(a) Parameters of Generator

i.

Rated terminal voltage (kV).

ii.

Rated MVA.

iii.

Rated MW.

iv.

Speed (rpm) or number of poles.

v.

Inertia constant H (MW sec./MVA).

vi.

Short circuit ratio.

vii.

Direct axis synchronous reactance Xd (% on MVA).

viii.

Direct axis (saturated) transient reactance (% on MVA) X’d.

ix.

Direct axis (saturated) sub-transient reactance (% on MVA) X”d.

x.

Quadrature axis synchronous reactance (% on MVA) Xq.

xi.

Quadrature axis (saturated) transient reactance (% on MVA) X’q.

xii.

Quadrature axis (saturated) sub-transient reactance (% on MVA).

xiii.

Direct axis transient open circuit time constant (sec) T’do.

xiv.

Direct axis sub-transient open circuit time constant (sec) T”do.

xv.

Quadrature axis transient open circuit time content (sec) T’qo.

xvi.

Quadrature axis transient open circuit time constant (sec) T”qo.

xvii.

Stator Resistance (Ohm) Ra.

xviii.

Stator leakage reactance (Ohm) X1.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

141

xix.

Stator time constant (Sec).

xx.

Rated Field current (A).

xxi.

Neutral grounding details.

xxii.

Open Circuit saturation characteristics of the Generator for various terminal voltages giving the compounding

current to achieve this.

xxiii.

Type of Turbine.

xxiv.

Operating Head (Metres)

xxv.

Discharge with full gate opening (cumecs)

xxvi.

Speed Rise on total Load throw off (%).

xxvii.

MW and MVAr Capability curve

(b)

Parameters of excitation control system:

As applicable to thermal Power Stations

(c)

Parameters of governor:

As applicable to thermal Power Station

(d) Operational parameter:

i

Minimum notice required to Synchronise a Generating Unit from de- synchronisation.

ii

Minimum time between Synchronising different Generating Units in a Power Station.

iii

Minimum block load requirements on Synchronising.

B.1.2.5 GENERAL STATUS

i

Detailed Project Report.

ii

Status Report.

(a) Topographical survey

(b) Geological survey

(c) Land

(d) Environmental Clearance

(e) Rehabilitation of displaced persons.

iii

Techno-economic approval by Central Electricity Authority

iv

Approval of State Government/Government of India.

v

Financial Tie-up.

i

Detailed Project Report.

ii

Status Report.

(a) Topographical survey

(b) Geological survey

(c) Land

(d) Environmental Clearance

(e) Rehabilitation of displaced persons.

iii

Techno-economic approval by Central Electricity Authority

B.1.2.6 CONNECTION

i. Reports of Studies for parallel operation with the State Transmission System.

(a)

Short Circuit studies

(b)

Stability Studies.

(c)

Load Flow Studies.

TAMIL NADU GOVERNMENT GAZETTE

142

[Part   VI—Sec. 2

ii. Proposed Connection with the State Transmission System.

(a)

Voltage

(b)

No. of circuits

(c)

Point of Connection.

B.1.2.7 RESERVOIR DATA

(a) Dead Capacity

(b) Live Capacity

B.1.3 GAS POWER STATIONS

For SSGS – Gas

B.1.3.1 GENERAL

i

Name of Power Station.

ii

Number and capacity of Generating Units (MVA).

iii

Ratings of all major equipments (Turbines, Alternators, Heat Recovery Boiler, Generator Unit

Transformers etc.)

iv

Single line Diagram of Power Station and switchyard.

v

Relaying and metering diagram.

vi

Neutral Grounding of Generating Units.

vii

Excitation control- (What type is used? e.g. Thyristor, Fast Brushless Exciters)

viii

Earthing arrangements with earth resistance values.

ix

Start up Engine

x

Turbine Details

B.1.3.2 PROTECTION AND METERING

i

Full description including settings for all relays and protection systems installed on the Generating

Unit, Generator unit Transformer, Auxiliary Transformer and electrical motor of major equipments

listed, but not limited to, under Sec. 3 (General).

ii

Full description including settings for all relays installed on all outgoing feeders from Power Station

switchyard, Tie circuit breakers, and incoming circuit breakers.

iii

Full description of inter-tripping of circuit breakers at the point or points of Connection with the

Transmission System.

iv

Most probable fault clearance time for electrical faults on the User’s System.

v

Full description of operational and commercial metering schemes.

