TELANGANA STATE ELECTRICITY REGULATORY COMMISSION
HYDERABAD
No. TSERC/ 2 /2018
Dated 30.04.2018
Regulation No. 2 of 2018
TSERC RENEWABLE POWER PURCHASE OBLIGATION (Compliance by
purchase of Renewable Energy / Renewable Energy Certificates)
REGULATIONS, 2018
Section 86 (1) (e) of the Electricity Act, 2003 provides for promotion of
renewable sources of energy including cogeneration by providing suitable
measures for connecting with the grid and sale of electricity to any person,
as also specify the percentage of total consumption to be purchased in the
area of distribution licensees.
PUBLIC WORKS NOTIFICATIONS
2
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
In order to achieve this objective, the erstwhile Andhra Pradesh
Electricity Regulatory Commission had issued a regulation setting forth the
target and other requirements in compliance of the above provisions vide
the regulation being the Andhra Pradesh Electricity Regulatory Commission
(Renewable Power Purchase Obligation (Compliance by purchase of
Renewable Energy / Renewable Energy Certificates) Regulations, 2012
(Regulation 1 of 2012) which was amended from time to time.
Subsequent to the formation of the State of Telangana, this
Commission was established and it had adopted all the regulations, orders
etc. vide Regulation No. 1 of 2014 including the above mentioned
regulation. However, during the course of time, certain changes have
takenplace on the policy front from the Government of India as well as the
State Government. Also the above said regulation was subsisting for the
period of five (5) years which ended on 31.03.2017. Therefore, framing of
fresh regulation is necessitated to take further steps in the matter of
providing mechanism as required under section 86 (1) (e) of the Act, 2003.
In this regard, it may be relevant to notice the relevant provisions of
the National Tariff Policy, 2016 as notified by the Government of India
exercising powers under section 3 of the Act, 2003.
´ 3XUVXDQW WR SURYLVLRQV RI VHFWLRQ H RI WKH $FW WKH
Appropriate Commission shall fix a minimum percentage of the total
consumption of electricity in the area of a distribution licensee for
purchase of energy from renewable energy sources, taking into
account availability of such resources and its impact on retail tariffs.
Cost of purchase of renewable energy shall be taken into account
while determining tariff by SERCs. Long term growth trajectory of
Renewable Purchase Obligations (RPOs) will be prescribed by the
Ministry of Power in consultation with MNRE.
Provided that cogeneration from sources other than renewable sources
shall not be excluded from the applicability of RPOs.
(i) Within the percentage so made applicable, to start with, the SERCs
shall also reserve a minimum percentage for purchase of solar energy
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
3
from the date of notification of this policy which shall be such that it
reaches 8% of total consumption of energy, excluding Hydro Power, by
March 2022 or as notified by the Central Government from time to
time.
(ii) Distribution Licensee(s) shall compulsorily procure 100% power
produced from all the Waste-to-Energy plants in the State, in the ratio
of their procurement of power from all sources including their own, at
the tariff determined by the Appropriate Commission under Section 62
of the Act.
(iii) It is desirable that purchase of energy from renewable sources of
energy takes place more or less in the same proportion in different
States. To achieve this objective in the current scenario of large
availability of such resources only in certain parts of the country, an
appropriate mechanism such as Renewable Energy Certificate (REC)
would need to be promoted. Through such a mechanism, the
renewable energy based generation companies can sell the electricity
to local distribution licensee at the rates for conventional power and
can recover the balance cost by selling certificates to other
distribution companies and obligated entities enabling the latter to
meet
their
renewable
power
purchase
obligations.
The
REC
mechanism should also have a solar specific REC.
(iv) Appropriate Commission may also provide for a suitable regulatory
framework for encouraging such other emerging renewable energy
technologies by prescribing separate technology based REC multiplier
(i.e. granting higher or lower number of RECs to such emerging
technologies for the same level of generation). Similarly, considering
the change in prices of renewable energy technologies with passage of
time, the Appropriate Commission may prescribe vintage based REC
multiplier (i.e. granting higher or lower number of RECs for the same
level of generation based on year of commissioning of plant).µ
Accordingly, the Commission had initiated the process of making
regulation for the purpose by placing the draft regulation on the website of
4
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
the Commission calling for comments, objections and suggestions on
17.01.2018. The last date for submission of comments, objections and
suggestions was fixed as 09.02.2018.
