1.

Short title and commencement. — These rules may be called the Goa Comunidade Land

Development and Regulation Rules, 2025.

(2) They shall come into force on the date of their publication in the Official Gazette.

2.

Definitions- In these rules, unless the context otherwise requires,-

“amenity” means road, water supply, street lighting, drainage, sewerage, public parks, playgrounds,

community centres and other community buildings, horticulture, internet connectivity, landscaping and any

other public utility service as the Comunidade may so desire;

(b) “financial bid” means the document containing the schedule or rates to be considered for the

purpose of evaluation and awarding permit/work order to the developer;

(c) “financially insecure Comunidade” means a Comunidade whose average annual approved

budget of the previous 3 years is less than Rs. 5,00,000/- (Rupees Five lakhs only) or zonn

paid to a Zonkar/Shareholder of the comunidade per year does not exceed Rs 20,000/- ;

(d) “form” means a form appended to these rules;

(e) “Government” means the Government of Goa;

17/7/2023-RD/1723

Date: 28-Feb-2025

Suggestions are welcomed on e-mail: [email protected]

2061

Reg. No. RNP/GOA/32/2024-2026

RNI No. GOAENG/2002/6410

Panaji, 28th February, 2025 (Phalguna 9, 1946)

SERIES I No. 48

PUBLISHED BY AUTHORITY

(f) “layout plan” means a plan of the Comunidade land depicting the division or proposed

division of land into plots, roads, open spaces, etc. and other details as may be necessary

and as approved by the Town and Country Planning Department;

(g) “technical bid” means the details of how the developer plans to execute the project, detailed

specifications of the materials or equipment to be used, layout plan and details of

utilization of the land area.

3.

Identification of land and approval of the Government. — (1) A financially insecure comunidade

who desires to develop its land by entrusting the work of development of such land to any private

agency under article 339-A shall first identify the land for the purpose of development and allotment

of plots and make an application to the Government in Form “I” hereto for obtaining approval of the

Government, after the managing Committee has scrutinized and approved the same.

(2) The area of the land proposed to be developed shall not be less than 10,000 square meters and

such land shall be permissible for development under applicable laws of the State.

(3) The application referred under sub-rule (1) shall be submitted along with the following

details/documents, namely:-

(i) name of the plot/land:

(ii) survey number.

(iii) survey plan,

(iv) plot boundaries, area and proposed use.

(v) statement whether the plot/lands is under ownership of comunidade

(vi) brief project report, and

(vii) draft terms and conditions of auction/bidding

4.

Monitoring of development of land by a Committee — (1) the application received under sub-rule

(1) of rule 3 shall be placed before the Government along with a scrutiny report of the managing

committee, for decision.

(2) Where the Government grants approval to such application, the monitoring, management and

evaluation of the entire mechanism of development of land covered under such application,

including technical and financial bid documents, shall be carried out by a committee consisting of

the President of the comunidade as the Chairperson, two persons nominated by the President of the

Comunidade one having expertise in the field of town planning and other having expertise in the

field of civil engineering both from the Government departments, Escrivao and the Attorney of the

respective Comunidade. The Attorney shall act as the member secretary of such committee.

(3) The term of the members of such committee who are elected members shall be co-terminus with

their term as members of the managing committee of the comunidade. The term of the nominated

members of such committee shall be 3 years.

(4) The meetings of such committee shall be convened bi-monthly and it shall submit its report to

the General Body of the Comunidade and the Government.

2062

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

5.

Manner of inviting bids. — After obtaining approval of the Government under rule 3 and the

Monitoring Committee, the Comunidade shall invite the developers for the development of land

though competitive public bidding in the manner provided hereunder:-

(A) The following details shall be specified in the bid document, namely:-

(i) area in sq. mtrs., survey number and survey plan of the land sought to be developed;

(ii) details of amenities to be developed, size of proposed plots to be developed in sq. mtrs;

(iii) non-refundable application fee at the rate of Rs. 10 per sq. mts. of land proposed for

develop;

(iv) any other details as the Monitoring Committee may specify.

(B) The bids shall be invited in two separate sealed envelopes super scribed as “Technical Bid” and

“Financial Bid” from the interested developers by publication of a notice in any two local

newspapers, having wide circulation in the State of Goa.

(C) The Government approval shall be obtained for tender documents prior to publishing notice in

the newspapers.

(D) Any developer who intends to participate in the competitive public bidding to undertake the

development in pursuance of a public notice shall provide information with regard to his legal,

technical, managerial and financial capacity to undertake the said land development with such

particulars as may be specified in such public notice;

(E) The Comunidade shall invite bids for the development of land from the developers in proportion

such that the Comunidade shall retain at least 50% of the plots of which 20% shall be reserved for

affordable housing to Gaunkars/Jonoeiros, after deducting the area used to develop amenities and

the remaining plots shall be transferred to the developer on payment of the financial bid value to the

Comunidade, in the manner provided in rule 11.