B.1.3.3 SWITCHYARD

In relation to interconnecting transformers:

i

Rated MVA.

ii

Voltage Ratio

iii

Vector Group.

iv

Positive sequence reactance for maximum, minimum, normal Tap.(% on MVA).

v

Positive sequence resistance for maximum, minimum, normal Tap.(% on MVA).

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

143

vi

Zero sequence reactance (% on MVA).

vii

Tap changer Range (+% to -%) and steps.

viii

Type of Tap changer. (off/on load).

In relation to switchgear including circuit breakers, isolators on all circuits connected to the points of Connection:

i

Rated voltage (kV).

ii

Type of circuit breaker (MOCB/ABCB/SF6).

iii

Rated short circuit breaking current (kA) 3 phase.

iv

Rated short circuit breaking current (kA) 1 phase.

v

Rated short circuit making current (kA) 3 phase.

vi

Rated short circuit making current (kA) 1-phase.

vii

Provisions of auto reclosing with details. Lightning Arresters -

Technical data

Communication -

Details of communication equipment installed at points of connections. Basic Insulation

Level (kV) -

i. Bus bar.

ii. Switchgear.

iii. Transformer bushings.

iv. Transformer windings.

B.1.3.4 GENERATING UNITS

(a) Parameters of Generating Units:

i

Rated terminal voltage(kV).

ii

Rated MVA.

iii

Rated MW.

iv

Speed (rpm) or number of poles.

v

Inertia constant H (MW Sec./MVA).

vi

Short circuit ratio.

vii

Direct axis synchronous reactance (% on MVA) Xd.

viii

Direct axis (saturated) transient reactance (% on MVA) Xd’.

ix

Direct axis (saturated) sub-transient reactance (% on MVA) Xd”.

x

Quadrature axis synchronous reactance (% on MVA)Xq .

xi

Quadrature axis (saturated) transient reactance (% on MVA) Xq’.

xii

Quadrature axis (saturated) sub-transient reactance (% on MVA) Xq”.

xiii

Direct axis transient open circuit time constant (Sec) T’do.

xiv

Direct axis sub-transient open circuit time constant (Sec) T”do.

xv

Quadrature axis transient open circuit time constant (Sec) T’qo.

xvi

Quadrature axis sub-transient open circuit time constant (Sec) T’’qo.

xvii

Stator Resistance (Ohm) Ra.

xviii

Neutral grounding details.

TAMIL NADU GOVERNMENT GAZETTE

144

[Part   VI—Sec. 2

xix

Stator leakage reactance (Ohm) X1

xx

Stator time constant (Sec).

xxi

Rated Field current (A).

xxii

Open Circuit saturation characteristic for various terminal Voltages giving the compounding current

to achieve the same.

xxiii

MW and MVAr Capability curve

B.1.3.5 Parameters of excitation control system:

i

Type of Excitation.

ii

Maximum Field Voltage.

iii

Minimum Field Voltage.

iv

Rated Field Voltage.

v

Details of excitation loop in block diagrams showing transfer functions of individual elements using

I.E.E.E. symbols.

vi

Dynamic characteristics of over - excitation limiter.

vii

Dynamic characteristics of under-excitation limiter.

B.1.3.6 Parameters of governor:

i

Governor average gain (MW/Hz).

ii

Speeder motor setting range.

iii

Time constant of steam or fuel Governor valve.

iv

Governor valve opening limits.

v

Governor valve rate limits.

vi

Time constant of Turbine.

vii

Governor block diagram showing transfer functions of individual elements using I.E.E.E. symbols.

B.1.3.7 Operational parameters:

i

Minimum notice required for synchronising a Generating Unit from de-synchronization.

ii

Minimum time between synchronizing different Generating Units in a Power Station.

iii

The minimum block load requirements for synchronizing.

iv

Time required for synchronizing a Generating Unit for the following conditions:

a. Hot

b. Warm

c. Cold

v

Maximum Generating Unit loading rates for the following conditions:

a. Hot

b. Warm

c. Cold

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

145

vi

Minimum load without oil support (MW).

B.1.3.8 GENERAL STATUS

i

Detailed Project report

ii

Status Report

(a) Land

(b) Gas/Liquid Fuel

(c) Water

(d) Environmental clearance

(e) Rehabilitation of displaced persons

iii

Approval of State Government/Government of India.

iv

Financial Tie-up.

B.1.3.9 CONNECTION

i. Reports of Studies for parallel operation with the State Transmission System.

(a)

Short Circuit studies

(b)

Stability Studies.