Further, on receipt of comments, objections and suggestions, a public
hearing was held on 28.03.2018. The Commission had considered all the
comments, objections and suggestions thoroughly and finalized the
regulation. One of the core issues is regarding the percentages to be fixed for
solar based renewable energy and non-solar based renewable energy. It has
been noticed by the Commission in the filing for tariff proposals of the
licensees that there are variations in the capacity drawn from the solar
generation than that of non-solar generation.
Some of the stakeholders submitted that bunching of the total
capacity of the renewable energy to be procured would result in haphazard
procurement of renewable sources of energy and also result in procurement
of one type of renewable energy leaving others. If the total percentage of
solar and non-solar renewable energy is bunched together, it may result in
the licensees opting for procuring only solar generation and leave other
sources. Therefore, the Commission has factored in this condition that a
minimum of non-solar capacity is also procured by the licensees.
In exercise of powers conferred under Sections 61, 66, 86 (1) (e) and 181
of the Electricity Act, 2003 and all other powers enabling it in this
behalf, the Telangana Electricity Regulatory Commission hereby makes the
following regulation for prescribing the obligation for purchase of Renewable
Power and
its
compliance
by
purchase
of Renewable
Energy /
Renewable Energy Certificates.
1.
Short Title and Commencement.
1.1. This Regulation may be called the TSERC Renewable Power Purchase
Obligation (Compliance by Purchase of Renewable Energy / Renewable
Energy Certificates) Regulations, 2018.
1.2. This Regulation shall come into force with effect from the date of its
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
5
publication in the Telangana State Gazette.
1.3. This Regulation shall apply throughout the state of Telangana.
1.4. This Regulation shall be construed harmoniously with the provisions of
the Act, Rules and other Regulations of this Commission as amended
and in force from time to time. In case of any conflict or inconsistency
in this Regulation with the provisions of the Act, Rules and other
Regulations of this Commission, the latter shall prevail.
1.5. The Andhra Pradesh General clauses Act shall apply to interpretation
of this regulations.
2.
Definitions and interpretation.
2.1. ´Act, 2003µ means the Electricity Act, 2003 as amended from time to
time.
´Captive UserµPHDQVWKHSHUVRQ RUPHPEHUZLWKLQWKHPHDQLQJRI
section 2 (8) of the Act, 2003 being the end user of the electricity
generated in captive generating plant primarily for his own use
and the term ´captive useµ shall be construed accordingly.
2.3. ´&HQWUDO $JHQF\µ means the agency operating the National Load
Dispatch Centre (NLDC) or such other agency as the Central
Commission may designate from time to time;
2.4. ´&HQWUDO &RPPLVVLRQµ means the Central Electricity Regulatory
Commission referred to in sub-section (1) of section 76 of the Act,
2003;
;
2.5. ´Certificateµ means the Renewable Energy Certificate (REC) Issued
by the Central Agency in accordance with the procedures prescribed
by it and under the provisions specified in the Central Electricity
Regulatory Commission (Terms and Conditions for recognition and
Issue of Renewable Energy Certificate for Renewable Energy Generation
) Regulations, 2010 [CERC Regulation, 2010], as amended from time to
time;
2.6. ´&RPPLssLRQµ means the Telangana State Electricity Regulatory
Commission as referred to in sub-section (1) of section 82 of the Act,
2003;
)
6
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
2.7. ´)ORRU 3ULFHµ means the minimum price as determined by the CERC
Regulation, 2010, as amended from time to time, at and above which
the certificate can be dealt in Power Exchange.
2.8. ´Forbearance 3ULFHµ means the ceiling price as determined by the
Central Commission in accordance with the CERC Regulation, 2010, as
amended from time to time, within which only the Certificate can be
dealt in Power Exchange;
2.9. ´M15(µ means the Ministry of New and Renewable Energy;
2.10. ´Obligated Entityµis an entity that is mandated to fulfil renewable
purchase obligation under this Regulation subject to fulfilment of
conditions outlined under clause 3 hereof and for the purposes of
this Regulation shall be the following;
(i) Distribution Licensee
(ii) Captive user - Any consumer who owns a grid
connected Captive Generating Plant based on conventional
fossil fuel with installed capacity of 1 MW and above, or such
other capacity as may be stipulated by the Commission from
time to time, and consumes electricity generated from such
plant for his own use.
(iii) Open Access Consumer in the State ²
Any person having a contracted demand of 1 MW and above
and consumes electricity procured from conventional fossil fuel
based generation through open access.