6. Participation in development of Comunidade land.— (1) Any developer who is desirous of

developing the Comunidade land shall participate in the competitive public bidding by writing to the

Comunidade and shall furnish therewith:-

A. a demand draft of the rates as specified in the public notice inviting bids along with the technical and

financial bids within time specified in public notice ;

B. the financial bid consisting of the details of the amount which the developer bids for the tendered

plots which he would be entitled to, after completion of the development of the land;

C. Technical bid consisting of the following particulars, namely:-

(i) Details of development done by developer i.e. showing the number and details of such

lands already developed (for a developed land not less than 10,000 sq. mts.);

(ii) particulars about the financial position and the following plans and documents in

triplicate, namely:-

(a) in the case of a Company, a copy of the Certificate of Incorporation of the Company,

Memorandum of Association and Articles of Association and its shareholders,

2063

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

Directors and other details;

(b) in the case of a Partnership firm, a copy of the Certification of Partnership, Deed of

Partnership and its Partners and other details;

(c) a copy of the Form No. I and XIV and Survey Plan showing the location of the

Comunidade Land;

(d) a draft layout plan of the Comunidade land on a scale of 1 centimeter to 10 meters

showing the existing and proposed means of access to the Comunidade land, the

width of streets, sizes and types of plots, sites reserved for open spaces, community

buildings and other amenities with the area under each and proposed development as

per the provisions of the Goa Town and Country Planning Act, 1974 (Act No. 21 of

1975);

(e) explanation regarding the salient feature of the proposed development, in particular,

the sources of wholesome water supply arrangement and site for disposal and

treatment of storm and sewerage water;

(f) plans showing the cross-sections of the proposed roads indicating, in particular, the

width of the proposed carriageways, cycle tracks and footpaths, green verges,

position of electric poles and any other works connected with such roads;

(g) plans indicating, in addition, the position of sewers, stormwater channels, water

supply and any other amenities;

(h) detailed specifications and designs of road works and estimated costs thereof;

(i) detailed specifications and designs of sewerage/ Sewerage Treatment Plant,

stormwater and water supply schemes with estimated costs of each;

(j) detailed specifications and designs for disposal and treatment of storm and sewerage

water and estimated costs of works;

(k) detailed specifications and designs for electric supply including street lighting.

Note: (1) The designs and specifications of the development works to be provided in the Comunidade

land shall include:—

(i) tarring of roads and paving of footpaths;

(ii) turfing and plantation of trees in open spaces;

(iii) street lighting;

(iv) adequate and wholesome water supply;

(v) sewers and drains both for storm and sewerage water/Sewerage Treatment Plant and necessary

provision for their treatment and disposal; and

(vi) any other works that the Comunidade may think necessary in the interest of proper

development of the Comunidade land;

(2) The preparation of the layout plans shall be the responsibility of the developer and such layout

plans must be submitted at the time of the development application.

7. Grant of development permission.— (1) After the selection of the successful bidder through

competitive bidding, the Comunidade shall grant the permission/ work order to the developer for the

development of Comunidade land, with the prior approval of the Government.

(2) The permission granted under sub-rule (1) shall be valid for a period of two years from the date of

its grant during which period all development works in the land shall be completed and a certificate of

2064

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

completion obtained from the Comunidade.

8. Agreement between Comunidade and the developer. — (1)

After the grant of permission to the

developer, an agreement of development shall be executed between the Comunidade and the

developer.

(2) Every agreement of development made under sub-rule (1) shall expressly specify the terms and

conditions in addition to the following:

(a) The developer shall undertake responsibility for the maintenance and upkeep of all roads, open

spaces, public parks and other amenities for a period of three years from the date of issue of

the completion certificate under rule 10 unless earlier relieved of this responsibility and

thereupon to transfer all such roads, open spaces, public parks and other amenities free of cost

to the Government or the local authority, as the case may be;

(b) The developer shall undertake to permit the Comunidade or any other individual authorized by

it, to inspect the execution of the layout and the development works in the land sought to be

developed.

9. Execution of works.— (1) The developer shall be responsible for obtaining all statutory permissions

such as conversion sanad, permissions from local authorities, sub-division approval, requisite NOC’s

etc., within a period of 6 months.

(2)The developer shall commence the development works within a period of three months of the grant

of permission under rule 7 and shall complete the same before the expiry of the period of the

permission.

(3) The Committee shall review the execution work bi-monthly.

10. Completion certificate. — (1) After the development has been carried out according to approved

layout plans and development works have been executed according to the approved designs and

specifications, the developer shall make an application to the Comunidade for the issue of completion

certificate.

(2) After such examination, as may be necessary, the Comunidade may issue a completion certificate

or refuse to issue such certificate stating the reasons for such refusal.

(3) No such certificate shall be granted by the Comunidade without prior approval of the Committee

and the Government.

