1051

Panaji, 13th August, 2021 (Sravana 22, 1943)

SERIES I No. 20

Reg. No. RNP/GOA/32/2021-2023

RNI No. GOAENG/2002/6410

PUBLISHED BY AUTHORITY

GOVERNMENT OF GOA

Department of Information Technology

__

Notification

10(29)/DOIT/2021/LAND PREMIUM

EMC-TUEM/P.F.-I/710

The Electronics Manufacturing Cluster

Land Allotment Policy, 2021 as adopted by

the Government is hereby published for

information of the public.

This is issued with administrative approval

of Hon’ble Minister (IT) vide U.O. No. 657/F

dated 03-08-2021 and concurrence of Hon’ble

Chief Minister/Finance Minister vide U.O.

No. 2635/F dated 11-08-2021.

By order and in the name of the

Governor of Goa.

Ankita Anand, IAS, Director (IT) & ex officio

Joint Secretary.

Altinho, Panaji, 12th August, 2021.

________

Electronics Manufacturing Cluster

Land Allotment Policy, 2021

1. Preamble

1.1. Project Background.—

1.1.1. Department of Information &

Technology, Government of Goa (DoIT) has

Suggestions are welcomed on e-mail: dir–[email protected]

established

a

Greenfield

Electronics

Manufacturing Cluster (EMC) in Tuem village

of Pernem Taluka, Goa.

1.1.2. DoIT has received approval (Approval

doc No. 36(31)/2016-IPHW (Vol.II) dated

03-03-2017) under Greenfield Electronic

Manufacturing Clusters Scheme promoted by

Ministry of Electronics and Information

Technology

(MeitY),

Ministry

of

Communications & IT, Government of India

for setting up the first Greenfield electronic

manufacturing cluster in the State.

1.2. Project Site.—

1.2.1. Location: The project site identified

for development of the Greenfield EMC is

located at Tuem Village in Pernem Taluka,

admeasuring approx. 5,97,125 square meters

in Tuem Village in Pernem Taluka, Goa

bearing in Survey Numbers 81/0, 82/0, 84/0,

85/0, 98/0, 99/0, 100/0, 101/0, 102/0, 103/0

and 104/0.

1.2.2. The Project site is well connected by

National Highway (NH-17) and the existing

Tuem Industrial Cluster and the upcoming

new International Airport adds to its

advantage.

EXTRAORDINARY

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1052

1.3. EMC Components.—

The concept plan for the proposed Greenfield Electronic Manufacturing Cluster is detailed

as below:

Development Components

Processing Zone

• Industrial Plots (varying from approx. 1-5 acres each)

• Micro Industrial Plots (varying from approx. 300 square meters to 800 square

meters each)

Open Space

About 15% of the total area has been identified under open spaces and

parking

Common Facilities

• Entrance gate/security and truck bays

• Roads

• Storm Water drains and underground trenches for utility cables

• Street Lighting

• Common STP

• Common ETP for Micro Industrial Plots

• Wet waste treatment and composting

• Utilities zone

Non-Processing Zone

Reserved in the range of 6-8 % of the total developable area

• Administrative block

• Dispensary

• Crèche/Nursery

• Tot-lots

• Local shopping facility

• Bank/ATMs

• Restaurant

• Parking bays

• Scope for Budget Hotel

1. EMC Land Allotment Policy

2.1. Electronics Manufacturing Cluster Land Allotment Policy, 2021.—

2.1.1. For the purpose of allotment of land to set up a Greenfield Electronics Manufacturing

Cluster (EMC) at Tuem village of Pernem Taluka, Goa, the Government of Goa hereby notifies

the “Electronics Manufacturing Cluster Land Allotment Policy, 2021”.

2.1.2. The main objective of this Policy is to make provision for planned development of the

Greenfield EMC at Tuem and promotion of industries related to electronics and matters

appurtenant thereto including judicious allotment of land under the command area of Greenfield

Electronics Manufacturing Cluster at Tuem. List of industries/verticals that are proposed to be

promoted under the Greenfield EMC Scheme of MeitY are specified under SCHEDULE A appended

to this guidelines.

2.1.3. This Policy shall apply to allotment of plots within the Greenfield Electronic Manufacturing

Cluster at Tuem and shall come into force on such date as the State Government may specify by

notification in the Official Gazette and shall supersede all earlier Policies, if any in this regard.

2.1.4. In this Policy unless the context otherwise requires,—

a. “DoIT” shall mean the Department of Information & Technology, Government of Goa;

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1053

b. “Director, IT” shall mean the Director

of Department of Information Technology

(DoIT) and also includes the official having

additional charge or acting in the said post;

c. “EMC” shall mean the Greenfield

Electronic Manufacturing Cluster promoted

by the Department of Information &

Technology, Government of Goa (DoIT)

under the EMC scheme of the Government

of India (Ref: Approval doc No. 36(31)/2016-

IPHW (Vol.II) dated 03-03-2017) and such

other Electronics Manufacturing clusters as

the Government may notify in future;

d. “Chief Promoter” means the Chief

promoter of the Greenfield Electronics

Manufacturing Cluster at Tuem, Goa;

e. “SPV” shall mean the legal entity which

has been formulated by the Chief Promoter

of EMC by the name “Tuem Electronics City

Limited” in accordance with the approval

received for the Greenfield Electronics

Manufacturing Cluster at Tuem, Goa (Ref:

Approval doc No. 36(31)/2016-IPHW (Vol.II)

dated 03-03-2017);

f. Category of Plots: There are 15 Industrial

Plots ranging from 7,000 square meters to

38,900 square meters and 45 micro industrial

plots ranging from 300 square meters to 800

square meters under two categories of plot:

(i) Category 1: “Industrial Plots” means

the plotted units of land provided to the

applicants for the industrial use within the

Greenfield EMC at Tuem;

(ii) Category 2: “MIZ Plots” means Micro

Industrial Zone Plots provided to the

applicants for the micro industrial use/

Cluster units within the Greenfield EMC at

Tuem.

g. “Board of Directors” shall mean and

include the Board of Directors of the SPV

namely Tuem Electronics City Limited which

has been formulated for the purpose of this

Greenfield EMC at Tuem;

h. “Applicant” means and include the

following entities registered in India who

intend to set up an industry/manufacturing

units in the Greenfield EMC at Tuem, Goa:

i. Proprietorship Concern,

ii. Registered partnership firm,

iii. Private Limited Company,

iv. Limited liability partnership firm,

v. Public Limited Company,

vi. Government Company,

vii.

State/Central

Public

Sector

Undertaking,

viii. Co-operative Societies/Societies.

i. “Allottee” means an applicant who has

been allotted plot;

j. “State Government” means the

Government of Goa.

k. “Commercial Date of Operations” is

defined as the date on which all testing and

commissioning of equipment and first sales

invoice is generated.

l. “Large/Mega Enterprise” is where the

investment in Plant and Machinery or

Equipment exceeds fifty crore rupees or

turnover exceeds two hundred and fifty crore

rupees.

m. “Lease Period” the land shall be given

on long term lease basis for a term of 30 years

with an option of renewal for subsequent term

of 30 years commencing from the date of issue

of Allotment order. The extension of

subsequent term of 30 years to the lease period

can be allowed subject to the allottee

completing the project within 5 years.

