THE TELANGANA GAZETTE

PART-II EXTRAORDINARY

PUBLISHED BY AUTHORITY

No. 32 ]

HYDERABAD, MONDAY, MARCH 5, 2018.

NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.,

–––x–––

HYDERABAD METROPOLITAN DEVELOPMENT AUTHORITY

DRAFT VARIATION TO THE HMDA FOR CHANGE OF LAND USE FROM PARTLY CONSERVATION

USE ZONE & PARTLY BUFFER USE ZONE TO MANUFACTURING USE ZONE IN RAMPALLY

(VILLAGE), KEESARA (M), MEDCHAL DISTRICT.

Lr.No.000760/MP1/Plg-3/TS-iPASS/HMDA/2017.- The following Draft Variation to the Land Use

envisaged in the Notified Master Plan Ershtwhile HUDA-2021, vide G.O.Ms.No. 288, MA, dt: 03.04.2008,

which is proposed in exercise of the powers conferred by sub-section (1) of Section 15 of Hyderabad Metropolitan

Development Act, 2008 (Act No. 8 of 2008).

DRAFT VARIATION

The site in Sy.No. 274/P situated at Rampally (Village), Keesara (Mandal), Medchal District to an extent

of Ac. 2-00 Gts or 8093.71 Sq.mtrs. which is presently earmarked for Partly Conservation use zone & partly

Buffer use zone area in the Notified Master Plan Erstwhile HUDA-2021, vide G.O.Ms.No. 288, MA, dated

03.04.2008, is now proposed to be designated as Manufacturing use zone for setting up unit for solar panels under

‘White’ category with the following conditions:

a)

The applicant shall pay the balance conversion charges and publication charges to HMDA as per rules

in force before issue of final orders.

b)

The applicant shall comply with the conditions laid down in the G.O.Ms.No.168 dt: 07.04.2012

and G.O.Ms.No. 33 MA, dt: 24.01.2013.

c)

The applicant shall obtain prior permission from HMDA before undertaking any development on

the site under reference.

d)

The applicant is whole responsible if any discrepancy occurs in the ownership aspects & ULC aspects

& if any litigations occurs, the change of land use orders will be withdrawn without any notice.

e)

The applicant should submit NALA clearance Certificate obtained from RDO/DRO concerned under

APAL (Conversion of Non-Agricultural purpose Act 2006) before issue of final orders.

R.N.I.No.TELMUL/2016/73158.

[Price: `. 5-00.

HSE No. 1051/2017-19.

[ 1 ]

G - 883.

2

TELANGANA GAZETTE EXTRAORDINARY

[Part-II

f)

The applicant shall allowed to take up the constructions in accordance with the rules and regulations

as per G.O.Ms.No. 168 MA, dt: 07.04.2012, with in the leftover land of Ac.1.10 Gts after leaving the

Ac.00.30. Gts of buffer strip.

g)

The applicant shall form the 40’-0” wide BT road before release of plans from HMDA.

h)

The applicant has to maintain buffer area of Act 00.30 Gts as per the NOC issued by the Distrtict

Collector, Medchal-Malkajgiri District, vide Lr.No. D2/3299/2017, dt: 16.12.2017.

i)

The applicant has to follow the conditions imposed in the NOC issued by the Irrigation Department and

Revenue Department and as per G.O.Ms.No.168 MA, dt: 07.04.2012.

j)

The applicant shall not take any kind of construction in the buffer strip as per the NOC issued by the

District Collector, Medchal-Malkajgiri District, and also shall not allowed any kind of sewerage or

effluents or garbage into the tank.

k)

CLU shall not be used as proof of any title of the land.

l)

The applicant has to fulfill any other conditions as may be imposed by the Competent Authority.

m) The Change of land use does not bar any public agency including HMDA/Local Authority to acquire

land for any public purpose as per law.

Further it is submitted that the schedule of Boundaries are as below.

SCHEDULE OF BOUNDARIES

North

:

FTL boundary of Rampally Cheruvu is Sy.No.389/1 of Rampally (V).

South

:

Sy.No. 274(P) of Rampally (V).

East

:

Existing 12.00Mtrs wide kacha road in Sy.No.274(P) of Rampally (V).

West

:

Sy.No.273 of Rampally (V).

Printed and Published by the Commissioner of Printing, Govt. of Telangana, at Govt. Central Press, Chanchalguda, Hyderabad.`

(Sd/-),

Hyderabad,

For Metropolitan Commissioner,

23-02-2018.

HMDA.

-----x-----