11. Transfer of developer’s share in the land developed. — (1) Upon the completion of the development

work and obtaining a certificate under rule 10, the Comunidade with the approval of the Government

shall execute a deed with the developer transferring his share as per rule 5 and the developer shall

then be allowed to dispose of the developed plots/land of his share and create any third party right

thereto.

(2) Any third party right created by the developer prior to executing such deed with the Comunidade

shall be null and void.

2065

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

12. Grant of developed plots by the Comunidade.— After the transfer of the developer’s share, the

Comunidade may proceed with the grant of the land to the allottees as per the procedure laid down

under articles 324 to 339.

13. Maintenance of register.— (1) The Comunidade shall maintain a register in Form II showing

particulars of all cases in which development permissions have been granted or refused.

(2) A copy of the register shall be maintained in the office of the Administrator of Comunidade. Such

register shall be available for inspection to public without any fee and such persons shall be entitled

to have copies of the extract therefrom on the payment of two rupees per entry.

14. Cancellation of development permission.— (1) If the Comunidade finds at any time that the

execution of the layout plans and the construction or other works is not proceeding according to the

permission granted under rule 7 or is below specification or is in violation of the provisions of these

rules or of any law or rules for the time being in force, it shall by notice, require the developer to

remove the various defects within the time specified in the notice.

(2) If the developer fails to comply with the requirements detailed in the notice issued under sub-rule

(1), the Comunidade shall issue him a further notice to accord him an opportunity to show cause

within a period of one month why the permission granted should not be cancelled.

(3) After hearing the developer and considering such representation as he may make, the Comunidade

may either cancel the permission or grant him further time for complying with the requirements of the

notice issued under sub-rule (1) If, however, the developer does not comply with the said

requirements within such an extended period, the Comunidade shall cancel the permission without

any further hearing or opportunity such cancellation shall be notified in the Official Gazette and

publication in any two local newspapers by the Comunidade within 15 days from the date of such

cancellation.

(4) On cancellation of the permission, no further work shall be undertaken or carried out by the

developer and he shall vacate the premises forthwith.

15. Renewal of permission: — (1) On receipt of an application, the Comunidade shall if satisfied after

making such examination as it may consider necessary, that the delay in execution of development

works was for reasons beyond the control of the developer, renew the permission for a period of one

year, with the approval of the Committee and the Government.

(2) In case the Comunidade is not satisfied, it shall reject the application and in that case, an

intimation in this regard shall be sent to the developer.

(3) Upon the rejection of such application in terms of sub-rule (2), the developer shall forthwith

vacate the site of development.

(4) In case the developer fails to complete the development within the extended time, and upon his

vacating the land in terms of sub-rule (3), the Comunidade shall invite fresh bids within 15 days, in

accordance with rule 5.

2066

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

16. Transfer of permission.— (1) The developer may transfer the permission granted to him under rule 7

to any other developer fulfilling the criteria as laid down in these rules with the approval of the

Comunidade by making an application to the Comunidade by giving reasons thereto.

(2) The Comunidade, after receipt of such request for transfer of development permission shall

examine the matter on merits and may with the approval of the Committee and the Government

grant in-principle approval for transfer of such development permission or reject the application.

(3) A new agreement shall be executed between the comunidade, the original developer and the new

developer to whom the permission is transferred upon the grant of such permission to transfer.

17. Fee for copy of development permission.— A fee of Rs. 500 shall be charged for obtaining a copy of

the development permission by any person interested.

**********************************************************************

FORM I

(see rule 3(1))

1.

Name of the Comunidade

:-

2.

Annual approval budget of 3 years

:-

3.

Zone paid to Zonnkar/Shareholder

in past 3 years

:-

4.

Details of land identified to be

developed.

a) Name of the Village/Taluka

:-

b) Survey No.

:-

c) Area

:-

d) Zoning

:-

5.

Is the area free from encroachment

:-

6.

Nil encumbrance certificate

:-

7.

Survey plan/ Demarcation sketch

:-

8.

Is the area demarcated

:-

2067

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

9.

Has the Managing Committee

resolved to develop its land

:-

Form II

(see rule 13(1))

Register of Cases where permissions are granted or rejected

1 Serial No

2. Village

3. Taluka

4 Survey. no

5. Description of work to be taken up

6 Area

7. Valuation of project

8. Statutory permissions received

9. Grant of development permission: Year Month

10.Agreement between Comunidade and the developer: Year Month

By Order and in the name

of the Governor of Goa

(Vrushika Kauthankar)

Under Secretary (Revenue-I)

Porvorim-Goa, 28th February, 2025.

2068

OFFICIAL GAZETTE — GOVT. OF GOA

SERIES I No. 48

(EXTRAORDINARY)

28TH FEBRUARY, 2025

www.goaprintingpress.gov.in

Published by the Director, Printing & Stationary,

Government Printing Press,

Mahatma Gandhi Road, Panaji-Goa 403 001.