2.2. Eligibility for Applicant.—

2.2.1. Applicants desirous of setting up an

industry in the Greenfield EMC at Tuem should

be operating or planning to operate in

Electronics System Design & Manufacturing

sector covered under the National Regulation

on Electronics and related notifications issued

by the Ministry of Electronics & Information

Technology (MeitY) and Ministry of

Communication & Information Technology,

Government of India.

2.2.2. List of verticals/Industries under

which applicant can submit application is as

per Schedule – A.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1054

2.3. Creation of Plots & Preparation of Site

Plans.—

2.3.1. The Chief Promoter/SPV shall ensure

that a detailed survey and measurement is

done and a site plan is prepared in accordance

with applicable Goa (Regulation of Land

Development and Building Construction) Act,

2008 and/or the Regulations made there under

or any other law in force from time to time,

with proper provision of land for open spaces,

roads, utilities etc. After this provisioning, the

balance available area shall be sub-divided/

earmarked as per Industrial plots (Micro

Industries, Medium Scale Industries & Larger

Scale Industries) and commercial plots.

2.3.2. The Chief Promoter/SPV/Board of

Directors reserves its right to modify the plans

of the Greenfield Electronics Manufacturing

Cluster at Tuem, Goa from time to time

including merging, sub-division, re-locating of

plots/open spaces etc. in accordance with the

applicable planning regulations, after taking

into account the difficulties relating to

topography of the land site, demand before

them, etc.

2.3.3. If any area, earmarked to a particular

category, remains vacant for a period of 2 years

from the date of publication of advertisement,

the Chief Promoter/SPV will have the

discretion to transfer such vacant areas to

another category, where there is a demand.

2.4 Amenities to be provided within

Greenfield EMC at Tuem.—

2.4.1. The Chief Promoter/SPV will offer

serviced plots to allottee within the Greenfield

EMC at Tuem, which will include motorable

road connection to the plot along with

connection for infrastructure services like

water, power, storm water drainage, STP

connection & ETP connection (for micro

industrial plots) till the plot boundary. The

Chief Promoter/SPV will also provide optic fibre

connectivity to each plot at a tap off point on

the plot boundary.

2.4.2. The allottee must give a written

confirmation, at least forty five (45) days’ prior

of commercial operation date, to the Chief

Promoter/SPV for activation of such

infrastructure and utility services. The Chief

Promoter/SPV will facilitate to provide water

and power connection to the allottee during

development of plot based on application made

by the Allottee. Charges as stipulated by the

Chief Promoter/SPV from time to time for such

trunk infrastructure shall be borne by the

allottee.

2.5. Procedure of Land Allotment.—

The procedure of land allotment shall apply

to all categories stipulated under clause 2.1.4

(f) above.

2.5.1. Release of Advertisement on national/

local newspapers:—

a. The Chief Promoter/SPV will release a

public advertisement in at least 3 local and

3 national newspapers and on the official

website of the Chief Promoter/SPV.

b. The advertisement shall provide details

on the area of the plot in sq. mt., price per

square meter of the land premium and other

related information and will remain in force

until all the plots within the EMC have been

allotted or earlier, as per the decision of the

Government.

2.5.2. Application for Allotment.—

a. Application for allotment of land in the

Greenfield Electronic Manufacturing Cluster

at Tuem shall be made in the prescribed

format to the Chief Promoter/SPV as

specified in the advertisement and the

allotment will remain in force until all the

plots within the EMC have been allotted or

earlier, as per the decision of the

Government.

b. The applicant shall furnish a Processing

Fee equivalent to 0.1% of the Land Premium

(non-refundable) along with Security

Deposit (interest free) equivalent to 10% of

the Land Premium (refundable) for the plot

area applied for. The Processing Fee is

subject to revision from time to time as per

discretion of the Chief Promoter/SPV, which

shall be intimated at the time of

advertisement. All payment shall be done

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1055

through “DD in favour of the Chief Promoter/

/SPV” or as defined in advertisement.

c. The applicant will have to submit the

following documents along with its

application as applicable:

i. Address Proof or Residence

Certificate of the applicant/promoter.

ii. Photocopy of the identity proof such

as PAN Card, Aadhaar Card, Driving

License, and Passport of the applicant in

case of individual proprietorship.

iii. PAN Card & GST Registration Details

of the Company/Firm/Partnership/LLP.

iv. Income Tax returns filed by the

assesse/assesses for the last three

financial years.

v. Registration Details of the Company/

Firm/Partnership/LLP etc.

vi. Copy of the Certificate of Registration

of Firm and Partnership Deed (As

applicable).

vii. Copy of Certificate of Incorporation,

Memorandum and Articles of Association

in case of Limited Companies and a copy

of resolution authorizing the applicant to

apply on behalf of the company (as

applicable).

viii. Audited Balance Sheet and Annual

Reports for last three financial years.

ix. Detailed Project Report/Business

Plan for the project with the application

in the format, as prescribed by the Chief

Promoter/SPV. Such Detailed Project

Report / Business Plan to include details

like layout plans of the proposed facility,

project cost estimates, debt: equity

provisions for the project and project

employment

data

with

relevant

supporting documents of man power

details (skilled, unskilled, technical) etc.

x. Payment Details furnished by the

bank with regards to Processing Fee

under clause 2.5.2.b.

xi. Other Documents as prescribed in

the advertisement issued on newspaper

and/or web portal.

d. Detailed Project Report:

DPR Components: Below is an indicative

checklist of the components that a DPR shall

contain. The application process mandates

the submission of DPR along with other

statutory documents. Below checklist and

the sample documents enclosed along

herewith are indicative only and not

exhaustive.

i. Company Profile and details of

existing business concerns: This section

shall elaborate on the existing company,

its products/services, strengths, market

position, annual turnover, years of

existence, etc. Statutory documents such

as Certificate of Incorporation and

Audited Annual Reports (of past 3

financial years)/IT returns/Net worth

certificates (as the case may be) shall be

submitted.

ii. Documentary evidence/proof to

showcase the experience of successfully

executing similar projects in past (if any):

Details of the existing business units (if

any), in terms of capacity/scale,

investment made, direct employment,

space utilization, etc. shall be provided.