(c)

Load Flow Studies.

ii. Proposed Connection with the State Transmission System.

(a)

Voltage

(b)

No. of circuits

(c)

Point of Connection.

B.2 DETAILED PLANNING DATA - TRANSMISSION

For STU and Transmission Licensees

B.2.1 GENERAL

i. Single line diagram of the Transmission System down to the 33kV bus at the Grid Sub-station detailing:

(a)

Name of Sub-station.

(b)

Power Station connected.

(c)

Number and length of circuits.

(d)

Interconnecting transformers.

(e)

Sub-station bus layouts.

(f)

Power transformers.

(g)

Reactive compensation equipment.

ii. Sub-station layout diagrams showing:

(a)

Bus bar layouts.

(b)

Electrical circuitry, lines, cables, transformers, switchgear etc.

(c)

Phasing arrangements.

(d)

Earthing arrangements.

(e)

Switching facilities and interlocking arrangements.

(f)

Operating voltages.

TAMIL NADU GOVERNMENT GAZETTE

146

[Part   VI—Sec. 2

(g)

Numbering and nomenclature:

i.1 Transformers.

ii.1 Circuits.

iii. Circuit breakers.

iv. Isolating switches.

B.2.2 LINE PARAMETERS (for all circuits)

i

Designation of Line.

ii

Length of line(km).

iii

Number of circuits.

iv

Per Circuit values.

(a) Operating voltage (kV).

(b) Positive Phase sequence reactance (pu on 100 MVA) X1

(c) Positive Phase sequence resistance (pu on 100 MVA) R1

(d) Positive Phase sequence susceptance (pu on 100 MVA) B1

(e) Zero Phase sequence reactance (pu on 100 MVA) X0

(f) Zero Phase sequence resistance (pu on 100 MVA) R0

(g) Zero Phase sequence susceptance (pu on 100 MVA) B0

B.2.3 TRANSFORMER PARAMETERS (For all transformers)

i.

Rated MVA

ii.

Voltage Ratio

iii.

Vector Group

iv.

Positive sequence reactance, maximum, minimum and normal (pu on 100 MVA) X1

v.

Positive sequence resistance, maximum, minimum and normal (pu on 100 MVA) R1

vi.

Zero sequence reactance (pu on 100 MVA).

vii.

Tap change range (+% to -%) and steps.

viii.

Details of Tap changer. (Off-load/On-load).

B.2.4

EQUIPMENT DETAILS (For all sub-stations)

i.

Circuit Breakers

ii.

Isolating switches

iii.

Current Transformers

iv.

Potential Transformers

B.2.5

RELAYING AND METERING

i.

Relay protection installed for all transformers and feeders along with their settings and

level of co-ordination with other Users.

ii.

Metering Details.

B.2.6

SYSTEM STUDIES

i.

Load Flow studies (Peak and lean load for maximum hydro and maximum thermal

generation).

ii.

Transient stability studies for three-phase fault in critical lines.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

147

iii.

Dynamic Stability Studies

iv.

Short circuit studies (three-phase and single phase to earth)

v.

Transmission and Distribution Losses in the Transmission System.

B.2.7

DEMAND DATA (For all sub-stations)

i.

Demand Profile (Peak and lean load).

B.2.8

REACTIVE COMPENSATION EQUIPMENT

i.

Type of equipment (fixed or variable).

ii.

Capacities and/or Inductive rating or its operating range in MVAr.

iii.

Details of control.

iv.

Point of Connection to the System.

B.3. DETAILED PLANNING DATA (DISTRIBUTION)

For DISCOMs /Distribution Licensees

B.3.1 GENERAL

i

Distribution map (To scale). Showing all lines up to 11kV and sub-stations belonging to the Supplier.

ii

Single line diagram of Distribution System (showing distribution lines from points of Connection with the

Transmission System, 33/11kV sub-stations, 11/0.4kV sub-station, consumer bus if fed directly from the

Transmission System).

iii

Numbering and nomenclature of lines and sub-stations (Identified with feeding Grid sub-stations of the

Transmission and concerned 33/11kV sub-station of Supplier).

B.3.2 CONNECTION

i

Points of Connection (Furnish details of existing arrangement of Connection).

ii

Details of metering at points of Connection.

B.3.3 LOADS

i

Connected load - Active and Reactive Load. Furnish consumer details, Number of Consumers category wise,

details of loads 1 MW and above, power factor.

ii

Information on diversity of load and coincidence factor.

iii

Daily demand profile (current and forecast) on each 33/11kV sub-station.

iv

Cumulative demand profile of Distribution System (current & forecast).