2.11. ´Open Access Consumerµ means a consumer availing open access
under sub- section (2) of Section 42 of the Act, 2003;
2.12.´3RROHGCost of Power 3XUFKDVHµ means the weighted average pooled
price at which the distribution licensee has purchased electricity in
the previous year from all the long-term energy suppliers excluding
the purchases based on liquid fuel.
Provided that the purchases from traders, short-term purchases and
purchases from renewable sources shall not be taken into account
2.13. ´3RZHU (xFKDQJHµ means any exchange operating as the power
while determining Pooled Cost of Power Purchase;
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
7
2.15. ´RPPOµ means Renewable Power Purchase Obligation prescribed
under clause (3) of this Regulation;
2.16. ´RESCOµ means Rural Electricity Supply Co-operative Society.
2.17. ´SMALL HYDELµ means Hydro Power projects with a station capacity
up to and including 25 MW.
2.18. ´State Agencyµ means the State Load Despatch Centre of the State
of Telangana as defined under section 2 (66) of the Act, 2003 or the
agency so designated by the Commission under Clause (6.6) of this
Regulation to act as the agency for accreditation and recommending
the renewable energy projects for registration and to undertake
functions under this regulation;
2.19. ´Yearµ means a Financial Year;
2.20. Words and expressions used and not defined in the Regulations but
defined in the Act and Reform Act shall have the meanings assigned to
them in the Act or Reform Act. Expressions used herein but not
specifically defined in the Regulations or in the Act but defined under
any law passed by a competent legislature and applicable to the
electricity industry in the state shall have the meaning assigned to
them in such law. Subject to the above, expressions used herein but
not specifically defined in these Regulations or in the Act or any law
passed by a competent legislature shall have the meaning as is
generally assigned in the electricity industry.
2.21. In the interpretation of these Regulations, unless the context
otherwise requires:
2.14. “Renewable Energy Sources (or RES)” means renewable Sources such
as Co-generation from renewable sources, Small Hydel, Municipal Waste,
Industrial Waste, Biomass, Wind, Solar including its integration with combined
cycle, bio-fuel co-generation, Geo-thermal, Tidal and such other sources as
recognized or approved by MNRE;
exchange for electricity in terms of the orders issued by the Central
Commission or recognised by the Commission.
8
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
a) words in the singular or plural term, as the case may be, shall also
be deemed to include the plural or the singular term, respectively;
b) references KHUHLQ WR WKH ¶5HJXODWLRQ· VKDOO EH FRQVWUXHG DV D
reference to these Regulations as amended or modified by the
Commission from time to time in accordance with the applicable laws
in force.
c) the headings are inserted for convenience and may not be taken
into account for the purpose of interpretation of these Regulations.
d) reference to the statutes, regulations or guidelines shall be
construed as including all provisions consolidating, amending or
replacing such statutes, regulations or guidelines, as the case may be,
referred to.
3. Renewable Power Purchase Obligation (RPPO)
3.1.
Every Obligated Entity shall purchase from Renewable Energy
Sources a minimum quantity (in kWh) of electricity expressed as a
percentage of its total consumption of energy, during FY 2018-19 to
FY 2021-22 as specified in this table below
Year / RPPO
2018-19
2019-20
2020-21
2021-22
Solar
5.33
5.77
6.21
7.10
Non-solar
0.67
0.73
0.79
0.90
TOTAL
6.00
6.50
7.00
8.00
Provided further that the obligation will be on total
consumption of electricity by an Obligated Entity excluding
consumption met from hydro sources of power other small-hydel
sources of power.
3.2.
Roof-top Solar PV System.
3.2.1. The quantum of electricity generated by the consumer from the Roof-
top Solar PV System under the net metering arrangements shall, if
such consumer is not an Obligated Entity, qualify towards meeting
the
3.2.2. The Distribution Licensee shall install, at its own cost and with the
Solar RPPO of the Distribution Licensee.
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
9
G - 77/2.
3.6.
y
3.5. The purchase of renewable power by the Distribution Licensee,
from other Distribution Licensees in the State of Telangana shall also
be taken into account for computing the fulfilment of RPPO by such
a Licensee.
The purchase of REC issued under the CERC Regulation, 2010, as
amended from time to time, shall also be treated as fulfilment of the
RPPO prescribed herein.
3.7. In the event of the Obligated Entity, fulfilling the RPPO through
self-retention of REC as allowed by the CERC Regulation, 2010, as
amended from time to time, the application for self-retention shall be
consent of the consumer, a solar generation meter conforming to the
applicable CEA Regulations at an appropriate location to measure
the energy generated from the Roof-top Solar PV System if it
desires that such energy be counted towards meeting its RPPO.