In case of a new firm, justification based

on

the

past

experience

of

the

management shall be provided.

iii. Brief on the proposed project: This

section shall provide details on the project

for which land is sought. The project

details must provide information on the

type of products/services proposed,

process flows, brief on technologies

(without revealing proprietary details)

and any other information that is relevant

to impart an understanding of the

proposed activity.

iv. Market analysis/justification for

proposed project: This section shall

present a business case while elaborating

on the ‘target market identification’ and

‘demand-supply dynamics’.

v. Justification for the extent of land

required for the proposed project: This

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1056

section shall include the layout of the

proposed project (clearly highlighting the

area utilization) and detailed area break-

up for each of the components proposed

(including built-up areas, open areas,

roads etc.) under the project. For

reference purposes, a sample area break-

up and a sample layout is enclosed to this

checklist.

vi. Implementation Timeline for various

phases of the proposed project.

vii. Investment proposed in various

phases & Means of Finance.

viii. Proposed Employment to be

generated (Direct & Indirect) in various

phases: Break-up shall be provided of the

employment estimates, in terms of

managerial staff, engineering staff,

administrative, labour, etc. In case of

service oriented business setups,

organisation and staffing chart shall be

provided along with the number of

employees planned to be recruited at

various levels/hierarchy.

ix. Financial analysis to justify the

feasibility of the proposed project: This

section shall include the assumptions on

cost and revenues on a time line (yearly/

quarterly), projected Profit & Loss

Statement and cash flow statements along

with financial viability indicators like IRR,

DSR, etc.

e. Separate application for each industrial

unit shall be submitted.

f. The application duly filled along with

enclosures and the prescribed Processing

Fee and Security Deposit details must be

submitted to the Chief Promoter/SPV at its

registered office address as mentioned in the

advertisement.

g. The application form should be filled in

completely. Particulars regarding the

requirement of water and electric power

should be furnished as accurately as

possible.

h. Conditional applications shall not be

accepted and rejected outright.

2.5.3. Allotment Procedure for Plots within

Greenfield EMC at Tuem.—

Step 1: Registration of Application:

a. The Chief Promoter/SPV shall publish

details of the applications received and the

registration number on the official website

of the Chief Promoter/SPV and also on the

notice board of the Chief Promoter/SPV on

monthly basis.

b. Applicants

with

incomplete

information/applications will be notified and

may be granted a period of 07 working days

to submit all the relevant documents as

listed. After the expiry of the specified

period of 07 working days granted for the

incomplete applications, only the completed

applications would be considered for further

processing.

Step 2: Screening of Applications:

c. The Screening Committee has been

constituted by the State Government

consisting of the following officials :

i. Director, Department of Information

Technology, Government of Goa (Chief

Promoter);

ii. Managing Director, M/s Info Tech

Corporation of Goa;

iii. Director, PPP Cell, Finance

Department;

iv. Chief Engineer, M/s Info Tech

Corporation of Goa Ltd. (Member

Secretary);

v.

Dy.

Manager

(Accounts

&

Administration),

M/s

Info

Tech

Corporation of Goa Ltd.;

vi. Nominee of Goa Industrial

Development Corporation;

vii. Nominee of Goa Chamber of

Commerce and Industry;

viii. Nominee of Goa State Industries

Association.

d. The Screening Committee shall

screen the completed applications with an

objective to establish the genuineness of

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1057

the applicant, the viability of the project,

employment and revenue generation to

the State.

e. The Director (Information Technology)

shall be the Chairperson and the Chief

Engineer, M/s Info Tech Corporation of Goa

Ltd. shall be the Member Secretary of the

Committee. The first meeting of the

Screening Committee shall held after 21

days of release of the advertisement;

thereafter the meeting would be held at

least in every month or earlier as and when

the need arise, for considering the

applications received. The quorum of the

meeting shall be 4 members.

f. The Screening Committee shall screen

and scrutinize the applications and the

project report furnished from the applicants.

The Committee can consider the following

aspects while scrutinizing the applications

received:

i. Background of the promoter.

ii. Experience in the relevant sector for

which applied.

iii. Projected Investment.

iv. Financial strength to setup the

project.

v. Product(s) to be manufactured/

assembled/development or Service(s) to

be rendered.

vi. Green/White Category Industry.

vii. Project timelines and production

plan to be detailed.

viii.

Employment

generation

envisioned

especially

for

local

employment.

ix. Women entrepreneur.

x. Differently abled entrepreneur.

g. The applicant may be called for one-

to-one interaction, to demonstrate his

project and for providing any further details

to the satisfaction of the Committee.

h. Priority shall be given for expansion of

the existing unit within State of Goa.

i. The Screening Committee may

recommend to the Government

modification and sub-division/merging of

plots for increase or decrease of their

respective areas with the objective of

accommodating maximum number of

applicants. However, the Chief Promoter/

SPV shall have the right to recover the cost

of infrastructure incurred in case of merger

of plots.

j. The said Committee shall shortlist the

applicants for allotment along with the

minutes, evaluation sheet and reasons for

recommendations.

Step 3: Finalization of Allotment:

k. Applications accepted and reco-

mmended by the Screening Committee shall

be placed before the Government for its

consideration and approval.

l. Applications

approved

by

the

Government will be considered for

allotment.

m. In case of more than one application

for the same Industrial Plot/MIZ Plot,

Allotment of plots shall be done through

limited e-auction process wherein plots

would be allotted on lease basis to the

highest bidder; from amongst the shortlisted

applicants.

n. The e-auction procedure is detailed at

section 2.8 below.

Step 4: Issue of Initial Offer of Allotment

& Letter of Allotment:

o. Based on the acceptance of the

recommendation of the Screening

Committee by the Government, the Chief

Promoter/SPV shall issue an initial offer of

allotment giving thirty days time period

for effecting payment towards the lease

premium, rent, other fees prescribed from

time to time and fulfilment of any stipulations

mentioned by the Screening Committee in

its recommendations, which will be binding

on the applicant.

p. The Offer letter should indicate the

particulars of the Land, Plots, and built-up

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1058

premises; and the terms and conditions to

be complied by the applicant.

q. The applicant shall comply with the

terms and conditions listed in the offer Letter

within a period of 30 (Thirty) days of the

receipt thereof failing which the Offer letter

shall automatically stand cancelled without

any further notice. However, the allottee

may, prior to the expiry of the prescribed

thirty days, apply for one time extension of

time for complying with the conditions listed

in the Offer letter. If the Chief Promoter is

satisfied with the genuineness of the reasons

stated therein, extension may be granted for

a further period of 15 days on payment of

penalty of Rs. 2 per sq. mt./-

r. The Chief Promoter/SPV upon receipt

of acceptance of Initial Offer of Allotment and

Security Deposit amount shall issue the

Allotment Order to the applicant.

s. All allotment orders shall be issued with

a draft lease deed and the allottee shall

also be notified of the value of non-judicial

stamp paper on which the lease deed to be

executed.

Step 5: Execution of Lease Deed:

t. The allottee shall execute the Lease

Deed with the Chief Promoter within a

period of 90 (ninety) days from the date of

issue of Allotment Order. The following

action items are a condition precedent for

execution of the Lease Deed:

i. Acknowledgement and acceptance of

the Initial Offer of Allotment within the

stipulated time.

ii. Payment of Land Premium amount

within 30 days from the date of issue of the

Allotment Order.

iii. Payment of Annual Lease Rent for the

first year, within 30 days from the date of

issue of the Allotment Order.

iv. Submission of the site layout, floor

plans and relevant elevations and sections

of the proposed development on the plot to

Chief Promoter/SPV for approval.