TAMIL NADU GOVERNMENT GAZETTE

148

[Part   VI—Sec. 2

Appendix C: Operational Planning Data

C.1 OUTAGE PLANNING DATA

REFER TO:

CHAPTER 14 - OUTAGE PLANNING CODE

C.1.1 DEMAND ESTIMATES

For DISCOMs /Distribution Licensees

Items

Due date / Time

Estimated aggregate annual sales of energy in Million Units and peak and

lean demand in MW & MVAr at each Connection point for the next financial

year.

15th November of current year

Estimated aggregate monthly sales of Energy in million Units and peak and

lean demand in MW & MVAr at each Connection point for the next month.

25th of current month

Hourly demand estimates for the day ahead.

10.00 Hours every day.

C.1.2 ESTIMATES OF LOAD SHEDDING

For DISCOMs/Distribution Licensee

Items

Due date / Time

Details of discrete load blocks that may be shed to comply with

instructions issued by SLDC when required, from each Connection

point.

Soon after Connection is made

C.1.3 YEAR AHEAD OUTAGE PROGRAMME (For the financial year)

C.1.3.1 GENERATOR OUTAGE PROGRAMME

For SSGS

Items

Due date / Time

Identification of Generating Unit.

15th November each year

MW, which will not be available as a result of Outage.

15th November each year

Preferred start date and start-time or range of start dates and start times

and period of Outage.

15th November each year

If outages are required to meet statutory requirements, then the latest-

date by which Outage must be taken.

15th November each year

C.1.3.2 YEAR AHEAD SRPC OUTAGE PROGRAMME

(Affecting Transmission System)

Items

Due date / Time

MW, which will not be available as a result of an Outage from Imports

through external Connections.

1st November each year

Start-date and start-time and period of Outage.

1st November each year

C.1.3.3 YEAR AHEAD CGP’s OUTAGE PROGRAMME

Items

Due date / Time

MW, which will not be available as a result of Outage

30th November each year

Start-date and start-time and period of Outage.

30th November each year

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

149

C.1.3.4 YEAR AHEAD DISCOMs OUTAGE PROGRAMME

Items

Due date / Time

Loads in MW not available from any Connection point.

15th November each year

Identification of Connection point.

15th November each year

Period of suspension of Drawal with start-date and start-time.

15th November each year

C.1.3.5 STU’s OVERALL OUTAGE PROGRAMME

Item

Due date/Time

Report on proposed Outage programme to SRPC

15th February each year

Release of finally agreed Outage plan

15th February each year

C- 2. GENERATION SCHEDULING DATA

REFER TO CHAPTER -11: SCHEDULE AND DESPATCH CODE

C-3 CAPABILITY DATA

REFER TO:

CHAPTER 12-FREQUENCY AND VOLTAGE MANAGEMENT CODE

For SSGS

Item

Due date / Time

Generators and IPPs shall submit to SLDC up-to-date capability curves

for all Generating Units.

On receipt of request from STU/ SLDC.

CGPs shall submit to STU net return capability that shall be available for

Export/Import from Transmission System.

On receipt of request from STU/ SLDC.

C-4 RESPONSE TO FREQUENCY CHANGE

REFER TO:

CHAPTER 12-FREQUENCY AND VOLTAGE MANAGEMENT CODE

For SSGS

Item

Due date / Time

Primary Response in MW at different levels of loads ranging from

minimum Generation to registered capacity for frequency changes

resulting in fully opening of governor valve.

On receipt of request from STU/ SLDC.

Secondary response in MW to frequency changes

On receipt of request from STU/ SLDC.

C-5 MONITORING OF GENERATION

REFER TO:

CHAPTER 13 - MONITORING OF GENERATION AND DRAWAL CODE

For SSGS

Items

Due date / Time

SSGS shall provide hourly generation summation to SLDC.

Real time basis

CGPs shall provide hourly export/ import MW to SLDC.

Real time basis

Logged readings of Generators to SLDC.

As required

Detailed report of Generating Unit tripping on monthly basis.

In the first week of the succeeding month

TAMIL NADU GOVERNMENT GAZETTE

150

[Part   VI—Sec. 2

C-6 ESSENTIAL AND NON-ESSENTIAL LOAD DATA

REFER TO:

CHAPTER 15 - CONTINGENCY PLANNING CODE

For DISCOMs /Distribution Licensee

Items

Due date / Time

Schedule of essential and non-essential loads on each discrete load

block for purposes of load shedding.