The solar generation meter shall be maintained by the Distribution
Licensee at its cost.
3.2.3. The purchases made from solar roof-top projects (gross metering), the
unutilised banked energy deemed to have been purchased by the
Distribution Licensees from renewable energy projects under open
access regulations, purchases made at mutually agreed prices and all
such other transactions for which the generator(s) does not claim
RECs shall also be treated as fulfilment of the RPPO prescribed
herein;
3.3. The Distribution Licensees shall purchase power from renewable
energy sources at the tariff determined by the Commission under
Section 62 of the Act, 2003 or at tariffs discovered through
process of bidding u/s 63 of the Act, 2003 directly or
transparent
through traders and adopted by the Commission.
g
p
y
3.4.
Captive user means a power plant set up by any person to generate
electricity primarily for his own use and includes a power plant set
up by any co-operative society or association of persons for
or association.
generating electricity primarily for use of members of such c
co-operative society
10
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
3.10. 'LVWULEXWLRQ /LFHQVHH·V RPPO shall include RESCO for the
purpose of this Regulation.
3.11. The power from renewable energy sources being purchased by
the
obligated
entity(s)
under
the
existing
power
purchase
agreements shall continue till the validity of the existing agreements,
even if the total purchases under such agreements exceed the
percentages specified hereinabove.
3.12. The Commission may, either on its own motion or on recommendation
of the State Agency or on receipt of an application from the obligated
entity(s) or eligible entity(S), revise for any year the percentage
targets given herein above or to carry forward to next year as
appropriately deemed fit by the Commission.
4. Certificates under the Regulations of the Central Commission.
4.1. The procurement, by the obligated entity(s) of RECs issued under the
CERC Regulation, 2010, as amended from time to time, shall be
subject to such directions as the Commission may issue from time to
time.
4.2. The
RECs purchased by the obligated entity from the Power
Exchange, or the purchase certificate(s) issued by State Agency
in
case of self-retention of RECs, shall be deposited by the
obligated entity with the State Agency.
renewable energy generating stations bundled with coal / lignite
based
generation shall be considered as fulfilment of RPPO;
thermal
towards fulfilment of RPPO of that financial year only; And the
Obligated Entity shall make an application accordingly.
3.8.
Distribution Licensees shall compulsorily procure 100% power
produced from all the Waste-to-Energy plants in the State.
3.9.
The renewable power procured by the Obligated Entity from
Notwithstanding
the
above,
the
State
Agency
can
also
independently verify the RECs purchased by the obligated entity from
Power Exchange, through Renewable Energy Certificate Registry of
website, and consider the same towards fulfilment of their RPPO.
India
4.3.
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
11
5.1.3. Despite availability of power from renewable energy sources and
certificates, if the Distribution Licensee fails to fulfil its commitment
towards minimum purchase from renewable energy sources, it
shall be liable to deposit amount into a separate fund as provided in
clause 8.
5.2.
Captive User and Open Access Consumer.
5.2.1. Every captive user and open access consumer shall have to submit
in advance necessary details regarding total estimated consumption of
electricity and the quantum of power proposed to be purchased from
renewable energy sources for fulfilling its RPPO. The details shall be
submitted to the State Agency on a yearly basis on or before 15th
March under intimation to the Commission.
5.2.2. The captive user and open access consumer shall submit
quarterly status to the State Agency in respect of compliance of
RPPO in accordance with the procedure as referred to in Clause
6.4.
5.2.3. The captive user and open access consumer shall submit under
affidavit a detailed statement in respect of compliance of RPPO to the
State Agency at the end of each year under intimation to the
Commission.
5.2.4. Captive user and open access consumer shall purchase power
5.
Obligated Entity
5.1.
Distribution Licensee.
5.1.1. Every Distribution Licensee shall, on a yearly basis on or before 15th
March, submit to the State Agency under intimation to the
Commission, the details of the estimated quantum of purchase from
renewable energy sources for the ensuing year. The estimated
quantum of such purchase shall be in accordance with clause 3.
5.1.2. The Distribution Licensee shall also submit a detailed statement
to the State Agency under intimation to the Commission at the end
each year in respect of compliance of RPPO and also place it on
of
website of Distribution Licensee.
the
12
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
from renewable energy sources in accordance with clause 3. They
may also fulfil their RPPO through purchase of RECs. If the captive
user or open access consumer is unable to fulfil the minimum
purchase criteria, then it shall deposit in to a separate fund the
amount as per clause 8 of this regulation.