• Execution of Lease Deed is a condition

precedent

for

commencing

any

development/construction activity on the

plot. Should the allottee fail to execute the

Lease Deed within 90 days from the date

of issue of the Allotment Order, the

allotment shall stand automatically

terminated/cancelled. In such an

instance the amount equal to the Security

Deposit paid by the allottee shall stand

forfeited and the balance amount (if any)

shall be paid to the allottee without any

interest.

• The 90 (ninety) days period stipulation

will not apply in instances of procedural

delay caused on the part of the Chief

Promoter/SPV and in such an instance

the period of 90 (ninety) days will be

extended for a period equivalent to the

delay so caused, with the approval of the

Chief Promoter/SPV.

• In the event of any dispute or

applicability or otherwise of this clause,

the decision of the Chief Promoter/SPV

shall be final and binding on the allottee.

Step 6: Physical Possession of the Plot:

u. A time period of 30 (thirty) days will be

stipulated in the Lease Deed for the allottee

to take physical possession of the plot. If the

allottee fails to take the possession within

the stipulated period, the allotment order

issued by the Chief Promoter shall stand

terminated/cancelled. In such an instance,

the Security Deposit paid by the allottee shall

stand forfeited and the balance amount (if

any) shall be paid to the allottee without any

interest.

2.6. Price of Plots and Land Premium.—

2.6.1. The land premium rates of the plots

shall be fixed by the Chief Promoter/SPV based

on the fixation of land rates by the Department

of Revenue, Government of Goa from time to

time and will be displayed in advertisement

or periodically updated on the website portal.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1059

2.6.2. The allotee has to pay the Land

Premium for the plot within a period of 30 days

from the date of the Allotment Order as lump

sum (without any interest) or the allottee may

opt to pay a token money @ 25% of the Land

Premium as 1st Land Premium Instalment and

advance payment of annual lease rent along

with applicable taxes within a period of 30 days

from the date of issue of the Allotment Order

and the balance amount in 7 equal instalments

over a period of 7 years along with simple

interest @ of 11%. Chief Promoter shall charge

a penal interest @18% per annum on defaulted

amount if the land premium is not paid within

the time specified or any arrears payable by

the allottee.

2.7. Lease Tenure and Rent.—

2.7.1. Plots shall be allotted to the allottee

(for setting up of the unit) on a lease basis for a

term of 30 (thirty) years from the date of the

Allotment Order with an option of renewal for

subsequent term of 30 years. The renewal of

lease period shall be considered by the Chief

Promoter/SPV on written request of the lessee,

one year prior to the expiry date of the lease

period, and renewal will be subjected to terms

and conditions as may be decided by the Chief

Promoter/SPV. The extension of subsequent

term of 30 years to the lease period can be

allowed subject to the allottee completing the

project within 5 years.

2.7.2. The Allottee will have to pay an

Annual Lease Rent at 2% of the Land Premium

or at such rate as may be specified by the Chief

Promoter/SPV from time to time and shall be

subject to increase in Lease Rent to be

determined by the Chief Promoter/SPV. Annual

Lease Rent shall be increased to 10% of the

Annual Lease Rent after every 3 years.

2.7.3. The Annual Lease Rent shall be paid

on or before 1st May of each year to the Chief

Promoter.

2.8. Allotment by e-auction.— (Limited

eAuction)

2.8.1. Allotment of plots in case of more than

one application for same Industrial Plot/MIZ

Plot, Allotment shall be done through

e-auction process wherein plots would be

allotted on lease basis to the highest bidder.

2.8.2. The reserve/base price for e-auction

of the plot on lease basis shall be decided by

the Chief Promoter/SPV in the Greenfield

Electronic Manufacturing Cluster, Tuem based

on the fixation of land rates by the Department

of Revenue, Government of Goa from time to

time.

2.8.3. The amount of 10% of the base price

in the form of the DD or Pay Order should be

collected by the Chief Promoter/SPV before

the commencement of e-auction who will be

allowed to participate.

2.8.4. After the highest bid is accepted, the

same shall be recorded in the Bidders Register.

2.8.5. Official Report should be submitted by

the officer in charge of the e-auction to the Chief

Promoter/SPV immediately after the bid is

accepted, detailing the percentage of the land

price remitted by the successful bidder and

the bid amount accepted.

2.8.6. The Demand Draft /Pay Order etc.

should be returned to the concerned

unsuccessful bidders immediately after

conclusion of the e-auction duly obtaining

their acknowledgement in the Bidders

Register.

2.8.7. After the e-auction is over, the Chief

Promoter/SPV shall give an offer letter to the

successful bidder within 15 days from date of

e-auction.

2.8.8. If the highest bidder fails to make the

payment within the stipulated time, the

Security Deposit and the 10% base price paid

shall be forfeited.

2.8.9. The Land, Plots, etc. e-auctioned by

the Chief Promoter shall be on lease basis and

shall continue to vest with the Chief Promoter.

2.9 Conditions for Delayed Completion.—

2.9.1. An allottee is expected to complete the

project and go into commercial operations

within a maximum period of 2 years from the

date of issue of the Allotment Order/Lease

Deed.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1060

a. In case of delay beyond two (02) years

for completion of the project and

commencement of operations, maximum

relaxation of one additional year shall be

granted subject to the allottee paying a

penalty of 25% of the prevailing Land

Premium rate per sq. mts. calculated on the

total plot area leased.

b. If the allottee fails to implement the

project and go into commercial operations

even after the period of three (03) years from

the date of issue of the Allotment Order

(subject to penalty payment made as per

“Relaxation for Delay” clause a above), the

allotment made shall stand terminated, the

plot along with the buildings and

appurtenances standing thereon shall stand

reverted to the Chief Promoter and the

amounts paid by the allottee to the Chief

Promoter/ SPV shall stand forfeited. Further

in case of any delay in handover of the plot

along with buildings and appurtenances by

the allottee to Chief Promoter/SPV, a penal

charge equivalent to twice the prevalent

annual lease rent shall be chargeable for

every day of the delay (applicable on pro

rata basis). The Chief Promoter/SPV shall

resume the land with all development on it

and evict the allottee. The Chief Promoter

reserves its right to grant any further

extension based on merit of each case and

on such terms and conditions as may be

imposed.

2.10. Mortgaging of Plot.—

2.10.1. Upon receipt of an application, the

Chief Promoter to that effect and extent, may

decide in respect of permitting an allottee to

mortgage the lease hold rights over the plot

allotted, over the machinery installed/to be

installed and the factory building constructed

on the said plot, to any Financial Institution

for raising funds for setting up the industrial

unit. Mortgage of land would be restricted to

the Land Premium paid by the allottee towards

the allotted plot.

2.10.2. Pursuant to the decision referred to

under clause 2.10.1 above, a letter conveying

no objection shall be issued to the Financial

Institution for financing the allottee for setting

up the project, to have the First, Second or pari

passu charge over the lease hold rights of the

plot allotted, over the machinery installed/to

be installed and the building constructed on

the said plot provided the allottee regularly

remits the annual lease rent fixed.

