(NO.PATNA 490) PAT
BIHAR ELEC
No. Case No. R
conferred under section
2003 (Act 36 of 2003), a
this behalf, the Bihar E
the Bihar Electricity Re
Open Access) Regulati
01/2006-191 dated 20th
1. Short title, extent a
be called the Bihar E
Conditions for Open Acc
(2) These Regulati
(3) These Regulat
publication in
2. Amendment of Re
regulations, after clause
(m) "Bilateral transactio
(MWh) between a spec
through a trading lice
anonymous bidding, fr
REGISTERED
Bihar Gazett
Bihar Gazett
Bihar Gazett
Bihar Gazett
XTRA ORDINARY
SHED BY AUTHORITY
28 BHADRA 1934(S)
TNA, WEDNESDAY, 19TH SEPTEMBE
CTRICITY REGULATORY COMMISSION
—————
NOTIFICATION
The 19th September 2012
Reg. 27/2012-07–938—In exercise
n 42 read with Section 181 of the Elec
and all other powers enabling the Com
Electricity Regulatory Commission here
egulatory Commission (Terms and Con
ions, 2005 notified vide no. BERC-R
h May, 2006.
and commencement.—(1) These regul
Electricity Regulatory Commission (T
cess) (1st Amendment) Regulations, 201
ions extend to the whole of the State of
tions shall come into force on the da
the official Gazette.
egulation 2.—In Regulation 2 of the
e 2 (1) (L) the following shall be inserted
on" means a transaction for exchange
cified buyer and a specified seller,
ensee or discovered at power exchan
rom a specified point of injection to
NO. PT.-40
tetetete
ER 2012
of powers
ctricity Act,
mmission in
by amends
nditions for
Regulation-
ations may
Terms and
2.
Bihar.
ate of their
e principal
d, namely:
e of energy
directly or
nge though
a specified
2
BIHAR GAZETTE (EXTRA) 19TH SEPTEMBER 2012
point of drawal for a fixed for varying quantum of power (MW) for any
time period during a month
(n) "Collective transaction" means a set of transactions discovered in
power exchange through anonymous, simultaneous competitive bidding
by buyers and sellers".
3. Amendment of Regulation 4.—(i) In clause 4 (1) of the principal
regulations the words “electricity traders” shall be inserted after the word
“licensees” and before the words “the generating companies”
(ii) In Regulation 4 of the principal regulations clause (4) shall be inserted
as under:-
“(4)A person having been declared insolvent or bankrupt or having
outstanding dues against him for two months or more of billing of any
transmission or distribution licensee shall not be eligible for open
access”.
4. Amendment of Regulation 12.—In regulation 12 of the principal
regulations new clause (5) shall be inserted as under-
"(5)The capacity available for the intra-state open access shall be
computed for each transmission segment and for every sub-station by
the STU following the methodology given below:
(a) Available open access capacity of a transmission system segment =
(DC-SD-AC) + NC where, DC= Designed capacity of the
transmission segment in MW, SD= Sustained demand in MW
recorded in the segment, AC= already allocated capacity, but not
availed and NC= capacity in MW expected to be added.
(b) Available open access capacity of sub-station=TC-SP-AC where,
TC= Transformer Capacity of the sub-station in MVA, SP= sub-
station peak in MVA and AC= Already allotted capacity in MVA, but
not availed.
The STU shall update these values on monthly basis on the first
calendar day of the month in their website.
The appropriate distribution licensee shall determine the available
capacity for the portion of the distribution system over which open
access in demanded”.
5. Amendment of Regulation 16.—In clause 6 of Regulation 16 of the
principal regulations, the following provisos shall be inserted, namely:
“provided that if difference between the readings of main and check
meters exceeds twice the percentage error applicable to relevant class,
both meters shall be tested and the one found defective shall be
immediately replaced and reading of other will be considered.
Provided also that the check meter readings shall be considered
when Main Meters are found to be defective or stopped."
6. Amendment of Regulation 18.—In Regulation 18 of the principal
regulations, for sub-clause (d) of clause 2, the following shall be
substituted, namely :-
“(d) The surcharge shall be reduced in the manner as determined
by the Commission in respect to reduction of cross subsidies in terms
and conditions of tariff of transmission/distribution licensees”
3
BIHAR GAZETTE (EXTRA), 19TH SEPTEMBER 2012
7. Insertion of new regulations 20A and 20B.—After Regulation 20 of
the principal regulations, the following regulations shall be inserted,
namely:-
20 A. Standby Power
In case of outage of a power plant supplying power to an open
access customer, the licensee will, on request, provide standby supply to
meet the requirement of load catered through open access. Such standby
supply will be provided by the licensee at day ahead request from the
open access customer. The open access customer will, for that supply, be
liable to pay charges under tariff for temporary connection to that
category of consumer.
20
B.
Non
drawal
of
scheduled
power
due
to
failure
of
transmission/distribution system
If an open access customer is unable to draw the scheduled
energy due to failure of transmission/distribution system of the licensee,
the power injected will be treated as Banked Power and the open access
consumer will be allowed to draw the same within a period of three
months with an advance notice of the 24 hours to the licensee. The
power will in no case be drawn during evening peak load hours, unless
banked during peak load hours.
In case the open access customer is unable to draw the banked power,
then he will be paid by the licensee as per Regulation 20”.
By order of the commission,
GANESH PRASAD,
Secretary.
————
PUBLISHED AND PRINTED BY THE SUPERINTENDENT,
BIHAR SECRETARIAT PRESS, PATNA.
Bihar Gazette (Extra) 490—571+400—Egazette
Website: http://egazette.bih.nic.in