The B
The B
The B
The B
EX
PUBLI
(NO.PATNA 696) PAT
Bihar Ele
Vidyut Bhaw
BIHAR ELECTRICITY
MANAG
No. BERC-SMP-2
Act 2003 provides that "If
necessary or expedient so
equitable distribution of elec
for regulating supply, distrib
AND WHEREAS Sect
be the duty of a distribution
and economical distribution
accordance with the provisio
AND WHEREAS Se
Appropriate Commission sha
conditions for the determin
following, namely:-"Clause
efficiency, economical use of
AND WHEREAS Sec
Commission shall advise the
namely:-"Clause (i) "promot
the electricity industry,"
REGISTERED
Bihar Gazett
Bihar Gazett
Bihar Gazett
Bihar Gazett
XTRA ORDINARY
SHED BY AUTHORITY
3 BHADRA 1936(S)
TNA, MONDAY, 25TH AUGUST 2014
ectricity Regulatory Commission
wan, J.L. Nehru Marg, Patna 800 021
Y REGULATORY COMMISSION (DEMA
GEMENT) REGULATIONS, 2014
—————
NOTIFICATION
The 22nd August, 2014
21/14–07-823––WHEREAS Section 23 of th
the Appropriate Commission is of the opini
to do for maintaining the efficient supply,
ctricity and promoting competition, it may, by o
ution, consumption or use thereof",
tion 42 (1) of the Electricity Act 2003 provides
licensee to develop and maintain an efficient,
n system in his area of supply and to supply
ons contained in this Act",
ction 61 of the Electricity Act 2003 provid
all, subject to the provisions of this Act, specify t
nation of tariff, and in doing so, shall be gu
(c) "the factors which would encourage
f the resources, good performance and optimum
ction 86 (2) of the Electricity Act 2003 provide
e State Government on all or any of the follow
tion of competition, efficiency and economy in
NO. PT.-40
tetetete
AND SIDE
he Electricity
ion that it is
securing the
order, provide
that "It shall
co-ordinated
electricity in
es that "The
the terms and
uided by the
competition,
investment",
es that "State
wing matters,
n activities of
2
BIHAR GAZETTE (EXTRA) 25TH AUGUST 2014
AND WHEREAS Clause 5.9.2 of the National Electricity Policy provides that "the
potential number of installations where demand side management and energy
conservation measures are to be carried out is very large. Bureau of Energy Efficiency
(BEE) shall initiate action in this regard. BEE would also make available the estimated
conservation and DSM potential, its staged implementation alongwith cost estimates for
consideration in the planning process for National Electricity Plan";
AND WHEREAS Clause 5.9.4 of the National Electricity Policy provides that "In
the field of energy conservation initial approach would be voluntary and self-regulating
with emphasis on labeling of appliances. Gradually as awareness increases, a more
regulatory approach of setting standards would be followed";
AND WHEREAS Clause 5.9.6 of the National Electricity Policy provides that "In
order to reduce the requirements for capacity additions, the difference between electrical
power demand during peak periods and off-peak periods would have to be reduced.
Suitable load management techniques should be adopted for this purpose. Different tariff
structure for peak and off peak supply and metering arrangements (Time of Day
metering) should be conducive to load management objectives. Regulatory Commissions
should ensure adherence to energy efficiency standards by utilities;
In exercise of the powers conferred by clause (zp) of sub-section (2)
of section 181 of the Electricity Act, 2003 (36 of 2003), the Bihar
Electricity
Regulatory
Commission
hereby
makes
the
following
regulations namely Bihar Electricity Regulatory Commission (Demand
Side Management) Regulations, 2014.
Chapter I: General
1.
Short Title, Extent and Commencement
1.1
These Regulations may be called the "Bihar Electricity Regulatory
Commission (Demand Side Management) Regulations, 2014.
1.2
These Regulations shall be applicable to the Distribution Licensees
in the State in their respective areas of supply.
1.3
These Regulations shall come into force from the date of its
notification in the Official Gazette.
2.
Definitions
2.1
In these Regulations, unless the context otherwise requires-
i.
"Act" means the Electricity Act, 2003 (36 of 2003);
ii.
"Baseline data" means the initial base level consumption and/or
demand for electricity before a DSM programme begins to provide a
starting point for comparison for assessing programme impact";
iii.
"Bureau" or "BEE" means the Bureau of Energy Efficiency
established under sub-section (1) of Section 2 of The Energy
Conservation Act, 2001;
iv.
"Commission" means the Bihar Electricity Regulatory Commission
constituted under sub-section (1) of Section 82 of the Act;
v.
"Cost Effectiveness Index" means an indicator of the attractiveness
of any investment in DSM programme or when compared to the
costs of energy produced and delivered in the absence of such an
investment.
vi.