2.10.3. The Chief Promoter shall issue letter

to the Financial Institution/Bank/Consortium

of Banks, facilitating the allottee for setting up

the project, to have the first/second/pari passu

charge over the lease hold rights over the plot

allotted.

2.10.4. The letter to the Financial Institution/

Bank/Consortium of Banks will be issued by

the Chief Promoter within a period of 15 days

from the receipt of the application and/or from

the date of payment of any outstanding dues

by the allottee, whichever is later.

2.10.5. For processing the applications, a

processing fee of Rs. 5,000/- shall be charged

to the applicant.

2.10.6. In case of any unforeseen

circumstances if the movable or immovable

assets of the allottee are attached by the

Financial Institution for recovery of dues

and the said assets are put to auction then

the financial institution shall also recover

the outstanding dues if any of the Chief

Promoter/SPV by the allottee and remit the

same to the Chief Promoter/ SPV.

2.10.7. No transfer shall be eventuated

unless and until the outstanding dues of the

Corporation are deposited with the

Corporation either by the financial institution

or the bidder parties. It would be incumbent

upon the bidder parties and/or financial

institutions to check the outstanding dues

of the Corporation if any, against the said assets

before bidding so as to avoid further

complication to get the plot transferred in their

names.

2.11. Surrender of Plot.—

2.11.1. In case, the allottee decides to

surrender the plot, due to unavailability of the

project, finances, change of management

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1061

decision. The application needs to be

submitted by the applicant to the Chief

Promoter/SPV detailing the reason for

surrender of plot.

2.11.2. The surrender application can be

given by the applicant within 18 (eighteen)

months from date of the Allotment Order or

taking over possession, whichever is earlier.

2.11.3. The plot/plots to be surrendered

should be vacant and peaceful possession

should be handed over to the Chief Promoter.

2.11.4. Surrender charges applicable to be

deducted for surrender of plot/land etc. shall

be as under:

i. 1% of the prevailing total Land Premium

amount of the plot.

ii. In addition to the surrender charges

specified under clause 2.11.4.i, the amounts

paid by the allottee towards land premium,

annual lease rent, penal interest, processing

fees, utility charges, GST, shall stand

forfeited.

iii. Any amount pending towards dues on

account of annual lease rent, penal interest,

and interest on Land Premium, processing

fees, GST or any other dues shall be

recovered from the land premium amount

and any shortfall after adjusting the

premium amount shall be recovered as land

revenue arrears.

2.11.5. In case the plot is mortgage with

bank/financial institution, the applicant needs

to submit the No objection certificate from the

Bank/Financial Institution prior to the

surrender of plots.

2.12. Utilization of Plot.—

2.12.1. The allottee within a period of two

(02) years from the date of issue of Allotment

Order, shall compulsorily utilize to the extent

of at least 50% of the land/plot area allotted,

for construction of factory or other buildings.

In case of the failure on part of the allottee to

utilize the minimum prescribed area for built-

up, the Chief Promoter/SPV shall levy 50%

additional Annual Lease Rent on the

permissible but unutilized area of the said plot.

However, any relaxation, indulgence granted

by the Chief Promoter / SPV in deserving cases

should not be treated as waiver on behalf of

the Chief Promoter / SPV and will not prejudice

or effect its rights to initiate action against the

defaulting allottees.

2.12.2. In case of the failure of the allottee to

comply with the above plot utilization norms,

the Chief Promoter will have the right to

repossess the unutilized/partially utilized

portion of the land without any compensation

to the allottee, subject to guidelines approved

by the Chief Promoter/SPV from time to time.

2.13. Transfer and Sub-lease.—

The allottee shall not transfer or assign its

rights in the allotted Land, Plot and Built-up

premises without obtaining prior permission

from the Chief Promoter. Permission, if granted

shall be on the basis of separate set of

guidelines to be notified. Under no

circumstances sublease would be permissible.

2.14. Change in Name or Change in Trade/

Use/Addition of Product to be manufactured.—

2.14.1. Any allottee which undergoes

change in name of the allottee entity without

changing the constitution or its shareholding

structure of the allottee entity shall apply to

the Chief Promoter/SPV with a request to

register the change in name in the records of

the Chief Promoter/SPV. The application should

be accompanied with the following

documents:

a. Certificate issued by the Registrar of

Companies in case of Limited Liability

Companies, or Certificate issued by the

Registrar of Firms in case of Partnerships or

an affidavit in case of a proprietor.

b. PAN Card of the allottee entity with the

change in name.

c. NOC from the financial institution in

case permission is granted by the Chief

Promoter/SPV to the allottee to mortgage the

lease hold rights.

d. Copy of the latest partnership deed/

shareholding structure certificate from a

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1062

Company Secretary and the latest

Memorandum and articles of association of

the Company.

e. Any other documents as required by

the Chief Promoter/SPV.

2.14.2. On scrutiny of the above documents

and payment of a non- refundable processing

fees of Rs. 5000/- plus applicable taxes, the

Chief Promoter/SPV will confirm in writing

having changed the name of the allottee entity

in its records.

2.14.3. Any allottee intending to change the

trade/use or add a product to be manufactured

shall submit an application along with the

project report, Certificate or Udyog Aadhar

with necessary amendments as issued by the

Director of Industries, Trade and Commerce,

to the Chief Promoter/SPV.

2.14.4. On scrutiny of the above documents

and payment of a non-refundable processing

fees of Rs. 5000/- plus applicable taxes, the

Chief Promoter/SPV may grant its permission

to the allottee for change in use or trade or for

the addition of product to be manufactured.

Provided the change in use or trade or addition

of product is in accordance with the Schedule

A appended hereto.

2.15. Change in Constitution/Share Holding

Structure.—

2.15.1. Any allottee which undergoes a

change in constitution or change in

shareholding structure within limits under

sub-clauses 2.16.2, and 2.16.3 below, shall have

to inform the Chief Promoter/SPV within a year

of effecting such change or along with

certificate issued by the Company Secretary

detailing the nature of such changes. The Chief

Promoter/SPV will make necessary changes

in its record on payment of a non- refundable

processing fees of Rs. 5000/- plus applicable

taxes. However, in the event any of such

changes in the constitution or shareholding

structure result in breaching the limits

stipulated under 2.16.2 and 2.16.3, the lease

hold rights over the plots will be deemed as

transferred and the Chief Promoter/SPV will

process the case in accordance with separate

set of transfer guidelines to be notified by the

State Government.

2.15.2. Change in constitution in case of a

proprietary or a partnership firm (including

limited liability partnership firm) which does

not result in the original/existing proprietor or

partner and their relatives diluting their share

of ownership in such firm below 51%.

2.15.3. Change in shareholding structure in

case of a private limited company, which does

not result in the original/existing promoter

shareholders diluting their share of ownership

in such firm below 26%.

2.16. Miscellaneous.—

2.16.1. The Chief Promoter/SPV reserves its

right to revise the Payment, Fees, Charges,

Taxes, Deposits etc. as stipulated and the

allottee shall be bound to pay the Payment,

Fees, Charges, Taxes, Deposits etc. on demand

by the Chief Promoter/SPV.