6. State Agency.
6.1. The State Agency shall function in accordance with the directions
issued by the Commission and shall act in accordance with the
procedures / rules laid down by Central Agency for discharge of its
functions under the CERC Regulation, 2010, as amended from time to
time.
6.2.
The State Agency shall devise an appropriate protocol for collection
6.3.1. The summary statement of RE procurement and RPPO compliance
by each obligated entity shall be published by the State Agency on
a cumulative basis every month on its website.
6.3.2. The summary statement shall cover RE procurement by each
obligated entity comprising renewable energy procurement under
preferential tariff route or other modality approved by the State
Commission with regard to RPPO as well as renewable energy
procurement through REC mechanism.
6.4.1. The State Agency shall submit quarterly status to the Commission
in respect of compliance of RPPO by the obligated entity(s) in the
format as approved by the Commission and may initiate appropriate
proceedings before the Commission if required for compliance of the
RPPO.
6.4.2. For this purpose, the State Agency shall develop formats for
submission of quarterly progress report in respect of compliance of
RPPO by the obligated entity(s) and get them approved by the
Commission within 90 days of the notification of this regulation.
generating companies, obligated entity, etc., and compute the
RPPO target by obligated entity.
compliance of
of information from various sources such as renewable energy
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
13
6.5.
Remuneration and charges:
The Commission may from time to time based on the proposal in
this regard from the State Agency fix the remuneration and charges
payable to the State Agency for discharge of its functions under
this regulations. The fees and charges paid by the obligated entities
and the renewable energy generating companies shall be collected by
the State Agency and utilised for its operations in respect of
furthering objects of this regulation.
Explanation:- The words for its operation would include both
technical and administrative action for carrying out the purpose of
this regulation.
7.2. For the purpose of this clause (7), determination of pooled cost of
power purchase shall be as follows:
7.2.1. DlSCOMs shall submit a petition for computation of pooled cost of
power purchase to the Commission by 30th April of that year. The
Commission shall issue an order relating to pooled cost of power
purchase for the particular year as expeditiously as possible after it
has been listed for hearing atleast once.
6.6.
If the Commission is satisfied that the State Agency is not able to discharge
its functions satisfactorily, it may by general or special order, and by recording
reasons in writing, designate any other agency to function as State Agency
as it considers appropriate.
6.7.
In the event of the State Agency functions have been withdrawn from the
existing agency and notified the new agency, the entire subsisting apparatus
both technical and administrative including finances held for this purpose
by the earlier agency shall be transferred to the new agency and the decision
in this regard of the Commission shall be final.
7.
Eligibility and Registration for Certificates.
7.1
The eligibility and registration of certificates shall be governed by the CERC
Regulation, 2010, dated 14.01.2010 as amended from time to time.
14
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
7.2.2. Till the issue of such order the pooled cost of power purchase of the
previous year shall continue to operate as provisional pooled cost of
power purchase.
7.2.3. After the issue of order for the pooled cost of power purchase by the
Commission, the difference between the provisional pooled cost of
power purchase and the final pooled cost of power purchase shall be
paid / recovered as the case may be in equal instalments in the
subsequent bills for the next two months or as decided by the
Commission in the order while determining the pooled cost of power
purchase for that year.
7.2.4. A draft PPA containing the provisions reflecting the payment of
pooled cost of power purchase shall be drafted and submitted by the
licensees to the Commission for approval.
7.2.5. Where there is a general PPA and such PPA involves or extends the
situation of payment of pooled cost of power purchase, then the
licensees shall endeavour to prepare a draft amendment to such
agreement on a generic basis and submit the same for approval to
the Commission.
7.2.6. After thorough examination and after following the due process
under the Conduct of Business Regulation, 2015 as amended from
time to time, the Commission may accord approval to the draft PPA
or amendments to the subsisting PPA(s).
7.2.7. Each such PPA or amendment PPA shall have to be submitted to the
Commission for consent even if there is no deviation from model PPA
approved by the Commission.
Consequences of default.
8.
8.1. If the obligated entity does not fulfil the RPPO as provided in Clause
(3) of this regulation during any year, the Commission may direct the
obligated entity to deposit into a separate fund, to be created and
maintained by the State Agency, such amount on the basis of the
shortfall in units of the RPPO and the Forbearance Price decided by
the Central Commission;
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
15
Provided that the fund so created shall be utilised in the manner
as may be specified by the Commission either through general or
special order.