As soon as possible after the Connection

Appendix D: Protection Data

REFER TO:

CHAPTER 18 – PROTECTION CODE

Item

Due date / Time

For SSGS

Generators / CGPs / IPPs shall submit details of protection requirement

and schemes installed by them as referred to in B-1. Detailed Planning

Data under “Protection And Metering”.

As applicable to Detailed Planning Data

For STU /Transmission Licensee

The STU shall submit details of protection equipment and schemes

installed by them as referred to in B-2. Detailed system Data, Transmission

under “Relaying and Metering” in relation to Connection with any User.

As applicable to Detailed Planning Data

Appendix E: Metering Data

REFER TO:

CHAPTER 19 - TRANSMISSION METERING CODE

Item

Due date / Time

For SSGS

SSGS shall submit details of metering equipment and scheme installed

by them as referred in B-1. Detailed Planning Data under “Protection

and Metering”.

As applicable to Detailed Planning Data

For STU /Transmission Licensee

STU shall submit details of metering equipment and schemes installed

by them as referred in B-2. Detailed System Data, Transmission under

“Relaying and Metering” in relation to Connection with any User.

As applicable to Detailed Planning Data

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

151

Appendix F: Planning Standards

REFER TO:

CHAPTER 6 - RESOURCE ADEQUACY AND SYSTEM PLANNING CODE

General Policy

The State Transmission System planning and generation expansion planning shall be in accordance with

the provisions of Manual on Transmission Planning Criteria issued by CEA and other guidelines. However, some

planning parameters of the State transmission System may vary according to directives of the Commission.

Planning Criterion

(a) The planning criterion is based on the security philosophy on which ISTS and InSTS has been planned.

The security philosophy shall be as per Manual on Transmission Planning Criteria and other CEA guidelines. The

general policy shall be as detailed below:

(i)

As a general rule, the InSTS shall be capable of withstanding and secured against the following contingency

outages without necessitating load shedding or rescheduling of generation during Steady State Operations:

•

Outage of a 110 kV D/C line or,

•

Outage of a 230kV D/C line or,

•

Outage of a 400kV S/C line or,

•

Outage of a single Interconnecting Transformer, or,

•

Outage of one pole of HVDC Bi-pole line, or,

•

Outage of a 765kV S/C line.

(ii)

The above contingencies shall be considered assuming as pre-contingency system depletion (Planned

Outage) of another 230kV D/C line or 400kV S/C line in another corridor and not emanating from same sub-

station. All the generating Units may operate within their reactive capability curves and the network voltage profile

shall also be maintained within voltage limits specified.

(b) The ISTS / InSTS shall be capable of withstanding the loss of most severe single system in feed without

loss of stability.

(c) Any one of these events defined above shall not cause:

i

Loss of supply

ii

Prolonged operation of the system frequency below and above specified limits

iii

Unacceptable high or low voltage

iv

System instability

v

Unacceptable overloading of ISTS/STS elements

Appendix G: Site Responsibility Schedule

REFER TO: CHAPTER 7 – Grid connectivity conditions

Item of Plant/

Apparatus

Plant

Owner

Safety

Responsibility

Control

Responsibility

Operation

Responsibility

Maintenance

Responsibility

Remarks

……kV

Switchyard

All equipment

including bus

bars

Feeders

Generating

Units

Name of Power Station/Sub-Station

Site Owner: Tel. Number: Fax Number:

TAMIL NADU GOVERNMENT GAZETTE

152

[Part   VI—Sec. 2

Appendix H: Incident Reporting

REFER TO:

CHAPTER 17 - Reports

Operational Event / Incidence reporting

FLASH REPORT : SLDC/STU/USERS/TRANSMISSION LICENSEE/GENERATORS

Agency Name/Month-Year/GD or GI- Number

Name of Incident:

1. Date and Time:

2. Antecedent Conditions

I. Frequency of the Grid

Event

Frequency

Time(hh:mm)

Pre incident

 

 

Post Incident

 

 

II. Demand Met - MW

State Generation - MW

State Load - MW

3. Event Description: Event and Likely cause as reported by SLDC./State Entities and as observed.

4. Lines/ICT/Units tripped and Restoration

Lines/ICT/Unit Tripped

Load prior to

fault

Tripping

time

Restoration Time

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5. Areas Affected By Disturbance :

6. Load Loss :

7. Generation Loss :

8. SUPPLY RESUMED FROM

Appendix-I: Third Party Protection System Checking & Validation Template For A Sub-Station

1.