"Demand Side Management" or "DSM" means the actions of a
Distribution Licensee, beyond the customer's meter, with the
objective of altering the end- use of electricity- whether it is to
3
BIHAR GAZETTE (EXTRA), 25TH AUGUST 2014
increase demand, decrease it, shift it between high and low peak
periods, or manage it when there are intermittent load demands-
in the overall interests of reducing Distribution Licensee costs;
vii.
"DSM Resource Acquisition" means a mechanism to implement
DSM projects through customers, Energy Service Companies, Non-
Government Organizations, Manufacturers/Suppliers, or other
Private Sector Organizations, with payment made to them by the
Distribution Licensee for the resultant energy and load reductions;
viii.
"Energy Service Company" means a company which is in the
business of providing energy efficient and load management
equipment and/or services to endues customers and is approved
by Bureau;
ix.
"Evaluation, Measurement and Verification" means activities which
evaluate, measure and verify performance or other aspects of
DSM/energy efficiency programs or their market environment; and
x.
"Monitoring and Reporting" means activities which monitor and
evaluate the progress of DSM/energy efficiency programs of the
Distribution Licensee.
Chapter II: DSM Objectives, Targets and Guidelines
3.
DSM Objectives
3.1
The Commission shall formulate DSM objectives that shall be
considered in the advancement and implementation of cost
effective DSM initiatives in the State. The objectives may include
power shortage mitigation, seasonal peak reduction/peak shifting,
cost effective energy savings, lowering the cost of electricity,
reduction in emissions of greenhouse gases etc.
3.2
While formulating the DSM objective, the Commission may take
into consideration the National DSM objectives/Plans formulated
by BEE, if any.
3.3
The DSM objectives may be consistent with the DSM objectives set
out by Bureau as a part of Energy Conservation Plan for the
country.
4.
Assessment of Technical Potential for DSM
4.1
The Distribution Licensee in the State shall carry out assessment
of potential for DSM in the State every year. The first assessment
of technical potential for DSM shall be carried out within three
months of the notification of these Regulations.
4.2
Distribution Licensee shall be guided by methodology developed by
Bureau of Energy Efficiency while assessing of technical potential
for DSM.
5.
DSM Targets
5.1
Each distribution licensee shall establish its DSM targets and get it
approved by the Commission.
5.2
While approving DSM target for the Distribution Licensee, the
Commission will give due consideration to factors such as
consumer mix, load profile, etc.
5.3
Examples of DSM targets may include the following :
(i)
Percentage reductions in peak load growth;
4
BIHAR GAZETTE (EXTRA) 25TH AUGUST 2014
(ii)
Savings in kW, kWh
(iii)
Savings as a percentage of total resources required to meet
load;
5.4
While establishing the targets, the Commission shall consider the
technical potential in the State as assessed by the Distribution
Licensee.
6.
Guidelines on DSM Process
6.1
The Commission shall issue guidelines to guide the Distribution
Licensee in execution of the following activities:
(i)
Load and market research;
(ii)
Implementation of DSM programmes;
(iii)
Cost Effectiveness Assessment of DSM programmes;
(iv)
Eligibility criteria for DSM programmes;
(v)
Methodology for setting DSM targets and funding levels; and
(vi)
Database development framework.
6.2
The Commission shall issue guidelines on these matters from time
to time.
6.3
Issuance of such guidelines shall not be a pre-requisite for
preparation and submission of the first DSM plan by the
Distribution Licensee.
Chapter III : DSM Cell
7.
Constitution of DSM Cell, its Roles and Responsibilities
7.1
Every Distribution Licensee shall, constitute DSM Cell within one
month of notification of these Regulations.
7.2
The DSM Cell so constituted shall be provided with necessary
authority, resources and training so as to execute the functions
assigned to it under these Regulations.
7.3
The DSM Cell shall be responsible for :
(i)
Load research and development of baseline data;
(ii)
Formulation of DSM Plan;
(iii)
Planning and development of DSM projects including cost
benefit analysis, plans for implementation, monitoring &
reporting and for measurement & verification;
(iv)
Seeking necessary approvals to DSM Plan and individual
programmes;
(v)
Implementation of DSM Programmes; and
(vi)
Any other additional function that may be assigned by the
Commission from time to time.