2.16.2. The allottee needs to achieve

financial closure within 180 days from the date

of issue of the Allotment Order.

2.16.3. The Chief Promoter/SPV shall

conduct inspection of the land allotted and

reserves the right of utilizing vacant portions

of the allotted land in case land is vacant for

more than two years from date of operation,

for laying pipe lines, cables, underground

drainage or drawing overhead electric lines

without paying any compensation other than

rectifying the damage caused due to such

activity to the allottee for such use.

2.16.4. The Chief Promoter/SPV with prior

approval of the State Government shall be

entitled for taking appropriate measures for

removal of difficulties, if any, that may arise at

any stage in the performance of its lawful

functions, so as to give full effect to the

Regulation.

2.16.5. The allottee will have to submit a

project progress or status report to the Chief

Promoter/SPV every six months, from the date

of issue of Letter of Allotment until commercial

date of operation. The project progress report

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1063

to provide factual position of the progress made in the approvals, construction/development of

the buildings along with related site infrastructure and equipment’s and machinery required

for operations.

2.16.6. The allottee shall have to take the necessary approvals, permissions and licenses for

development of the plot, construction of the buildings and operations of the unit from all statutory

authorities including but not limited to town planning, pollution control, environment clearances

and all other necessary relevant statutory authorities. All necessary costs and expenses will

have to be borne by the allottee itself.

2.16.7. The allottee, during construction stage and subsequent operation stage, shall ensure

that they conduct all activities with respect to the units as well as the ancillary process within

permissible limits and not cause Air Water and Noise Pollution. The allottee must keep periodic

documentations like Third Party Verification of Air Water and Noise Levels from certified agencies

of Goa State Pollution Control Board. The SPV/Chief Promoter may request such documents at

any point of time and must be submitted within seven days from date of written communication

from the SPV/Chief Promoter. If the allottee is found violating these practices, it shall be notified

of the same in written communication from the SPV/Chief Promoter. The allottee must give

clarification to this matter with remedial measures and timeline for same within 15 days from

the date of the receiving the letter from SPV/Chief Promoter. In case negligence and continuance

of violation, the SPV/Chief Promoter may issue an order to immediate shutdown of operation by

seven-day prior notice issued to the allottee. If such shutdown continues for 6 months from the

date of final notice without remedial action to resolve the issue, the SPV/Chief Promoter may

initiate the procedure for surrender of plots.

2.16.8. The Chief Promoter/SPV reserves the right to interpret any of the clauses of the terms

and conditions of land allotment.

2.16.9. All payments to the Chief Promoter/SPV through DD shall be drawn in the name of

“Director (IT), Department of Information Technology, Government of Goa” or as specified in

the advertisement.

Schedule - A

List of Verticals/Industries under which application can be submitted

1. Electronic Products

1.1.

Telecom Products

1.2.

Nano Electronics Products

1.3.

I.T Hardware

1.4.

Consumer Electronics/Durables

1.5.

Health and Medical Electronics

1.6.

Strategic Electronics

1.7.

Solar Photovoltaics including thin film, polysilicon etc.

1.8.

Light Emitting Diodes (LED)

1.9.

Liquid Crystal Displays (LCDs)

1.10. Avionics

1.11. Industrial Electronics Products

1.12. E-waste processing/recycling

1.13. Automotive Electronics

1.14. Agri-Electronics

1.15. Energy Conservation Electronics

1.16. Opto-Electronics

1.17. Bio-metric and identity devices/RFID

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1064

1.18. Power Supplies for ESDM products

1.19. IOT related products

1.20. Drones

1.21. E- mobility segment (including cells/battery, BMS, ECU etc.)

1.22. Security Devices (CCTV, NVR, DVR)

1.23. Smart meter

1.24. TWS like earbuds etc.

1.25. Smart watch/wearable devices

1.26. AR/ VR devices etc.

2. Intermediates

2.1. Nano Electronics Components

2.2. Semi-conductor wafering

2.3. Semiconductor Chips including logic, memory and analog

2.4. All Assembly, Testing, Marking and Packaging of ESDM Units

2.5. Chip Components

2.6. Discrete Semiconductors like Transistors, Diodes

2.7. Power Semiconductors (including diffusion) like FETs, MOSFETS, SCRs, GTDs, IGBT etc.

2.8. Electromechanical Components and Mechanical Parts as Multilayer PCBs, Transformers, Coils,

Connectors, Switches, Ferrites, Micro Motors, Stepper Motors, Films etc.

2.9. Consumables and Accessories such as Mobile Phones and IT accessories – Batteries, Chargers etc.,

PCBs, Foils, Tapes, Epoxy, Cabinets etc.

2.10. All Fabrication Manufacturing facilities (Fabs) for ESDM products

3. Electronic Manufacturing Services (EMS)

4. Electronics components covered under Scheme for Promotion of manufacturing of Electronic Components

and Semiconductors (SPECS)

_________

Department of Information & Technology

Government of Goa

IT HUB, 2nd Floor

Altinho, Panaji, Goa 403 001

Place: _____________________

Date: _____________________

To,

The Director/Chief Promoter,

Department of Information & Technology,

Government of Goa,

IT HUB, 2nd Floor,

Altinho, Panaji, Goa 403 001.

Sub.: Application for plot No.(s). ______ admeasuring _______________sq.mt. in the Greenfield

Electronic Manufacturing Cluster at village Tuem, Taluka Pernem, Goa.

Sir,

1. I/We have read and agree to the terms and conditions for the allotment of plots enclosed as Annexure–

II (Terms & Conditions for allotment of Plots) of this form.

2. I/We ______________________ the undersigned are submitting our application along with necessary

supporting documents herewith for allotment of plot No(s). ________ admeasuring approximately

_________________ sq. mt. at Greenfield Electronic Manufacturing Cluster at village Tuem, Taluka Pernem,

Goa on the terms and conditions referred to Electronic Manufacturing Cluster Land Allotment Policy, 2021

and Notification No. 10(29)/DOIT/2021/Land Premium EMC – Tuem/P.F. – I/710 dt. 12-08-2021.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1065

3. I/We upon acceptance of our application for allotment of land, agree to acknowledge and accept the

Initial Offer of Allotment and further execute the Lease Deed at my/our cost.

4. The lease will commence from the date of execution of the Allotment Order. I/We agree to make complete

payment of Land Premium and Annual Lease Rent for the first year, as mentioned in the Letter of Allotment

as per clause 2.6 of the Land Allotment Policy. All the obligations and liabilities under the Lease Deed will be

deemed to have come into effect from that date.

5. I/We have enclosed herewith DD in favour of Chief Promoter/SPV amount of Rs. ___________ (Rupees

_____________________________) being the non-refundable processing fees of 0.1% of the land premium

value and DD in favour of Chief Promoter/SPV amount of Rs._______________________________ (Rupees

_____________________________) towards Security Deposit (interest free–refundable) equivalent to 10% of

the land premium value.