INTRODUCTION

(i)

The audit reports, along with action plan for rectification of deficiencies found, if any, shall be submitted

to PCC and/or SLDC within a month of submission of report by auditor.

(ii)

The third-party protection system checking shall be carried at site by the designated agency. The agency

shall furnish two reports:

(a) Preliminary Report: This report shall be prepared on the site and shall be signed by all the parties

present.

(b) Detailed Report: This report shall be furnished by agency within one month after carrying out detailed

analysis.

2.

CHECKLIST

(i)

The protection system checklist shall contain information as per this Regulation.

(a) General Information (to be provided prior to the checking as well as to be included in final report):

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

153

(i)

Sub-station name

(ii)

Name of Owner Utility

(iii) Voltage Level (s) or highest voltage level?

(iv) Short circuit current rating of all equipment (for all voltage level)

(v)

Date of commissioning of the sub-station

(vi) Checking and validation date

(vii) Record of previous trippings (in last one year) and details of protection operation

(viii) Previous Relay Test Reports

(ix) Overall single line diagram (SLD)

(x)

AC aux SLD

(xi) DC aux SLD

(xii) SAS architecture diagram

(xiii) SPS scheme implemented (if any)

(b) The preliminary report shall inter-alia contain the following:

TABLE: FORMAT OF PRELIMINARY REPORT

S.No.

Issues

Remarks

1

Recommendation of last protection checking and validation

Status of works and pending issues if any

2

Review of existing settings at sub-station

Recommended Action

3

Disturbance Recorder output available for last 6 trippings (Y/N)

Recommended Action

4

Chronic reason of tripping, if any

Recommended Action

5

Major non-conformity / deficiency observed

Recommended Action

(c) The relay configuration checklist for available power system elements at station:

(i)

Transmission Line

(ii)

Bus Reactor/Line Reactor

(iii) Inter-connecting Transformer

(iv) Busbar Protection Relay

(v) AC auxiliary system

(vi) DC auxiliary system

(vii) Communication system

(viii) Circuit Breaker Details

(ix) Current Transformer Details

(x) Capacitive Voltage Transformers Details

(xi) Any other equipment/system relevant for protection system operation

(d) The minimum set of points on which checking and validation shall be carried out is covered in this

Regulation. The detailed list shall be prepared by checking and validation team in consultation with concerned

entity, PCC and SLDC.

(i)

Transmission Line Distance Protection/Differential Protection

a.

Name and Length of Line

b.

Whether series compensated or not

c.

Mode of communication used (PLCC/OPGW)

TAMIL NADU GOVERNMENT GAZETTE

154

[Part   VI—Sec. 2

d.

Relay Make and Model for Main-I and Main-II

e.

List of all active protections & settings

f.

Carrier-aided scheme if any

g.

Status of Power Swing/Out of Step/SOTF/Breaker Failure/Broken Conductor / STUB/Fault Locator/

DR/VT fuse fail/ Overvoltage Protection /Trip Circuit supervision/Auto-reclose/Load encroachment etc.

h.

Relay connected to Trip Coil-1 or 2 or both

i.

CT ratio and PT ratio

j.

Feed from DC supply-1 or 2

k.

Connected to dedicated CT core (mention name)

l.

Other requirements for protection checking and validation

(ii)

Shunt Reactor & Inter-connecting Transformer Protection

a.

Whether two groups of protections used (Group A and Group B)

b.

Do the groups have separate DC sources

c.

Relay Make and Model

d.

List of all active protections along with settings

e.

Status of Differential Protection/Restricted Earth Fault Protection/Back-up Directional Over current/

Backup Earth fault/ Breaker Failure

f.

Status of Oil Temperature Indicator/Winding Temperature Indicator / Bucholz/Pressure Release Device

etc.

g.

Relay connected to Trip Coil-1 or 2 or both

h.

CT ratio and PT ratio

i.

Feed from DC supply-1 or 2

j.

Connected to dedicated CT core (mention name)

k.

Other requirements for protection checking and validation

(iii) Bus-bar Protection Relay

a.

Bus-bar and redundant relay make and model

b.

Type of Bus-bar arrangement

c.

Zones

d.

Dedicated CT core for each busbar protection (Yes/No)

e.

Breaker Failure relay included (Yes/No), if additional then furnish make and model

f.

