3089

Panaji, 5th April, 2022 (Chaitra 15, 1944)

SERIES I No. 53

Reg. No. RNP/GOA/32/2021-2023

RNI No. GOAENG/2002/6410

PUBLISHED BY AUTHORITY

GOVERNMENT OF GOA

Department of Power

Office of the Chief Electrical Engineer

__

Notification

120/2/CEE/TECH/SDA-4

In exercise of the powers conferred by sub-

section (3) of section 1 of the Goa Public

Lighting Duty Act, 2021 (Goa Act 25 of 2021),

the Government of Goa hereby appoints the

5th day of April, 2022 as the date on which

the provisions of the said Act shall come into

force.

By order and in the name of the Governor

of Goa.

Stephen Fernandes, CEE & ex officio Addl.

Secretary (Power).

Panaji, 5th April, 2022.

———

Notification

120/2/CEE/TECH/SDA-4

In exercise of the powers conferred by sub-

section (1) of section 8 of the Goa Public

Lighting Duty Act, 2021 (Goa Act 25 of 2021),

the Government of Goa hereby notifies the

Chief Electrical Engineer, Superintending

Engineers, Executive Engineers (Electrical)

and Assistant Engineers (Electrical) of the

Electricity Department of the Government of

Suggestions are welcomed on e-mail: dir–[email protected]

Goa as the Inspecting Officer, for the purposes

of the said Act.

By order and in the name of the Governor

of Goa.

Stephen Fernandes, CEE & ex officio Addl.

Secretary (Power).

Panaji, 5th April, 2022.

———

Notification

120/2/CEE/TECH/SDA-4

In exercise of the powers conferred by

section 9 of the Goa Public Lighting Duty Act,

2021 (Goa Act 25 of 2021) and all other powers

enabling it in this behalf, the Government of

Goa hereby makes the following rules,

namely:—

1. Short title and commencement.—(1)

These rules may be called the Goa Public

Lighting Duty Rules, 2021.

(2) They shall come into force on the date

of their publication in the Official Gazette.

2. Definitions.— (1) In these rules, unless

the context otherwise requires,—

a) “Act” means the Goa Public Lighting

Duty Act, 2021 (Goa Act 25 of 2021).

b)“Public lighting duty” means duty

payable as per section 4 of the Act.

EXTRAORDINARY

No. 3

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 53

(EXTRAORDINARY No. 3)

5TH APRIL, 2022

3090

(2) Words and expressions used and not

defined in these rules but defined in the Act

shall have the meanings respectively assigned

to them in the Act.

3. Operation and maintenance of public

lights.— (1)The existing public lighting

infrastructure in working condition alongwith

AMC and warranty of lights shall be handed

over by other Government Departments and

Government Corporations to the Department

within the period specified in section 7 of the

Act. The bills of the AMC contractors as on

the date of such handing over shall be settled

by the concerned Government Department

or Government Corporation and no dues

certificate in respect of the Annual

Maintenance Charges (AMC) shall be

submitted to the Department by the

concerned Department/Corporation.

(2) Maintenance and switching ON/OFF of

all streetlights shall be looked after by the

Department, however, facade illumination of

temples, churches, mosques and their outskirt

shall be looked after by the Government

department/corporation concerned.

4. Creation of infrastucture for public

lighting.—

(1) Sanction of works —

(i) For extension of Low Tension (LT)

network for new streetlights along the

roads in Municipal or Panchayat area,

the resolution to that effect shall be

submitted by the Municipal Corporation/

Council or Village Panchayat concerned

to the Executive Engineer or Assistant

Engineer of respective area. The

Department shall execute the work of

extension of LT network after sanctioning

the estimate as per the delegation of

Technical and Financial powers of

Technical Officers of the Department as

per the Central Public Works Department

(CPWD) Manual in force. The energy

efficient LED fixtures shall be provided

on poles as per requirement.

(ii) New proposals of the other

Government

Departments

and

Government Corporations for public

lighting shall be submitted to the

Department. The execution of such

proposals shall be done only on

depositing of funds with the Department

by such Government Department or

Government Corporation concerned as

the case may be.

(iii) The new proposals for public

lighting by Central Government or under

Member of Parliament Local Area

Development (MPLAD) Scheme or any

another Central Government Scheme

shall be executed by the Department

after required funds are made available

to the Department on sanctioning of the

estimate.

(iv) The uniformity in energy efficient

streetlights fixtures and poles shall be

maintained by the Department.

(2) Execution of works —

The works shall be executed as per CPWD

Manual and by following all codal formalities

as envisaged under General Financial Rules

(GFR) and any other procedure as put in

place by the Government or the Department

from time to time. The Department shall take

all necessary approvals like clearance from

Technical Advisory Committee, Expenditure

Sanctions including approval of Expenditure

Finance Committee(EFC) and Goa State

Works Board (GSWB) wherever necessary as

per the rules inforce.

5. Payment of Energy bills of public

lighting.—Energy bills of all public lighting

except the facade illumination of temples,

churches, mosques and their outskirt shall

be settled by the Department from public

lighting duty levied and collected as per the

provisions of the Act.

By order and in the name of the Governor

of Goa.

Stephen Fernandes, CEE & ex officio Addl.

Secretary (Power).

Panaji, 5th April, 2022.

www.goaprintingpress.gov.in

Printed and Published by the Director, Printing & Stationery,

Government Printing Press,

Mahatma Gandhi Road, Panaji-Goa 403 001.

PRICE – Rs. 2.00

PRINTED AT THE GOVERNMENT PRINTING PRESS, PANAJI-GOA—10/150—4/2022.