7.4
DSM Consultative Committee
7.4.1 Constitution of DSM Consultative Committee (DSM-CC) and its
functions-
(1) A DSM Consultative Committee (DSM-CC) shall be constituted
by the Commission which shall be the nodal agency to assist the
Licensee and the Commission to drive the DSM programme under
DSM Regulations. The DSM-CC shall be constituted as indicated
below:-
(i)
Secretary of the Commission- Convener
5
BIHAR GAZETTE (EXTRA), 25TH AUGUST 2014
(ii)
One representative from each of the Distribution Licensee
not below the rank of Chief Engineer- Members
(iii)
One representative from each of the Transmission Utility not
below the rank of Chief Engineer- Members
(iv)
Chief
Electrical
Inspector
to
the
Government
(State
designated agency for energy audit and efficiency)- Member
(v)
Maximum five representatives from educational and research
institutions; industry, agriculture and general public who
have special knowledge or experience of and interest in
power sector to be nominated by the Commission- Members
7.4.2 The functions of the DSM-Consultation Committee shall be-
(a)
to advise the licensee on conducting continuous consumer
surveys and Load Research to seek information on end-use
technologies, usage patterns, willingness to pay, sensitivity
studies, market research etc. to assess DSM potential;
(b)
to promote cross-learning among the stakeholders to design
appropriate DSM programmes and plans;
(c)
to review DSM programme and DSM Plans submitted by the
licensee and to advise the Commission in assessment and
approval;
(d)
to provide support to the Commission for instituting DSM
Plan/Programme
monitoring,
review,
evaluation,
measurement and verification (EM&V) as and when required;
(e)
to study the impacts of already implemented DSM
Programmes;
(f)
to apprise the Commission about all DSM related activities
on quarterly basis.
Chapter IV: DSM Process
8.
Load and Market Research and Development of Baseline Data-
8.1
Distribution Licensee shall undertake load research to identify the
target consumer segment/s and end uses for DSM programmes to
build the necessary database.
8.2
Distribution Licensee shall undertake market research to estimate
market potential for specific energy efficiency technologies and
applications, establish key performance indicators, and determine
existing baseline market conditions.
8.3
On the basis of the results of load and market research, the
Distribution Licensee shall develop baseline data for its area of
supply.
8.4
Distribution Licensee shall design, develop and implement initially
some DSM programmes on the basis of available data and studies
completed by BEE till the complete baseline data is available for its
area of supply and establishment of base line data shall not be a
pre-requisite for design of such initial DSM programmes by the
Distribution Licensee.
6
BIHAR GAZETTE (EXTRA) 25TH AUGUST 2014
Formulation of DSM Plan
9.1.
Distribution
Licensee
shall
formulate
and
submit
to
the
Commission a perspective DSM plan every year. The Plan shall
include-
(i)
An overall goal for DSM Plan;
(ii)
Description of DSM programmes to form a part of DSM Plan;
(iii)
Implementation process and schedule of each programme in
the plan as a whole;
(iv)
Plan for Monitoring and Reporting, and indicative cost
effectiveness assessment of programmes. Notwithstanding
above, the first DSM plan shall be prepared within three
months of the date of notification of these Regulations.
9.2.
The Distribution Licensee shall include all relevant DSM
programmes (including multi-state programmes) developed by
Bureau of Energy Efficiency in its perspective plan as and when
such programmes are announced by Bureau.
9.3.
The Distribution Licensee shall submit on rolling basis, an annual
plan, not inconsistent with the perspective plan, for upcoming
year, along with the Annual Performance Review.
9.4.
Selection and prioritization of various DSM programmes in the
DSM Plan shall be guided by the following factors:
(i)
The Cost effectiveness guidelines issued by the Commission;
(ii)
DSM Objectives identified in Regulation 3;
(iii)
Whether the proposed programmes supplement National
level efforts adopted by the Bureau; and
(iv)
Programmes with high visibility and therefore potential for
creation of awareness within consumers.
Commission Review and Approval of DSM Plan
10.1 Distribution Licensee shall submit the DSM plan to the
Commission every year for approval at least three months before
the start of the year.
10.2 The Commission may adopt procedures as specified in the Conduct
of Business Regulations for according approval to the DSM Plan.
11.
Preparation of DSM Programme Document
11.1. For each DSM programme included in the DSM Plan, a detailed
description shall be provided in a separate Programme Document.
The description shall include general information, technology,
schedule for deployment, budget, cost effectiveness assessment,
detailed implementation plan, estimation of savings, etc.
11.2. For each DSM programme cost benefit analysis shall be carried out
as per guidelines issued by the Commission on cost effectiveness
from time to time.
12.
Approval of DSM programme Document
12.1 Prior to implementing any DSM programme, Distribution Licensee
must obtain approval of the Commission.
12.2 Each Programme Document shall include the following:
(i)
Description of the programme;
(ii)
Objective and rationale for the programme;
7
BIHAR GAZETTE (EXTRA), 25TH AUGUST 2014
(iii)
Consumer segments and estimated level of participation;
(iv)
Estimate of baseline;
(v)
Assessment of programme in line with Cost Effectiveness
Guidelines issued by the Commission;
(vi)
Mechanism for recovery of cost and performance incentives;
(vii)
Marketing, delivery strategy and Implementation schedule;
(viii) Implementation mechanism e.g. Energy Service Companies,
DSM Bidding, DSM Resource Acquisition, etc;
(ix)
Monitoring and evaluation plan; and
(x)
Plan for Training/ Seminars/ Workshops to increase
consumer awareness.