Trip issued to both Busbar protection in case of enabling

g.

Isolator indication and check relays

h.

Other requirements for protection checking and validation

(iv) AC auxiliary system

a.

Source of AC auxiliary system

b.

Supply changeover between sources (Auto/Manual)

c.

Diesel generator (DG) details

d.

Maintenance plan and supply changeover periodicity in DG

e.

Single Line Diagram

f.

Other requirements for protection checking and validation

(v) DC auxiliary system

a.

Type of Batteries (Make, vintage, model)

b.

Status of battery Charger

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

155

c.

Measured voltage (positive to earth and negative to earth)

d.

Availability of ground fault detectors

e.

Protection relays and trip circuits with independent DC sources

f.

Other requirements for protection checking and validation

g.

Communication system

(i)

Mode of communication for Main-1 and Main-2 protection

(ii)

Mode of communication for data and speech communication

(iii) Status of PLCC channels

(iv) Time synchronization equipment details

(v) OPGW on geographically diversified paths for Main-1 and main-2 relay

(vi) Other requirements for protection checking and validation

(vi) Circuit Breaker Details

a.

Details and Status

b.

Healthiness of Tripping Coil and Trip circuit supervision relay

c.

Single Pole/Multi pole operation

d.

Pole Discrepancy Relay available(Y/N)

e.

Monitoring Devices for checking the dielectric medium

f.

Other requirements for protection checking and validation

(vii) Current Transformer (CT)/Capacitive Voltage Transformer (CVT) Details

a.

CT/CVT ID name and voltage level

b.

CT/CVT core connection details

c.

Accuracy Class

d.

Whether Protection/Metering

e.

CT/CVT ratio available and ratio adopted

f.

Details of last checking and validation of CT/CVT healthiness

g.

Other requirements for protection checking and validation

h.

Other protections: Direction earth fault, negative sequence, over current, over voltage, over frequency,

under voltage, under frequency, forward power, reverse power, out of step/power swing, HVDC protection etc.

3.

SUMMARY OF CHECKING:

The summary shall specifically mention minimum following points:

(i)

The settings and scheme adopted are in line with agreed protection philosophy or any accepted

guidelines (e.g. Ramakrishna guidelines or CBIP manual based).

(ii)

The deviations from the RPC protection philosophy, if any and reasons for taking the deviations

shall be recorded.

(iii) All the major general deficiency shall be listed in detail along with remedial recommendations.

(iv) The relay settings to be adopted shall be validated with simulation based or EMTP studies and

details shall be enclosed in report.

(v) The cases of protection mal-operation shall be analysed from protection indices report furnished by

concerned utility, the causes of failure along with corrective actions and recommendations based on the findings

shall be noted in the report.

TAMIL NADU GOVERNMENT GAZETTE

156

[Part   VI—Sec. 2

Appendix-J: Reactive Power Compensation

1.

REACTIVE POWER COMPENSATION

(a) Reactive power compensation should ideally be provided locally, by generating reactive power as close

to the reactive power consumption as possible. The state entities are therefore expected to provide local VAr

compensation or generation such that they do not draw VARs from the EHV grid, particularly under low-voltage

condition. To discourage VAr drawals by state entities, VAr exchanges with Intra State Transmission System shall

be priced as follows:

(i)

The State entity pays for VAr drawal when voltage is below 97%

(ii)

The State entity gets paid for VAr return when voltage is below 97%.

(iii) The State entity gets paid for VAr drawal when voltage is above103%.

(iv) The State entity pays for VAr return when voltage is above 103%.

Where all voltage measurements are at the interface point with ISTS / InSTS.

(b) The Reactive Energy Charges shall be fixed by the Commission vide separate order / notification from

time to time.

(c) The SLDC shall issue monthly statement for Reactive Energy Charges to all intra-state entities and shall

finalize methodology & procedure for carrying out reactive energy accounting of intra state entities within 60 days

of notification of these regulations duly consulting the stakeholders and submit to the Commission for approval.

Appendix-K: Summary of the procedures to be formulated by the SLDC

The SLDC shall formulate the following procedures duly consulting the stakeholders concerned and submit

the same to the Commission for approval within 60 days from the date of issue of this Code:

1.

Procedure for functioning of Grid Code Review Committee as per the Regulation 5.3(a) of this Code;

2.

Procedure for first time energization as per the Regulation 7.7(m)(vi) of this Code;

3.