6. The Security Deposit shall be only refunded in case the application is not considered by the Screening

Committee to qualify for plot allotment, which is not a result of lapse in procedure compliance from me/us.

7. I/We hereby agree to pay the Land Premium along with Annual Lease Rent for the first year and

subsequently execute the Lease Deed, as specified in the Allotment Order within 90 days of the date of its

issue.

8. I/We understand that the Security Deposit mentioned herein will be adjusted against the Land Premium

payable towards the plot(s) and the same is acceptable to me/us.

9. I/We agree to pay the Annual Lease Rent per year at a rate, as may be decided by the Chief Promoter, from

time to time commencing from the date of issue of the Allotment Order.

10. I/We understand that no interest will be payable by the Chief Promoter for any of the sums referred to

in para 5 of this application form.

11. Should I/We fail to take possession of the plot(s) and/or to execute and complete the Lease Deed within

the period specified by the Chief Promoter/SPV, the allotment of plot is liable for cancellation and the Chief

Promoter/SPV shall be at liberty to forfeit the amount deposited with the plot application and Security

deposit amount without prejudice to all other rights mentioned in the Electronic Manufacturing Cluster

Land Allotment Policy, 2021.

12. I/We understand that development and operations of the unit on the designated plot shall be done

with measure to prevent any contamination of air, water or ground and to ensure prevention of any noise

pollution. In case of any violation of the same, the SPV/Chief Promoter may order shut down of the allotted

premises.

13. Any Notice, letter or communication addressed to me/us at the address given below will be deemed as

a valid and proper notice of intimation to me/us.

14. I/We understand and agree that I/we will have to take all necessary layout, building, pollution,

environment permissions and all other licenses required for development and operations of the unit. All

necessary costs and expenses will have to be borne by me/us.

15. I/We also enclose the appended questionnaire duly filled.

Signature(s) of the Applicant(s)

___________________________

Full name in block letters with designation and address:

___________________________

___________________________

___________________________

Name and address of witnesses should be written legibly after their signature.

1.

2.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1066

ANNEXURE-I

Questionnaire

1. Name of Individual/Firm/Company: For which plot is applied for:

2. Address:

a. Registered Office & Tel No.:

b. Corporate Office & Tel No.:

c. Local Office & Tel No.:

d. E mail:

3. Constitution: Proprietary/Partnership/Private or Public Limited Company (enclose a copy of Partnership

Deed or Memorandum and Articles of Association along with Registration. Certificate/Certificate of

Incorporation, as applicable).

4. Date of Registration/Establishment of Firm/Company.

5. In the case of Proprietary/Partnership/Private or Public Limited Company, please state:

Names of Director/

Shares in the

Residential address

Qualifications

Business

/Partners

Company

with Phone No.

Background

6. Plot No.(s). _____________

Area of plot(s): _________________

7. In case of plot, state:

i. Plot Area & Built Up Area to be constructed immediately:

ii. Plot Area & Built Up Area to be reserved for further expansion:

8. Attach PAN Card, Adhar Card, Driving License, Passport of the applicant & income tax returns of the

applicant in case of individual proprietorship.

9. Attach the following supporting documents in case of a Company/Firm/Partnership/LLP/Society:

a) PAN Card & GST Registration Details

b) Income Tax returns filed for the last three financial years.

c) Copy of the Certificate of Registration, Copy of Certificate of Incorporation and Memorandum and

Articles of Association in case of Limited Companies and a copy of resolution authorizing the applicant

to apply on behalf of the company (as applicable).

d) Audited Balance Sheet and Annual Reports for last three financial years.

10. Please give the particulars of firms/industrial units wherein proprietor/partners/directors of this unit

are having interest association.

Names of Director/

Name and Address of

Activities

Relationship

Shares in

Partners/Proprietor

Business Firm

carried out

Business

11. If already holding/applied for plot under industrial estates promoted and developed by Goa Industrial

Development Corporation of Goa - Yes/No

12. If Yes to No. 11, then provide attachments of Allotment Letter and Lease Deed Copy - Yes/No

13. Nature of Industry:

i. Name of the Products:

ii. Is it an ancillary unit (if so enclose copy of approval)

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1067

14. Give details about products to be manufactured:

Items to be

Annual Quantity

Production

Use of the

Manufactured

(Nos.)

Value (Rs.)

Product

15. Kindly provide more information on the market share of your product/company in this segment and any

supporting statistics to indicate the market depts. In such product/industry segment.

16. Water requirement per day (in MLD.) for the proposed unit:

17. Total power required for the proposed unit (in KVA), kindly provide details:

18. List of machinery along with their power: requirement in H. P. (enclose sheet if required)

i. ______________________

ii. ______________________

iii. ______________________

iv. ______________________

19. In case the machinery is old & being shifted: from one State to another (copy of the consent letter from

that Government is to be submitted).

20. Raw Material (Annual requirement)

i. Indigenous:

a. Type of raw material

b. Volume & Cost (annually)

c. Source of Supply

ii. Imported:

a. Type of raw material

b. Volume and Cost (annually)

c. Source of supply

d. State Country of origin (in case of imports and if such import is controlled/free)

21. Number of persons proposed to be employed:

Skill Level

Qualification

Male/Female

Experience Goan/Non Goan

Managerial

Skilled

Semi-Skilled

Un-Skilled

Other Staff

Technical Staff

22. Please state, if you have entered into a foreign: collaboration, If so, please enclose copy of approval.

23. Submit details of collaboration agreements if any entered into by the unit

24. Uses of bye products, if any

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1068

25. Kindly provide total project cost. Kindly enclose DPR/Business Plan as Annexure:

Project Cost (excl. Land Premium):

Cost (Rs. in lacs)

Site Development Cost

Rs.

Factory Building and Ancillary Buildings

Rs.

Plant & Machinery

a) Indigenous

Rs.

b) Imported

Rs.

Power supply & cabling etc.

Rs.

Erection charges

Rs.

Preliminary & pre-operative expenses

Rs.

Provision for contingencies

Rs.

Margin for working capital

Rs.

TOTAL PROJECT COST

Rs.

26. Means of Finance:

Promoters Capital

Rs.

Unsecured loans and deposits

Rs.

Terms loan from Financial Institution/Banks

Rs.

TOTAL

Rs.

27. Whether machinery has been booked (attach documents)

The information provided above is correct to the best of my knowledge and belief.

Signature of Proprietor

_________________

Signature of Partner

_________________

Signature of Director

_________________

Seal of the Company _________________

WITNESSES: (Name and full Address)

1.

2.

_________

Department of Information & Technology

Government of Goa

IT HUB, 2nd Floor

Althino, Panaji, Goa 403 001

ANNEXURE – II

TERMS AND CONDITIONS FOR ALLOTMENT OF PLOTS

1. The plots will be allotted to applicants desirous of setting up industry/unit that include the entire value

chain of all electronic verticals/ products covered under the National Policy on Electronics and related

notifications issued by the Ministry of Electronics & Information Technology (MeitY), Government of India.