8.2. Where any obligated entity fails to comply with the obligation
prescribed in clause (3) of this regulation, it shall, in addition to the
compliance of the directions under clause 8.1 above, be liable for
penalty as may be decided by the Commission under section 142
of the Act, 2003.
8.3. For this purpose, the Commission may initiate proceedings either suo
moto or on a representation made by any of the affected parties
including but not limited to the State Agency.
8.4. Such proceedings shall be in accordance with the Conduct of
Business Regulation, 2015 of the Commission.
9. Information System.
9.1. The State Agency shall post the following documents / information
on its website in a separate web-page titled ´$FFUHGLWDWLRQ of RE
3URMHFWVµ
a) This regulation;
b ) Procedure as mentioned in this regulation;
c) List of applications along with necessary details received by the
State Agency for accreditation;
d) List of accreditation granted, indicating-
(i) Name of RE generating company / station;
(ii) Point of injection;
(iii) Capacity (MW) for which accreditation has been granted.
e) List of applications where approval for accreditation has not
been granted along with reasons thereof;
10. Saving.
10.1. Anything done or any action taken or purported to have been done
in pursuance of the provisions of the earlier APERC Renewable
Power Purchase Obligation (RPPO) Regulation 1 of 2012 and its
amendments shall be in so far as it is not inconsistent with the
16
TELANGANA GAZETTE EXTRAORDINARY
[Part-II
10.2. Any rights and liabilities arising out of the earlier regulation shall be
settled within the applicable provisions as may be appropriately
relevant.
11. Power to remove difficulties.
The Commission, suo-moto or on an application from any person
generating electricity from renewable sources or an entity mandated
under clause (e) of sub-section (1) of section 86 of the Act, 2003 to
fulfil the RPPO may review, add, amend or alter this regulation and
pass appropriate orders to remove any difficulty in exercising the
provisions of this regulation.
12. Miscellaneous.
12.1. Nothing in this regulation shall be deemed to limit or otherwise affect
the inherent power of the Commission to make such orders as
may be necessary to meet the ends of justice or to prevent abuse of
process of the Commission.
12.2. Nothing in this regulation shall bar the Commission from adopting a
procedure which is at variance with any of the provisions of this
regulation. If the Commission, in view of the special circumstances
of a matter or class of matters and for reasons to be recorded in
writing, deems it necessary or expedient for so doing with such a
matter or class of matters.
12.3. Nothing in this Regulations shall, expressly or impliedly, bar the
Commission to deal with any matter or exercise any power under the
Act, 2003 or Reform Act, 1998 for which no provisions have been
framed, and the Commission may deal with such matters, powers
and functions in a manner it deems fit in appropriate case.
13.
Regulations to be in addition to and not in derogation of other
laws.
The clauses in this Regulation are in addition to and not in
provisions of this Regulation, be deemed to have been done or taken
corresponding provisions of this Regulation.
under the
May 2, 2018]
TELANGANA GAZETTE EXTRAORDINARY
17
UMAKANTA PANDA,
Hyderabad,
Commission Secretary (A/C),
30-04-2018.
Telangana State Electricity
Regulatory Commission.
––––x––––
Printed and Published by the Commissioner of Printing, Govt. of Telangana, at Govt. Central Press, Chanchalguda, Hyderabad.`
14.
Other provisions.
14.1. The Telangana State Electricity Regulatory Commission (adoption of
previously subsisting regulations, decisions, directions or orders,
licenses and practice directions) Regulation, 2014 (Regulation No. 1
of 2014) to the extent relating to:
The Andhra Pradesh Electricity Regulatory Commission (Renewable
Power Purchase Obligation (Compliance by purchase of Renewable
Energy
/
Renewable
Energy
Certificates)
Regulations,
2012
(Regulation 1 of 2012) as amended from time to time, stands
repealed on and from the date this regulation is published in the
Official Gazette for the State of Telangana to the extent relating to the
matters covered in this Regulation out of Regulation No. 1 of 2014.
14.2. Anything done or any action taken or purported to have been done or
taken including any rule, notification, inspection, order or notice
made or issued or any appointment, confirmation or declaration
made or any licence, permission, authorization or exemption granted
or any document or instrument executed or any direction given
under the repealed regulation shall, in so far as it is not inconsistent
with the provisions of this regulation, be deemed to have been done
or taken under the corresponding provisions of this regulation shall
be deemed to be not invalid by virtue of such repeal.
(BY ORDER OF THE COMMISSION)
derogation of any provision made under the Act, 2003,
rules or regulations framed thereunder or under any other laws.