Detailed operating procedure of SLDC (Regulation 10.3(c)) including operating procedures under grid

disturbance/emergencies (Regulation 8.3(d)), restoration procedure (Regulation 15.4(a)), Procedure for carrying out

Reactive Energy Accounting (Appendix-J of this Code), etc.;

4.

Detailed procedure for Scheduling and Despatch;

5.

Procedures for functioning of various Committees to be formulated under this Code;

6.

Any other procedures essentially required for day-to-day operation.

Mar. 11, 2026]

TAMIL  NADU  GOVERNMENT  GAZETTE

157

Explanatory Statement

The Tamil Nadu Electricity Regulatory Commission (hereinafter referred to as “the Commission”) notified the

Tamil Nadu Electricity Grid Code (TNEGC) vide Notification No. TNERC/GC/13/1 dated 19.10.2005, which came

into effect from 14.12.2005.

The Central Electricity Regulatory Commission (CERC), upon notifying the Indian Electricity Grid Code

(IEGC), 2023, revised the IEGC, 2010 and introduced provisions including, inter alia, declaration of the date of

commercial operation of generating stations, mandatory trial runs for generators, system planning for 765 kV

circuits, compensation mechanisms for under-utilized thermal power plants, and enhanced flexibility in revising

capacity schedules.

In alignment therewith, it is proposed to incorporate the aforesaid provisions into the State Grid Code, along

with an expanded operating frequency band of 49.90 Hz to 50.05 Hz.

The installation of LVRT / HVRT protection systems in Wind and solar generators has been stipulated in

this regulation as mandated in the IEGC / CEA (Technical standards of connectivity to the Grid) Regulations as

amended from time to time.

The Central Electricity Authority (CEA) vide its letter dated 28.04.2025 advised all State Electricity Regulatory

Commissions (SERCs) and Joint Electricity Regulatory Commissions (JERCs) to forthwith review and amend their

respective State Grid Codes in consonance with the IEGC, 2023.

Further, the Ministry of Power, Government of India, vide its letter dated 24.12.2025, directed the SERCs to

align their State Grid Codes with the IEGC, 2023.Pursuant to the above directions and in exercise of the powers

conferred under Sections 61, 86(1)(e), and other enabling provisions of the Electricity Act, 2003, the Commission

hereby repeals the Tamil Nadu Electricity Grid Code, 2005, and notifies the Tamil Nadu Electricity Grid Code,

2026 (hereinafter referred to as “the Grid Code”) to ensure efficient supervision, grid control, and operation of

the intra-State power system. 

The Grid Code incorporates the provisions of the IEGC, 2023, subject to the following minor deviations

tailored to State-specific requirements:

1.

Revisions to Declared Capacity and schedules shall take effect from the 6th time block, as against the

7th or 8th time block stipulated in the IEGC, 2023;

2.

In the event of bottlenecks in power evacuation arising from outages, failures, or limitations in the

transmission system or other constraints and in the interest of better system operation by SLDC, revisions to

dispatch and drawal schedules shall take effect from the next time block, as against the 7th or 8th time block

under the IEGC, 2023, to optimize system operation and facilitate more integration of renewable energy into the

grid;

3.

The definition of the term “Hot Start” stands modified in accordance with the CEA (Technical Standards

for Construction of Electrical Plants and Electric Lines) Regulations, 2022, for enhanced clarity;

4.

The definition of the term “Drawee Entity” has been incorporated into the Grid Code for greater precision;

5.

Voltage operating limits for 220 kV and 110 kV systems shall follow Tamil Nadu-specific bands

(e.g., ±10% for 220 kV), as against IEGC uniform limits, to accommodate regional transmission constraints and

high renewable energy penetration in southern districts; and

6.

Renewable energy generators shall submit day-ahead forecasts with ±15% tolerance (extendable to ±20%

during monsoons), diverging from IEGC’s ±12% band, to better reflect Tamil Nadu’s variable solar/wind profile and

TNERC RE integration mandates.

Accordingly, this Grid Code is framed to give effect to the Government of India’s policy of “One Nation,

One Grid”, with a view to enable integrated, coordinated and efficient operation of the power system, to ensure

grid security, system reliability, operational discipline and system stability and to provide safe, secure and reliable

operation of the State Grid in conformity with national grid operation principles, including all allied operational,

protection and safety aspects.

(By Order of the Commission)

Chennai-600 032,

S. JOHN SUNDARARAJ,

17th February 2026.

Secretary (in-charge),

Tamil Nadu Electricity Regulatory Commission.