2. The plot holder will not be allowed to let or dispose their plots by sale or lease hold interest or otherwise

except with the prior written permission of Chief Promoter. The permission for the transfer will be issued with

such conditions as may be prescribed by the Chief Promoter. However, sub division or disposal of part of plot

will not be allowed under any circumstances.

3. The plots are allotted on long lease basis, initially for a period of 30 years which can be extended for

additional period of 30 years, subject to terms and conditions as decided by the Chief Promoter/SPV, from time

to time.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1069

4. The interest free Security Deposit for booking a plot is 10% of Land Premium amount for the entire plot

area required to be paid.

5. Security Deposit amount paid shall be adjusted against the Land Premium amount payable by the

allottee.

6. No interest is payable by the Chief Promoter/SPV on the Security Deposit amount paid by the applicant.

7. Land Premium for the plot is payable within a period of 30 days from the date of the Allotment Order as

lump sum (without any interest) or the allottee may opt to pay a token money @ 25% of the Land Premium as

1st Land Premium Instalment and advance payment of annual lease rent alongwith applicable taxes within

the period of 30 days and the balance amount in 7 equal instalments over a period of 7 years alongwith simple

interest @ of 11%. Chief Promoter shall charge a penal interest @18% per annum on defaulted amount if the

land premium is not paid within the time specified or any arrears payable by the allottee.

8. The plot holders will have to pay an Annual Lease Rent at 2% of the Land Premium or at such rate as, may

be specified by the Chief Promoter/SPV shall from time to time.

9. Any amount due to the Chief Promoter/SPV if not paid in time will be recovered as arrears of land

revenue & steps will also be taken to file such cases for eviction.

10. The plot holders should at all times comply with all the laws, rules, regulations etc. of the Chief

Promoter/SPV.

11. The plans of the buildings are to be approved by the local authority and the planning authorities in

force.

12. The Allotment Order will be issued and possession of the plot will be given only after the applicant has

acknowledged and accepted the Initial Offer of Allotment and paid the Security Deposit amount.

13. If the allottee does not wish to accept allotment of the plot, the communication in this regard should

reach Chief Promoter before 15th day from the date of issue of Initial Offer of Allotment, failing which any

amount deposited with the application shall be forfeited.

14. The allottee has to execute with Chief Promoter/SPV a Lease Deed immediately within 90 days of the

issue of the Allotment Order. Payment of the Land Premium, Annual Rent for the First Year and preparation of

all detailed drawings along with written approval of Chief Promoter on the same is a condition precedent for

execution of the Lease Deed.

15. The Chief Promoter/SPV will facilitate to provide water and power connection to the allottee during

development of plot based on application made by the Allottee. Charges as stipulated by the Chief Promoter/

SPV from time to time for such trunk infrastructure shall be borne by the allottee.

16. The plans & detailed drawings of the buildings and other documents notified should be submitted to

the Chief Promoter/SPV for approval within 90 days from the date of issue of Allotment Order. The construction

of the building should be started within one year of the date of issue of the Allotment Order. The building

should be completed and production started within two years from the date of issue of the Allotment Order.

In case of failure to comply with these conditions, the allotment is liable for cancellation.

17. Any loss which may hereby occur to Chief Promoter/SPV will be recovered from the allottee. For the

delay caused in submitting the building plans/ starting construction work and completion of factory building,

the allottee/lessee will be liable to pay fines to the Chief Promoter/SPV at rates prescribed by Chief Promoter/

SPV from time to time and will be liable to be evicted on account of all or any of the aforesaid defaults.

18. The allottee shall have to comply with the Goa (Regulations of Land Development and Building

Construction) Act, 2008 and the Goa Land Development and Building Construction Regulation, 2010 made

there under or any other laws in force for carrying out any construction and other allied activities.

19.

No change in the name of the client or ownership or constitution of the firm to whom the plot is

allotted shall be made without the previous written consent of the Chief Promoter/SPV. The consent of the

Chief Promoter/SPV will be given on the conditions as may be specified in the Electronics Manufacturing

Cluster Land Allotment Policy, 2021 or the Transfer Guidelines to be notified separately.

20. The application form and the terms and conditions of allotment is available on the official website of

the Chief Promoter/SPV.

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 20

(EXTRAORDINARY)

13TH AUGUST, 2021

1070

21. The application form should be filled up completely. Particulars regarding the requirement of water

and electric power should be invariably furnished as accurately as possible. It should be noted that an

application which is incomplete in any respect is liable to be summarily rejected without further consideration.

For any other particulars, please contact us during working hours at the address given below:

The Director/Chief Promoter,

Department of Information & Technology,

Government of Goa,

IT HUB, 2nd Floor.

Altinho, Panaji, Goa 403 001.

AFFIDAVIT-CUM-UNDERTAKING

I __________________________, son of ___________________, __________________, of _________________,

aged ____ years, resident of _____________, do hereby on solemn affirmation state and submit as under:

1. I say that I am duly authorized to swear this affidavit cum undertaking on behalf of _____________.

2. I say that I have applied for plot No. (s) ______ measuring ______ sq. mts. with the Chief Promoter, for

setting up __________________.

3. I say that the unit to be set-up by us is under the Industrial category or ____________ under the

notified Electronics Manufacturing Cluster Land Allotment Policy, 2021 and the document listed at

sub-clauses __________ of Clause____ of the said policy document are not applicable to us.

4. I hereby undertake to remit to the Chief Promoter/SPV any amount being difference in the premium

and any other dues regarding the allotment on lease as demanded by the Chief Promoter/SPV within

the time prescribed for payment.

5. I say that I shall abide by all the terms and conditions set forth in the Policy document, allotment

Policy , offer letter, allotment order or the lease deed, in respect of the allotment to be made in my

favour.

6. I undertake to pay the lease rent presently payable or subsequently modified/fixed from time to time

in respect of the allotment to be made in my favour.

7. I undertake to abide by the prevailing environmental laws and obtain all necessary permissions.

8. I undertake to obtain and produce all the necessary permissions from the authorities as and when

demanded by the Chief Promoter/SPV.

9. I undertake to submit the plans, start the construction activities and commence production within

the time frame notified by the Chief Promoter/SPV.

10. I undertake to utilize the minimum area for built up as per the policy of the Corporation and shall not

carry out any illegal construction or any unauthorized business activities which are not permitted by

Authorities in the plot/land, to be allotted.

11. I undertake to plant at least 6 Nos. of ornamental/fruit bearing trees within the area/plot allotted to

me.

12. I undertake to pay all the fees, taxes, charges etc. payable to the local authority or planning authority

having jurisdiction over the plot/land etc. to be allotted to me.

Solemnly affirmed at _____ on

this the ____th day of _____ .

Deponent.

www.goaprintingpress.gov.in

Printed and Published by the Director, Printing & Stationery,

Government Printing Press,

Mahatma Gandhi Road, Panaji-Goa 403 001.

PRICE – Rs. 20.00

PRINTED AT THE GOVERNMENT PRINTING PRESS, PANAJI-GOA—157/150—8/2021.