12.3 The Commission shall approve a DSM program if it is in line with
the objectives set out in Section-3 of the Regulations. The
Commission may direct modifications to proposed or on-going
programmes to ensure consistency with the DSM Objectives.
However, the Commission shall allow Distribution Licensee
adequate time to notify such activities.
13.
Implementation of DSM programmes
13.1 Distribution Licensee shall undertake implementation of DSM
programmes in line with the guidelines issued by the Commission
from time to time.
13.2 The implementation of the programme shall be undertaken in the
manner as approved by the Commission.
13.3 Distribution Licensee shall undertake implementation of quick
gain DSM programmes.
13.4 Distribution Licensee shall carry out implementation of activities
assigned to it either by itself or through engagement of appropriate
independent entity. While doing so, the Distribution Licensee shall
ensure that continuity and consistency is maintained and interest
of the consumers is not compromised.
14.
Mechanism for Cost Recovery
14.1 Distribution Licensee shall identify the net incremental cost, if any,
associated
with
planning,
design
and
implementation
of
programmes.
14.2 Cost of all DSM programmes and plans to be implemented by the
Distribution Licensee shall be included in the Annual Revenue
Requirement (ARR) and the licensee will clearly indicate the
mechanism for financing of each DSM Programme.
14.3 In order to qualify for cost recovery, each program must be:
(i) Approved prior to implementation;
(ii) Implemented in accordance with the approved program plan;
and
(iii) Implemented cost effectively.
14.4 Distribution Licensee shall provide all necessary assistance to the
Commission, or third party assigned by the Commission in
undertaking Evaluation Measurement and Verification of DSM
programmes implemented by it.
8
BIHAR GAZETTE (EXTRA) 25TH AUGUST 2014
15.
Monitoring and reporting of DSM Programmes
Distribution Licensee shall prepare plan and undertake monitoring
and reporting of DSM programmes as per Guidelines on Monitoring
and Reporting issued by Commission from time to time or as
approved
by
the
Commission
while
approving
the
DSM
programme.
16.
Evaluation Measurement and verification of DSM Programme
16.1 Distribution
Licensee
shall
prepare
plan
for
evaluation,
measurement and verification of savings from DSM programmes as
per Guidelines on Evaluation, Measurement and Verification
issued by the Commission from time to time.
16.2 Third party Evaluation Measurement and Verification of DSM
programmes may be undertaken by the Commission or third party
assigned by Commission. While engaging the agency, the
Commission shall ensure that the Agency is not undertaking any
other engagement which could conflict with the interests of the
consumers in the State.
16.3 Distribution
Licensee
shall
make
available
necessary
information/data to the Commission or third party assigned by the
Commission to measure and verify the savings from DSM
programmes.
Chapter V: DSM Plan and Programme Completion Report
17.
Report on progress of DSM plan and expenses incurred on
implementation of DSM Plan shall be submitted by the
Distribution licensee every six months.
18.
The Distribution Licensee will prepare and submit a detailed
Programme Completion Report and submit the same to the
Commission within one month of completion of such programme.
19.
The Report shall cover the programme expenses, achievements,
outcomes
and
outputs,
constraints
and
difficulties
faced,
conclusions recommendations, lessons learnt and way forward.
Chapter VI: Incentives
20.
The Commission may provide incentives to Distribution Utilities for
achieving or exceeding DSM Objectives as identified in Section 3 of
the Regulations.
Chapter VII: Miscellaneous
21.
Compliance of Directions
The Commission may from time to time, issue orders and practice
directions in regard to the implementation of the Regulations and
procedures to be followed.
22.
Disputes
All disputes arising under these Regulations shall be decided by
the Commission based on an application made by the person
aggrieved.
23.
Power to Remove Difficulties
If any difficulty arises in giving effect to the provisions of these
Regulations the Commission may by general or specific order,
9
BIHAR GAZETTE (EXTRA), 25TH AUGUST 2014
make such provisions not inconsistent with the provisions of the
Act, as may appear to be necessary for removing the difficulty.
24.
Power to Amend
The Commission may, at any time add, vary, alter, modify or
amend any provisions of these Regulations.
By order of the Commission,
PARMANAND SINGH,
Secretary,
Bihar Electricity Regulatory Commission.
————
PUBLISHED AND PRINTED BY THE SUPERINTENDENT,
BIHAR SECRETARIAT PRESS, PATNA.
Bihar Gazette (Extra) 696—571+400—Egazette
Website: http://egazette.bih.nic.in