THE TELANGANA GAZETTE

PART - I EXTRAORDINARY

PUBLISHED BY AUTHORITY

No. 17 ]

HYDERABAD, FRIDAY, JANUARY 13, 2023.

NOTIFICATIONS BY GOVERNMENT

–––x–––

MUNICIPAL ADMINISTRATION AND URBAN DEVELOPMENT DEPARTMENT

(PLG .I (2))

R.N.I. No. TELMUL/ 2016 / 73158.

[Price: `.

`.`.

`.

`. 5-00.

HSE No. 1051/2023-2025.

G-666.

THE TELANGANA STATE LAND ACQUISITION (CONSENT AWARD, VOLUNTARY ACQUISITION AND

LUMP-SUM PAYMENT TOWARDS REHABILITATION AND RESETTLEMENT) RULES, 2017 -

NOTIFICATIONS SUBMITTED IN RESPECT OF HYDERABAD DISTRICT.

[Memo No.16411/Plg.I(2)/2022, Municipal Administration &Urban Development (PLG .I(2)),

22nd December, 2022.]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Manikeshwari Nagar to Indira Nagar via

18

1200.00

RUB across Railway line

[This has got the approval of Special Chief Secretary, MA & UD Department]

[1]

2

TELANGANA GAZETTE EXTRAORDINARY

[Part-I

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Construction of Flyover from ESSAR petrol pump

59

7083.39

to Nanal Nagar Junction via Andhra Flour mill

[This has got the approval of Special Chief Secretary, MA & UD Department]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Tolichowki ‘X’ Road to Seven Tombs ‘T’ Junction

90

3699.41

(Circle-13)

[This has got the approval of Special Chief Secretary, MA & UD Department]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

MLA Colony road, Road No. 12 Jubilee Hills to

163

9984.163

Hakeempet Junction upto Salar Bridge.

[This has got the approval of Special Chief Secretary, MA & UD Department]

January 13, 2023 ]

TELANGANA GAZETTE EXTRAORDINARY

3

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Banjara Darwaza to Fathe Darwaza

290

12177.08

[This has got the approval of Special Chief Secretary, MA & UD Department]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Girkapalli Junction (Mogal-Ka-Nala) to Puranapool

490

17695.85

[This has got the approval of Special Chief Secretary, MA & UD Department]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Tolichowki Jn to Jubilee Hills Road No. 82 via Salar

72

3494.69

Bridge and Paramount Hills (Circle-13)

[This has got the approval of Special Chief Secretary, MA & UD Department]

4

TELANGANA GAZETTE EXTRAORDINARY

[Part-I

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt (following projects) from the application

of provisions of the Chapter-II and Chapter-III of the RFCTLARR Act. It is also certified that the all efforts have’

been made in finalizing the minimum extent of land required for the said project.

SPECIAL COLLECTOR LAND ACQUISITION (GHMC)

HYDERABAD DISTRICT

S.No

Project / Junction

No. of

Extent in

Properties

Sq. Yds

AFFECTED UNDER ROAD WIDENING

1

Junction Improvement Plan at YMCA Junction

19

1464.92

(Narayanguda)

[This has got the approval of Special Chief Secretary, MA & UD Department]

EXEMPTION OF LAND ACQUISITION FOR THE DEVELOPMENT OF MULTIPLE ACTIVITIES AT

KOMATI CHERUVU RECREATION ZONE TOURISM SPOT LIKE SHILPARAMAM FACILITIES

TO AN EXTENT OF AC. 30.09 GTs.

[Memo No.18572/Plg.I(2)/2022, Municipal Administration &Urban Development (PLG .I(2)),

4th January, 2023.]

FORM-A

(See Section 10A and Rule 4)

In accordance with the provisions contained in Sec 10(A) of the Right to Fair Compensation and Transparency

in Land Acquisition, Rehabilitation and Resettlement Act, 2013 in its application to the State of Telangana, the

Government have decided and accordingly hereby, in the public interest, exempt the land acquisition proposal for the

development of Multiple activities at Komati Cheruvu recreation zone tourism spot like shilparamam facilities to an

extent of Ac. 30.09 Gts. from the application of provisions of the Chapter-II and Chapter-III of the RFCTLARR

Act. It is also certified that the all efforts have’ been made in finalizing the minimum extent of land required for the

said project.

[This has got the approval of Special Chief Secretary, MA & UD Department]

Sd/-,

for Special Chief Secretary to Government.

–––x–––